5 CROSS-CHECKING AGAINST OTHER RELEVANT FEP SOURCES 29
5.1 Cross-checking against the Swedish SR-Site 29
The SR-Site FEP catalogue (SKB 2010a) has been mapped to TURVA-2012 FEPs in
Appendix C to check the comprehensiveness of the TURVA-2012 FEP list. All SR-Site
FEPs that could not be mapped directly to any TURVA-2012 FEP are shown in Table
5-1. It came out that the FEP lists are fairly similar with the few exceptions mentioned
in Table 5-1. Differences are mainly due to the fact that assessment methodology issues
(including quality control issues) are not treated as FEPs in TURVA-2012 but are han-
dled elsewhere in the safety case and/or in other documents presented for the construc-
tion licence application (CLA). Also, a few irrelevant FEPs (e.g. earth currents, lique-
faction of bentonite) have been excluded from Posiva’s FEP list already before
TURVA-2012, but they are included in the SR-Site FEP catalogue, even if concluded to
be irrelevant in the assessment.
Table 5-1. SR-Site FEPs (SKB 2010a, Tables 5-1...5-12, Sections 5.6, 5.7 and 5.8 and
Appendix 2) that were not found in the TURVA-2012 FEP list (see Table C-1). FEPs
that were excluded from the SR-Site assessment (shown in grey in Table C-1) are not
included here, nor any surface environment FEPs.
FEP
number in
SR-Site
FEP name in SR-Site
Note
ISGen02
Effects of phased op-
eration
Operation schedule is handled elsewhere in TURVA-2012 (e.g. waste emplacement schedule used in thermal dimensioning).
ISGen03
Incomplete closure
Out of the scope of the post-closure safety case TURVA-2012 that
assumes the disposal facility to be properly closed.
ISC01
Mishaps – canister
Canister handling accidents discussed in Performance Assess-
ment but not included as a FEP, as any canister damaged during
operation is assumed to be replaced. Operational safety is outside
the scope of TURVA-2012.
ISC02
Design deviations –
canister
Initial penetrating defect(s) assumed in several radionuclide re-lease scenarios.
ISBu01
Mishaps – buffer
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to buffer production and
emplacement. QC issues are related to assessment methodology
and are handled elsewhere in TURVA-2012.
ISBu02
Design deviations –
buffer
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to buffer production and
emplacement. QC issues are related to assessment methodology
and are handled elsewhere in TURVA-2012.
ISBfT01
Mishaps – backfill in
tunnels
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to backfill production and
emplacement. QC issues are related to assessment methodology
and are handled elsewhere in TURVA-2012.
ISBfT02
Design deviations –
backfill in tunnels
Out of scope of TURVA-2012. It is assumed that quality control (QC) measures are successfully applied to backfill production and
emplacement. QC issues are related to assessment methodology
and are handled elsewhere in TURVA-2012.
ISBP01
Mishaps – bottom plate
in deposition holes
The bottom plate is not a component in Posiva’s current repository design.
ISBP02
Design deviations –
bottom plate in deposi-
tion holes
The bottom plate is not a component in Posiva’s current repository
design.
ISPg01
Mishaps – plugs
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to the production and
emplacement of closure plugs (auxiliary components). QC issues
are related to assessment methodology and are handled else-
where in TURVA-2012.
ISPg02
Design deviations –
plugs
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to the production and
emplacement of closure plugs (auxiliary components). QC issues
are related to assessment methodology and are handled else-
where in TURVA-2012.
ISCA01
Mishaps – central area
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to the selection, produc-
tion and emplacement of closure materials and structures. QC
issues are related to assessment methodology and are handled
elsewhere in TURVA-2012.
ISCA02
Design deviations –
central area
Out of scope of TURVA-2012. It is assumed that quality control (QC) measures are successfully applied to the emplacement of
closure materials and structures. QC issues are related to as-
sessment methodology and are handled elsewhere in TURVA-
2012.
ISTS01 Mishaps/Design devia-
tions – top seal
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to the emplacement of
closure materials and structures. QC issues are related to as-
sessment methodology and are handled elsewhere in TURVA-
2012.
ISBhS01 Mishaps/Design devia-
tions – borehole seals
Out of scope of TURVA-2012. It is assumed that quality control
(QC) measures are successfully applied to the emplacement of
borehole seals. QC issues are related to assessment methodology
and are handled elsewhere in TURVA-2012.
F06
Mechanical cladding
failure
Not a FEP in itself in TURVA-2012, but the potential consequence of other FEPs, such as e.g. 3.2.7, 4.2.3.
C13
Earth currents – stray
current corrosion
Excluded already in Posiva’s previous Process Report (Miller & Marcos 2007) because the FEP had insignificant consequences
as reported in SR-Can.
Bu09 Liquefaction
Not relevant. Disregarded also in SR-Site since liquefaction from a
short pulse cannot occur in a high density bentonite, due to high
effective stresses (SKB 2010b, Table 2-4).
BfT08 Liquefaction
Not relevant. Disregarded also in SR-Site as not relevant (SKB
2010b, Table 2-9).
BfT17
Radiation-induced
transformations
Not a relevant FEP for backfill. Radiation effects on backfill proper-ties were disregarded also in SR-Site (SKB 2010a, p. 132).
Ge05
Displacements in intact
rock
Not a specific FEP, but taken into account in the modelled rock properties.
Ge09
Surface weathering and
erosion
Erosion is discussed in Complementary Considerations in Section 7.5. Surface weathering effects are considered in the geological
model of the Olkiluoto site.
In SR-Site this FEP has been moved under Climate and Bio-
sphere (SKB 2010a, Section 4.1.5).
Ge22
Radiation effects (rock
and grout)
Radiation effects are not significant in the geosphere. They were disregarded also in SR-Site because of too low radiation fluxes
(SKB 2010c, Table 1-4).
Ge23 Earth currents
Not relevant. Disregarded also in SR-Site since expected electrical
potential fields are too small to affect groundwater flow or solute
transport (SKB 2010c, Table 1-4).
Pg08,
CA08,
TS08,
BhS08
Liquefaction
Not relevant. Disregarded also in SR-Site, since impact is low (in
central area backfill) or cannot occur at all (in other components)
(SKB 2010b, Tables 2-14 and 2-16).
VarBu08 Stress state
Taken into account in 5.2.2, but not a feature of the buffer in itself.
VarBfT07 Stress state
Taken into account in 6.2.2, but not a feature of the backfill in
itself.
VarPg07 Stress state
Will vary according to water uptake and swelling in the clay com-
ponents of the plugs.
VarCA07 Stress state
Will vary according to water uptake and swelling in the clay com-
ponents of the central areas.
Cli04
Climate system – Cli-
mate in Sweden and
Forsmark
Climate in Finland and at Olkiluoto is considered (10.2.1).
LSGe01
Mechanical evolution of
the Shield
Not included as a specific FEP because the tectonic situation in
the Olkiluoto area is very likely to be stable in the one million year
assessment time frame (post-glacial earthquake effects consid-
ered in FEP 8.2.3 and in the RS and RS-DIL scenarios).
FHA01 General considerations Not a FEP in itself, but relates to assessment methodology (pro-
jected to the near future).
FHA02
Societal analysis, con-
sidered societal as-
pects
Not a FEP in itself, but relates to assessment methodology (pro-
jected to the near future).
FHA03
Technical analysis,
general aspects
Not a FEP in itself, but relates to assessment methodology (pro-jected to the near future).
SiteFact02 Construction of nearby
rock facilities
Taken into account in the site selection process. Dealt with else-
where in the construction licence application (CLA) – also in
Olkiluoto Site Descriptive model (OSD).
SiteFact03 Nearby nuclear power
plant
Taken into account in the site selection process. Dealt with else-
where in the CLA.
SiteFact04 Mine excavation
Taken into account in the site selection process. Dealt with else-
where in the CLA – also OSD.
Meth01
Assessment basis
Related to assessment methodology and thus handled elsewhere
in TURVA-2012.
Meth02 Assessment methodol-
ogy
Assessment methodology is handled elsewhere in TURVA-2012.
The mapping of TURVA-2012 process FEPs to SR-Site process FEPs (Table C-2 in
Appendix C) revealed that all TURVA-2012 process FEPs can be directly mapped to
SR-Site FEPs, indicating that the TURVA-2012 FEP list includes only processes that
are considered relevant also in SR-Site.
In document
Safety Case for the Disposal of Spent Nuclear Fuel at Olkiluoto
(Page 35-38)