• No results found

Cross-checking against the Swedish SR-Site 29 

5  CROSS-CHECKING AGAINST OTHER RELEVANT FEP SOURCES 29 

5.1  Cross-checking against the Swedish SR-Site 29 

The SR-Site FEP catalogue (SKB 2010a) has been mapped to TURVA-2012 FEPs in

Appendix C to check the comprehensiveness of the TURVA-2012 FEP list. All SR-Site

FEPs that could not be mapped directly to any TURVA-2012 FEP are shown in Table

5-1. It came out that the FEP lists are fairly similar with the few exceptions mentioned

in Table 5-1. Differences are mainly due to the fact that assessment methodology issues

(including quality control issues) are not treated as FEPs in TURVA-2012 but are han-

dled elsewhere in the safety case and/or in other documents presented for the construc-

tion licence application (CLA). Also, a few irrelevant FEPs (e.g. earth currents, lique-

faction of bentonite) have been excluded from Posiva’s FEP list already before

TURVA-2012, but they are included in the SR-Site FEP catalogue, even if concluded to

be irrelevant in the assessment.

Table 5-1. SR-Site FEPs (SKB 2010a, Tables 5-1...5-12, Sections 5.6, 5.7 and 5.8 and

Appendix 2) that were not found in the TURVA-2012 FEP list (see Table C-1). FEPs

that were excluded from the SR-Site assessment (shown in grey in Table C-1) are not

included here, nor any surface environment FEPs.

FEP

number in

SR-Site

FEP name in SR-Site

Note

ISGen02

Effects of phased op-

eration

Operation schedule is handled elsewhere in TURVA-2012 (e.g. waste emplacement schedule used in thermal dimensioning).

ISGen03

Incomplete closure

Out of the scope of the post-closure safety case TURVA-2012 that

assumes the disposal facility to be properly closed.

ISC01

Mishaps – canister

Canister handling accidents discussed in Performance Assess-

ment but not included as a FEP, as any canister damaged during

operation is assumed to be replaced. Operational safety is outside

the scope of TURVA-2012.

ISC02

Design deviations –

canister

Initial penetrating defect(s) assumed in several radionuclide re-lease scenarios.

ISBu01

Mishaps – buffer

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to buffer production and

emplacement. QC issues are related to assessment methodology

and are handled elsewhere in TURVA-2012.

ISBu02

Design deviations –

buffer

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to buffer production and

emplacement. QC issues are related to assessment methodology

and are handled elsewhere in TURVA-2012.

ISBfT01

Mishaps – backfill in

tunnels

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to backfill production and

emplacement. QC issues are related to assessment methodology

and are handled elsewhere in TURVA-2012.

ISBfT02

Design deviations –

backfill in tunnels

Out of scope of TURVA-2012. It is assumed that quality control (QC) measures are successfully applied to backfill production and

emplacement. QC issues are related to assessment methodology

and are handled elsewhere in TURVA-2012.

ISBP01

Mishaps – bottom plate

in deposition holes

The bottom plate is not a component in Posiva’s current repository design.

ISBP02

Design deviations –

bottom plate in deposi-

tion holes

The bottom plate is not a component in Posiva’s current repository

design.

ISPg01

Mishaps – plugs

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to the production and

emplacement of closure plugs (auxiliary components). QC issues

are related to assessment methodology and are handled else-

where in TURVA-2012.

ISPg02

Design deviations –

plugs

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to the production and

emplacement of closure plugs (auxiliary components). QC issues

are related to assessment methodology and are handled else-

where in TURVA-2012.

ISCA01

Mishaps – central area

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to the selection, produc-

tion and emplacement of closure materials and structures. QC

issues are related to assessment methodology and are handled

elsewhere in TURVA-2012.

ISCA02

Design deviations –

central area

Out of scope of TURVA-2012. It is assumed that quality control (QC) measures are successfully applied to the emplacement of

closure materials and structures. QC issues are related to as-

sessment methodology and are handled elsewhere in TURVA-

2012.

ISTS01 Mishaps/Design devia-

tions – top seal

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to the emplacement of

closure materials and structures. QC issues are related to as-

sessment methodology and are handled elsewhere in TURVA-

2012.

ISBhS01 Mishaps/Design devia-

tions – borehole seals

Out of scope of TURVA-2012. It is assumed that quality control

(QC) measures are successfully applied to the emplacement of

borehole seals. QC issues are related to assessment methodology

and are handled elsewhere in TURVA-2012.

F06

Mechanical cladding

failure

Not a FEP in itself in TURVA-2012, but the potential consequence of other FEPs, such as e.g. 3.2.7, 4.2.3.

C13

Earth currents – stray

current corrosion

Excluded already in Posiva’s previous Process Report (Miller & Marcos 2007) because the FEP had insignificant consequences

as reported in SR-Can.

Bu09 Liquefaction

Not relevant. Disregarded also in SR-Site since liquefaction from a

short pulse cannot occur in a high density bentonite, due to high

effective stresses (SKB 2010b, Table 2-4).

BfT08 Liquefaction

Not relevant. Disregarded also in SR-Site as not relevant (SKB

2010b, Table 2-9).

BfT17

Radiation-induced

transformations

Not a relevant FEP for backfill. Radiation effects on backfill proper-ties were disregarded also in SR-Site (SKB 2010a, p. 132).

Ge05

Displacements in intact

rock

Not a specific FEP, but taken into account in the modelled rock properties.

Ge09

Surface weathering and

erosion

Erosion is discussed in Complementary Considerations in Section 7.5. Surface weathering effects are considered in the geological

model of the Olkiluoto site.

In SR-Site this FEP has been moved under Climate and Bio-

sphere (SKB 2010a, Section 4.1.5).

Ge22

Radiation effects (rock

and grout)

Radiation effects are not significant in the geosphere. They were disregarded also in SR-Site because of too low radiation fluxes

(SKB 2010c, Table 1-4).

Ge23 Earth currents

Not relevant. Disregarded also in SR-Site since expected electrical

potential fields are too small to affect groundwater flow or solute

transport (SKB 2010c, Table 1-4).

Pg08,

CA08,

TS08,

BhS08

Liquefaction

Not relevant. Disregarded also in SR-Site, since impact is low (in

central area backfill) or cannot occur at all (in other components)

(SKB 2010b, Tables 2-14 and 2-16).

VarBu08 Stress state

Taken into account in 5.2.2, but not a feature of the buffer in itself.

VarBfT07 Stress state

Taken into account in 6.2.2, but not a feature of the backfill in

itself.

VarPg07 Stress state

Will vary according to water uptake and swelling in the clay com-

ponents of the plugs.

VarCA07 Stress state

Will vary according to water uptake and swelling in the clay com-

ponents of the central areas.

Cli04

Climate system – Cli-

mate in Sweden and

Forsmark

Climate in Finland and at Olkiluoto is considered (10.2.1).

LSGe01

Mechanical evolution of

the Shield

Not included as a specific FEP because the tectonic situation in

the Olkiluoto area is very likely to be stable in the one million year

assessment time frame (post-glacial earthquake effects consid-

ered in FEP 8.2.3 and in the RS and RS-DIL scenarios).

FHA01 General considerations Not a FEP in itself, but relates to assessment methodology (pro-

jected to the near future).

FHA02

Societal analysis, con-

sidered societal as-

pects

Not a FEP in itself, but relates to assessment methodology (pro-

jected to the near future).

FHA03

Technical analysis,

general aspects

Not a FEP in itself, but relates to assessment methodology (pro-jected to the near future).

SiteFact02 Construction of nearby

rock facilities

Taken into account in the site selection process. Dealt with else-

where in the construction licence application (CLA) – also in

Olkiluoto Site Descriptive model (OSD).

SiteFact03 Nearby nuclear power

plant

Taken into account in the site selection process. Dealt with else-

where in the CLA.

SiteFact04 Mine excavation

Taken into account in the site selection process. Dealt with else-

where in the CLA – also OSD.

Meth01

Assessment basis

Related to assessment methodology and thus handled elsewhere

in TURVA-2012.

Meth02 Assessment methodol-

ogy

Assessment methodology is handled elsewhere in TURVA-2012.

The mapping of TURVA-2012 process FEPs to SR-Site process FEPs (Table C-2 in

Appendix C) revealed that all TURVA-2012 process FEPs can be directly mapped to

SR-Site FEPs, indicating that the TURVA-2012 FEP list includes only processes that

are considered relevant also in SR-Site.

Related documents