• No results found

3   Problems with the Production Management Systems: Understanding the problem and the context

3.3   Root causes behind the problems

3.3.3   Planning in production management

Traditionally,   in   construction,   planning   is   considered   to   be   an   equivalent   of   creating  a  Gantt  chart  of  tasks  to  be  performed  (Henrich  et  al.,  2005).  This  Gantt   chart   on   most   occasions   is   created   at   the   early   stage   of   the   project   at   the   head   office   without   consulting   the   project   team   (Ballard,   2000).   At   this   stage   of   the   project  the  reliability  of  information,  i.e.  resource  availability,  external  conditions,   client  changes  are  not  yet  available  and  hence  the  reliability  of  the  plan  is  quite  low   (Ballard,   2000).   However,   this   master   plan   is   taken   as   the   base   document   and   pushed  to  the  site  team  to  be  followed  regardless  of  the  current  situation  on  the   ground.  The  other  shortcoming  of  this  plan  is  that  it  seldom  shows  various  flows  of   resources   such   as   labour,   equipment,   material   etc.,   hence   the   site   team   has   to   decipher  this  detail  on  their  own.  From  the  discussion  about  current  ICT  systems,   it   is   observed   that   not   many   organisations   have   achieved   complete   integration   between   their   information   systems,   and   this   leaves   the   site   team   without   the   critical  information  regarding  these  resources  during  the  execution  of  the  project.   Also,  most  planning  methods  do  not  include  the  spatial  information  in  the  plan,  i.e.   it  does  not  show  where  the  work  is  going  be  carried  out  and  how  to  resources  will   flow   during   the   project   (i.e.   smooth   flow   of   resource   between   locations   without   interruptions).  This  leads  to  resource  clashes  during  the  execution;  i.e.  two  work   teams   working   within   the   same   space,   material   being   stacked   too   far   from   the   project,  not  knowing  where  the  equipment  are  or  when  they  will  be  available.  All   such  factors  add  to  the  inefficiencies  during  the  execution  stage.  In  the  following  

paragraphs  some  of  the  main  production  planning  and  control  systems  being  used   in  construction  will  be  discussed.  

3.3.3.1  Critical  Path  Method  (CPM)    

The  CPM  method  was  developed  by  DuPont  and  Remington  Rand  around  1957.  It   was   developed   to   mathematically   calculate   the   sequence   of   activities   in   order   to   complete  a  project  in  the  minimum  time  possible.  CPM  programmes  show  activity   dependencies  and  duration  allocated  for  each  activity.  It  also  allows  for  calculating   the  float  of  an  activity,  where  float  is  the  amount  of  time  a  non-­‐critical  activity  can   be   delayed   without   affecting   the   overall   programme.   A   majority   of   construction   projects  today  use  CPM  as  the  main  project  management,  planning  and  controlling   mechanism.   It   is   the   most   popular   method   in   construction   over   the   last   five   decades.   The   project   plan   is   shown   using   Gantt   charts,   which   are   the   visual   representation  displaying  activities  as  horizontal  bars  where  time  is  plotted  on  the   X  axis.  Due  to  this  visual  representation,  Gantt  charts  are  quite  easy  to  understand   and  have  made  the  CPM  method  very  popular  amongst  construction  professionals.     The  CPM  method  can  be  seen  as  the  direct  implementation  of  the  transformation   view.  It  implies  that  by  breaking  the  tasks  into  smaller  chunks  or  by  way  of  work   breakdown   structures,   a   project   can   be   managed.   The   aspects   such   as   flow   of   materials,  labour,  equipment  or  information  are  not  taken  into  account  (Howell  &   Koskela,  2000).  CPM  is  effective  in  providing  a  big  picture  but  if  one  tries  to  add   information   such   as   material   and   labour   flows,   it   starts   to   get   very   cumbersome   and   difficult   to   manage   (Peer,   1974;   Birrel,   1980).   Also,   one   further   essential   element   that   is   missing   from   the   CPM   method   is   spatial   information   (i.e.   smooth   flow  of  labour  and  resources  between  locations).  It  is  understood  that  construction   takes  place  in  space  and  time.  CPM  addresses  the  time  element  (although  not  in  a   complete   way);   the   spatial   element   is   completely   missing.   If   one   tries   to   add   a   spatial   element,   i.e.   where   a   particular   task   will   be   carried   out,   the   Gantt   chart   starts   becoming   too   complicated   and   as   a   result,   is   seldom   updated.   The   consequence  is  that  without  the  spatial  element,  the  programme  becomes  difficult   to   manage;   as   it   frequently   leads   to   resource   clashes,   i.e.   Two   labour   teams   working   in   the   same   place   at   the   same   time   where   there   is   not   enough   space,  

material  being  stacked  in  the  wrong  place,  crew  sitting  idle  as  there  is  no  space  or   direction  where  they  should  work  next,  etc.  

3.3.3.2  Line  of  Balance  (LOB)  

Line  of  Balance  is  a  linear  scheduling  method,  which  shows  the  tasks  in  a  project  as   a   single   line   on   a   graph   as   opposed   to   a   series   of   individual   activities   on   a   bar/Gantt   chart.   It   is   mostly   used   on   projects   where   there   are   a   number   of   repetitive  activities  such  as  a  housing  or  a  road  construction  project.  

LOB   was   originally   developed   by   the   Goodyear   Co.   in   the   early   1940s   and   was   further  developed  by  the  US  Navy  in  the  early  1950s  for  programming  and  control   of  both  repetitive  and  non-­‐repetitive  projects.  (Turban  1968;  Lutz  &  Halpin,  1992).   The   LOB   technique   assumes   that   the   rate   of   production   for   an   activity   remains   uniform   during   the   execution   time.   Most   commonly,   time   is   plotted   on   the   horizontal  axis  where  as  work  units  are  plotted  on  the  vertical  axis.  The  resultant   chart   shows   sloping   lines,   which   represent   the   production   rate   of   an   activity.   Another   characteristic   of   the   LOB   is   that   it   represents   work   activities   being   continuously   performed,   even   if   the   work   is   being   carried   out   in   different   locations.    

Recently,  Seppänen  (2009)  has  attempted  to  improve  the  location  based  planning   tools   and   their   processes.   In   the   research,   the   author   implemented   the   location   planning  methods  on  three  case  study  projects  and  studied  their  performance.  It   was  observed  on  the  case  studies  that,  even  after  project  activities  were  subjected   to  cascading  delays  from  an  initial  phase,  the  actual  finish  date  of  the  project  was   not  affected.  This  was  due  to  the  long  end-­‐buffer  that  was  put  in  the  schedule.  Also,   the   author   found   that   the   problems   occurring   on   projects   could   be   envisaged   earlier  due  to  the  location-­‐based  control  data  available.    

LOB  partially  addresses  the  issue  of  spatial  information,  as  there  is  a  possibility  to   show  the  space  where  the  task  will  be  carried  out  over  time  on  the  activity  line.   However,  there  are  limitations  to  this  approach  as  it  works  well  in  projects  where   there  are  repetitive  tasks,  as  LOB  does  not  work  well  where  the  project  has  many   unique  tasks.  Also,  the  issue  of  temporary  structures  is  not  addressed  by  the  LOB   method.   A   typical   construction   project   during   their   lifetime   see   erection   and  

demolition  of  many  temporary  structures,  which  have  to  be  managed  during  the   planning   and   execution   stage.   As   these   are   unique   in   nature   the   LOB   approach   does  not  work  well  in  this  case.  The  simple  nature  of  the  LOB  charts  also  limits  the   amount  of  information  that  can  be  shown  on  them.  

3.3.3.3  Critical  Chain  

Developed   by   Goldratt   (1997),  Critical   Chain   Project   Management   (CCPM)   is   a   method   of   planning   and   managing   projects   that   put   the   main   emphasis   on   the   resources  required  to  execute  project  tasks.  As  opposed  to  other  methods  such  as   CPM,  which  advocate  rigid  task  order  and  timeline  based  scheduling,  Critical  Chain   requires   the   schedule   to   be   flexible   and   tries   to   keep   resources   level   throughout   the  project.  Overall,  it  focuses  on  taking  out  the  individual  task  “float”  or  “buffer”   and  allocating  them  to  one  big  collective  buffer.  It  assumes  that  this  way  the  tasks   are  started  as  soon  as  the  previous  one  finishes  and  project  completes  on  time.  The   Critical  Chain  theory  is  based  on  the  Theory  of  Constraints  developed  by  Goldratt   (1997)  which  is  based  on  the  premise  that  rate  of  goal  achievement  is  limited  by  at   least  one  constraining  process.  As  described  by  Goldratt  (1997)  the  five  key  steps   in  organisational/process  improvement  are:  

1. Identify   the   constraint   (the   resource   or   policy   that   prevents   the   organization  from  obtaining  more  of  the  goal)  

2. Decide  how  to  exploit  the  constraint  (make  sure  the  constraint's  time  is  not   wasted  doing  things  that  it  should  not  do)  

3. Subordinate  all  other  processes  to  above  decision  (align  the  whole  system   or  organization  to  support  the  decision  made  above)  

4. Elevate   the   constraint   (if   required   or   possible,   permanently   increase   capacity  of  the  constraint;  "buy  more")  

5. If,   as   a   result   of   these   steps,   the   constraint   has   moved,   return   to   Step   1.   Don't  let  inertia  become  the  constraint.  

Koskela  et  al.  (2010)  have  compared  the  Critical  Chain  Production  Management  to   the   Last   Planner   System™   within   the   context   of   construction   management.   The   authors   summarise   that   while   Critical   Chain   endeavours   to   shorten   the   project   duration  with  cost  reductions  (where  other  benefits  are  secondary),  Last  Planner   primarily  endeavours  to  reduce  the  variability  in  work  flows,  which  directly  leads  

to  increased  productivity  and  cost  reduction  along  with  gains  in  safety  and  quality.   In  addition,  Last  Planner  helps  with  schedule  compression  as  it  reduces  variability.   In   criticism,   Koskela   et   al.   (2010)   mention   that   the   Critical   Chain   method   is   restricted  to  buffer  management,  as  it  does  not  try  to  address/reduce  the  cause  of   the   buffers   or   variability.   Hence,   there   is   a   limited   scope   for   productivity   improvement   through   variability   reduction.   In   comparison,   Last   Planner   fails   to   maintain   an   explicit   link   with   the   master   plan   (Junior   et   al.,   1998),   hence   the   current   situation   on   site   can   not   be   readily   assessed   from   an   overall   project   perspective.   Also   in   Last   Planner   there   is   no   direct   method   of   schedule   compression  at  the  master  plan  level.  

3.3.3.4  Last  Planner  

The  Last  Planner™  system  (Ballard,  2000)  –  as  the  name  suggests  is  based  on  the   planning   and   scheduling   that   is   carried   out   by   the   people   responsible   for   the   execution   of   work,   i.e.   site   manager,   foreman   and   work   crews.   Traditionally,   planning   and   production   management   is   carried   out   with   a   top-­‐down   approach.   Planners   mostly   based   at   the   head   office   prepare   the   schedules   right   at   the   estimating  stage.  This  is  then  pushed  to  site  teams  to  follow  during  the  entirety  of   the  execution  stage.  Very  little  input  window  to  planning  is  left  for  the  site  teams.   As  discussed,  this  makes  the  execution  plans  quite  unreliable,  as  they  are  prepared   when  there  is  not  much  reliable  information  available.    

Last   Planner   tries   to   overcome   problems   of   traditional   planning   methods   by   introducing   shorter   planning   cycles   during   the   execution   stage,   which   are   prepared  by  the  work  teams  and  are  based  on  work  commitments  on  “what  CAN   be  done”  rather  than  “what  SHOULD  be  done”.  Here,  the  master  schedule  is  taken   as   a   guideline,   and   informs   the   work   teams   about   major   milestones   and   overall   schedule.  Based  on  the  master  schedule  a  look  ahead  plan  is  prepared  4-­‐6  weeks  in   advance,  which  is  based  on  the  current  resource  situation  and  up-­‐to-­‐date  forecasts.   Further  to  this,  weekly  meetings  are  organised  where  all  work  teams  take  part  and   “pull   tasks”   from   the   look-­‐ahead   plan.   Also,   the   weekly   meetings   are   used   to   analyse   the   reasons   for   non-­‐completion   for   previous   week’s   tasks,   and   a   task   is   only   selected   if   all   the   pre-­‐requisites   to   starting   that   task   are   met.   This   clearly   improves   the   reliability   of   the   planned   work   and   improves   the   efficiency   of  

workers.   The   method   also   builds   a   network   of   promises,   as   each   week,   all   stakeholders  commit  to  the  work  being  planned  and  are  then  held  responsible  for   the   same.   This   gradually   builds   the   trust   and   improves   social   environment   (collaboration)  on  site  as  all  units  operate  as  a  team.  

Last  Planner  takes  into  account  the  flow  aspects  of  the  construction  process  during   the   execution   stage.   It   has   generally   been   found   to   improve   the   reliability   of   the   projects   due   to   the   increased   reliability   of   the   plans.   Here   the   responsibility   of   production   control   shifts   from   the   top   level   to   the   comparatively   lower   ranks   as   the   work   is   pulled   based   on   all   the   prerequisites   being   met.   On   the   other   hand,   commitment  to  the  method  becomes  a  prerequisite  for  all  parties.  As  a  result,  last   planner   may   not   work   properly   in   situations   where   it   is   not   possible   to   create   a   network   of   trust.   Also,   in   organisations   where   the   control   is   mostly   kept   in   top   circles,   the   managers   find   it   too   difficult   to   allow   the   site   team   to   control   the   production  process.  Again,  in  cultures  where  this  is  the  case  the  system  might  not   work  in  its  current  form  (i.e.  it  may  need  adapting  to  suit  the  cultural  and  process   issues).    

Even   though   the   Last   Planner   system   takes   into   account   the   variability   in   the   process,   it   does   not   go   beyond   the   weekly   planning   meetings.   A   construction   project  is  a  dynamic  environment  and  much  could  happen/change  during  the  span   of   a   week.   Reliability   can   be   further   improved   if   a   shorter   planning   cycle   is   introduced  (Sacks  et  al.,  2009).  

3.3.3.5  Summary  of  planning  methods    

Despite   its   shortcomings   CPM   remains   one   of   the   most   popular   methods   being   taught   and   used   in   the   academia   and   the   industry.   The   majority   of   construction   planning   and   scheduling   software   are   also   based   around   CPM.   The   linear   scheduling   methods   help   in   selective   projects   but   cannot   provide   an   overall   solution   to   the   industry.   Critical   Chain   is   not   yet   followed   in   the   mainstream   construction   and   is   undergoing   further   research.   It   has   some   parallels   with   the   Last  Planner  System,  and  it  can  be  argued  that  they  complement  each  other  well.   The  Last  Planner™  system  of  production  management  and  control  is  beginning  to   become   popular   where   there   is   a   reasonably   supportive   environment   for   its   implementation.   It   can   be   concluded   that   there   is   a   need   for   a   streamlined  

construction   process   through   a   systematic   implementation   of   a   production   management  and  control  system  which  takes  into  account  the  transformation,  flow   and  value  concepts.