Specified Requirements (Cont'd) Material Testing Laboratory

1.13 Establishment of site material testing laboratory A212.1 sum 1.14 Maintenance of site material testing laboratory A212.2 Day 1.15 Removal of site material testing laboratory A212.3 sum

Services for the Engineer's staff

1.16 Supply, Maintenance of Vehicles supplied to

Engineer's staff including fuel and driver A221.1 Day 1.17 Telephone and Telefax for office facilities A222.1 Day 1.18 Local Area Network with DSL internet connection

(minimum 2mbps and router) A229.1 Day

1.19 Set of Progress Photographs ( to cover all major activities ) including supply of Cameras, lenses,

prints etc. as in specification. A229.2 nr 1.20 Printing, Distribution and Preparation of Record

Drawings A229.3 sum

Services for Employer's staff

1.21 Supply, Maintenance of Vehicles supplied to

Employer's staff including fuel and driver A221.2 Day 1.22 Telephone and Telefax for office facilities A222.2 Day 1.23 Local Area Network with DSL internet connection

(minimum 2mbps and router) A229.4 Day

Equipment for Use by the Engineer's Staff Office Equipment for the Engineer's Staff (Item 1.24 to 1.26)

1.24 Establishment A231.1 sum

1.25 Maintenance A231.2 Day

1.26 Removal A231.3 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Specified Requirements (Cont'd)

Equipment for Use by the Engineer's Staff (Cont'd)

Survey equipments, facilities and associated works required as described in specification for the project duration. (Item 1.27 to 1.29)

1.27 Establishment A233.1 sum

1.28 Maintenance A233.2 Day

1.29 Removal A233.3 sum

Softwares, including technical supports as in specification. Item 1.30 to 1.32)

130 Establishment A239.1 sum

1.31 Maintenance A239.2 Day

1.32 Removal A239.3 sum

...(Nos.) Laptops and ….. ( Nos ) Desktop computers with printers as per specifications, including the following services: Telecommunication infrastructure, Local Area Network hardware, Network/Server room, Cabling, Scanners, Photo Copying Machines for the project duration as in specification. (Item 1.33 to 1.35)

1.33 Establishment A239.4 sum

1.34 Maintenance A239.5 Day

1.35 Removal A239.6 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Specified Requirements (Cont'd)

Kitchen Equipment - Cutlery etc., Kitchen and Sanitary supplies, Stationary supplies, Bottled water supplies and all other miscellaneous equipment supplies as described in specification.

(Item 1.36 to 1.38)

1.36 Establishment A239.7 sum

1.37 Maintenance A239.8 Day

1.38 Removal A239.9 sum

Equipment for Use by Employer's Staff Office Equipment for the Employer's Staff (Item 1.39 to 1.41)

1.39 Establishment A231.4 sum

1.40 Maintenance A231.5 Day

1.41 Removal A231.6 sum

Attendance upon the Engineer's staff

1.42 Chainmen A242 Day

1.43 Office attendance A249 Day

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Testing of Materials

1.44 Specified tests for Bridge bearings A250.1 sum 1.45 Specified tests for prestressing tendons A250.2 sum

Allow for all specified testing to be carried out in accordance with specification

1.46 All testing relating to Bill Part 4 - Earthworks A250.3 sum 1.47 All testing relating to Bill Part 5 - Roads and

Pavings A250.4 sum

1.48 All testing relating to Bill Part 6 - Bridge Works A250.5 sum 1.49 All testing relating to Bill Part 7 - Tunnel /

Underpass Works A250.6 sum

1.50 All testing relating to Bill Part 8 - Retaining

Structures A250.7 sum

1.51 All testing relating to Bill Part 9 - Storm Water

Drainage Network A250.8 sum

1.52 All testing relating to Bill Part 10 - Sanitary Sewer

Network A250.9 sum

1.53 All testing relating to Bill Part 11 - Potable Water

Network A250.10 sum

1.54 All testing relating to Bill Part 12 - Irrigation Network

A250.11 sum 1.55 All testing relating to Bill Part 13 - Electrical Network

A250.12 sum 1.56 All testing relating to Bill Part 14 - Street Lighting

Works A250.13 sum

1.57 All testing relating to Bill Part 15 - Duct Network for

Telecommunication Cables A250.14 sum

1.58 All testing relating to Bill Part 16 - Traffic Signal

Control System A250.15 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Testing of Materials (Cont'd)

1.59 All testing relating to Bill Part 17 - Culverts A250.16 sum 1.60 All testing relating to Bill Part 18 - Building Works A250.17 sum 1.61 Allow for any other testing required as per

specifications not listed above (the Tenderer shall separately list and price below any other clause

considered to have a monetary value) A250.18 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Testing of Materials (Cont'd)

Testing of materials; to be carried out within or outside U.A.E by independent Specialist Laboratories as required by relevant specifications.

1.62 Allow for any other testing required as per specifications (the Tenderer shall separately list and

price below) A250.19 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Testing of Materials (Cont'd)

Testing of the Works; as specified, including tests at manufacturer's works

1.63 All testing relating to Bill Part 4 - Earthworks A260.1 sum 1.64 All testing relating to Bill Part 5 - Roads and

Pavings A260.2 sum

1.65 All testing relating to Bill Part 6 - Bridge Works A260.3 sum 1.66 All testing relating to Bill Part 7 - Tunnel /

Underpass Works A260.4 sum

1.67 All testing relating to Bill Part 8 - Retaining

Structures A260.5 sum

1.68 All testing relating to Bill Part 9 - Storm Water

Drainage Network A260.6 sum

1.69 All testing relating to Bill Part 10 - Sanitary Sewer

Network A260.7 sum

1.70 All testing relating to Bill Part 11 - Potable Water

Network A260.8 sum

1.71 All testing relating to Bill Part 12 - Irrigation Network

A260.9 sum 1.72 All testing relating to Bill Part 13 - Electrical Network

A260.10 sum 1.73 All testing relating to Bill Part 14 - Street Lighting

Works A260.11 sum

1.74 All testing relating to Bill Part 15 - Duct Network for

Telecommunication Cables A260.12 sum

1.75 All testing relating to Bill Part 16 - Traffic Signal

Control System A260.13 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Testing of Materials (Cont'd)

Testing of the Works; as specified, including tests at manufacturer's works (Cont'd)

1.76 All testing relating to Bill Part 17 - Culverts A260.14 sum 1.77 All testing relating to Bill Part 18 - Building Works A260.15 sum 1.78 Allow for any other testing required as per

specifications not listed above (the Tenderer shall separately list and price below any other clause

considered to have a monetary value) A260.16 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Specified Requirements (Cont'd) Temporary Works

Traffic Diversions as per Specification Clause_

(Item 1.79 to 1.81)

1.79 Establishment A271.1 sum

1.80 Maintenance A271.2 Day

1.81 Removal A271.3 sum

Traffic Regulation (management), safety and control as per Specification Clause _ (Item 1.82 to 1.84)

1.82 Establishment A272.1 sum

1.83 Maintenance A272.2 Day

1.84 Removal A272.3 sum

1.85 Site Screen Fencing including Relocation

as in specification Clause _ A279.1 m

1.86 Extra over for Decorative paint for Sight Screen

Fencing A279.2 m²

1.87 Protection and Upkeep of Site, adjacent areas and

properties, as specification Clause _ A279.3 sum 1.88 Tidying and cleaning the site, as specification

Clause _ A279.4 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Specified Requirements (Cont'd) Temporary Works

1.89 Allow for Co-ordination with Service Authorities, Consultants, Subconsultants and provide all necessary facilities as required as Specification,

Clause_ A279.5 sum

1.90 Allow for Health and Safety requirements as

Specification, Clause_ A279.6 sum

1.91 Allow for compliance with the Construction Environment Management Plan (CEMP) as

Specification, Clause_ A279.7 sum

1.92 Allow for compliance with the Quality Assurance

Standards as Specification, Clause_ A279.8 sum

1.93 Allow for preparing Project Schedule, reports, manuals, submittals and other deliverables as

Specification, Clause_ A279.9 sum

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

Specified Requirements (Cont'd)

Project Sign Board as described in specification, Clause_ (Item 1.94 to 1.96)

1.94 Establishment A279.10 nr

1.95 Maintenance A279.11 Day

1.96 Removal A279.12 nr

Dhs.

Carried to Part Summary

REF AED PART 1 - GENERAL ITEMS (Cont'd)

In document Standard BoQ (UAE - DoT) - CESMM4 .pdf (Page 102-113)