• No results found

1.1 ‐ Sheet piles ‐ Sheet piles are made in Z and flat sections and they are driven two simultaneously

The flat section is designed to interlock with each other to provide strength.  They are suitable for  construction of cellular structures.  The Z section is designed for bending and hence it is more suitable  for construction of retaining walls, bulkheads, cofferdams, and for supporting excavation. Table VII.1  gives representative number of sheet piles driven per hour.   

      Table VII.1 Representative number of sheet piles driven per hour 

         

From Table VII.1, knowing the length of pile and the type of soil, the number of piles that can be driven  in an hour can be calculated.  From this information, the total time required for the job can be 

calculated.  Once the total time is determined, the total cost can be calculated by multiplying the  respective labor, material and equipment cost with the number of hours.   

VII.1.2 Wood piles – Wood piles are classified as load‐bearing and friction piles.  If the pile is driven such  that it rests on the hard ground and supports the superimposed load, it is called load a bearing pile.  If  the soil resistance (skin friction – the friction between the pile and the adjoining soil) is adequate to  oppose the superimposed load on the pile, the pile need not be driven to the hard stratum.  It can be  stopped at such depth where the soil resistance developed is more than the load on the pile.  Such a pile  is called a friction pile.  Wood piles are tapered from an end point diameter of 6 to 8 in to a butt 

diameter of 12 to 14 in.  Lengths vary from 30 to 50 ft.  A preservative treatment of creosote or  pentachlorophenol is generally applied.  A steel boot is placed on the pile end point (tip) to reduce the  tendency of breakage during driving of the pile.  A reasonable allowance for extra piles should be  included in the estimate since the piles may be broken during the driving process.  While costing the  equipment, use of crane, hammer, leads for hammer, and air compressor must be considered.  Table  VII.2 gives approximate number of wood piles that can be driven/hour to full penetration for various  lengths in two different soil resistances. 

       Table VII.2 Representative of wood piles driven per hour, full penetration 

        

From the information from Table VII.2, for a given length of the pile and the nature of soil friction, the  number of piles that can be driven per hour can be obtained.  Then the total time can be calculated by  dividing the total number of piles by the piles/hr obtained form Table VII.2.  Once the total hours for the  job is known, the total cost can be calculated as explained under Section VII.1.1.   Example VII.2 

illustrates the method of estimating the cost for driving wood piles. 

Example VII.2: 

Estimate the cost of furnishing and driving 160 wood piles 36 ft long into a soil having normal frictional  resistance.  The piles will be purchased in 40‐ft lengths and the tops will be cut to the required elevation  after driving.  The piles will be approximately 14 in. in diameter at the butt, and 7 in. at the tip.  The piles  will be treated with creosote preservative at a rate of 2.5 lb/cf, and breakage should be considered.  The  average weight of the pile will be 37 lb/ft.  One crane operator, 3 laborers and one foreman will be on  the job.  The following cost information will apply: piles = $10.85/ft., pile points = $64.78.,  

other equipment and supplies = $9.35/hr., foreman = $25.00/hr., crane operator = $21.67/hr., and  general laborers = $15.56/hr. 

 

Solution:  

Quantity of materials: 

      Number of piles to be driven = 160        Add 5% for breakage =       8        Total =      168 

     Number of linear feet of piles to be purchased = 168 x 40 = 6,720       Number of linear feet of piles to be driven = 160 x 36 =        5,760       Number of boots required = 168 

     Number of piles that must be cut at top = 160  Time to drive piles: 

     From Table VII.2, for 36‐ft long pile to be driven in normal friction to full penetration, the rate       of driving will be 3 piles/hr and time to drive 168 piles = 168/3 = 56 hrs. 

Cost of driving: 

    Material cost: 

       Treated piles = 6,720 ft x $10.85 =       $72,912.00         Pile points = 168 x $64.78 =       10,883.04          Total material cost =       $83,795.04   Equipment cost:  

 

       Crane = 56 hrs x $82.40 =      $4,614.40         Leads for hammer = 56 hrs x $14.63 =       819.28         Hammer = 56 hrs x $10.80 =      604.80         Air compressor = 56 hrs x $14.65 =       820.40         Other equipment and supplies 56 hrs x $9.35 =       523.60        Total equipment cost =       $7,382.48  Labor cost: (Add 8 hrs for the crew to setup and take down equipment)        Foreman ( 56 + 8)= 64 hrs x $25.00 =      $1,600.00        Crane operator = 64 hrs x $21.67 =       1,386.88        General laborers = 64 hrs x 3 x $15.56 =      2,987.52        Total labor cost =      $5,974.40 

   

Summary of costs: 

      Material =      $83,795.04        Equipment =     7,382.48        Labor =       5,974.40        Total cost =    $97,152.92 

      Cost/driven pile = $97,151.92/160 = $607.20  

      Cost/linear foot of driven pile = $97,151.92/5,760 = $16.86      

VII.1.3 Cast‐in‐place concrete piles – These piles are suitable for use on projects where the soil 

conditions are such that the length of penetration is not known in advance and the depth varies among  the piles driven.  Tapered steel shells or steel pipes are driven to the required depth and later filled with  concrete. The shells are left in place but the pipes are withdrawn as the concrete is deposited.  Any  length of pile, up to approximately 125 ft, can be obtained by welding extensions to the shell.  In 

estimating the cost of cast‐in‐place concrete piles, it is necessary to determine the cost of the shells, the  cost of equipment and the cost of labor to drive the shells, and the cost of concrete placed in the shells.  

The rate of driving varies with the length of the piles, topography of the site, class of soil into which they  are driven, type of driving equipment used, spacing of the piles, and weather conditions. 

VII.1.4 Steel piles – These are used where it is necessary to drive piles through considerable depths of  poor soil to reach solid rock or another formation having high load‐bearing properties.  Standard rolled  steel HP sections or wide flange beams are most frequently used.  Driving operations are similar to those  of other piles.  A cap can be installed on the top of piles to reduce the potential for damage during the  driving operation.  Table VII.3 gives approximate number of steel piles driven to full penetration per  hour.  

      Table VII.3 Approximate number of steel piles driven to full penetration per hour 

          

the number of piles that can be driven per hour can be obtained.  Then the total time can be calculated  by dividing the total number of piles by the piles/hr obtained form Table VII.3.  Once the total hours for  the job is known, the total cost can be calculated as explained under Section VII.1.1.   

Example VII.3 illustrates the method of estimating the cost for driving steel piles. 

Example VII.3: 

Estimate the cost of furnishing and driving 180 steel piles, 40 ft long.  The piles weigh 73 lbs/ft and are  driven to full penetration into soil having high frictional resistance.  A foreman with one crane operator  and three laborers will be on the job.  The following cost information will apply: piles = $0.32/lb., pile  caps = $87.00., crane = $82.40/hr., leads for hammer = $14.63/hr., hammer = $10.80/hr., air compressor 

= $14.65/hr., other equipment and supplies = $9.35/hr., foreman = $25.00/hr., crane operator = 

$21.67/hr., and general laborers = $15.56/hr.  Actual working time will be 45 min in one hour. 

Solution: 

Quantity of materials: 

      Linear feet of piles = 180 x 40 = 7,200 

      Total weight of piles = 7,200 x 73 = 525,600 lbs  Time to drive piles: 

      From Table VII.3 for a 75 lb/ft pile and 40 ft long, the driving rate is 2.25piles/hr        Total time for driving piles = 180/2.25 = 80 hrs 

      With only 45 min working in one hour, actual time = 80 x (60/45) = 107 hrs        Rounding this to full 8‐hr day, the total time = 112 hrs 

Cost to drive piles: 

         Material cost: 

       Piles = 525,600 lbs x $0.32 =       $168,192.00         Pile caps = 180 x $87.00 =       15,660.00          Total material cost =       $183,852.00   

       Equipment cost:  

       Crane = 112 hrs x $82.40 =      $9,928.80         Leads for hammer hrs = 112 hrs x $14.63 =       1,638.56           Hammer = 112 hrs x $10.80 =       1,209.60           Air compressor = 112 hrs x $14.65 =      1,640.80         Other equipment and supplies 112 hrs x $9.35 =    1,047.20        Total equipment cost =      $15,464.96 

 

    Labor cost: (Add 8 hrs for the crew to setup and take down equipment)        Foreman (112 + 8 )= 120 hrs x $25.00 =      $3,000.00        Crane operator = 120 hrs x $21.67 =       2,600.40        General laborers = 120 hrs x 3 x $15.56 =       5,601.60        Total labor cost =       $11,202.00  Summary of costs: 

      Material =      $183,852.00        Equipment =      15,464.96        Labor =      11,202.00        Total cost =     $210,518.96 

      Cost/ pile = $210,518.96/180 = $607.20  

      Cost/linear foot of pile = $210,518.96/7,200 = $29.24   

VII.2 Shaft foundation – Shaft foundations are installed by placing reinforced concrete in holes that  have been drilled into the soil.  Drilling rigs mounted on trucks can drill holes from 12 to 96 in diameter  and up to approximately 100 ft depth.  The bottom of the drilled hole can be under‐ reamed with a  belling tool to provide an increased capacity of the foundation.  When drilling into unstable soils or  where water may be present, it is usually necessary to install cylindrical steel casing to hold the sides of  the shaft until the reinforcing steel and concrete are placed.  The casing is pulled from the hole during  placement of the concrete.  Table VII.4 shows representative rates of drilling various diameters of shafts  into soils and Table VII.5 gives approximate rates for drilling into soft rock, such as shales. 

      Table VII.4 Representative rates of drilling shafts in soils 

         

           

           

Vertical reinforcing steel is tied together by horizontal ties or spiral hoops, and lowered into position in  the drilled shaft.  Lugs attached to the reinforcing cage hold them into position at the center of the hole  until concrete is placed.  The cost of shaft foundations will include mobilization of equipment, drilling of  the shaft, casing (if required), fabrication and placement of the reinforcement steel, and depositing  concrete. 

Related documents