Case study;
A sustainable Green Data Centre,
fact or fiction?
Brian O’Hora, BSc MBA MPM Networks & Infrastructure Manager
200 Pearse Street
• Single UPS, no external bypass • 20 low power racks
• Total IT/IS capacity 40kW • Multiple contracts
O’Reilly building
• 4 racks • No backup mains • No fire suppression • Split AC units • Multiple tenants • IT/IS capacity 10kW• Other on campus hosting service providers and needs
• College Strategic Plan 2009/14 action item 6.10 make College a Green campus • College high level risk register
Project trigger
Procurement strategy
•
Initially to include IT/IS
•
Final excluding IT/IS
Project risk management
Contracting approach
•
ICE standard contract
•
D&B
Post project operational risk management approach
•
D&B and maintenance for 4 years (alliance)
Procurement strategy
and risk management
Challenges identified
•
Single shared sub station
•
Over capacity in 200PS DC
•
External routes
•
Indoor physical spaces
•
Outdoor physical spaces
•
Planning permission?
•
Occupied working building
•
Disruptive works window
•
Site establishment
•
Internal/external site access
•
H & S
Pre project feasibility,
proposal and initiation
Feb 2009 - May 2010 - Pre project feasibility, proposal and initiation
June 2010 - Project planning
Aug 31st to March 31st 2011 – Procurement and selection phase, PQQ & ITT
April 2011 - grant of planning permission pending appeal period & final grant May 13th 2011 - final confirmation of funding availability and allocation
July /Aug 2011 – Detailed Design phase - prime contactor instructed to proceed with design including 4th floor roof space
Aug/Dec 2011 - Build phase, construction
Jan/March 2012 – Integration, testing , commissioning, training & familiarisation
March 16th 2011 – Substantial completion & handover
• Green showcase – minimum EU CoC compliance across load range • Resilience and availability - Tier Level 3 desirable
•Scalability and modularity – 25kW to 250kW in 25kW increments and two phases •Phase 1 - 150kW IT load, all single upstream sized for phase 2 - 250kW IT load • Phase 1 - min x16 - 20kW capable racks, plus passive wiring rack and adjacent active network equipment rack
• Energy monitoring; live PUE and detailed monitoring to PDU outlet level • Supporting tools for IaaS; shared service & multi tenancy aligned, capacity management, fault management, performance management, accounting and security management
•
Procurement restricted EU competition, PQQ and ITT and phases
•
Q3 2010 PQQ, 17 responses to PQQ, 9 successful
•
Q4 – 2010 ITT release and site visits scheduled Dec 2010 Jan 2011
•
Q1 Jan 2011 Planning application lodged for generator enclosure
on roof and ITT closes, clarifications & selection starts Feb, preferred
bidder appointed end Q1
•
Q2 2011 Contract negotiations, staged payments agreed, DCC
planning award favourable, detailed design commences, focus on
structural issue
•
Q3 2011 Structural issue resolved, design completed, focus on
long lead time items and disruptive works, rooms cleared & services
relocated, site established
Procurement and
Roof challenges
•
Enabling works
•
Surface condition
•
Leak avoidance
•
Access
•
Heavy equipments - road closure notice PS opposite fire station
•
Capacity issue in main DC
- Additional 3 phase long autonomy UPS-B on general services
- Installation of UPS-B also complicated due to capacity issue
•
Impacts related to single shared sub station with main DC
-
Full day substation down time required to connect new facility
-Failure of emergency backup system in main DC - reschedule
- Impact on cost and schedule
- Additional local and full functional testing requirements
- Multiple failures of contractors generator on second connection
attempt
•Formal witness testing and commissioning of all major systems
• Snagging
• Substantial completion agreement • Security system integration & testing CCTV, door access control, intruder alarm • Fire Alarm and VESDA system
• Familiarization training including (H & S fire detection gas suppression) • End to end Management System & network integration
Integration and
• Modular room - installed within the existing building to enclose the data centre, constructed of a powder coated metal skin internal & external and rockwool infill
• Raised floor, leak detection, no leak prevention
• x20 20kW IT racks plus one passive wiring plus adjacent network equipment rack, 25% uplift of rack space
• Overall power room power budget 150kW
• Dual 3 phase ePDUs per rack, all ePDU outputs monitored (≈ 1,000) for power and kW hours
• Link from room passive wiring rack to main communications room 120 pair SM and 120 pair OM3 MM and 12 pair SM and MM and 24 CAT6A to each rack
• Dual high efficiency UPS, 20min autonomy per UPS at full phase 2 load, 10 year batteries
• 700kVA generator, 32 hr tank at full phase 2 load, dump tank at ground level
• Rear door heat exchangers, 18oC water temp in, 22-24oC return water temp,
• Standalone Dry Air Cooler, partial free cooling below 20-22oC, 100% free cooling at 15oC and below
• Operation of rear door heat exchangers and DAC
Operation of rear door
heat exchangers
• Independently Verified load test results
• PUE below EU CoC over entire range and < 1.2 @ > 33% load, below 15oC OAT
• Broader definition of Green or sustainability includes carbon foot print of input power,
facility PUE and efficiency of network/compute/storage
• Highly integrated UCS network/compute and storage selected as IaaS platform to
populate facility, further encouraging virtualization and discouraging over provisioning
• Design driven by energy efficiency – e.g. RDHC & no leak prevention
• Design options selection driven by energy efficiency - colour or racks, lighting
• Strategic Plan action item 6.10 make College a Green campus aligned, a Green showcase
and shared services aligned, less control over input power sustainability
• A community shared services low latency HA facility offers opportunity to extend energy
sustainability upstream to include low carbon foot print electrical supply
A sustainable
Green Data Centre?
PUE measured (OAT 12-13.7 degrees)
IT load 25kW 50kW 75kW 100kW 125kW 150kW
PUE 1.36 1.17 1.15 1.16 1.13 1.18
Thank you
Brian O’Hora, BSc MBA MPM Networks & Infrastructure Manager