• No results found

Case study; A sustainable Green Data Centre, fact or fiction?

N/A
N/A
Protected

Academic year: 2021

Share "Case study; A sustainable Green Data Centre, fact or fiction?"

Copied!
18
0
0

Loading.... (view fulltext now)

Full text

(1)

Case study;

A sustainable Green Data Centre,

fact or fiction?

Brian O’Hora, BSc MBA MPM Networks & Infrastructure Manager

(2)

200 Pearse Street

• Single UPS, no external bypass • 20 low power racks

• Total IT/IS capacity 40kW • Multiple contracts

O’Reilly building

• 4 racks • No backup mains • No fire suppression • Split AC units • Multiple tenants • IT/IS capacity 10kW

• Other on campus hosting service providers and needs

• College Strategic Plan 2009/14 action item 6.10 make College a Green campus • College high level risk register

(3)

Project trigger

Procurement strategy

Initially to include IT/IS

Final excluding IT/IS

Project risk management

Contracting approach

ICE standard contract

D&B

Post project operational risk management approach

D&B and maintenance for 4 years (alliance)

Procurement strategy

and risk management

(4)

Challenges identified

Single shared sub station

Over capacity in 200PS DC

External routes

Indoor physical spaces

Outdoor physical spaces

Planning permission?

Occupied working building

Disruptive works window

Site establishment

Internal/external site access

H & S

Pre project feasibility,

proposal and initiation

(5)

Feb 2009 - May 2010 - Pre project feasibility, proposal and initiation

June 2010 - Project planning

Aug 31st to March 31st 2011 – Procurement and selection phase, PQQ & ITT

April 2011 - grant of planning permission pending appeal period & final grant May 13th 2011 - final confirmation of funding availability and allocation

July /Aug 2011 – Detailed Design phase - prime contactor instructed to proceed with design including 4th floor roof space

Aug/Dec 2011 - Build phase, construction

Jan/March 2012 – Integration, testing , commissioning, training & familiarisation

March 16th 2011 – Substantial completion & handover

(6)

• Green showcase – minimum EU CoC compliance across load range • Resilience and availability - Tier Level 3 desirable

•Scalability and modularity – 25kW to 250kW in 25kW increments and two phases •Phase 1 - 150kW IT load, all single upstream sized for phase 2 - 250kW IT load • Phase 1 - min x16 - 20kW capable racks, plus passive wiring rack and adjacent active network equipment rack

• Energy monitoring; live PUE and detailed monitoring to PDU outlet level • Supporting tools for IaaS; shared service & multi tenancy aligned, capacity management, fault management, performance management, accounting and security management

(7)

Procurement restricted EU competition, PQQ and ITT and phases

Q3 2010 PQQ, 17 responses to PQQ, 9 successful

Q4 – 2010 ITT release and site visits scheduled Dec 2010 Jan 2011

Q1 Jan 2011 Planning application lodged for generator enclosure

on roof and ITT closes, clarifications & selection starts Feb, preferred

bidder appointed end Q1

Q2 2011 Contract negotiations, staged payments agreed, DCC

planning award favourable, detailed design commences, focus on

structural issue

Q3 2011 Structural issue resolved, design completed, focus on

long lead time items and disruptive works, rooms cleared & services

relocated, site established

Procurement and

(8)

Roof challenges

Enabling works

Surface condition

Leak avoidance

Access

Heavy equipments - road closure notice PS opposite fire station

(9)

Capacity issue in main DC

- Additional 3 phase long autonomy UPS-B on general services

- Installation of UPS-B also complicated due to capacity issue

Impacts related to single shared sub station with main DC

-

Full day substation down time required to connect new facility

-Failure of emergency backup system in main DC - reschedule

- Impact on cost and schedule

- Additional local and full functional testing requirements

- Multiple failures of contractors generator on second connection

attempt

(10)

•Formal witness testing and commissioning of all major systems

• Snagging

• Substantial completion agreement • Security system integration & testing CCTV, door access control, intruder alarm • Fire Alarm and VESDA system

• Familiarization training including (H & S fire detection gas suppression) • End to end Management System & network integration

Integration and

(11)
(12)
(13)
(14)
(15)

• Modular room - installed within the existing building to enclose the data centre, constructed of a powder coated metal skin internal & external and rockwool infill

• Raised floor, leak detection, no leak prevention

• x20 20kW IT racks plus one passive wiring plus adjacent network equipment rack, 25% uplift of rack space

• Overall power room power budget 150kW

• Dual 3 phase ePDUs per rack, all ePDU outputs monitored (≈ 1,000) for power and kW hours

• Link from room passive wiring rack to main communications room 120 pair SM and 120 pair OM3 MM and 12 pair SM and MM and 24 CAT6A to each rack

• Dual high efficiency UPS, 20min autonomy per UPS at full phase 2 load, 10 year batteries

• 700kVA generator, 32 hr tank at full phase 2 load, dump tank at ground level

• Rear door heat exchangers, 18oC water temp in, 22-24oC return water temp,

• Standalone Dry Air Cooler, partial free cooling below 20-22oC, 100% free cooling at 15oC and below

• Operation of rear door heat exchangers and DAC

(16)

Operation of rear door

heat exchangers

(17)

• Independently Verified load test results

• PUE below EU CoC over entire range and < 1.2 @ > 33% load, below 15oC OAT

• Broader definition of Green or sustainability includes carbon foot print of input power,

facility PUE and efficiency of network/compute/storage

• Highly integrated UCS network/compute and storage selected as IaaS platform to

populate facility, further encouraging virtualization and discouraging over provisioning

• Design driven by energy efficiency – e.g. RDHC & no leak prevention

• Design options selection driven by energy efficiency - colour or racks, lighting

• Strategic Plan action item 6.10 make College a Green campus aligned, a Green showcase

and shared services aligned, less control over input power sustainability

• A community shared services low latency HA facility offers opportunity to extend energy

sustainability upstream to include low carbon foot print electrical supply

A sustainable

Green Data Centre?

PUE measured (OAT 12-13.7 degrees)

IT load 25kW 50kW 75kW 100kW 125kW 150kW

PUE 1.36 1.17 1.15 1.16 1.13 1.18

(18)

Thank you

Brian O’Hora, BSc MBA MPM Networks & Infrastructure Manager

References

Related documents

Participants were asked “What should counselors or counseling centers do to make potential Native American clients more comfortable with the idea of getting

HydroMassage is a fully customizable, user-friendly massage system that gives users a powerful, heated, deep-tissue massage in as little as 10 minutes. You enjoy all the

Moreover, in his retranslations of Horace, which are not only classically metrical and unrhymed but also appear much closer to the source text ’s (inverted) word order

As there was no increase in shear force, tenderness and flavor with high residual feed intake, so it is not related with the beef meat quality (Baker et al. 2006).Animal

[ 34 ] Figure 3 provides a comparison of the multimodel best estimate ensemble and individual model ensembles for the time-mean surface precipitation averaged over the active

opposing team, the kick to be taken from the place where the infringement occurred  (see Law 13 - Position of Free Kick)) If, after the ball is in play, the goalkeeper

The variation over the current RBAC state is minimal ( sim = 1 ) and the complexity of the state is almost unchanged at opt = 0.252 (same number of roles and the addition of a

The adoption of sharing economy principles, systems and drivers has the potential to reshape business models and create valuable opportunities for companies – large and