• No results found

OVERVIEW OF THE VICTORIAN SMART METER PROGRAM

N/A
N/A
Protected

Academic year: 2021

Share "OVERVIEW OF THE VICTORIAN SMART METER PROGRAM"

Copied!
15
0
0

Loading.... (view fulltext now)

Full text

(1)

OVERVIEW  OF  THE  VICTORIAN  SMART  

METER  PROGRAM  

A  MANDATED  SMART  METER  ROLL-­‐OUT  

                                   

(2)

 2  |  P a g e    

 

 

This  report  has  been  completed  as  part  of  the  New  Zealand  Smart  Grid  Forum’s  Workstream  D  –  Facilitating  the  Smart   Grid  Forum  Vision.  Report  completed  by  Katherine  Moore.  

(3)

REPORT  SUMMARY  

The  Smart  Grid  Forum  has  been  investigating  potential  challenges  to  a  market-­‐led  model  for  implementing   smart  grid  technologies.  An  initial  part  of  this  work  included  a  review  of  market-­‐led  investments  in  smart   metering  and  ripple  control  upgrades  in  New  Zealand  to  identify  possible  coordination  challenges.  The  Forum   has  discussed  and  published  a  report:  Learnings  from  Market  Investments  in  Ripple  Control  and  Smart  Meters.     This  paper  provides  an  overview  of  a  mandated  roll  out  of  smart  meters  for  comparison;  the  Smart  Meter   Program  in  Victoria,  Australia.    Its  main  purpose  is  to  review  the  various  reports  on  the  Victorian  Smart  Grid   Program  to  identify  lessons  that  might  apply  to  a  mandated  roll-­‐out  of  smart  grid  technologies.    

The  Victoria  Smart  Meter  Program  has  been  widely  reviewed  and  criticised.  Even  as  the  program  was  at  its   very  beginning  the  Victorian  Auditor-­‐General’s  Office  (VAGO)  pointed  to  failures  in  project  governance,   customer  engagement  and  economic  analysis  of  the  costs  and  benefits.    VAGO’s  audit,  cost  blow-­‐outs,   customer  concerns  led  to  a  government  review  of  the  program  and  subsequent  changes  to  the  program.  As   the  program  has  progressed,  there  have  been  further  concerns  highlighted  by  the  Productivity  Commission.       The  main  issues  highlighted  by  the  reviews  are  summarised  below.  

Customer  implications  and  engagement  

• There  was  insufficient  engagement  and  consultation  with  customers  

• Customers  have  faced  (increasing)  costs  before  they  can  take  advantage  of  the  benefits   • Customers  did  not  have  choice  in  meter  service.  

Cost  concerns  

• Cost  estimates  have  risen  through  the  program  from  an  initial  estimate  of  AUS$1.6  billion  to  over   AUS$2  billion.  

• Incentives  for  distributors  to  contain  costs  seemed  to  have  been  weak     • Changes  and  delays  to  the  program  have  increased  costs  

• Flaws  in  cost–benefit  analysis  

• Lack  of  competition  in  metering  services  and  misalignment  of  risks  and  rewards.    

   

(4)

CONTENTS  

1.  Introduction  ...  2

 

2.  Background  to  the  Victoria  smart  meter  roll-­‐out  ...  2

 

3.  HIgh-­‐Level  Comparison  with  New  Zealand’s  SMart  MEter  roll  out  ...  4

 

4.  The  Victoria  smart  meter  roll-­‐out  ...  5

 

5.  National  and  other  state  smart  metering  ...  8

 

The  national  AMI  program  ...  8

 

Other  State  developments  ...  9

 

6.  Summary  of  issues  ...  10

 

(5)

1.  INTRODUCTION    

The  Smart  Grid  Forum  has  been  investigating  potential  challenges  to  a  market-­‐led  model  for  implementing   smart  grid  technologies.  An  initial  part  of  this  work  included  a  review  of  market-­‐led  investments  in  smart   metering  and  ripple  control  upgrades  in  New  Zealand  to  identify  possible  coordination  challenges.  The  Forum   has  discussed  and  published  a  report:  Learnings  from  Market  Investments  in  Ripple  Control  and  Smart  Meters.     This  paper  provides  an  overview  of  a  mandated  roll  out  of  smart  meters  for  comparison;  the  Smart  Meter   Program  in  Victoria,  Australia.    

The  rest  of  this  report  provides:  

-­‐ Background  to  the  Victoria  electricity  market  and  the  Smart  Meter  Program   -­‐ A  high-­‐level  comparison  of  the  New  Zealand  and  Victorian  models  

-­‐ An  overview  of  the  Victoria  smart  meter  roll-­‐out  and  the  reviews  and  reports  by  date   -­‐ An  overview  of  national  and  other  Australian  state  smart  meter  developments  

-­‐ A  summary  of  the  Victoria  Smart  Meter  Program  issues  identified  by  regulators,  advisory  bodies  or   consultants.  

This  paper  draws  on  other  reports  and  reviews  of  the  Victorian  Smart  Meter  Program  to  provide  an  overview   of  the  issues  or  lessons  from  the  mandated  program.  There  are  different  ways  to  mandate  and  run  a  smart   meter  roll-­‐out;  some  of  the  issues  associated  with  the  Victorian  programme  may  not  apply  to  other  mandated   programmes.  

2.  BACKGROUND  TO  THE  VICTORIA  SMART  METER  ROLL-­‐OUT  

Victoria  was  the  first  jurisdiction  in  Australia  to  consider  a  state-­‐wide  rollout  of  smart  meters.  

In  New  Zealand,  the  switch  to  smart  meters  was  largely  driven  by  electricity  retailers  seeking  cost  or  service   advantages  and  customers  could  opt  out.  In  comparison,  the  smart  meter  roll-­‐out  in  Victoria  was  mandated  by   the  state  government.      

In  2004,  the  Victorian  Essential  Service  Commission  (ESC),  mandated  the  rollout  of  manually  read  smart  meters   through  Victoria,  termed  the  'Interval  Meter  Rollout'  (IMRO)  program.  However,  the  Victorian  Department  of   Infrastructure  (DoI)  and  the  electricity  supply  industry  had  the  view  that  developments  in  metering  technology   meant  that  the  functionalities  of  the  IMRO  could  potentially  be  expanded  to  produce  more  overall  benefits.   Subsequently  in  2005,  DoI  and  the  electricity  supply  industry  commissioned  a  cost-­‐benefit  study  to  examine   the  net  benefits  for  adding  advanced  functionality  to  the  IMRO  mandate.  This  became  known  as  the  Advanced   Interval  Metering  Rollout  study.  

As  a  result  of  this  study,  the  Parliament  passed  an  amendment  to  the  Electricity  Industry  Act  in  August  2006   that  gave  Government  the  authority  to  make  ‘Orders-­‐in-­‐Council’  (OIC)—which  are  enforceable  orders  by  the   executive  branch  of  government—to  establish  a  range  of  requirements  for  the  deployment  of  Advanced   Metering  Infrastructure  (AMI).  

(6)

 3  |  P a g e     In  August  2007  the  government  issued  an  OIC,  setting  up  the  initial  regulatory  framework  for  cost  recovery   and  installation  targets  for  Victoria’s  five  privately-­‐owned  distributors.    

The  OIC  established  a  regulated  cost  recovery  framework  to  provide  certainty  for  electricity  distributors  to   commit  to  AMI  deployment  expenditure  through  to  December  2013.  The  OIC  required  each  distributor  to   submit  budget  and  pricing  information  to  the  Australian  Energy  Regulator  (AER).  

A  further  OIC  in  November  2007  mandated  the  initial  minimum  specifications  for  functionality,  performance   and  service  levels  of  the  smart  meters.    

Department  of  Primary  Industries  (DPI)  coordinated  technology  trials  to  identify  communication  systems  that   would  suit  the  AMI  project  objectives  and  produced  a  technology  trial  report  in  November  2007.    

DPI  transferred  the  AMI  project  governance  to  the  Victorian  electricity  industry  in  October  2007  through  an   Industry  Steering  Committee  with  an  independent  chairperson.  This  steering  committee  initially  coordinated   implementation  and  its  members  included  representatives  of  electricity  distribution  and  retail  businesses,  as   well  as  consumer  advocacy  groups  and  relevant  energy  policy  and  regulatory  agencies.  

The  Government  did  not  impose  a  particular  technology  for  the  smart  meters  installed,  although  it  did   prescribe  a  relatively  high  level  of  minimum  functionality  of  the  meters  and  standards  for  associated  service  

G

OVERNMENT

,

 REGULATORS  AND  ADVISORY  BODIES

 

Various  government,  regulatory  and  advisory  bodies  operate  in  the  electricity  market  both  at  the  Federal   and  State  level.    

The  Council  of  Australian  Governments  (COAG)  is  the  peak  intergovernmental  forum  in  Australia.  The  role   of  COAG  is  to  promote  policy  reforms  that  are  of  national  significance,  or  which  need  co-­‐ordinated  action   by  all  Australian  governments.  The  COAG  Energy  Council  was  set  up  by  COAG  to  provide  a  forum  for   collaboration  on  developing  an  integrated  and  coherent  national  energy  policy.  The  COAG  Energy  Council   superseded  the  Standing  Council  on  Energy  and  Resources  which  superseded  the  Ministerial  Council  on   Energy  (MCE).  

The  Australian  Energy  Regulator  (AER)  regulates  energy  markets  and  networks  under  National  Energy   Market  (NEM)  legislation  and  rules.  (The  NEM  interconnects  five  regional  market  jurisdictions  (Queensland,   New  South  Wales,  Victoria,  South  Australia  and  Tasmania)).      

Australian  Energy  Market  Commission  (AEMC)  is  the  rule  maker  for  Australian  electricity  and  gas  markets.   It  makes  and  amends  the  National  Electricity  Rules  (which  include  the  regulation  of  distributors),  National   Gas  Rules  and  National  Energy  Retail  Rules.  It  also  provides  market  development  advice  to  governments.   The  Essential  Services  Commission  (ESC)  is  the  independent  regulator  of  essential  services  in  Victoria.  It   regulates  the  retail  energy  industry  in  Victoria  and  issues  energy  distribution  and  retail  licenses.    

The  Victorian  Auditor-­‐General’s  Office  (VAGO).  The  Victorian  Auditor-­‐General  is  an  independent  officer  of   the  Victorian  Parliament,  appointed  to  examine  the  management  of  resources  within  the  public  sector  on   behalf  of  Parliament  and  Victorians.  

The  Productivity  Commission  is  an  advisory  body  providing  independent  advice  and  information  to   governments.  The  Commission  is  an  agency  of  the  Australian  Government.    

(7)

levels.  These  meters  must  conform  to  minimum  functionality  and  performance  levels  for  the  AMI  systems   across  the  following  elements:    

• Meter  configurations  

• Remote  and  local  reading  of  meters   • Supply  disconnect  and  reconnect   • Time  clock  synchronisation   • Load  control  

• Meter  loss  of  supply  detection  and  outage  detection   • Quality  of  supply  and  other  event  recording  

• Supply  capacity  control  

• Interface  to  the  home  area  network  (HAN).  

The  Government  expected  that  the  rollout  would  lower  electricity  prices  for  consumers,  increase  retail   competition,  improve  service  quality  and  increase  the  efficiency  of  electricity  suppliers.  However,  the  rollout   experienced  problems.  

3.  HIGH-­‐LEVEL  COMPARISON  WITH  NEW  ZEALAND’S  SMART  METER  ROLL  OUT  

The  Victorian  Smart  Meter  Program  is  an  example  of  a  mandated  roll  out.  In  New  Zealand,  the  switch  to  smart   meters  was  driven  by  retailers  seeking  cost  efficiencies  and  competitive  advantage  in  the  retail  electricity   market.  Both  Jurisdictions  have  seen  similar  technology  smart  meters  installed  at  the  majority  of  electricity   consumers’  premises  over  broadly  similar  timeframes.    

The  two  approaches  have  differences  in  how  service  levels  and  functionality  are  determined,  in  the  way  the   costs  are  handled  and  passed  through  to  customers,  and  who  bears  the  cost  and  technology  risks.  These   differences  are  summarised  below.  

  Victoria   New  Zealand  

Framework  overview   The  distributors  are  charged  with   installing  smart  meters  at  all  customer   premises.  

There  is  no  mandate  to  install  smart   meters.  Electricity  retailers  can  choose   to  switch  to  smart  meters  and  whether   or  not  the  customer  can  opt  out.   Service  level  and  

functionality  

The  Government  prescribed  a   standard  minimum  service  level  and   functionality.  

Individual  retailers  determined  the   required  services  and  service  levels  to   be  received  (eg  data  frequency,  file   format,  event  services.)  

Costs   Costs  passed  directly  to  consumer  as  a   line  item  on  their  bill.  The  costs  are   reviewed  by  the  AER  annually  and   range  from  AUS$109  to  $226  for  2015   (per  meter  per  annum).  

Costs  are  generally  not  identified  on   customers  bill.  Retailers  have  signed  8   to  15  year  service  agreements  with   metering  service  providers  with  annual   fees  of  around  $60  to  $120  per  year.     Risks   The  risks  of  meter  deployment  and  

system  cost  overruns  and  technology   risk  are  borne  by  customers.  The   distributors  have  already  recovered   portions  of  the  cost  overruns  from   customers,  and  will  continue  to   recover  the  costs.    

The  metering  service  provider  or   retailer,  depending  on  their  agreement,   carries  the  risks  of  meter  deployment   and  system  cost  overruns  and  the  risks   that  their  technology  is  superseded,  or   that  their  meter  is  switched  out  by  a   new  retailer.  

(8)

 5  |  P a g e  

4.  THE  VICTORIA  SMART  METER  ROLL-­‐OUT    

The  smart  meter  roll-­‐out  began  in  late  2009.    Distributors  were  mandated  to  install  smart  meters  at  all  homes   and  businesses  by  Dec  2013.      

Two  major  types  of  smart  metering  systems  have  been  deployed  by  the  distributors.  The  first  is  based  on  RF   Mesh  technology  created  by  Silver  Springs  Networks,  and  the  second  is  WiMAX  based  on  technology  created   by  GridNet  technology  is  being  deployed  by  SP  AusNet,  while  the  remaining  four  distributors  are  using  RF   Mesh.  

The  roll-­‐out  of  smart  meters  in  Victoria  is  now  effectively  complete  with  almost  2.8  million  meters  installed   across  the  state.    There  have  been  a  number  of  changes  to  the  programme  prompted  by  customer  concerns,   cost  overruns.  

This  section  steps  through  the  reviews  and  decisions  affecting  the  roll-­‐out.  More  detailed  information  and   access  to  reports  is  given  on  the  Smart  Meters  in  Victoria  website,  Department  of  Economic  Development,   Jobs,  Transport  and  Resources,  Victoria  http://www.smartmeters.vic.gov.au/home  

NOV  2009  VICTORIAN  OFFICE  OF  THE  AUDITOR  GENERAL  (VAGO)  

AUDIT

 

At  the  beginning  of  the  roll-­‐out,  an  audit  by  VAGO  raised  concerns  and  made  a  series  of  recommendations  to   change  the  programme.    The  concerns  were  in  the  following  areas:  

• project  governance    

• the  economic  merits  of  the  roll  out  

• implementation  risks  including  technology  risks   • consumer  implications  and  engagement.  

2010  COST-­‐BENEFIT  REPORTS  

The  Victorian  Government,  through  the  Department  of  Primary  Industries,  commissioned  three  assessments   to  update  previous  studies  into  the  costs  and  benefits  of  the  AMI  Program.  These  three  assessments  are   consolidated  in  a  report  by  Oakley  Greenwood,  Benefits  and  Costs  of  the  Victoria  AMI  Program,  Aug  2010.  This   concluded  that  there  was  a  sound  economic  basis  for  the  AMI  Program.  

2010  MORATORIUM  ON  TIME  OF  USE  PRICING  

In  March  2010  the  Victorian  Government  arranged  a  moratorium  by  Victorian  electricity  distribution   businesses  on  the  introduction  of  time  of  use  pricing,  as  enabled  by  AMI.  The  moratorium  was  introduced  in   response  to  community  concern  about  the  potential  distributional  impacts  of  time  of  use  pricing.  

2011  REVIEW  

In  June  2011,  the  Victorian  Government  announced  a  review  by  the  Department  of  Treasury  and  Finance  of   the  AMI  programme,  largely  in  response  to  the  VAGO  2009  audit,  and  increasing  customer  concerns.       The  Review  found  that  the  most  responsible  option  was  to  continue  the  meter  rollout,  with  improvements   aimed  at  bringing  greater  benefits  to  households.  

(9)

One  part  of  the  review  was  an  independent  cost-­‐benefit  analysis  by  Deloitte,  Advanced  Metering  

Infrastructure  Customer  Impacts  Study  ,  2011  which,  although  estimating  the  program  might  have  a  net  cost  to   consumers,  recommended  that,  at  the  current  stage  of  the  program’s  life,  the  maximum  benefit  would  be   delivered  by  continuing  the  rollout.  The  review’s  other  main  findings  were:  

• smart  meters  are  safe  and  fall  well  within  the  requirements  for  electromagnetic  and  radiofrequency   emissions  

• consumers  can  benefit  from  an  orderly  introduction  of  flexible  pricing,  including  the  continuation  of   flat  rates  

• greater  customer  engagement  is  required  to  better  explain  smart  meters  and  their  operation.    

The  Victorian  Government  made  the  following  main  changes  to  the  AMI  Program,  now  rebranded  the  Smart   Meter  Program:  

• subsidising  in-­‐home  displays  to  help  households  control  their  energy  bills,  with  some  basic  in-­‐home   displays  available  at  low  cost  by  mid-­‐2012  

• progressively  offering  remote  connections  for  Victorians  moving  house  from  1  Jan  2012,  saving   customers  around  $15,  or  more  than  $100  after  hours  

• extending  the  delay  on  the  introduction  of  flexible  pricing  until  at  least  2013,  to  allow  time  for   consumers  to  learn  more  about  their  options  

• ensuring  Victorian  consumers  can  choose  to  remain  on  flat  rates  even  when  flexible  pricing  is   introduced  

• toughening  the  regulation  of  smart  meter  cost  recovery  by  distribution  businesses  through  removing   the  automatic  allowance  for  cost  overruns  of  10  to  20  per  cent    

• providing  greater  oversight  by  government  and  giving  consumer  and  welfare  groups  a  stronger  voice   in  the  smart  meter  rollout  process  through  a  new  Ministerial  Advisory  Council.  

2011  

AER  DETERMINATION

 ON  SMART  METER  CHARGES  FOR  2012-­‐15  

The  Australian  Energy  Regulator  issued  its  final  determination  on  applications  from  the  Victorian  electricity   distribution  businesses  for  ‘smart  meter’  budgets  and  forecast  charges  over  the  period  2012  to  2015.  The   estimated  charges  ranged  from  around  AUS$90  to  AUS$220  per  year.  The  AER  expected  at  the  time  that  the   distributors  would  spend  over  AUS$2  billion  combined  from  2009  to  2015,  compared  to  a  2010  estimate  of   AUS$1.  6  billion.    SP  AusNet’s  application  and  the  AER  determination  was  particularly  controversial,  the  costs   of  SP  AusNet’s  WiMAX  technology  had  overrun  significantly.  The  AER  refused  AUS$107  million  of  SP  AusNet’s   application.    

The  AER  considered  SP  AusNet  should  have  reconsidered  its  decision  to  proceed  with  its  AMI  rollout  using   WiMAX  communications  technology.  Following  a  legal  challenge  to  this  decision,  by  SP  AusNet,  the  Australian   Competition  Tribunal  required  the  AER  to  revisit  certain  parts  of  its  decision  in  April  2012.  

The  Tribunal  agreed  with  the  AER  that  a  reasonable  business  in  SP  AusNet’s  circumstances  would  have   undertaken  a  thorough  reconsideration  of  its  communications  solution  when  it  realised  that  its  original  cost   estimates  had  blown  out.  However,  the  Tribunal  required  the  AER  to  examine  the  cost  of  changing  to  another   technology,  including  whether  switching  costs  would  have  been  incurred  if  SP  AusNet  had  changed  

technology.  The  amount  of  funds  under  consideration  for  the  communications  technology  amounted  to   $72.2m.  

(10)

 7  |  P a g e   The  AER  made  its  revised  determination  on  4  February  2013.  The  AER  found  that  a  reasonable  business  in  SP   AusNet’s  circumstances  would  have  switched  communications  technology  in  early  2011.  However,  the  AER   found  that  the  allowance  it  originally  approved  for  2011  would  have  been  more  than  sufficient  to  cover  the   costs  of  switching  to  the  alternative  technology  in  that  year.  The  AER  considered  customers  should  not  pay   more  for  cost  overruns  because  of  SP  AusNet’s  choice  of  communications  technology.  The  AER  denied  SP   AusNet  the  $72.2m  it  had  sought.  

APRIL  2013  

PRODUCTIVITY  COMMISSION  REPORT

 

The  Productivity  Commission’s  report,  Electricity  Network  Regulatory  Frameworks,  Productivity  Commission  

Inquiry  Report,  April  2013,  covered  wide  issues  around  network  regulation,  including  smart  meter  issues  and  

was  critical  of  the  Victorian  Smart  Meter  program.      

By  this  time  there  had  been  a  consumer  backlash  against  smart  meters  with  consumers  concerned  about   privacy,  safety,  costs,  the  lack  of  choice,  and  that  costs  were  increasing.  The  report  noted1  issues  around:  

• Consumer  engagement  

• The  impact  of  the  moratorium  on  time  of  use  tariffs  on  efficiency  gains   • Excessive  initial  optimism  and  high  costs  

• Incentives  for  distributors  to  contain  costs  seemed  to  have  been  weak   • Flaws  in  cost–benefit  analysis  

DEC  2014  

New  regulations  announced  in  December  2014  require  electricity  distributors  to  continue  to  install  smart   meters  after  the  end  of  2013.  

FUTURE:  UPDATED  VAGO  REPORT  EXPECTED  

Between  2009  and  2014,  Victoria’s  electricity  distribution  businesses  have  installed  roughly  2.8  million  smart   meters  at  an  estimated  cost  of  $2  billion.    VAGO  is  currently  preparing  an  audit  to  assess  the  extent  to  which   deficiencies  in  the  AMI  program  have  been  addressed,  and  whether  benefits  for  consumers  are  being  realised.   The  audit  will  assess  whether  the  Department  of  State  Development,  Business  and  Innovation:  

• has  effectively  addressed  recommendations  from  VAGO’s  Towards  a  ‘smart  grid’—the  rollout  of   Advanced  Metering  Infrastructure  report  

• can  demonstrate  that  the  AMI  program  is  delivering  expected  consumer  benefits  and  is  set-­‐up  to   maximise  longer-­‐term  benefits.  

The  report  is  expected  to  be  tabled  in  June  2015.  

FUTURE:  CHANGES  TO  THE  NATIONAL  REGULATORY  FRAMEWORK  FOR  METERING  

The  AEMC  is  currently  working  on  rule  changes  (AEMC  consultation  paper  on  rule  change)  to  introduce  a   national  regulatory  framework  for  competitive  metering.  (See  section  below).  

                                                                                                                                       

1  Volume  2,  box  10.2  Productivity  Commission,  Electricity  Network  Regulatory  Frameworks,  Productivity   Commission  Inquiry  Report,  April  2013  

(11)

5.  NATIONAL  AND  OTHER  STATE  SMART  METERING  

THE  NATIONAL  AMI  PROGRAM  

In  April  2007,  the  Council  of  Australian  Governments  (COAG)  committed  to  a  national  roll-­‐out  of  electricity   smart  meters  to  areas  where  benefits  could  be  demonstrated  to  outweigh  costs.  These  areas  were  chosen   from  a  cost-­‐benefit  analysis  which  looked  at  different  markets  in  each  state  and  territory  and  the  

circumstances  of  different  groups  of  consumers.  The  national  AMI  cost-­‐benefit  report  was  released  in  mid-­‐ 2008  and  found  a  positive  case  for  Victoria  (and  for  most  other  jurisdictions).    

The  National  Smart  Metering  Program  (NSMP2)  was  established  by  the  Ministerial  Council  on  Energy  (MCE)  to   develop  a  framework  for  an  efficient,  flexible  and  open-­‐access  smart  metering  infrastructure  across  the   national  electricity  market  (NEM).  

From  mid-­‐2008,  the  MCE  worked  with  industry  stakeholders  (including  electricity  retailers,  distribution   businesses,  metering  providers,  consumer  organisations,  market  operators  and  jurisdictions)  to  deliver:  

• the  Smart  Metering  Infrastructure  (SMI)  Minimum  Functionality  Specification  

• proposed  changes  to  the  National  Electricity  Rules  to  support  a  mandated  rollout  of  smart  metering   • draft  issue  change  forms  for  changes  to  the  NEM  Procedures  to  support  the  provision  of  smart  

metering  services  

• an  evaluation  of  home  area  network  (HAN)  interface  standards  

• advice  to  the  MCE  in  relation  to  in  home  displays  guidelines  and  direct  load  control  in  priority   appliance  guidelines  

• pilots  and  trials  status  reports  for  2008,  2OO9,2O1O  

• business,  consumer  and  technology  reporting  frameworks  to  support  the  consistent  reporting  and   sharing  of  information  from  pilots  and  trials  

• the  smart  metering  future  pilots  and  trials  report  

• a  national  testing  framework  for  the  testing  of  changes  to  NEM  systems  to  support  smart  metering   services.  

In  April  2011,  the  National  Stakeholder  Steering  Committee  (NSSC)  for  the  National  Smart  Metering  Program   confirmed  completion  of  the  majority  of  agreed  NSMP  deliverables,  handover  of  remaining  deliverables  to   responsible  parties,  and  the  appropriateness  of  formally  closing  the  NSSC.    

In  August  2011,  the  Australian  Energy  Market  Operator  (AEMO)  and  the  electricity  industry's  Information   Exchange  Committee  put  on  hold  the  ongoing  NSMP  work  that  had  been  transferred  to  it  from  the  NSSC.  This   work,  the  development  of  NEM  procedures,  could  not  proceed  efficiently  until  key  policy  issues  were  resolved.   Despite  COAG’s  commitment  to  the  development  of  a  national  smart  meter  legislative  and  regulatory  

framework,  other  jurisdictions  have  been  more  cautious  than  Victoria  with  its  implementation,  and  the  AEMC   is  working  on  rule  changes  to  enable  contestable  metering  service,  partly  as  a  result  of  the  Victoria  experience.  

CHANGES  TO  THE  NATIONAL  REGULATORY  FRAMEWORK    

The  Ministerial  Council  on  Energy  (which  was  superseded  by  the  Standing  Council  on  Energy  and  Resources   (SCER))  commissioned  the  Australian  Energy  Market  Commission  (AEMC)  in  March  2011  to  undertake  a  review                                                                                                                                          

(12)

 9  |  P a g e   of  the  market  and  regulatory  arrangements  across  the  electricity  supply  chain  to  facilitate  efficient  investment   in,  operation  and  use  of  DSP  in  the  NEM3.  

In  October  2007  the  Australian  Energy  Market  Commission  (AEMC)  initiated  a  three-­‐stage  review  of  whether   the  demand-­‐side  of  the  National  Electricity  Market  (NEM)  is  participating  effectively  and  efficiently  in  the   market.  

The  AEMC  presented  its  final  Power  of  Choice  recommendations  (Nov  2012)  to  the  Standing  Council  on  Energy   and  Resources  (SCER),  now  known  as  the  COAG  Energy  Council.  One  of  these  recommendations  was  to  make   rule  changes  to  introduce  a  national  regulatory  framework  for  competitive  metering;  this  will  enable  retailers   and  metering  providers  to  contest  metering  service  provision.  

The  AEMC  is  currently  working  on  the  rule  changes  (AEMC  consultation  paper  on  rule  change).    

OTHER  STATE  DEVELOPMENTS  

NEW  SOUTH  WALES  

New  South  Wales  has  recently  announced  a  market-­‐led  roll  out  policy  under  which  retailers  and  metering   providers  will  be  able  to  offer  customers  smart  meters.  This  followed  a  2  year  consultation  and  the  New  South   Wales    

As  stated  in  the    announcement  from  the  Minister  of  Energy  and  Resources:  ‘The  policy  follows  the  lessons   learned  from  the  troubled  rollout  of  smart  meters  in  Victoria….Not  only  were  Victorian  customers  not  given  a   choice  of  meters,  they  were  also  charged  the  upfront  cost  of  the  meter  and  its  installation,  a  decision  which  is   still  costing  them.’  

QUEENSLAND  

Queensland  has  recently  published  a  Government  Discussion  Paper:  Powering  Queensland’s  Future.     The  paper  rules  out  a  mandated  approach  to  smart  meter  roll-­‐out:    

‘There  are,  broadly  speaking,  two  approaches  to  the  rollout  of  advanced  metering  technology.  One  is  a   mandated,  distributor-­‐led  rollout.  This  approach  was  taken  in  Victoria  where  it  was  criticised  as  not  being   based  on  a  clear  economic  case  and  not  well  communicated  to  customers.  The  alternative  is  a  customer-­‐driven   rollout,  where  a  range  of  different  service  providers  can  compete  to  offer  customers  advanced  metering   services  and  associated  product  choices.  Customers  can  choose  to  adopt  the  technology  based  on  their   assessment  of  the  benefits.  Based  on  the  Victorian  experience,  the  Queensland  Government  has  ruled  out  a   mandated  rollout  of  advanced  meters  in  Queensland  and  will  support  the  customer-­‐driven  approach.’  

SOUTH  AUSTRALIA  

South  Australian  Government  issued  a  consultation  paper  in  January  2014,  but  has  said  it  will  decide  its  policy   after  the  AEMC  determination.      

                                                                                                                                       

3  http://www.aemc.gov.au/Media/docs/MCE%20Terms%20of%20Reference-­‐35e6904a-­‐e39d-­‐4348-­‐8ad5-­‐ 1a7970af354d-­‐0.pdf    

(13)

WESTERN  AUSTRALIA  

The  Economic  Regulation  Authority  (WA)  approved  stage  government-­‐owned  company  Westpower  installing   smart  meters  but  budget  cuts  have  stalled  installation.  A  recent  review  by  the  Electricity  Supply  Association  of   Australia  has  recommended  private  operators  are  given  the  chance  to  install  the  meters.  

TASMANIA  

Previous  analysis  indicated  that  a  mandated  roll  out  of  smart  meters  in  Tasmania  would  come  at  a  higher  cost   than  the  benefits  it  would  deliver.  A  recent  Energy  Strategy  Issues  Paper  from  the  Department  of  State  Growth     stated  that  ’with  technological  developments  and  changing  consumer  preferences  and  responsiveness  to  price   signals,  smart  meters  to  support  tariff  reform  could  become  viable.’  

6.  SUMMARY  OF  ISSUES    

The  Victoria  Smart  Meter  Program  has  been  widely  reviewed  and  criticised.  Even  as  the  program  was  at  its   very  beginning  the  Victorian  Auditor-­‐General’s  Office  (VAGO)  pointed  to  failures  in  project  governance,   customer  engagement  and  economic  analysis  of  the  costs  and  benefits.    VAGO’s  audit,  cost  blow-­‐outs,   customer  concerns  led  to  a  government  review  of  the  program  and  subsequent  changes  to  the  program.   As  the  program  has  progressed,  there  have  been  further  concerns  highlighted  by  the  Productivity  Commission.   Victoria  continued  with  the  program,  and  it  is  now  all  but  complete.  In  the  meantime,  other  Australian  states   have  been  more  cautious.  Recently  New  South  Wales  Minister  for  Energy  Resources  referred  to  the  ‘troubled   roll-­‐out  of  smart  meters  in  Victoria’  and  New  South  Wales,  with  Queensland  and  potentially  other  states  are   now  favouring  a  market-­‐led  roll-­‐out.  

The  problems  have  focused  on  two  key  areas:     • customer  implications  and  engagement   • cost  concerns.      

CONSUMER  IMPLICATIONS  AND  ENGAGEMENT  

The  Victorian  Auditor-­‐General’s  Office  questioned  the  adequacy  of  consultation  with  consumers  in  the  process   leading  up  to  the  rollout.  After  the  rollout  was  in  progress,  the  review  by  Deloitte)  and  a  broader  Government   review  emphasised  the  need  for  customer  engagement  so  that  people  were  aware  of  the  benefits  of  the   meters.  In  response,  the  Government  announced  it  was  giving  consumer  and  welfare  groups  a  voice  in  the   smart  meter  rollout  through  a  new  Ministerial  Advisory  Council,  as  well  as  undertaking  other  measures  (such   as  a  smart  meter  website  and  a  price  comparison  web  portal).    

There  has  been  a  backlash  amongst  consumers  and  media  triggered  by  safety,  privacy  and  cost  concerns.   Under  the  mandated  arrangement,  customers  did  not  have  a  choice,  were  faced  with  paying  for  the  smart   meters  before  they  could  take  advantage  of  the  benefits  of  smart  meters,  and  have  seen  costs  rise  from  an   estimated  $AUS  1.6  billion  to  over  $2  billion.  

The  moratorium  on  ‘time  of  use’  pricing,  whilst  introduced  in  response  to  concerns  about  the  impacts  on   consumers,  contributed  to  delays  in  consumers  realising  the  benefits.  

(14)

 11  |  P a g e   about  the  impacts  on  consumers,  particularly  vulnerable  consumers.  In  the  view  of  the  Productivity  

Commission,  the  moratorium  added  further  delays  to  the  realisation  of  benefits  from  the  smart  meter  rollout.   Following  analysis  of  the  customer  impacts  of  time-­‐based  pricing,  the  Government  has  since  decided  that   flexible  pricing  would  be  encouraged  on  a  voluntary  basis  for  residential  consumers.    

COST  CONCERNS  

Despite  initial  optimism  that  a  smart  meter  rollout  would  produce  net  benefits,  the  Deloitte  analysis  found   that  the  rollout  would  be  likely  to  incur  a  net  cost  over  its  lifetime.  Nevertheless,  given  that  a  large  share  of  the   investments  was  sunk,  that  study  found  that  a  continued  rollout  would  pass  a  cost–benefit  test.  The  Deloitte   study  was  preceded  by  many  other  studies  looking  at  aspects  of  the  project  (Futura,  EMCa  and  Strata  Energy   Consulting  2010;  and  Oakley  Greenwood    which  summarised  the  earlier  studies),  which  suggested  positive  net   benefits.    

It  appears  that  costs  were  significantly  underestimated  (in  the  view  of  both  VAGO  and  Deloitte).  For  example,   the  Deloitte  study  found  rollout  costs  of  $2.2  billion  compared  with  a  2010  study  estimate  of  $1.6  billion.  This   is  around  $800  compared  with  around  $600  per  meter  based  on  installing  2.9  million  meters  at  around  2.7   million  small  customer  points.    

From  2009  to  2015,  the  AER  estimated  that  distributors  would  ultimately  spend  over  $2  billion  on  the  rollout.   It  also  appears  that  initial  benefits  were  over-­‐estimated.  For  example,  Deloitte  estimated  benefits  of  just  over   $2  billion,  while  the  Futura  (2009)  study  estimated  $2.6  billion.      

From  a  customer  perspective  the  annual  charges  for  smart  meters  are  significant.  These  are  included  as  a   separate  line  item  on  customers’  bills.  The  2015  fees  approved  by  the  AER  are:  

• Jemena  (northwest  suburbs):  $226.30  up  $32.50  

• AusNet  Services  (eastern  suburbs,  northeast  and  eastern  Victoria):  $205.50  up  $45.30   • United  Energy  (south-­‐eastern  suburbs  and  Mornington  Peninsula)  $154.50  up  $12.80   • CitiPower  (CBD,  inner  suburbs):  $115.90  down  60c  

• Powercor  (western  suburbs,  western  and  northwest  Victoria):  $109.40  down  $5.90   Studies,  commentators,  and  the  distributors  have  given  a  number  of  reasons  for  the  cost  blow-­‐outs.  

Incentives  for  distributors  to  contain  costs  seemed  to  have  been  weak    

(VAGO,  AER,  Productivity  Commission)  Victorian  cost-­‐recovery  regulations  for  smart  meters  (overseen   by  the  AER)  effectively  took  the  form  of  cost  pass-­‐through.  This  provides  few  incentives  for  cost   management.  In  2012,  the  AER  approved  proposals  by  the  distributors  to  increase  their  smart  meter   charges,  noting  that  the  higher  charges  were  attributable  to  all  the  distributors  spending  more  than   their  approved  expenditure  allowances  in  2011.  Some  distributors  spent  close  to  120  per  cent  of  their   approved  budget,  which  was  allowed  by  the  Victorian  regulation.  The  Victorian  Government  decided   in  late  2011  to  tighten  its  cost  recovery  regulation,  including  removing  the  cost  overrun  allowance  and   reversing  the  onus  of  proof  of  prudent  expenditures.    

Changes  to  the  Program  

Distributors  have  claimed  some  increased  costs  are  a  result  of  the  program  delays  and  changes   following  the  2011  government  review.  

(15)

Flaws  in  cost–benefit  analysis  

VAGO  was  critical  of  the  initial  study  that  prompted  the  rollout  of  smart  versus  ordinary  interval   meters,  arguing  that  it  only  considered  the  incremental  costs  and  benefits,  failed  to  reconsider  the   overall  costs  and  benefits  of  a  smart  meter  rollout,  and  did  not  consider  implementation  and   technology  risks.  The  Productivity  Commission  noted  that,  regardless  of  the  merits  of  VAGO’s   comments,  cost–benefit  analysis  is  challenging  when  it  is  used  to  inform  a  commitment  to  make  a   single  large  indivisible  investment  (a  mandatory  universal  rollout)  and  where  there  are  large  technical   uncertainties  (as  there  were  at  the  time).    

 

The  Commission  argued  that  technology  risks  were  not  addressed  sufficiently.  The  2005  cost–benefit   study  noted  the  need  for  technology  trials.  In  2006,  the  department  administering  the  project   provided  advice  to  Government  that  a  technology  trial  be  conducted,  but  that  the  Government   should  endorse  the  universal  rollout  before  the  results  of  the  trial.  VAGO  claimed  that  these  decisions   introduced  ‘significant  risks’  to  the  project,  which  was  compounded  by  insufficient  oversight  of  the   trials,  and  the  failure  to  adequately  use  them  to  inform  the  subsequent  rollout.  Since  then,   distribution  businesses  throughout  the  NEM  have  conducted  many  trials.    

 

Lack  of  competition  in  metering  services  and  misalignment  of  risks  and  rewards  

In  its  report  (Volume  2,  box  10.3),  the  Productivity  Commission  refers  to  a  number  of  parties  who  see   competition  in  smart  meters  as  important,  in  particular  for  encouraging  innovation  and  economic   efficiencies.  In  the  Victorian  model,  the  consumer  faces  the  cost  of  the  meters,  including  technology   risk,  but  without  the  choice  of  meter  or  service;  the  distributor,  with  the  major  influence  on  price  and   to  some  extent  service,  has  been  able  to  pass  through  a  large  portion  of  cost  overruns.  

There  are  different  ways  to  mandate  and  run  a  smart  meter  roll-­‐out;  some  of  the  issues  associated  with  the   Victorian  programme  may  not  apply  to  other  mandated  programmes,  but  provide  a  useful  comparison  to  the   issues  identified  with  market-­‐led  investments  in  smart  metering  in  New  Zealand.  

References

Related documents

Background of the Protection Profile development A (very) short introduction to Protection Profiles / Common Criteria.. The German Smart Meter Protection Profile: an overview

(iii) The smart meter pilot will evaluate the smart metering technology with respect to all aspects of commissioning and operating smart meter systems including business

A market maker sells a European, 91 −day, $50-strike call option on the above stock for $0.42 and delta-hedges the commitment using shares of stock.. The market-maker does not

One-component PU liquid-applied waterproofing membrane can be easily applied to podium deck areas to provide a seamless coating. Detailing around upstands and drains

European smart meter and smart grid services contracts in 2012 and 2013.  EOn Sweden/Capgemini and Ericsson – smart meter deployment; AMI

Hasil penelitian di perairan hulu, tengah dan hilir Sungai Cisadane: kiri, jumlah familia dan spesies ikan; kanan, jumlah spesies dan spesimen yang berhasil dikoleksi.. Keanekaragaman

Modify Windows Management Instrumentation Control permissions, registry permissions, and DCOM remote access permissions as described in the section Modifying Permissions in

experiences in discriminating between latent trajectory classes, we regressed class membership on childhood sexual abuse, parental physical abuse, and witnessing domestic