• No results found

SYSTEMS ENGINEERING FOR: REGIONAL ADAPTIVE SIGNAL CONTROL TECHNOLOGY (ASCT) Systems Engineering Management Plan

N/A
N/A
Protected

Academic year: 2021

Share "SYSTEMS ENGINEERING FOR: REGIONAL ADAPTIVE SIGNAL CONTROL TECHNOLOGY (ASCT) Systems Engineering Management Plan"

Copied!
17
0
0

Loading.... (view fulltext now)

Full text

(1)

S

YSTEMS

 

E

NGINEERING

 

FOR

:

 

R

EGIONAL

 

A

DAPTIVE

 

S

IGNAL

 

C

ONTROL

 

T

ECHNOLOGY

 

(ASCT)

 

‐ 

Systems

 

Engineering

 

Management

 

Plan

   

 

 

S

UBMITTED TO

:

 

 

Metropolitan

 

Area

 

Planning

 

Agency

 

 

 

December

 

2013

 

 

 

Job No. 19‐J12‐1912 

 

 

 

 

 

 

 

(2)

 

D

OCUMENT

 

V

ERSION

 

C

ONTROL

 

DocumentName SubmittalDate VersionNo.

Version 1.0  October 2012  1.0 

Version 2.0  May 2013  2.0 

Response to FHWA Comments  December 2013  3.0 

    Submitted By:  Iteris, Inc.  In Association with:  HDR Engineering, Inc.  

(3)

MAPA

Version3.0

 

ii   Systems Engineering for Regional ASCT 

SEMP 

   

TABLE OF CONTENTS 

Document Version Control ... i 

Table of Contents ... ii 

List of Figures ... ii 

1.0  Introduction ... 1 

2.0  Project Overview ... 3 

2.1  PROJECT PURPOSE ... 5 

2.2  PROJECT SCOPE AND SCHEDULE ... 5 

2.3  STAKEHOLDERS ... 6 

2.4  RELEVANT PROJECT DOCUMENTATION ... 6 

3.0  Project and Systems Engineering Documentation ... 7 

4.0  Project Management and Control ... 9 

4.1  PROCUREMENT MANAGEMENT ... 10 

4.2  RISK MANAGEMENT ... 12 

4.3  CHANGE MANAGEMENT ... 12 

4.4  QUALITY MANAGEMENT ... 13 

4.5  SYSTEMS ACCEPTANCE ... 13 

4.6  OPERATIONS AND MAINTENANCE, UPGRADE AND RETIREMENT ... 13 

 

LIST OF FIGURES

  FIGURE 1:  SYSTEMS ENGINEERING PROCESS "V" DIAGRAM ... 2  FIGURE 2:  PRELIMINARY REGIONAL ASCT CORRIDORS ... 4  FIGURE 3:  MAPA REGIONAL ASCT SYSTEM ENGINEERING PROJECT ORGANIZATIONAL CHART .. 9 

  

LIST OF TABLES 

TABLE 1: PRELIMINARY PROJECT TASKS AND SCHEDULE ... 5  TABLE 2: MAPA REGIONAL ASCT SYSTEMS DOCUMENTATION ... 7 
(4)

 

1.0

INTRODUCTION

 

The Metropolitan Area Planning Agency (MAPA) has commissioned the development of system 

engineering documents  for  the deployment of  adaptive signal  control  technology  (ASCT) 

systems throughout the region.  This Systems Engineering Management Plan (SEMP) represents  a portion of the systems engineering deliverables and provides a high‐level plan for MAPA and 

other stakeholder’s management of the systems engineering process in compliance with the 

Federal Highway Administration (FHWA) Federal Rule 23 CFR 940.11 and Systems Engineering 

Guidelines.     

The MAPA System Engineering for Regional ASCT project will work through the identification of  stakeholder needs assessment, project requirements and verification procedures.   The project  will blend the project deliverables identified by the FHWA Local office which include the Project 

Plan, SEMP (this document), Concept of Operations, Requirements and Verification Plan, with 

the FHWA ASCT Model Documents (FHWA Model Systems Engineering Document for ASCT, 

Draft  –  Guidance  Document,  FHWA‐HOP‐11‐027,  August  2011).    The  Model  Systems 

Engineering Documents for Adaptive Signal Control Technology systems offer guidance and 

associated templates that will be used to support the creation of regional and corridor specific 

planning and design documents.   A primary goal for using this FHWA model document is to 

streamline  the  documentation  and  evaluation  of  stakeholder  needs  and  to  prepare 

requirements that can successfully procure and implement an ASCT corridor within the region.   Subsequent to the project scoping and initiation, FHWA provided updated Guidance Documents 

in September, 2012.   While the newer documents provide a significant information update 

three months after project startup, a majority of these templates are being utilized to help 

streamline agency review.     

This systems engineering documentation that will be conducted as part of this project and 

potential  future  deployment  projects  relate  directly  to  Congestion  Management  and 

Safety/Incident Management components identified in the MAPA ITS Architecture for key, 

congested corridors in the MAPA region.      Some specific objectives, not listed in any particular order, include:    - Decreased number of crashes (primary and secondary)  - Improved level of service  - Reduced congestion  - Reduced queuing  - Reduced emissions  - Better responsiveness to fluctuating traffic demands  - Improved travel time reliability  - Public acceptance and support  - Ability to deploy with existing or planned staffing levels 

(5)

MAPA

Version3.0

 

2   Systems Engineering for Regional ASCT 

SEMP 

   

 

The SEMP describes how the project will follow the Systems Engineering Process illustrated in 

Figure 1 on the following page.  The SEMP will guide the project from conception to operations  and maintenance in a systematic way.  The SEMP is an evolving document that will be updated  as the project progresses.      FIGURE 1:  SYSTEMS ENGINEERING PROCESS "V" DIAGRAM     

 

(6)

 

2.0

PROJECT

 

OVERVIEW

 

ASCT system projects have been constructed throughout North America to manage congested 

corridors and locations with varying peak directions and side streets.  Some of these projects 

are now 30 years old.   Many initial deployments struggled with the ability to collect the 

necessary real‐time information on the approaches, communicate consistently to the controller 

and  the  adjacent  intersections  in  real‐time  to  achieve  the  performance  that  the  traffic 

engineering community and traveling  public expected.   The amount of  maintenance  and 

calibration was more than anticipated.   Additional struggles were due to lack of systems 

engineering, lack of critical stakeholder involvement, and systems not being configured to 

address the problems that needed to be solved. Ultimately many were turned off.   The 

performance  of  systems  engineering,  as  well  as  the  improvement  in  communications 

infrastructure, ATMS control software, controller firmware, and sensor accuracy has allowed 

for ASCT projects to be successful for many agencies.   This has led to a wide variety of ASCT 

systems all claiming to satisfy every agency need.   

The City of Omaha Traffic Engineering Division requested Safety Funds from the Nebraska 

Department of Road Safety Committee to complete traffic signal improvements and implement 

an ASCT solution along West Dodge Road from 69th Street to 93rd Street.   The City has tried 

different traffic management options along this congested corridor which has varied land uses 

including commercial, educational, and retail activity.  Prior to moving forward with plans and 

construction, FHWA, MAPA, NDOR, and Iowa DOT recognized that the variety of ASCT systems 

would  require  a  detailed  evaluation  and  documentation  of  the  needs  of  the  region.  

Additionally, they recognized the new ASCT Model Documents provided a significant new 

resource to support the planning and design of the system on both a regional and corridor 

specific level.    

MAPA prepared a scope of work that organizes the stakeholders in the region (Nebraska and 

Iowa agencies) to prepare an ASCT strategy and System Engineering documents for the region.  

In addition to providing sound information to regional stakeholders, the scope includes the 

evaluation of three specific corridors including:   

 Dodge Street / West Dodge Road from 69th Street to 93rd Street in Omaha, Nebraska 

 84th Street from West Center Road to Lincoln Street in Omaha, Ralston, La Vista, and 

Papillion, Nebraska 

 South Expressway from 19th Avenue to 35th Avenue in Council Bluffs, Iowa 

 

In  addition  to  these  primary  corridors,  Figure  2  illustrates  the  MAPA  region  and  other 

preliminary locations that the MAPA stakeholders are considering for ASCT systems. 

(7)

! ( ! ( ! ( !( ! ( !( !( !( ! ( ! ( ! ( !( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( !( !( !( !( !( ! ( !(!( !( ! (!(!( !( ! ( ! ( !( !( ! ( !( !( ! ( !( ! ( !( !( !( !( ! (!( !(!( ! ( !( ! ( !(!( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !(!( !( !( ! ( !( !( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! (!( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! (!( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( !( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( !( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! (!( ! ( ! ( ! (!( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! (!( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !(!( ! ( ! ( ! ( ! ( ! ( !(!( ! ( ! ( !( !(!( !( !( !(!( ! ( ! ( ! ( ! ( ! ( ! (!(!(!(!(!(!( ! ( ! (!( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! (!(!( ! ( ! ( ! ( ! ( ! ( ! (!( !( ! (!( ! ( ! ( ! ( ! (!( ! ( !(!(!(!( !( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( !( !( !(!(!( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( ! ( Council Bluffs Lake Crescent Lewis Garner Hazel Dell Carter Lake Crescent 9 AV 5 AV 23 AV AVENUE G AVENUE A N 16 S T N 2 5 S T NA SH BLV D N 3 5 S T S 1 S T S 3 S T S 16 S T S 3 5 S T

t

u

275

t

u

6 Omaha

Carter Lake, Iowa

Fort St Harrison St State St Blondo St 1 6 8 th S t 12 0 th S t Ida St Q St 1 5 6 th S t 6 0 th S t 2 4 th S t 16 th S t 19 2 n d S t Pacific St 2 0 th S t F St 50 th S t 3 0 th S t 5 2n d S t 13 2 n d S t 1 14 th S t Farnam St Harney St Lake St Leavenworth St 8 4 th S t 1 0 th S t 1 0 8 th S t Rainwood Rd Cass St Military Rd F o n ten e lle B lv d 1 0 2 nd S t 13 th S t 1 1 th S t F lo re n ce B lv d 85 th S t Douglas St Burt St Martha St Cuming St 1 4 th S t Hartman Ave Hamilton St Milla rd Av e Underwood Ave Abbott Dr Mo rmo n B rid ge R d 3 6 th S t Vinton St Center St Crown Point Ave

Jo hn J P e rsh in g D r St Marys Ave Blondo Pkwy 8 8 th S t 9 6 th S t W en n ing ho ff R d Martin Ave R e ge n c y P k w y Jackson St Redman Ave Highland St 9 8 th S t 10 8 th Av e 5 6 th S t Miracle Hills Dr R idg ew oo d A ve California St C ou ntr y C lub A ve 8 th S t F St 3 6 th S t State St F lo re nc e B lvd 6 0 th S t 2 4 th S t A bb ott D r 1 6 th S t 1 1 th S t 3 6th S t 1 6 8 th S t 1 3 2 n d S t 13 2 n d S t 1 0 8 th S t Q St 1 5 6 th S t Ida St 1 0 8 th S t Pacific St 52 n d S t L St 2 04 th S t 7 2 nd S t 1 4 4 th S t W Center Rd 9 0 th S t W Maple Rd Pacific St Dodge St 1 3th S t 4 2 n d S t Ames Ave 84 th S t Maple St Bla ir H igh Rd 1 8 0 th S t 30 th S t Sorensen Pkwy Abb ott D r Mc Kinley St Bennington Rd Military Ave In dustr ia l Rd N W R ad ia l H w y Cuming St Center St U S 75 H w y S S ad dle Cre ek Rd 36 Hwy Missouri Ave Frede rick St N o rth Fre ew ay W Dodge Rd 30th A ve L St 1 8 0 th S t Omaha Bellevue Papillion La Vista Chalco Offutt AFB Ralston Gretna Boys Town Offutt AFB Bennington Richfield Gretna

§

¨

¦

80

§

¨

¦

680

¬

«

370

¬

«

64

¬

«

50

¬

«

85

t

u

6

t

u

275

t

u

75

t

u

75

§

¨

¦

29

§

¨

¦

680

§

¨

¦

80

§

¨

¦

68 0 0.5 1 2 Miles

Figure

 

2

Proposed

 

Corridors

for

 

Adaptive

 

Signal

 

Control

Technology

 

(ASCT)

Í

N

Legend

! ( Traffic Signals Primary Corridors Secondary Corridors
(8)

 

2.1

P

ROJECT 

P

URPOSE

 

The goal of the project is to evaluate the potential deployment of adaptive signal control 

technology  in  the  MAPA  region.   This includes the development  of Systems Engineering 

documentation  that  will  support  and  facilitate  deployment  of  ASCT,  if  it  is  deemed  an 

appropriate traffic control solution for the region.   Overarching objectives include developing 

traffic management solutions that provide value, improve safety, improve operations and have 

broad support from regional agencies and stakeholders.   Traffic signal system improvements 

must be compatible with the needs of multiple jurisdictions that are responsible for traffic 

management in the greater Omaha metropolitan area, and must be scalable and expandable to  meet future system needs.   

 

2.2

P

ROJECT 

S

COPE AND 

S

CHEDULE

 

Table 1 summarizes the project scope and key schedule dates.  For each task, the table briefly 

describes the effort, team members involved, and expected deliverables.   Dates of draft 

deliverables are approximate and subject to change based on meetings and stakeholder review.    

TABLE 1: PRELIMINARY PROJECT TASKS AND SCHEDULE 

 

Tasks and Deliverables  Key Team Members  Start Date  Completion 

Date 

1. Project Management and Stakeholder Coordination 

- Iteris (Lead)

- HDR 

- MAPA 

July, 2012  Dec., 2012 

2. Data Collection and Review of Existing Information 

- Iteris (Lead)

- HDR 

- MAPA 

July, 2012  Aug., 2012 

3. Project Plan Verification 

- MAPA (Lead)

- Iteris 

- HDR 

July, 2012  Aug., 2012 

4. Systems Engineering Management Plan 

- Iteris (Lead) - HDR  - MAPA  Aug., 2012  Oct., 2012  5. Concept of Operations  - HDR (Lead) - Iteris  - MAPA  Sept., 2012  June, 2013 

6. Requirements and Verification Plan 

- Iteris (Lead)

- HDR 

- MAPA 

Oct., 2012  July, 2013 

7. Design Phase(s)*  - City of Omaha 

(Lead)  Aug., 2013  Oct., 2013 

8. Construction Phase(s)*  - City of Omaha 

(Lead)  Oct., 2013  Dec., 2013 

 

*Assumes final design and construction/deployment commences immediately following approval of the Systems Engineering for ASCT project.  

(9)

MAPA

Version3.0

 

6   Systems Engineering for Regional ASCT 

SEMP     

2.3

S

TAKEHOLDERS

 

Project Stakeholders for the deployment of Regional ASCT systems include:     MAPA   FHWA   City of Omaha, NE   City of Council Bluffs, IA    NDOR   Iowa DOT   Metro Transit   Other Local Agencies   Traveling Public   

2.4

R

ELEVANT 

P

ROJECT 

D

OCUMENTATION

 

The  concept  of  adding  ASCT  solutions  to  select  corridors  has  been  discussed  between 

stakeholders and planned by agencies for a number of years.    

The following Statewide and Regional planning‐level documents are relevant to this project 

because they identify the need for the ASCT solutions.     

1. NDOR Statewide ITS Architecture – Traffic signal control is covered for all Districts within  NDOR and specifically District 2 in the MAPA region.  

2. MAPA Regional ITS Architecture – The Metropolitan Area Planning Agency (MAPA) 

Regional ITS Architecture was completed in 2005.   MAPA has recently contracted to 

update the ITS Regional Architecture and it will include ASCT systems. . 

3. Omaha Traffic Signal System Master Plan – Omaha completed this comprehensive 

master  plan  including  SE documents  in 2012.  The  system  engineering  documents 

identify  the  need  and high‐level requirements to include ASCT  projects  on select 

corridors during the traffic signal system upgrades and ATMS software deployment and  integration. 

4. FHWA Model Systems Engineering Documents for Adaptive Signal Control Technology 

(ASCT) Systems ‐ This document is a resource for the stakeholders and consultant team  to follow during the development of the ASCT System Engineering documents. 

5. Nebraska 2012‐2016 Strategic Highway Safety Plan   ‐ This plan outlines strategies for 

reducing  the  number  of  fatalities  in  Nebraska,  including  those  at  signalized 

intersections. 

(10)

 

3.0

PROJECT

 

AND

 

SYSTEMS

 

ENGINEERING

 

DOCUMENTATION

 

Table 2 on the following page lists the documents and processes that contain important 

descriptions  of stakeholders,  systems, and  operational  practice  that  support the systems 

engineering for proposed regional ASCT systems.   The table describes the documents and 

deliverables, and their relevance to the systems engineering process.   

TABLE 2: MAPA REGIONAL ASCT SYSTEMS DOCUMENTATION   

Systems Engineering 

Docs / Processes  Status  Description  Deliverables 

1. Project Plan  Complete  This document will provide project 

managers and stakeholders an overview 

of the project, magnitude of the project, 

proposed process, schedule, and 

expected budget for the project.  

Draft & Final Project 

Plan  

2. System 

Engineering 

Management Plan 

Complete  This document utilizes the project plan, 

goals & objectives, and agency 

capabilities to assess project 

management activities and define 

needed SE processes and resources. 

Draft & Final SEMP

3. Concept of 

Operations 

Complete  This document is written from the system 

operator perspective and defines the 

needs and objectives of stakeholders to 

determine desirable functions of the 

proposed ASCT system. 

Draft & Final Concept of 

Operations 

4. Requirements   Draft Complete This document describes what needs to 

be achieved by the system. Each 

requirement is traced to a need 

described in the ConOps, and it provides 

a basis for verifying the systems when 

delivered. 

Draft & Final High Level 

Requirements  

5. Verification Plan  Draft Complete This document describes how the system 

will be tested, ensuring that the desired 

requirements are satisfied. It will lay out 

a template plan for the vendor & agency 

to conduct the verification effort. 

Draft Verification Plan & 

template information for 

use in the verification 

effort. 

6. Validation Plan  Not started 

To be 

completed 

under next 

phases 

This document describes how the 

performance of the system will be 

measured to determine if the needs in 

the ConOps have been satisfied. Can 

include initial validation plan, user’s 

manuals, and report on validation results 

(11)

MAPA

Version3.0

 

8   Systems Engineering for Regional ASCT 

SEMP 

   

Systems Engineering 

Docs / Processes  Status  Description  Deliverables 

7. Detailed Design,  Requirements, and  Procurement  documents  Not started  To be  completed  under next  phases 

Final plans and specifications will be 

prepared as needed.  Detailed 

requirements traceability spreadsheet 

based on the system requirements and 

the detailed design. Procurement plan 

process finalized. 

Final Plans & 

Specifications, Detailed 

Project Requirements, 

and procurement docs 

8. Technical Reviews  Portions of this 

effort will be 

completed with 

this project and 

future phases. 

Throughout the project, agency staff will 

perform technical reviews of the 

consultant & contractor deliverables.  The 

frequency and thoroughness of the 

technical reviews determined by agency. 

Progress Meeting 

Minutes & Documents. 

Subsequent design 

review info and 

procurement docs  review.  9. Testing,  Integration and  Acceptance  Not started To  be completed  under next  phases 

This process will summarize the expected 

testing associated with the project and 

will build on the Draft Verification Plan. 

The documentation of the test is 

expected to include inspection, 

demonstration and execution of systems. 

Once the Contractor is selected, the 

Contractor will be responsible for review 

and submittal of an Acceptance Test that 

describes the anticipated schedule and 

potential modifications to the Acceptance 

Test. The Contractor will be responsible 

for performing and documenting all 

testing with agency or its representatives 

present to observe and verify the results.   

Final Acceptance Test 

Plans 

 

As illustrated in Table 2 above, items 1 through 5 are included in the current scope of work as 

part  of  the  MAPA  Systems  Engineering  effort  for  Regional  ASCT.    The  follow  on  items 

(illustrated after the dashed line) will need to be completed as part of next phases of the 

project deployments.   

(12)

   

4.0

PROJECT

 

MANAGEMENT

 

AND

 

CONTROL

 

Figure 3 shows the organizational structure for the MAPA Regional ASCT Project.  Following the  chart is a brief description of the project roles.     FIGURE 3:  MAPA REGIONAL ASCT SYSTEM ENGINEERING PROJECT ORGANIZATIONAL CHART    Project Support Consultants MAPA Project Manager FHWA Local Office Project Steering Committee FHWA Resource Center NDOR Operations Division IowaDOT Omaha Council Bluffs NDOR D-2 Other Agencies Traffic Signal System Managers Project Oversight NDOR Traffic Engineering Division    

MAPA Project Manager – The MAPA Project Manager will be responsible for the management 

of this project and the acceptance of the final SE documents.     The MAPA Project Manager will be responsible for the following:   Managing the consultant  throughout the project   Monitoring project progress and approving or denying any changes to the scope   Delegating roles for specific efforts throughout the project   

 Ensuring the project is completed as agreed upon, that the system meets its goals and 

(13)

MAPA

Version3.0

 

10   Systems Engineering for Regional ASCT 

SEMP 

   

Project Steering Committee – The Project Steering Committee (PSC) will provide input at key 

stages of the project to guide the documentation and prioritization of the regional needs and 

requirements of the ASCT system.   They will support the identification of the preliminary 

corridors for ASCT system evaluation.   

Project Support Consultant – The Project Support Consultant will provide technical support to 

the MAPA Project Manager and all stakeholders throughout the duration of the project.  In that 

role, the Consultant will ensure the project is consistent with systems engineering processes 

and that all systems engineering documentation is produced.  With future design contracts, the 

Project Support Consultant will finalize the requirements, plans, specifications and estimates. 

The  Consultant  may  support  the  project  in  reviewing the efforts  of  the  Contractor and 

supporting testing.   

Traffic Signal System Managers – The Traffic Signal System Managers will provide input to the 

needs and requirements on a regional level.   Additionally, these representatives will provide 

detailed information regarding the existing signal systems and agency specific needs for specific  corridors.  They are expected to have a significant role in all phases of the creation of the draft  and final System Engineering documents. 

 

As the ASCT projects move from preliminary design to final design plan preparation and 

development of specifications and more detailed requirements, these agencies will need to 

provide further input, and additional information including as‐built information etc. for the  

selected corridors.   

Project Oversight Agencies – These agencies will play a key role in the management and 

planning of ASCT on a high level for the MAPA region.  Additionally, FHWA Resource Center will 

provide a review of the System Engineering documents relative to the use of the Model ASCT 

documents.   

Beyond  the  MAPA  ASCT  System  Engineering  project,  the  plan  is  to  move  forward  with 

deployment of three corridors.  MAPA staff will not be the contracting agency for the specific 

corridor deployments  ‐ that is expected to be the responsibility of the agency or multiple 

agencies that control the traffic signal system along each corridor.  The organizational structure 

for these next steps will be out lined in the Verification Plan, as the deployment approach and 

available staff could vary based on each agency.    

4.1

P

ROCUREMENT 

M

ANAGEMENT

 

The lead agencies currently have several options for the procurement of equipment, software,  and professional services.  Typically each community has the following options:     
(14)

   

Equipment and Software 

For procurements under an established threshold, vendors and/or contractors may submit 

price quotes.  The agency may select based on a “lowest and best” provision, which means the 

lowest bidder that complies with the specifications by the issuing department is selected and 

issued a purchase order.      

For procurements over the established threshold, a bid package is prepared.   The lowest 

responding bidder, pending approval by agency, is awarded the contract.   For federal‐aid 

projects in Nebraska, the bid must be let by NDOR using its specifications (with the agency 

specs as special provisions).   

Procurements for maintenance follow a similar low‐bid process.   

As discussed at the Project Steering Committee on January 18, 2013, NDOR will allow the City of 

Omaha to procure the system as long as all federal procurement regulations are followed, 

NDOR and FHWA approve the process, and NDOR is on the selection committee.   FHWA has 

agreed to this arrangement.   

Currently, most agencies have a list of approved products and vendors for certain traffic signal 

system components such as, inductive loops, traffic signal detector cards, video detection 

cameras,  emergency  vehicle  preemption,  signal  heads  and  pedestrian  signals,  wireless 

interconnect radios, service disconnect pedestals, fiber communication equipment etc.   

Professional Services 

For  services  involving  federal‐aid  funds,  the  agencies  must  follow  state  and  federal 

requirements.  In Nebraska, agencies can utilize the NDOR On‐Call ITS Consultant contract (at 

the discretion of NDOR).     

Summary 

Several procurement options are available for the deployment of ASCT systems, including: 

qualifications based (RFP) selection combined with design‐bid‐build, system manager, and “best 

value”  equipment  purchases  supported  by  Systems  Engineering  documentation.    It  is 

envisioned that the following competitive procurement procedure is utilized in Omaha:   

1. Use the functional requirements document to generate an RFP specific to the corridor. 

2. Use the proposals solicited through the RFP process to create a short‐list of three 

products/vendors. 

3. Through a testing and documentation procedure, select the product that demonstrates 

the “best value” in meeting schedule, cost (from a life‐cycle perspective), and quality 

goals.   

(15)

MAPA

Version3.0

 

12   Systems Engineering for Regional ASCT 

SEMP 

   

The City of Council Bluffs will follow the same procedure in accordance with City or Iowa DOT 

procurement processes. 

 

Once the stakeholders have worked through the FHWA Model ASCT Documents, the potential 

exists that a specific corridor may have just one ASCT system that meets the needs for the 

agency and the corridor.  The result could be the need for a sole source justification letter to 

support  the  System  Engineering  documents.    This  justification  letter  would  need  to  be 

approved in accordance with the requirement of 23 CFR 635.411 –  Material or Product 

Selection.   

4.2

R

ISK 

M

ANAGEMENT

 

The risk associated with this project has been discussed with stakeholders.  Project needs were  discussed to reduce the amount of risk in the project.  Areas of risk include:   Keeping backup timings current in the event of all possible system failures   Extensive system oversight during construction   Maintaining a trained staff on multiple ASCT systems   Corridors require significant intersection enhancements prior to deployment   Corridors require significant communications upgrades prior to deployment   Regional integration of multiple ASCT systems   Inability to remotely monitor and trouble‐shoot the ASCT systems   Project Delays based on multiple reviews by multiple agencies 

 System not providing  meaningful  measurement  against clearly  stated performance 

objectives, including measures not tied to objectives, too simplistic, and not transparent  or verifiable 

 Measures do not directly map to specific functions of the adaptive algorithm (eg, travel 

time, stops, and delays) 

 Not properly identifying needs and requirements to address the specific problems on 

the corridor    These areas will be addressed as specific needs during the remainder of the System Engineering  Documentation.   

4.3

C

HANGE 

M

ANAGEMENT

 

The MAPA Project Manager will be responsible for change management.  In this capacity, the 

MAPAProject  Manager will review all proposed project changes and coordinate with  the 

appropriate management for approval or rejection.  Proposed changes will be discussed in the  project steering committee meetings.   

(16)

 

During the deployment phase each lead agency will be responsible for identifying the project 

manager or designated staff to be responsible for change management for each specific 

corridor.   

4.4

Q

UALITY 

M

ANAGEMENT

 

Agency Quality Management practices will be applied to the MAPA ASCT System Engineering 

project.  Due to the technical components of this project, the need for a Traffic Signal Engineer  with experience with ASCT systems is important.  Additionally, an experienced Project Manager  will provide project balance between the technical components and the traditional contracting 

elements.    Finally,  a  Test  Manager  that  is  familiar  with  the  necessary  traffic  signal 

enhancements, ASCT systems, communications, sensor placement and system acceptance test  procedures will provide the necessary project oversight and lead to improved quality. 

 

4.5

S

YSTEMS 

A

CCEPTANCE

 

System acceptance is the point at which the local agency accepts and becomes responsible for 

the  corridor  specific  ASCT  deployment.    The  verification  plan  will  outline  the  agency 

organizational chart and the responsibilities of each staff person.   The agency is expected to 

have a Test Manager that will be responsible for taking information provided in the bid 

documents and creating the final System Acceptance Plan.   The Plan will document how the 

ASCT deployment will function and must be consistent with the agreed‐upon requirements.   

The Test Manager will be responsible for review and verification of the System Acceptance 

Plan.  Verification by the Test Manager means the acceptance test plan has adequate tests for 

each system requirement.  Once the acceptance test plan has been accepted, the Test Manager 

will be responsible for conducting or overseeing the performance of the plan.   The Test 

Manager will be responsible for reporting the status of all tests, either in the test plan or a 

separate report.   The agency Project Manager will use this information to make decisions on 

partial and complete system acceptance.   

4.6

O

PERATIONS AND 

M

AINTENANCE

,

 

U

PGRADE AND 

R

ETIREMENT

 

Operations and Maintenance, Upgrade and Retirement are dependent upon the technology 

deployed and the warranty of service provided by the selected ASCT system and contractor.  

The Concept of Operations should document at the high‐level, the expected plan for:   

 Operations – This will include a high‐level summary of the staffing needs to operate the 

system, the roles and responsibilities for ASCT operation, management, information 

sharing and reporting. 

 Maintenance – This  will include the staff needed to maintain  the system, system 

(17)

MAPA

Version3.0

 

14   Systems Engineering for Regional ASCT 

SEMP 

   

 Upgrade  –  This  will  include  opportunities  to  upgrade  hardware,  software  and 

communications.  Each agency is expected to use potential upgrade options to develop 

a strategy for  budgeting  and  performing system  upgrades  which may include  the 

deployment of additional corridors, the integration of with surrounding entities, and 

increased dissemination of system data. 

 Retirement – This will include estimates for software, hardware and communications 

References

Related documents

As a result, I would not expect the slightly lower GPA means for African-American students compared to their Caucasian cohorts to have any meaningful impact on the negotiation

40, City of Palmdale, Palmdale Water District, Littlerock Creek Irrigation District, Palm Ranch Irrigation District, Quartz Hill Water District, California Water

the 'knowledge' domain with regard to 5 main items (curriculum, research, campus operations, services and outreach, and building and physical environment) and 68 sub-items

General Distribution: Albania, Algeria, Austria, Belgium, Bulgaria, Canary Is" Cyprus, England, France, Germany, Hungary, Iraq, Ireland, Israel, Italy, Mongolia,

In previous work, we derived parametric models to estimate activity energy expenditure intensity from non-dominant wrist acceleration (reproduced in Table 2 ) using a dataset (n =

For Microsoft SQL Server users only: If you uninstall Microsoft SQL Server which has earlier version of HPDM database and reinstall Microsoft SQL Server on the same installation

If there is a professionally appropriate reason for a psychologist to convert individual subtest scores based on the ss 1 to 19 scale to an IQ SS scale, the psychologist should not

In the period of disruption in the 1980s and 1990s, the state agencies setting minimum wages and income support were able to both remove industrial leverage from minimum wage