Project information: Management and Protection of Key Biodiversity Areas in Belize (P130474)
Project Implementation agency: PACT
Preamble
In accordance with paragraph 5.9 of the “ World Bank Procurement Regulations for IPF Borrowers”
(July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project.
This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP.
The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP.
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
PROCUREMENT
PLAN Belize : Management and Protection of Key Biodiversity Areas in Belize General Information
Country:
BelizeBank’s Approval Date of the Original Procurement Plan: 2018-04-13 Revised Plan Date(s): (comma delineated, leave blank if none)2019-08-26
Project ID:
P130474GPN Date:
Project Name:
Management and Protection of Key Biodiversity Areas in BelizeLoan / Credit No:
TF / 13004, TF / 16773Executing Agency(ies):Protected Areas Conservation Trust
WORKS
Activity Reference No. /Description Loan / Credit
No. Component Review Type Method Market
Approach
Procurement Process
Prequalification (Y/N)
Estimated Amount (US$)
Actual Amount (US$)
Process Status
Draft Pre-qualification Documents
Prequalification Evaluation Report
Draft Bidding Document / Justification
Specific Procurement Notice / Invitation
Bidding Documents as Issued
Proposal Submission / Opening / Minutes
Bid Evaluation Report and Recommendation for
Award
Signed Contract Contract Completion Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
GOODS
Activity Reference No. /Description Loan / Credit
No. Component Review Type Method Market
Approach
Procurement Process
Prequalification (Y/N)
Estimated Amount (US$)
Actual Amount (US$)
Process Status
Draft Pre-qualification Documents
Prequalification Evaluation Report
Draft Bidding Document / Justification
Specific Procurement Notice / Invitation
Bidding Documents as Issued
Proposal Submission / Opening / Minutes
Bid Evaluation Report and Recommendation for
Award
Signed Contract Contract Completion
Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
BZ-PACT-65673-GO-RFQ / 2 vehicles for the Department of Environment
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 50,000.00 86,490.06 Completed 2018-09-25 2018-11-03 2019-01-02
BZ-PACT-65676-GO-RFQ / Purchase of skiff and outboard engine to facilitate water quality monitoring
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 30,000.00 27,757.11 Signed 2018-09-15 2018-10-24 2019-01-22
BZ-PACT-71076-GO-RFQ / 1 vehicle for the Biodiversity Monitoring program
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 40,000.00 34,171.92 Completed 2018-07-30 2018-09-25 2018-11-09
BZ-PACT-81698-GO-RFQ / 3 Laptops for Biodiversity activities
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 10,000.00 4,934.30 Completed 2018-10-17 2018-11-21 2018-12-21
BZ-PACT-82320-GO-RFQ / 100 Camera Traps &
accessories to be used for Biodiversity Monitoring activities .
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 20,000.00 33,983.23 Completed 2018-10-19 2018-11-25 2019-01-24
BZ-PACT-82332-GO-RFQ / 10 GPS Collars for Biodiversity Monitoring Activities
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - International
Single Stage - One
Envelope 30,000.00 25,022.00 Completed 2018-10-23 2018-11-29 2019-01-28
BZ-PACT-82337-GO-RFQ / Tracking equipment for Biodiversity Monitoring activities
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - International
Single Stage - One
Envelope 20,000.00 9,125.00 Completed 2018-10-24 2018-12-05 2019-03-05
BZ-PACT-94404-GO-RFQ / 20 Rain coats for the DOE Compliance Unit.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 5,000.00 4,216.90 Completed 2019-01-12 2019-02-10 2019-03-12
BZ-PACT-95495-GO-RFQ / Equipment for water quality Lab - Incubator,Infrated thermometer etc.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 10,000.00 16,539.41 Completed 2019-02-04 2019-03-23 2019-05-07
BZ-PACT-95497-GO-RFQ / tools for ECMU unit - machete , tool kits,tape measure etc.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 5,000.00 0.00
Pending Implementati on
2019-02-08 2019-05-16 2019-06-15
BZ-PACT-95499-GO-RFQ / tablets, cameras,GPS, computers, projector, for DOE
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 27,000.00 22,009.42 Signed 2019-02-08 2019-03-20 2019-05-04
BZ-PACT-95502-GO-RFQ / waterproof boots for DOE staff for water quality monitoring.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 4,000.00 3,111.00 Completed 2019-01-22 2019-03-01 2019-03-31
BZ-PACT-95503-GO-RFQ / shirts/polos/caps for DOE TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Request for
Quotations Open - National Single Stage - One
Envelope 15,000.00 8,782.00 Completed 2019-02-08 2019-03-20 2019-04-19
BZ-PACT-102649-GO-RFQ / 6 GPS units for the Biodiversity Monitoring Activities
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 1,600.00 1,762.76 Completed 2019-02-25 2019-03-22 2019-04-21
BZ-PACT-102657-GO-RFQ / Heavy Duty Multi_Function photocopier
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 9,500.00 1,762.76 Completed 2019-02-26 2019-03-16 2019-04-15
BZ-PACT-107180-GO-RFQ / 300 camera traps TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 66,000.00 65,969.64 Completed 2019-03-26 2019-05-04 2019-06-18
BZ-PACT-107584-GO-RFQ / Fire Fighting Equipment TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 13,000.00 0.00
Under Implementati on
2019-04-03 2019-05-29 2019-07-31
BZ-PACT-107585-GO-RFQ / Fire Management - Protective Clothing
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 16,000.00 0.00
Pending Implementati on
2019-04-03 2019-05-29 2019-07-31
BZ-PACT-107756-GO-RFQ / Purchase of 1 water tanks built on trailer - 100 gallons capacity
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 4,000.00 0.00
Pending Implementati on
2019-04-13 2019-05-28 2019-08-30
BZ-PACT-107757-GO-RFQ / Purchase of 1 ATV TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 13,000.00 0.00
Pending Implementati on
2019-04-20 2019-06-15 2019-08-30
BZ-PACT-71073-GO-RFQ / Provide equipment such as radio communications, camping gear, GPS, cameras, first aid kits for the Compliance Unit
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 55,000.00 0.00 Canceled 2018-07-27 2018-09-22 2018-11-06
BZ-PACT-102656-GO-RFQ / Promotional items for World Forest Day
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Request for
Quotations Open - National Single Stage - One
Envelope 5,000.00 0.00 Canceled 2019-02-25 2019-03-09 2019-04-08
NON CONSULTING SERVICES
Activity Reference No. /Description Loan / Credit
No. Component Review Type Method Market
Approach
Procurement Process
Prequalification (Y/N)
Estimated Amount (US$)
Actual Amount (US$)
Process Status
Draft Pre-qualification Documents
Prequalification Evaluation Report
Draft Bidding Document / Justification
Specific Procurement Notice / Invitation
Bidding Documents as Issued
Proposal Submission / Opening / Minutes
Bid Evaluation Report and Recommendation for
Award
Signed Contract Contract Completion Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
CONSULTING FIRMS
Activity Reference No. /Description Loan / Credit
No. Component Review Type Method Market
Approach
Contract Type Estimated Amount (US$)
Actual
Amount (US$) Process Status Terms of Reference Expression of Interest Notice
Short List and Draft Request for Proposals
Request for Proposals as Issued
Opening of Technical Proposals / Minutes
Evaluation of Technical Proposal
Combined Evaluation Report and Draft Negotiated Contract
Signed Contract Contract Completion Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-26 / KBA CS 26.
Develop and Implement Functional Web-based Information Management Systems (IMS) for the Department of the Environment and the Forest Department
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Prior Quality And Cost-
Based Selection Open -
International 302,000.00 232,142.50 Signed
BZ-PACT-65524-CS-CQS / Consultancy to review the PA Statutory Instrument, ground truth boundary lines and map land incursions Vaca FR, Chiquibul NP MMFR and CRFR
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 89,000.00 0.00Pending
Implementation 2018-08-06 2018-08-20 2018-09-01 2018-09-16 2018-10-02 2019-03-31
BZ-PACT-107181-CS-CQS / Monitoring Data Warehouse Solution (DWS), with an emphasis on high volume camera trap data
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 80,000.00 89,543.25 Signed 2019-03-27 2019-04-17 2019-05-31 2019-06-30 2019-07-21 2019-09-30
BZ-PACT-65523-CS-CQS / Analyse and draft the legislation for improved wildlife management including research, monitoring, wildlife rehabilitation, reintroduction to the wild
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 75,000.00 0.00 Canceled 2018-08-27 2018-09-10 2018-09-29 2018-10-09 2018-10-21 2019-04-19
BZ-PACT-65515-CS-CQS / Develop a protected areas GIS database and application for data management and analysis that will contribute to the FIS
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 75,000.00 0.00 Canceled 2018-10-08 2018-10-22 2018-11-06 2018-11-21 2018-12-03 2019-06-01
BZ-PACT-65514-CS-CQS / Consultancy to develop and implement a capacity development plan aimed at ensuring that individuals and organizations have the requisite capacities to ensure effective management of the targeted KBAs
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 30,000.00 0.00 Canceled 2018-09-24 2018-09-26 2018-10-15 2018-10-25 2018-11-06 2019-05-05
BZ-PACT-65521-CS-CQS / Capacity building of co- management organizations including funds accounting technical reporting and proposal writing
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 116,000.00 0.00 Canceled 2018-09-03 2018-09-17 2018-10-08 2018-10-18 2018-10-30 2019-04-28
BZ-PACT-65504-CS-CQS / Development of a management plan for Fresh Water Creek Forest Reserve
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 35,000.00 0.00 Canceled 2018-08-22 2018-08-27 2018-09-16 2018-09-26 2018-10-08 2019-04-06
BZ-PACT-65533-CS-INDV / Consultancy to review and revise the national water quality monitoring program with a view to modernize and equip the capacity of the DOE.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Consultant Qualification Selection
Open - National 60,000.00 0.00 Canceled 2018-08-02 2018-08-16 2018-09-04 2018-09-14 2018-09-25 2019-03-24
BZ-PACT-65476-CS-CQS / Support for the implementation of community- based rehabilitation sub- projects for sustainable harvesting and marketing of NTFPs and for other community-based forestry opportunities
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post
Consultant Qualification Selection
Open - National 70,000.00 0.00 Canceled 2018-07-23 2018-07-24 2018-08-13 2018-08-28 2018-09-05 2019-08-30
INDIVIDUAL CONSULTANTS
Activity Reference No. /Description Loan / Credit
No. Component Review Type Method Market
Approach
Contract Type Estimated Amount (US$)
Actual
Amount (US$) Process Status Terms of Reference
Invitation to Identified/Selected
Consultant
Draft Negotiated
Contract Signed Contract Contract Completion Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
No. 1 . Procurement Officer / Procurement Officer TF / 13004
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Prior
Individual Consultant Selection
Open 0.00 26,060.61 Signed
No. 3 Project Manager / Project Manager TF / 13004
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Prior
Individual Consultant Selection
Open 0.00 36,666.67 Signed
KBA/SER/006 / KBA Project Manager TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Prior Direct Selection Direct 0.00 34,328.36 Signed
No. 2 Project Officer / Project Officer TF / 13004
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Prior
Individual Consultant Selection
Open 0.00 30,606.06 Signed
BZ-PACT-65511-CS-INDV / Sustainable Forest Management Specialist
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post
Individual Consultant Selection
Open 46,800.00 36,484.08 Signed 2018-06-05 2018-06-25 2018-07-05 2018-07-11 2019-06-07
BZ-PACT-65528-CS-INDV / Biodiversity Monitoring Coordinator
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Individual Consultant Selection
Limited 50,000.00 55,970.15 Signed 2018-06-05 2018-06-19 2018-06-24 2018-07-06 2019-08-31
BZ-PACT-65530-CS-INDV / conduct training of DOE staff and other key public agencies on topics related to monitoring, enforcement, and use of key equipment
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Individual Consultant Selection
Open 28,000.00 0.00Pending
Implementation 2018-08-02 2018-08-29 2018-09-08 2018-09-20 2018-11-19
BZ-PACT-65536-CS-INDV / consultancy to develop a manual with standardized guidelines and methodology for EIA preparation and NEAC Procedural Manual
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Individual Consultant Selection
Open 39,000.00 16,594.73 Signed 2018-07-31 2018-08-29 2018-09-08 2018-09-19 2019-03-18
BZ-PACT-65677-CS-INDV / Institutional Development Specialist
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Individual Consultant Selection
Limited 37,500.00 19,844.22 Signed 2018-07-09 2018-07-14 2018-07-29 2018-08-11 2018-11-09
BZ-PACT-65679-CS-INDV / Administrative Assistant for the project
TF / 16773
Component 4: Project Management, Monitoring and Assessment
Post
Individual Consultant Selection
Limited 8,400.00 19,850.75 Signed 2018-06-06 2018-06-11 2018-06-16 2018-06-29 2019-09-30
BZ-PACT-73647-CS-INDV / Consultancy for the development of a Procedural Manual for the National Environmental Appraisal Committee (NEAC)
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Individual Consultant Selection
Open 16,000.00 0.00Under
Implementation 2018-08-10 2018-09-08 2018-10-08 2018-10-15 2018-11-14
BZ-PACT-73649-CS-INDV / Forest Ranger for the Compliance Monitoring Unit
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Individual Consultant Selection
Open 7,500.00 7,520.90 Signed 2018-08-13 2018-10-01 2018-10-11 2018-11-06 2019-09-30
BZ-PACT-81702-CS-INDV / 2 additional Rangers for the Compliance Unit
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Individual Consultant Selection
Limited 15,000.00 5,624.68 Signed 2018-10-12 2018-10-13 2018-10-23 2018-10-29 2019-09-30
BZ-PACT-98278-CS-CDS / Joares May Jr, Wildlife Veterinarian .The safe capture and anaesthetizing of jaguars in the Northern Corridor KBA site of Fresh Water Creek, allowing the deployment of GPS collars.
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 6,000.00 7,600.00 Completed 2019-02-04 2019-02-06 2019-02-15 2019-03-09
BZ-PACT-104175-CS-CDS / Toledo Institute for Development and the Environment (TIDE) to increase capacity of community-based organizations, NGOs, and the Forest Department on wildland fire management through a provision of training.
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Direct Selection Direct 7,000.00 6,428.54 Completed 2019-03-04 2019-03-05 2019-03-15 2019-03-20
BZ-PACT-105753-CS-CDS / Finalization of the Resettlement Audit and Action Plan (RAAP) for the Columbia River Forest Reserve in the Toledo District, Belize
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Direct Selection Direct 7,000.00 0.00Pending
Implementation 2019-03-12 2019-03-13 2019-04-02 2019-05-02
BZ-PACT-105755-CS-CDS / Quality Systems Solutions &
Initiatives (QSSI) to conduct the ISO 14001 and ISO 17020 standards training to DOE staff.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post Direct Selection Direct 30,000.00 41,635.00 Signed 2019-03-12 2019-03-17 2019-04-16 2019-05-16
BZ-PACT-107174-CS-INDV / Logistic for the Monitoring training for hicatee (Spanish Creek), including development of monitoring protocol
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Individual Consultant Selection
Limited 30,000.00 30,108.65 Completed 2019-03-21 2019-03-26 2019-04-02 2019-04-13 2019-06-30
BZ-PACT-107176-CS-CDS / Corozal Sustainable Future Initiative to conduct training, set up and maintain camera trap surveys in Freshwater Creek Forest Reserve .
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 10,000.00 15,776.16 Signed 2019-03-22 2019-03-25 2019-06-07 2019-09-15
BZ-PACT-107177-CS-CDS / Panthera Belize to conduct training, set up and maintain camera trap surveys in Spanish Creek Wildlife Sanctuary .
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 12,000.00 12,620.93 Signed 2019-03-25 2019-03-25 2019-04-15 2019-08-30
BZ-PACT-107178-CS-CDS / Friends for Conservation and Development, large scale camera trap training in Vaca Forest Reserve
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 17,000.00 17,353.82 Signed 2019-03-25 2019-03-26 2019-04-08 2019-07-27
BZ-PACT-107179-CS-CDS / Ya'axche Conservation Trust, large scale camera trap training in Maya Mountain Forest Reserve
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 15,000.00 15,518.18 Signed 2019-03-25 2019-03-26 2019-04-19 2019-07-31
BZ-PACT-107170-CS-CDS / Monitoring training for hicatee (Spanish Creek), including development of monitoring protocol by Missouri State University
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 35,000.00 43,700.00 Signed 2019-03-20 2019-04-05 2019-04-15 2019-09-30
BZ-PACT-107175-CS-CDS / Monitoring training for the capture of large mammals (Freshwater Creek), including development of monitoring protocols by Corozal Sustainable Future Initiative
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post Direct Selection Direct 15,000.00 10,517.44 Signed 2019-03-25 2019-04-06 2019-04-23 2019-06-06
BZ-PACT-114169-CS-CDS / Annual Plan of Operations (APO) Preparation
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post Direct Selection Direct 10,000.00 6,326.37 Signed 2019-05-16 2019-05-16 2019-05-31 2019-06-10
BZ-PACT-114170-CS-INDV / 2 - Permanent Sample Plots Field Laborers
TF / 16773
Component 1: Supporting Forest Protection and Sustainable Forest Management Activities in Key Biodiversity Areas
Post
Individual Consultant Selection
Limited 2,000.00 1,964.58 Signed 2019-05-16 2019-05-21 2019-05-26 2019-06-02 2019-07-31
BZ-PACT-65681-CS-INDV / M&E specialist TF / 16773
Component 4: Project Management, Monitoring and Assessment
Post
Individual Consultant Selection
Open 25,000.00 0.00 Canceled 2018-09-03 2018-10-02 2018-10-17 2018-11-10 2019-04-30
BZ-PACT-119246-CS-INDV / Consultancy to review and revise the national water quality monitoring program with a view to modernize and equip the capacity of the DOE.
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Individual Consultant Selection
Limited 64,000.00 54,375.00 Signed 2019-06-23 2019-07-03 2019-07-07 2019-07-13 2019-09-30
BZ-PACT-65512-CS-INDV / Support establishing procedures/guidelines criteria and corresponding regulations for the declaration re-alignment and de-reservation of Pas
TF / 16773
Component 2: Promoting Effective Management of Key Biodiversity Areas
Post
Individual Consultant Selection
Open 29,000.00 0.00 Canceled 2018-08-13 2018-09-06 2018-09-16 2018-09-28 2019-03-27
BZ-PACT-80708-CS-INDV / Assist DOE's Liaison Officer with the KBA project, will provide technical support to the DOE and the PIAG, and will coordinate the implementation of activities under Component 3 of the Project .
TF / 16773
Component 3: Institutional Strengthening and Capacity Building for Enhanced Enforcement of Environmental Regulations
Post
Individual Consultant Selection
Open 37,500.00 0.00 Canceled 2018-10-03 2018-11-01 2018-11-11 2018-11-28 2019-09-30