~TY
OF
NEU District Heating Expansion Southeast False Creek Energy Transfer Stations
Division 15 & 16 Specifications
Issue for Tender June 30, 2010
This document is the property of FVB Energy Inc. and the information hereon is not to be used or copied, except for
the specific project it was issued, without the written authorization of FVB Energy Inc.
CITY OF VANCOUVER TABLE OF CONTENTS
NEUETSEXPANSION ETSDIVISION 15&16 PAGE 1 OF 1
PROJECT NO.210243 JULY 19,2010
NEIGHBOURHOOD ENERGY UTILITY
DISTRICT HEATING EXPANSION
SOUTH EAST FALSE CREEK
ENERGY TRANSFER STATIONS
Table of Contents
Section Description Pages No. of
D
IVISION15
-
M
ECHANICALW
ORKS15010 Mechanical General Requirements 11
15051 Pipe Welding 7
15061 Pipe Hangers and Supports 9
15075 Identification 8
15081 Thermal Insulation for Piping 6
15142 Domestic Water Supply Piping - Copper 5
15180 District Heating Primary Piping, Valves and Fittings 19
15210 Seismic Restraint Systems 3
15280 Painting and Surface Preparation 4
15513 Secondary Piping 14
15755 Request For Quotation – Heat Exchangers 2
15916 ETS Controls and Metering 2
D
IVISION16
-
E
LECTRICALW
ORKS16010 General Requirements for Electrical Work 11
16051 Control Signal Wiring 7
M
ECHANICALD
RAWINGS(A
TTACHEDS
EPARATELY,
I
SSUE FORT
ENDER,
D
ATEDJ
UNE30,
2010,
R
EVISION0)
M-0243-000 ETS LEGEND & NOTES REV 0
M-0243-001 ETS HANGER AND SUPPORT DETAILS REV 0
M-0243-002 ETS TYPICAL INSTALLATION DETAILS REV 0
M-0243-003 ETS CONTROL AND METER ARCHITECTURE REV 0
M-0243-MS01 ETS 1723 MAIN ST. HEATING SCHEMATIC REV 0
M-0243-MS02 ETS 1723 MAIN ST. PIPING LAYOUT AND SECTIONS REV 0
M-0243-CS01 ETS 1887 CROWE ST. HEATING SCHEMATIC REV 0
M-0243-CS02 ETS 1887 CROWE ST. PIPING LAYOUT AND SECTIONS REV 0
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 1 OF 11
PROJECT NO.210243 JUNE 23,2010
SECTION 15010 MECHANICAL GENERAL REQUIREMENTS
1
PART 1. - GENERAL
1.1 G
ENERAL1.1.1 This section covers items common to all sections of Division 15 and applies
to all new buildings in the NEU South East False Creek 2010 Expansion.
1.1.2 Energy Transfer Station (ETS):
.1 The Work generally includes the installation, and/or supply and
commissioning of the piping, valves, Owner pre-purchased equipment (i.e. heat exchangers, energy meters and controls), and auxiliary equipment for the Neighborhood Energy Utility (NEU) District heating system. The contractor shall also be responsible for taking possession of Owner supplied heat exchangers, control devices, control valves, energy meters, control panels, and primary side isolation valves for installation and commissioning.
.2 In addition to supplying the equipment listed in the specification, the
contractor will supply required quantities of carbon steel pipe, stainless steel tubing, copper pipe, elbows, tees, reducers, unions, flanges, insulation, thermal blankets, couplers, isolation valves, strainers, and suspension devices for all of the heating and domestic hot water energy transfer stations.
1.2 D
EFINITIONS1.2.1 “Provide” shall mean supply, install and connect.
1.3 E
QUIPMENTL
IST1.3.1 Submit a complete list of equipment and materials to be used on this project.
1.3.2 Submit for approval within ten (10) days after award of contract.
1.3.3 Owner purchased equipment material list is attached at the end of this
section and details will be provided as an Addendum. Further details can be found in the drawings attached separately to this document.
1.3.4 Approved vendor data sheets/shop drawings of Owner purchased equipment
will be provided after award of contract.
1.4 E
QUIPMENT/P
IPINGI
NSTALLATION1.4.1 Space for servicing, disassembly and removal of equipment and components:
provide as recommended by Manufacturer or as indicated by Consultant.
1.4.2 Provide unions or flanges for ease of maintenance. Install as required in
paragraph 1.3.1.
1.4.3 Manual drains shall be piped downwards to a screwed cap or hose
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 2 OF 11
PROJECT NO.210243 JUNE 23,2010
1.4.4 Air vents shall be piped as per detail on drawings, away from piping and
equipment, with a downwards turn valve. Allow room for a bucket to catch any water.
1.4.5 Strainer blow downs shall be piped away from other piping and equipment
with adequate room for a bucket for drainage.
1.4.6 Relief valve discharge piping shall be piped to floor drains for hot water
systems and for glycol systems to glycol fill tanks (provided by others).
1.4.7 Allow for an additional ball valve at 1500mm above floor level when
installing drains, air vents or strainers higher than 1800mm above floor level.
1.4.8 Install equipment, rectangular cleanouts and similar items parallel to or
perpendicular to building lines.
1.4.9 Heat exchanger locations shall not be changed without prior approval of
Consultant.
1.4.10 The Work requires piping to be routed through spaces that could be
congested. Recommended pipe routes are shown on the drawings. In general, piping 80mm and smaller is to be field routed by the Contractor. For pipe larger than 80mm the Contractor may choose an alternate route if it is reviewed and accepted by the Consultant. Pipe shall be routed with consideration for overhead clearance, for required pipe supports, and to avoid blocking service pathways and access to other utility valves and equipment.
1.4.11 Contractor shall:
.1 Identify and confirm all support locations.
.2 Provide any supplemental structural steel required for pipe supports.
.3 Provide support details sealed and signed by a licensed structural
engineer for pipe sizes larger than 150mm. Such details shall confirm the building structure is suitable for the pipe attachments and resulting loads.
1.4.12 Tie-ins to existing piping shall not be changed without prior approval of
Consultant (NOT APPLICABLE).
1.4.13 Provide all temporary bypasses, end caps and connections to enable flushing
and testing of system. Submit details for flushing and testing of lines to Engineer for review, as specified in Section 15180.
1.5 T
RIALU
SAGE1.5.1 Consultant and Owner may use equipment and systems for test purposes
prior to acceptance.
1.5.2 Provide labour, material, and instruments required for testing.
1.6 P
ROTECTION OFO
PENINGS1.6.1 Protect piping, equipment and system openings from dirt, dust, and other
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 3 OF 11
PROJECT NO.210243 JUNE 23,2010
1.7 E
QUIPMENTS
UPPORTS1.7.1 Equipment supports supplied by equipment manufacturer are specified in
Section 15061.
1.7.2 Fabricate equipment supports not supplied by equipment manufacturer from
structural grade steel. Submit structural calculations with shop drawings.
1.7.3 Install base mounted equipment on chamfered edge housekeeping pads,
minimum of 100mm high and 100 mm larger than equipment dimensions all around, or as shown on drawings. Pads to be constructed from concrete; 30 MPa yield strength after 28 days of curing time. Housekeeping pads shall be sealed against water ingress.
1.7.4 Provide pipe stanchions at heat exchanger connections as shown on
drawings and/or as directed by Consultant.
1.8 S
LEEVES1.8.1 Pipe and conduit sleeves: install at all points where pipes pass through
masonry, concrete or fire rated assemblies and as indicated.
1.8.2 Shall be schedule 40 steel pipe.
1.8.3 Sleeves with annular fin continuously welded at midpoint shall be installed:
.1 Through foundation walls.
.2 Where sleeve extends above finished floor.
1.8.4 Sizes: minimum 6mm clearance all around or as stated on penetration
drawing for pipes subjected to thermal movement, between sleeve and uninsulated pipe or between sleeve and insulation.
1.8.5 Terminate sleeves flush with surface of concrete and masonry walls, concrete
floors on grade and 25mm above other floors.
1.8.6 Prime all sleeves with rust inhibitive primer paint.
1.8.7 Fill voids around pipes:
.1 For pipes subject to thermal movement provide flexible fire stop. For
other pipework caulk between sleeve and pipe in foundation walls and below grade floors with waterproof fire retardant non-hardening mastic.
.2 Fill between hole and pipe in foundation walls with non-shrink grout.
.3 Where sleeves pass through walls or floors, provide space for fire
stopping. Where pipes/ducts pass through fire rated walls, floors and partitions, maintain fire-rating integrity.
.4 Ensure no contact between copper tube or pipe and ferrous sleeve.
.5 Fill future-use sleeves with lime plaster or other easily removable filler.
.6 Coat exterior exposed steel sleeves with two coats of rust inhibitive
paint.
.7 Coat around exterior wall penetrations with two coats of tar based
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 4 OF 11
PROJECT NO.210243 JUNE 23,2010
.8 Coat exposed exterior surfaces of wire brushed ferrous sleeves with
heavy application of zinc rich paint to CGSB 1-GP-181M+Amdt-Mar-78.
.9 Slab on Grade Floor Penetrations: Fill between hole and pipe with
non-shrink grout for heating pipes.
.10 Frost Walls: Fill between hole and pipe with non-shrink grout for
heating pipes.
.11 Basement Walls: Fill between pipe sleeve and pipe casing with a seal
ring and non-shrink grout for heating pipes.
.12 Valve Chamber Walls: Fill between hole and pipe in with non-shrink
grout and seal ring for heating pipes.
1.9 P
REPARATION FORF
IRE STOPPING1.9.1 Provide for fire stopping material and insulation within annular space between
pipes, ducts, insulation and adjacent fire separation.
1.9.2 Insulated pipes and ducts: ensure integrity of insulation and vapor barrier at
fire separation.
1.9.3 Uninsulated unheated pipes not subject to movement: no special preparation.
1.9.4 Uninsulated heated pipes subject to movement: wrap with non-combustible
smooth material to permit pipe to move without damaging fire stopping material
1.10 E
SCUTCHEONS1.10.1 Provide escutcheons on pipes passing through walls, partitions, floors and
ceilings in finished areas.
1.10.2 Provide chrome or nickel-plated brass or Type 302 stainless steel, one-piece
type with set screws.
1.10.3 Outside diameter to cover opening or sleeve.
1.10.4 Inside diameter to fit around finished pipe.
1.11 C
UTTING ANDP
ATCHING1.11.1 Approvals
.1 Submit written request in advance of cutting or alteration which
affects:
.1 Structural integrity of any element of Project.
.2 Integrity of weather-exposed or moisture-resistant elements.
.3 Efficiency, maintenance, or safety of any operational element.
.4 Visual qualities of sight-exposed elements.
.5 Work of Owner or separate Contractor.
.6 Penetration of fired rated assemblies.
1.11.2 Inspection
.1 Inspect existing conditions, including elements subject to damage or
movement during cutting and patching.
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 5 OF 11
PROJECT NO.210243 JUNE 23,2010
.3 Beginning of cutting or patching means acceptance of existing
conditions. 1.11.3 Execution
.1 Perform cutting, fitting, and patching including excavation and fill, to
complete the Work.
.2 Remove and replace defective and non-conforming work.
.3 Provide openings for penetrations of mechanical and electrical work.
.4 Perform work in such a way as to avoid damage to other work.
.5 Prepare proper surfaces to receive patching and finishing.
.6 Employ original installer to perform cutting and patching for
weather-exposed and moisture-resistant elements, and sight-weather-exposed surfaces.
.7 Cut rigid materials using power saw or core drill. Pneumatic or impact
tools are not allowed.
.8 Restore work with new products in accordance with Contract
Documents.
.9 Fit work airtight to pipes, sleeves, ducts, conduit, and other
penetrations through surfaces.
.10 At penetration of fire-rated wall, ceiling, or floor construction,
completely seal voids with fire-rated material through the full thickness of construction element. Seal with non-hardening, resilient sealer. Package material and sealer to be UL approved for penetrations through fire rated walls and floors.
.11 Refinish surfaces to match adjacent finishes. For continuous
surfaces, refinish to nearest intersection. For an assembly, refinish entire unit.
.12 Remove and reinstall all suspended ceilings and replace any
damaged tiles or tee-bars.
.13 Where required, electrical fixtures shall be disconnected and
reinstalled or relocated.
1.12 T
ESTS1.12.1 Hydrotest and/or pneumatic test all piping systems as required by applicable
piping code and as identified in project specifications. Refer to Section 15180 for the pressure testing procedure for the primary heating piping.
1.12.2 Give 72 hours written notice of test date.
1.12.3 Insulate or conceal work only after testing and approval by Consultant.
1.12.4 Conduct tests in presence of Consultant and, as required, in the presence of
British Columbia Safety Authority representative.
1.12.5 Welding examination and non-destructive testing as per Section 15051 of this
Specification.
1.12.6 Provide spool pieces for heat exchangers, flow meters and control valves for
purposes of system testing and flushing.
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 6 OF 11
PROJECT NO.210243 JUNE 23,2010
1.12.8 Piping:
.1 Prior to tests, isolate all equipment or other parts, which are not
designed to withstand test pressures or test medium.
.2 Hydraulically test at minimum test pressure according to Section
15051 and 15180
.3 Continuously monitor and record (log) pressure during test.
.4 Maintain test pressure for 4 hours, unless otherwise specified.
.5 Pressure test piping systems at 1.5 times system design pressure,
unless otherwise stated.
1.12.9 Equipment: performance test as specified in relevant sections.
1.12.10 Prepare Test Document and Include in Contractor’s QC Manual with Final
Submissions. See Section 01780 – Closeout Submittals.
1.13 P
AINTING1.13.1 Refer to Section 15280 – Painting.
1.13.2 Owner to approve paint colour selection and specification details.
1.13.3 Apply at minimum one coat of rust inhibitive paint to ferrous supports and site
fabricated work.
1.13.4 Prime and touch up marred finished paintwork to match original.
1.13.5 Restore to new condition, finishes that have been damaged too extensively to
be merely primed and touched up. This includes all pipe penetrations.
1.13.6 Paint all gas piping including vents with one coat of primer and two coats of
finish paint. Paint colour to meet the applicable code requirements.
1.14 A
CCESSD
OORS(N
OTA
PPLICABLE)
1.14.1 Supply access doors for operating, inspecting, adjusting and servicing
concealed mechanical equipment.
1.14.2 Flush mounted [600 x 600] mm for body entry and [300 x 300] mm for hand
entry unless otherwise noted. Doors to open 180º, have rounded safety corners, concealed hinges, screwdriver latches and anchor straps.
1.14.3 Material:
.1 Special areas such as tiled or marble surfaces: use stainless steel
with brushed satin or polished finish as directed by Consultant.
.2 Remaining areas: use prime coated steel.
1.14.4 Installation:
.1 Locate so that concealed items are accessible.
.2 Locate so that hand or body entry (as applicable) is achieved.
.3 Installation is specified in applicable sections.
.4 Paint the access hatch the colour specified by the Consultant’s
1.14.5 Acceptable material:
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 7 OF 11
PROJECT NO.210243 JUNE 23,2010
1.15 D
IELECTRICC
OUPLINGS1.15.1 To be compatible with and to suit pressure rating of piping system.
1.15.2 Install dielectric couplings where pipes of dissimilar metals are joined and
when joining buried coated (e.g. yellow-jacket) or insulated district cooling piping to building cooling piping.
1.15.3 To be compatible with and to suit pressure rating of piping system.
1.15.4 Pipes NPS less than or equal to 50 mm (2”): unions or valves in brass or
bronze will be acceptable between copper and steel. Dielectric unions will be acceptable between copper and steel where permitted by Code.
1.15.5 Pipes NPS greater than or equal to 65mm (2½”): electric insulating/isolating
kits between flanges and bolts. Full face isolating gasket is required between flanges and bolts.
1.16 D
RAINA
NDV
ENTP
IPING1.16.1 Interior piping: Locate at low points and at section isolating valves, unless
otherwise specified.
1.16.2 Exterior piping: Locate as specified on drawings.
1.16.3 Minimum NPS 20mm (¾”) as specified in Section 15180. End caps to be
threaded forged steel quality.
1.16.4 Pipe manual drains, air vents, and strainers downwards, with a screwed cap
400 mm above floor level.
1.16.5 For any drains, air vents or strainers installed over 1800 mm above floor
level, allow for an additional ball valve at an elevation of 1000 mm above floor level - screw cap is no longer required.
1.16.6 Air vents shall be piped away from piping and equipment, with a downward
turn valve. Allow room for a bucket to catch water.
1.17 D
EMONSTRATION ANDO
PERATING ANDM
AINTENANCEI
NSTRUCTIONS1.17.1 Provide tools, equipment and personnel to instruct operating and
maintenance personnel in start-up, commissioning, and regular operation. This is to occur during regular working hours, prior to acceptance.
1.17.2 Organize and assist manufacturers to provide demonstrations and
instructions, as specified throughout Section 15.
1.17.3 Use operation and maintenance manuals, as-built drawings, audio visual
aids, etc. as part of instruction materials.
1.17.4 Instruction duration time requirements as specified in appropriate sections.
1.17.5 Where deemed necessary, Owner and/or Consultant may record these
demonstrations on videotape for future reference.
1.18 C
LOSEOUTS
UBMITTALS1.18.1 Provide operation and maintenance data for incorporation into manual as
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 8 OF 11
PROJECT NO.210243 JUNE 23,2010
1.18.2 Operation and maintenance manual to be approved by, and final copies
deposited with, Consultant before final inspection.
1.19 O
PERATION ANDM
AINTENANCEM
ANUAL1.19.1 Refer to Section 01780: Closeout Submittals for more details.
1.20 S
HOPD
RAWINGS1.20.1 Submit shop drawings and product data in accordance with Section 01330:
Submittal Procedures.
1.20.2 Drawing review by Consultant is for the sole purpose of ascertaining
conformance with the general design concept. The Contractor is responsible for the design details inherent in the shop drawings.
1.20.3 Drawing review does not relieve the Contractor of responsibility for errors or
omissions in the shop drawings or of his responsibility for meeting all requirements of the Contract Documents.
1.20.4 Shop drawings and product data shall indicate:
.1 Mounting arrangements.
.2 Operating and maintenance clearances. e.g. access door
swing.
.3 Maintenance lifting beam locations, bottom of lifting beam
elevation and gross lifting weight.
.4 Detailed drawings of bases, supports, and anchor bolts.
.5 Acoustical sound power data, where applicable.
.6 Points of operation on performance curves.
.7 Manufacturer certification as to current model production.
.8 Certification of compliance to applicable codes.
1.20.5 In addition to transmittal letter referred to in Section 01330: Submittal
Procedures: use MCAC "Shop Drawing Submittal Title Sheet." Identify section and paragraph number.
1.21 A
S-B
UILTD
RAWINGS1.21.1 As-built drawings:
.1 Submit production of as-built drawings 14 days prior to Substantial
Completion of the work.
.2 Identify each drawing in lower right hand corner in letters at least 12
mm high as follows: - "AS BUILT DRAWINGS: THIS DRAWING HAS BEEN REVISED TO SHOW MECHANICAL/ELECTRICAL SYSTEMS AS INSTALLED" (Signature of Contractor) (date) (copies of change orders).
.3 Submit to Consultant for approval and make corrections as directed.
.4 Submit completed, reproducible as-built drawings with Operating and
Maintenance Manuals.
1.22 C
LEANING1.22.1 Clean the installation areas to as-received condition. Remove debris and
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 9 OF 11
PROJECT NO.210243 JUNE 23,2010
1.22.2 Prior to the operation of any of the equipment, the contractor shall clean the
entire plant space such that it is free of any dust and debris that may become airborne during ventilation system operation and/or equipment operation. This includes the cleaning of all floor surfaces, wall surfaces and equipment surfaces.
1.22.3 Clean interior and exterior of all systems including strainers. The Contractor
shall be responsible for maintaining the condition of piping, heat exchanger(s), strainers, and accessories until such a time that substantial completion of the work has been achieved.
1.22.4 In preparation for final acceptance, clean and refurbish all equipment to
operating condition, including replacement or cleaning of all filters in all piping systems.
1.23 C
ONNECTION TOE
XISTINGD
ISTRIBUTIONS
YSTEM(N
OTA
PPLICABLE)
1.23.1 Make connection to existing distribution system at a time approved by Owner
and Consultant.
1.23.2 Request written approval from Owner for when tie-in connections can be
made.
1.23.3 Allow for draining and refilling existing district energy system.
1.23.4 Contractor shall be responsible for repair or replacement, as instructed by
Consultant, for damage to existing distribution system during performance of Work.
1.24 C
ONNECTIONT
OP
LANTS
YSTEMS(N
OTA
PPLICABLE)
1.24.1 Flush and clean piping prior to tie-in connection to heating and/or cooling
plant.
1.24.2 Request for tie-in connection to heating and/or cooling plant systems to be
made in writing to Owner. Approval at sole discretion of Owner.
1.24.3 Be responsible for damage to plant system during performance of Work, by
repair or replacement, as instructed by Consultant,.
1.25 F
LUSHING ANDF
ILLING1.25.1 Circulate, clean and flush in accordance with Section 15180.
1.26 S
TART-
UP ANDC
OMMISSIONING1.26.1 Refer to Paragraph 1.10 in Section 01001. Provide assistance to the Owner
during start-up and commissioning, and rectify deficiencies. Conduct trouble shooting and otherwise take corrective action of the installed systems.
1.26.2 Refer to Section 15180: District Heating Primary Piping for procedures.
1.27 S
ITER
ECORDS1.27.1 Refer to Section 01780: Closeout Submittals for more details.
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 10 OF 11
PROJECT NO.210243 JUNE 23,2010
1.28.1 Submit to applicable Mechanical Inspection Department and supply the
necessary number of drawings and specifications for examination and approval prior to commencement of work.
1.28.2 Organize and obtain all necessary permits and approvals from the Local,
Regional and Provincial Authorities prior to commencement of work.
1.28.3 Pay all associated fees.
1.29 C
ODES ANDR
EGULATIONS1.29.1 Codes and regulations referred to throughout the various sections of these
specifications shall mean the latest edition at the time of tendering, even if indicated otherwise.
1.30 D
EFICIENCYL
IST1.30.1 Lists of work deficiencies will be issued at anytime. Rectify the work
immediately to the satisfaction of Owner.
1.30.2 Submit requests for substantial completion (takeover) inspection in writing.
1.31 I
NTERPRETATIONS OFP
LANS&
S
PECIFICATIONS1.31.1 The Consultant's interpretation of plans and specifications shall be final.
CITY OF VANCOUVER MECHANICAL GENERAL REQUIREMENTS
NEUETSEXPANSION SECTION 15010 PAGE 11 OF 11
PROJECT NO.210243 JUNE 23,2010
2
PART 2. - APPENDIX 1 – Owner Supplied Equipment List
City of Vancouver
Owner Supplied Equipment List June 23, 2010
Item Description Qty.
1887 Crowe Street
HX-101 Heat Exchanger, Space Heating 1
HX-501 Heat Exchanger, Domestic Hot Water 1
PLC Programmable Logic Controller 1
FCV Flow Control Valves 3
PT Water Pressure Transmitters 2
XQI Energy Meter 1
FE/FIT Flow Element, Indicator & Transmitter 1
TT/TE 1## Primary Hot Water Temperature Transmitters 2
TT/TE 2## Secondary Hot Water Temperature Transmitters 2
TT/TE 5## Domestic Water Temperature Transmitters 3
TT/TE 9## Ambient Air Temperature Transmitter 1
1723 Main Street
HX-101 Heat Exchanger, Space Heating 1
HX-102 Heat Exchanger, Indirect Domestic Hot Water & Heat Pump Loop 1
PLC Programmable Logic Controller 1
FCV Flow Control Valves 2
PT Water Pressure Transmitters 2
XQI Energy Meter 1
FE/FIT Flow Element, Indicator & Transmitter 1
TT/TE 1## Primary Hot Water Temperature Transmitters 2
TT/TE 2## Secondary Hot Water Temperature Transmitters 4
TT/TE 9## Ambient Air Temperature Transmitter 1
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 1 OF 7
PROJECT NO.210243 JUNE 23,2010
SECTION 15051 PIPE WELDING
1
PART 1. - GENERAL
1.1 R
EFERENCES1.1.1 American National Standards Institute/American Society of Mechanical
Engineers (ANSI/ASME)
.1 ANSI/ASME B31.1, Power Piping.
.2 ANSI/ASME Boiler and Pressure Vessel Code:
.i Section I: Power Boilers.
.ii Section V: Nondestructive Examination.
.iii Section IX: Welding and Brazing Qualifications.
1.1.2 American National Standards Institute/American Water Works Association
(ANSI/AWWA)
.1 ANSI/AWWA C206, Field Welding of Steel Water Pipe.
1.1.3 American Welding Society (AWS)
.1 AWS B3.0, Welding Procedures and Performance Qualifications.
.2 AWS C1.1M/C1.1, Recommended Practices for Resistance Welding.
.3 AWS W1, Welding Inspection.
.4 AWS Z49.1, Safety in Welding, Cutting and Allied Process.
1.1.4 Canadian Standards Association (CSA International)
.1 CSA W48, Filler Metals & Allied Materials for Metal Arc Welding.
.2 CSA B51, Boiler, Pressure Vessel and Pressure Piping Code.
.3 CAN/CSA-W117.2, Safety in Welding, Cutting and Allied Processes.
.4 CSA W178.1, Certification of Welding Inspection Organizations.
.5 CSA W178.2, Certification of Welding Inspectors.
.6 CSA W59 – 03, Welded Steel Construction.
1.1.5 Canadian General Standards Board
.1 CGSB 48-GP-2M, Spot Radiography of Welded Butt Joints in Ferrous
Materials.
1.2 S
UBMITTALS1.2.1 Submit, in accordance with Section 01330 – Submittal Procedures,:
.1 Each welder’s qualification
.2 Confirmation that project welding procedures are suitable for the
project and that the procedures have been registered and approved by the Provincial Boilers Branch or Safety Authority.
1.2.2 Inspection and Test Plan
.1 Weld maps to be provided in Operation and Maintenance Manual.
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 2 OF 7
PROJECT NO.210243 JUNE 23,2010
1.3.1 Welding qualifications to be in accordance with CSA B51 or ASME B31.1
section 127.5.
1.3.2 Use qualified and licensed welders possessing certificate for each procedure
to be performed from authority having jurisdiction.
1.3.3 Submit welder's qualifications to Consultant.
1.3.4 Each welder shall possess an identification stamp, issued by an authority
with jurisdiction, for stamping each weld performed.
1.3.5 Buried pre-insulated district heating pipe work (Not Applicable):
.1 Each welder shall be prequalified by Consultant and testing agent as
described in this section, prior to commencement of welding on the piping system.
1.4 I
NSPECTORQ
UALIFICATIONS1.4.1 Inspectors to be qualified to CSA W178.2.
1.4.2 Radiography: CGSB certified to Level II or higher with a piping endorsement.
1.4.3 Visual: CGSB certified to Level II or higher with a piping endorsement.
1.4.4 Ultrasonic: CBSB certified to Level II or higher with a piping endorsement.
1.5 W
ELDINGP
ROCEDURES1.5.1 Registration of welding procedures in accordance with CSA B51 or ASME
B31.1 Section 127.5.
1.5.2 Copy of locally approved welding procedures to be available for inspection at
all times.
1.5.3 Safety in welding, cutting and allied processes to be in accordance with
CAN/CSA-W117.2.
2
PART 2. - PRODUCTS
2.1 F
ILLERM
ATERIALS2.1.1 Electrodes to be in accordance with CSA W48 Series.
2.1.2 Identify all filler materials by the ASME Specification number and the AES
classification number.
2.1.3 Utilize filler metal storage and handling procedures to maintain the material in
a clean and dry condition up to the time of use.
2.1.4 Low hydrogen electrodes shall be handled and stored in accordance with the
manufacturer’s recommendations to avoid pickup and to retain the low hydrogen characteristics of the electrode.
2.1.5 A method of keeping electrodes warm and moisture free shall be available
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 3 OF 7
PROJECT NO.210243 JUNE 23,2010
2.2 B
ASEM
ATERIALS2.2.1 Use base materials consisiting of carbon steels listed in Table 126.1 or ANSI
B31.1 that have ASME equivalents listed in P-1 group No. 1, Table QW422 of ASME Section IX. The ASTM materials listed or their ASME equivalents are acceptable.
2.2.2 All base materials shall be identified by specification number and grade,
class, or type when recorded on a welding procedure specification’s qualification record, or the record of welder qualification test.
2.2.3 Use ring or saddle reinforcements, doublers, lugs, etc., made from material
having the same general chemical composition as the pipe headers, or nozzles to which they will be joined unless otherwise specified or unless prior written approval is obtained from the Consultant.
3
PART 3. - EXECUTION
3.1 W
ORKMANSHIP3.1.1 Welding to be in accordance with ANSI/ASME B31.1, ANSI/ASME Boiler and
Pressure Vessel Code, Sections I and IX and ANSI/AWWA C206, using procedures conforming to AWS B3.0, AWS C1.1, and special procedures specified elsewhere in Division 15.
3.2 I
NSTALLATIONR
EQUIREMENTS3.2.1 Identify each weld with the welder's identification stamp.
3.2.2 Prepare and maintain a weld location map identifying pipe spool, specific
weld location on each spool, and the welder that performed each weld.
3.2.3 Backing rings:
.1 The use of backing rings will not be permitted.
3.2.4 Fittings:
.1 NPS 2” and smaller: install welding type sockets.
.2 Branch connections: install welding tees or forged branch outlet
fittings.
3.3 Q
UALITYA
SSURANCE3.3.1 Maintain a Quality Assurance (QA) Program for defect prevention and in
service reliability conforming to CSA B51 Part 1.
3.3.2 Maintain an on-site copy of the Contractor’s QA Program and Quality Control
Manual including welder certifications, weld procedures and radiography and/or ultrasonic test results.
3.3.3 Maintain during the construction period, weld maps identifying the location of
all welds performed on the piping system together with the identification of the welder performing the weld.
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 4 OF 7
PROJECT NO.210243 JUNE 23,2010
3.4.1 Review all weld quality requirements and defect limits of applicable codes
and standards with the Consultant before any Work is started.
3.4.2 Formulate and submit to Consultant "Inspection and Test Plan".
3.4.3 Provide qualified welding inspector to visually inspect all stages of welding
procedures in accordance with AWS W1.
3.4.4 Submit welding procedures, which have been registered and approved by the
Provincial Boilers Branch, to the Consultant for approval.
3.4.5 Prepare a separate welding procedure for each method intended to be
employed during construction.
3.4.6 Ensure all welders are qualified for each procedure to be welded. The
Consultant may waive the test upon proof of qualification under an equivalent test.
3.4.7 Do not conceal welds until they have been inspected, tested and approved by
Inspector.
3.4.8 Prequalification Tests
.1 The prequalification test as described below is in addition to that
testing required by the regulatory authority.
.2 The first three welds by each welder are to be radiographically tested
by testing agent approved by Owner.
.3 Provide all necessary fittings and attachments to permit the welds to
be pressure tested with water.
.4 Welders will be considered approved only after completing three
successive welds to approval of radiographic testing agent, and after providing the proper welding qualification documentation. Final approval of each welder is at sole discretion of Consultant.
.5 Incur all testing, and re-testing, costs until three successive welds
have been completed.
3.4.9 Repair or replace all defects as required by codes and as specified herein.
3.4.10 The Owner/Consultant reserves the right to request a welder to be removed
from a project due to poor performance including weld failure rate deemed to be excessive.
3.5 S
PECIALISTE
XAMINATIONS ANDT
ESTS3.5.1 General:
.1 Perform examinations and tests by Inspector qualified in accordance
with CSA W178.1 and CSA W178.2, CGSB 48-GP-2M, and approved by Consultant.
.2 Testing and examination in accordance with ANSI/ASME Boiler and
Pressure Vessels Code, Section V, CSA B51 and requirements of authority having jurisdiction.
.3 Hydrostatically test all welds to requirements of ANSI/ASME B31.1.
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 5 OF 7
PROJECT NO.210243 JUNE 23,2010
.4 Visually inspect all welds, including entire circumference of weld
externally and, wherever possible, internally, in accordance with ASME B31.1 code requirements.
.5 Interpretation of radiographic films and performance of visual
inspection of welds to be conducted by a technician with a minimum CGSB Level II certification for the method of inspection utilized.
.6 Payment for the original radiographic or visual inspections shall be
paid by the Owner or from a Contractor’s provisional sum if identified in the contract.
.7 Costs of subsequent re-inspections of welds that failed inspection and
were repaired, will be paid by the contractor.
3.5.2 Weld Procedure;
.1 Welding shall be done in accordance with the type of piping system to
be welded and associated piping code standard that would apply (either ASME B31.1 as indicated in associated piping system specification)
.2 Contractor shall submit confirmation to Owner/Consultant that
proposed project welding procedures are registered and approved by the Provincial Boilers Branch or Safety Authority.
.3 Contractor shall have a separate welding procedure for each method it
intends to employ during construction.
.4 All welders shall be qualified for each procedure to be welded. Owners
Representative may waive the test upon proof of qualification under an equivalent test.
.5 Consultant may use any method of inspection necessary to establish
quality control and assure adherence to proper welding procedures. Owners Representative shall have the right to reject any weld not meeting the requirements of this specification.
.6 Selection of welds for inspection will be made by the Consultant.
.7 The method of inspection to be used may be changed by the Owner at
their discretion.
.8 The limitations as to weld imperfections shall be in accordance with
the applicable section of the ASME B31.1 piping codes.
.9 Structural welding shall conform to CSA Standard W59.
.10 Weld Inspections will be performed as a minimum, by the method and
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 6 OF 7
PROJECT NO.210243 JUNE 23,2010
Table 1: Weld Inspection
Piping Design Code Frequency of Inspection
Weld Setup Radiographic
Inspection Visual
B31.1 Power Piping –
Process Hot Water 10% of all welds
Owners Discretion (minimum or 10% of all welds) Owners Discretion (Minimum 75% of completed welds and a minimum 20% of root passes) B31.1 Bldg Services Piping – Process Chilled Water and Condenser Piping.
10% of all welds N/A
Owners Discretion (Minimum 75% of completed welds and a minimum 20% of root passes) B31.9 Bldg Services
Piping – All Other Piping Except for Process Chilled Water and Condenser Piping.
N/A N/A
Owners Discretion (Minimum 50% of completed welds)
.11 A minimum of 2 welds or 10%, whichever is the greater, from each
welder will be radiographed for B31.1 piping.
3.5.3 Defective Welds Identified by radiographic, visual or hydrostatic testing:
.1 If any weld fails its inspection, (or leaks in the pressure test), the failed
weld will be repaired and inspected per the method in Table 1 above.
.2 Further, the Consultant will select another 10% of the welds (not
including the repair) from the identified welder, for additional NDE testing per Table 1 above.
.3 This additional inspection process repeats as more welds from the
same welder are found to be deficient in each 10% grouping of welds inspected.
.4 The Owner reserves the right to request any welder be replaced if the
number of failures are deemed excessive by the Owner. The welder will not be permitted to make further welds on the project without the approval of the Consultant and having been re-tested to determine the welder’s competence.
3.5.4 All tests indicating defective welds and re-tests (all pipe) will be at the
Contractor’s own expense.
3.5.5 Hydrostatically test all welds to requirements of the applicable ANSI/ASME
piping code (B31.1) and as described below:
.1 Refer to Section 15180 – District Heating Primary Piping for
CITY OF VANCOUVER PIPE WELDING
NEUETSEXPANSION SECTION 15051 PAGE 7 OF 7
PROJECT NO.210243 JUNE 23,2010
3.5.6 Radiographic film:
.1 Identify each radiographic film with date, location, name of welder, and
submit to Consultant. Replace film if rejected because of poor quality. Type 4 film shall not be used.
.2 Interpretation of radiographic films: by CGSB Level II qualified
radiographer.
3.6 D
EFECTSC
AUSINGR
EJECTION3.6.1 As described in ANSI/ASME B31.1 and ANSI/ASME Boiler and Pressure
Vessels Code.
3.6.2 Rejection of welds will be based on the weld evaluation as performed by a
qualified NDT technician.
3.7 R
EPAIR OFW
ELDS,
W
HICHF
AILEDT
ESTS3.7.1 Bear the cost of reinspection, retesting and repairing or reworking welds.
3.8 C
LAIMSA
GAINSTO
WNER FORD
ELAYS3.8.1 Claims against Owner for delays in completion of project will not be
entertained for reason of failures of welds to pass examinations.
3.9 J
OINTF
IT-U
P3.9.1 Valves welded into the system shall be in the open position as the welding is
carried out.
3.9.2 The geometry of pipe weld joints (i.e. joint preparation and root opening) shall
be in accordance with the tolerance specified by the weld joint sketches contained in the welding procedures submitted to the Consultant.
3.9.3 In cases where the internal misalignment exceeds 1/16”, trim the inside of the
component with the wall extending internally so that the adjoining internal surfaces are approximately flush. Ensure that this does not result in a piping component wall thickness less than the minimum design thickness and that the change in contour does not exceed 30 degrees.
3.10 T
RANSITION,
D
IFFERENTO
UTSIDED
IAMETERS3.10.1 When pipes of different outside diameters are to be welded together, follow
either of the two listed procedures:
.1 Taper the outside diameter of the larger pipe by grinding or matching
before welding to the outside diameter of the smaller pipe, the angle not exceeding 30°.
.2 Fill the weld joint with weld metal, flush with the outside surface of the
pipe having the larger diameter. Ensure the weld metal transition between the larger and smaller pipe does not exceed 1:3, which may be obtained by grinding.
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 1 OF 9
PROJECT NO.210243 JUNE 23,2010
SECTION 15061 PIPE HANGERS AND SUPPORTS
1
PART 1. - GENERAL
1.1 R
EFERENCES1.1.1. American National Standards Institute/American Society of Mechanical
Engineers (ANSI/ASME)
.1 ANSI/ASME B31.1 [04], Power Piping.
.2 ANSI/ASME B31.5, Refrigeration Piping
1.1.2. American Society for Testing and Materials International (ASTM)
.1 ASTM A 125-[1996(R2001)], Specification for Steel Springs, Helical,
Heat-Treated.
.2 ASTM A 307-[04], Specification for Carbon Steel Bolts and Studs,
60,000 PSI Tensile Strength.
.3 ASTM A 563-[04a], Specification for Carbon and Alloy Steel Nuts.
1.1.3. Canadian Standards Association
.1 CSA B51, Boiler, Pressure Vessel, and Pressure Piping Code.
.2 CSA B52-05, Mechanical Refrigeration Code
1.1.4. Manufacturer's Standardization Society of the Valves and Fittings Industry
(MSS)
.1 MSS SP 58-[2002], Pipe Hangers and Supports - Materials, Design
and Manufacture.
.2 ANSI/MSS SP69-[2003], Pipe Hangers and Supports - Selection and
Application.
.3 MSS SP 89-[2003], Pipe Hangers and Supports - Fabrication and
Installation Practices.
1.1.5. Underwriter's Laboratories of Canada (ULC)
1.2 S
HOPD
RAWINGS ANDP
RODUCTD
ATA1.2.1. Submit shop drawings and product data in accordance with Section 01330:
Submittal Procedures.
1.2.2. Product data: provide manufacturer’s printed product literature, specifications
and data sheets for products; include product characteristics, performance criteria, physical size, finish, and limitations, engineering data and installation instructions for the following:
.1 Upper attachment.
.2 Middle attachment.
.3 Pipe attachment.
.4 Riser clamps.
.5 Shields and saddles.
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 2 OF 9
PROJECT NO.210243 JUNE 23,2010
.7 Pre-Engineered Restraints
.8 Pre-Engineered Anchors
.9 Pre-Engineered Spring Hangers
.10 Spring Hangers
.11 Connection to equipment and structures.
1.2.3. Quality assurance submittals: submit the following in accordance with Section
01330 – Submittal Procedures.
.1 Certificates: submit certificates signed by manufacturer certifying that
materials comply with specified performance characteristics and physical properties.
.2 Instructions: submit manufacturer's installation instructions.
1.3 D
EFINITIONS1.3.1. Cold Piping: all piping of nominal temperature 25C or less.
1.3.2. Hot Piping: all piping of nominal temperature greater than 25C.
1.4 M
AINTENANCED
ATA1.4.1. Provide maintenance data for incorporation into manual specified in Section
15010 - Mechanical General Requirements.
2
PART 2 - PRODUCTS
2.1 G
ENERAL2.1.1. Construct pipe hangar and supports to manufacturer’s recommendations
utilizing manufacturer’s regular production components, parts and assemblies.
2.1.2. Fabricate hangers, supports and sway braces in accordance with ANSI B31.1
and MSS-SP-58.
2.1.3. Use components for intended design purposes only. Do not use for rigging or
erection purposes.
2.1.4. Provide supplementary steel members where structural bearing does not
exist or inserts are not in suitable locations.
2.1.5. Obtain all necessary approvals before attaching fixings to building structure.
2.2 F
INISHES:
2.2.1. Pipe hangers and supports: [galvanized] [painted with zinc-rich paint] after
manufacture.
2.2.2. Use [electro-plating galvanizing process] [hot dipped galvanizing process].
2.2.3. Ensure steel hangers in contact with copper piping are [copper plated] [epoxy
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 3 OF 9
PROJECT NO.210243 JUNE 23,2010
2.3 U
PPERA
TTACHMENTS2.3.1. To concrete:
.1 Inserts for cast-in-place concrete: galvanized steel wedge to
MSS-SP-58, type 18. ULC listed for pipe NPS ¾” through NPS 8”. Maximum load 1200lb.
.i Acceptable material: Anvil Wedge Type Concrete Insert Fig. 281.
.2 Ceiling: carbon steel plate with clevis, for surface mount: malleable
iron socket and expansion case and bolt. Acceptable material: Anvil Universal C-type Clamp Fig. 92.
.i Acceptable material: Anvil Concrete Clevis Plate Fig. 49
2.3.2. Steel beam (bottom flange):
.1 Cold piping NPS ≤2”: malleable iron C clamp to MSS-SP-58, type 23.
ULC listed.
.i Acceptable material: Anvil Universal C-type Clamp Fig. 92.
.2 Cold Piping NPS ≥2½”: steel beam clamp to MSS-SP-58, type 28 or
29, or welded beam attachment, type 22. ULC listed.
.i Acceptable material: Anvil UFS Beam Clamp with Weldless Eye
nut Fig. 292 or Welded Beam Attachment Fig. 66.
.3 Hot piping NPS All sizes: steel beam clamp to MSS-SP-58, type 28 or
29, or welded beam attachment, type 22. ULC listed.
.i Acceptable material: Anvil UFS Beam Clamp with Weldless Eye
nut Fig. 292 or Welded Beam Attachment Fig. 66.
2.3.3. Steel beam (top):
.1 Cold piping NPS ≤2”: malleable iron "top of beam" C clamp to
MSS-SP-58, type 19. ULC listed.
.i Acceptable material: Anvil Universal C-type Clamp Fig. 92.
.2 Cold piping NPS 2½” to NPS 8”: steel jaw, hook rod with nut, spring
washer and plain washer, to MSS-SP-58, type 25. ULC listed.
.i Acceptable material: Anvil Top Beam Clamp Fig. 227.
.3 Cold and hot piping of all sizes. Welded beam attachment
MSS-SP-58, type 22
.i Acceptable material: Anvil Welded Beam Attachment Fig. 66.
2.3.4. Steel joists (including back to back channels):
.1 Cold piping all sizes: steel washer plates with double locking nut,
carbon steel clevis and malleable iron socket.
.i Acceptable material: Anvil Steel Washer Plate Fig. 60.
.2 Cold and hot piping of all sizes. Welded beam attachment
MSS-SP-58, type 22.
.i Acceptable material: Anvil Welded Beam Attachment Fig. 66.
2.3.5. Steel channel or angle (bottom) - Requires permission From Structural
Engineer:
.1 Cold piping NPS ≤2”: malleable iron C clamp to MSS-SP-58, type 23.
ULC listed.
.i Acceptable material: Anvil C-Clamp Fig. 86.
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 4 OF 9
PROJECT NO.210243 JUNE 23,2010
.i Acceptable material: Myatt Channel Clamps Fig. 502 or 503.
.3 Hot Piping All sizes: universal channel clamp. ULC listed.
.i Acceptable material: Myatt Channel Clamps Fig. 502 or 503.
2.3.6. Steel channel or angle (top) - Requires permission From Structural Engineer:
.1 Cold piping NPS ≤2”: malleable iron "top of beam" C clamp to
MSS-SP-58, type 19. ULC listed.
.i Acceptable material: Anvil Universal C-type Clamp Fig. 92.
.2 Cold piping NPS ≥2½”: steel jaw, hook rod with nut, spring washer and
plain washer, to MSS-SP-58, type 25. ULC listed., Maximum load 940 lb.
.i Acceptable material: Anvil Top Beam Clamp Fig. 227.
.3 Hot Piping All sizes: steel jaw, hook rod with nut, spring washer and
plain washer, to MSS-SP-58, type 25. ULC listed., Maximum load 940 lb.
.i Acceptable material: Anvil Top Beam Clamp Fig. 227.
2.3.7. Middle Attachment (rod)
.1 Carbon steel continuous threaded rod or welded eye rod electro-galvanized for mechanical rooms.
.i Acceptable material: Anvil Continuous Threaded Rod Fig. 146 or
Eye Rod Welded Fig. 278.
2.3.8. Pipe Attachment
.1 Cold piping, steel or cast iron; hot piping steel, with less than 25mm
horizontal movement; hot piping, steel, with more than 300mm middle attachment (rod) length: adjustable clevis to MSS-SP-58, type 1. ULC listed.
.i Use insulation protection shields with clevis for insulated piping.
.ii Acceptable material for cold water NPS 16” and less and for cold
vapour, NPS 30” and less: Anvil Adjustable Clevis Hanger Fig. 260.
.iii Acceptable material for cold water NPS 18” to 30”: Anvil Heavy Pipe Clamp Fig. 216.
.iv Acceptable material for hot water NPS 12” and less: Anvil Adjustable Clevis for Insulated Lines Fig. 300.
.v Acceptable material for hot water NPS 14” and above and for hot
vapour NPS 14” to 30”: Anvil Heavy Duty Double Bolt Clamp Fig. 295H.
.2 Cold copper piping; hot copper piping with less than 25 mm horizontal
movement; hot copper piping with more than 300 mm middle attachment (rod) length: adjustable clevis to MSS-SP-58, type 1. Copper plated.
.i Acceptable material: Anvil Lightweight Adjustable Clevis Fig.
CT-65.
.ii Use insulation protection shields with clevis for insulated piping.
See Section 2.4. Acceptable material: Anvil Insulation Protection Shield Fig. 167.
.3 Suspended hot piping, steel and copper, with horizontal movement in
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 5 OF 9
PROJECT NO.210243 JUNE 23,2010
.i Acceptable material: Anvil Adjustable Steel Yoke Pipe Roll Fig.
181.
.ii Use insulation protection shields with clevis for insulated piping.
.4 Bottom supported hot piping, steel and copper: pipe roller stand to
MSS-SP-58, type 44.
.i Acceptable material: Anvil Pipe Roll Stand Fig. 271.
.ii Use insulation protection shields with clevis for insulated piping.
2.4 R
ISERC
LAMPS2.4.1. Steel or cast iron pipe: black carbon steel to MSS-SP-58, type 42. ULC
listed, state maximum load.
.1 Acceptable material: Anvil Riser Clamp Standard Fig. 40. Confirm
maximum load with engineer.
2.4.2. Copper pipe: carbon steel copper finished to MSS-SP-58, type 42, and state
maximum load.
.1 Acceptable material: Anvil Copper Tubing Riser Clamp Fig. CT-121.
Confirm maximum load with engineer.
2.4.3. All risers to be isolated from structure using neoprene steel isolation pads as
per the drawings.
2.4.4. Bolts: to ASTM A307.
2.4.5. Nuts to ASTM A563.
2.5 A
NCHORS,
G
UIDES,
ANDS
LIDES2.5.1. Anchor:
.1 Provide as indicated on drawings.
.2 Vapor barriers, jackets to remain uninterrupted.
.3 Interior
.i Standard of Acceptance: Anvil #436A (up to 200 mm pipe sizes),
Anvil #439 (for 250mm pipes and larger), for hot piping.
.ii Standard of Acceptance: Shaw Pipe Shields for cold piping
.4 Exterior
.i As indicated on drawings.
2.5.2. Pipe Slides with Alignment guides:
.1 Provide as per manufacturers recommendations and indicated on
drawings.
.2 For longitudinal and lateral movement as indicated with carbon steel
base with PTFE bonded slide plates (with counter sunken screws) covering full face of saddle.
.3 Vapor barriers, jackets to remain uninterrupted (Cooling Only).
.4 To accommodate specified thickness of insulation
.5 Interior:
.i Standard of Acceptance: Anvil #436 (up to 200 mm pipe sizes),
Anvil #439 (for 250mm pipes and larger), for hot piping.
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 6 OF 9
PROJECT NO.210243 JUNE 23,2010
.6 Exterior
.i As indicated on drawings.
2.6 S
ADDLES ANDS
HIELDS2.6.1. Cold piping NPS ≥1¼”: protection shield with high-density insulation under
shield with uninterrupted vapor barrier.
2.6.2. Cold piping ≤40mm: use insulation shields only.
2.6.3. All to MSS-SP-69, type 40.
.1 Acceptable Material: Anvil Insulation Protection Shield Fig. 167, Myatt
Shield #251.
2.6.4. Hot piping NPS ≥1½”: protective saddle with insulation under saddle to
MSS-SP-58, type 39.
.1 Acceptable material: Anvil Pipe Covering Protection Saddle Fig. 160 to
166A, Myatt #210 to 240 selection to suit insulation thickness..
2.6.5. Hot piping NPS <1¼”: hanger in direct contact with the pipe.
2.7 P
IPINGR
ESTRAINTS2.7.1. Restraints shall be installed at the locations indicated on the piping drawings
to prevent motion in the specified axis.
2.7.2. Restraints shall be selected and anchored in such a manner to be able to
withstand the loading indicated on the drawings.
.1 Standard of Acceptance: Anvil Sway Braces
2.8 P
RE-E
NGINEEREDS
PRINGH
ANGERS2.8.1. Pre - Engineered Spring Hangers to meet the requirements of ANSI B31.1 for
piping subject to vertical movement.
2.8.2. Provide on water piping and elsewhere as applicable or specified.
.1 Acceptable material: Anvil, Myatt.
3
PART 3 - EXECUTION
3.1 H
ANGERS
PACING(U
NLESS SPACING IS DETERMINED BY STRESS ANALYSIS)
3.1.1. Spacing and middle attachment rod diameter as specified in paragraphs
below or as in table below, whichever is more stringent.
.1 Plumbing piping: most stringent requirements of Canadian Plumbing
Code, Provincial Code, or authority having jurisdiction.
.2 Flexible joint roll groove pipe; in accordance with table below, but not
less than one hanger at joints.
.3 Position hangers adjacent to horizontal elbow.
.4 Hanger selection or structural integrity may reduce hanger / support
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 7 OF 9
PROJECT NO.210243 JUNE 23,2010
.5 Support plastic piping in accordance to manufacturer’s recommendation.
Table 1: Maximum Hangar Spacing and Rod Diameter
Pipe Size (NPS) Maximum Spacing Steel Piping Maximum Spacing Copper Rod Diameter ≤1¼” 2.1 m (7 ft.) 2.1 m 10 mm 1½“ 2.7 m (9 ft.) 2.4 m 10 mm 2” 3.0 m (10 ft.) 2.4 m 10 mm 2½” 3.4 m (11 ft.) 2.7 m 10 mm 3” 3.7 m (12 ft.) 3.0 m 10 mm 3½” 4.0 m (13 ft.) 3.4 m 10 mm 4” 4.3 m (14 ft.) 3.7 m 16 mm 5” 4.9 m (16 ft.) 16 mm 6” 5.2 m (17 ft.) 22 mm 8” 5.8 m (19 ft.) 22 mm 10” 6.1 m (22 ft.) 22 mm 12” 7.0 m (23 ft.) 22 mm 14” 7.6 m (25 ft.) 22 mm 16” 8.2 m (27 ft.) 22 mm
3.2 H
ANGERI
NSTALLATION3.2.1. Install hanger so that rod is vertical under operating conditions.
3.2.2. Adjust hangers to balance load.
3.2.3. Support from top of structural members. Where structural bearing does not
exist or inserts are not in suitable locations, provide supplementary structural steel members, prime coated before installation.
3.2.4. Obtain approval from Consultant before using vertical expansion shields.
Use a minimum of two expansion shields for each hanger.
3.2.5. Do not suspend hangers from metal deck.
3.2.6. Anchoring of piping shall be as per manufacturers’ recommendations.
Submit anchorage system for review before installation.
3.2.7. The use of perforated band, wire chain, or solid ring type hangers will not be
accepted.
3.2.8. Hangers are not to be structurally supported from another pipe.
3.2.9. Offset hanger pipe and structural attachments in such a manner that rod is
vertical when piping is hot.
3.3 A
NCHORS,
G
UIDES,
ANDS
LIDESCITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 8 OF 9
PROJECT NO.210243 JUNE 23,2010
.1 Provide as indicated on drawings.
.2 Vapor barriers, jackets to remain uninterrupted.
.3 Interior
.4 Acceptable material for hot water piping up to NPS 200 mm: Anvil Pipe
Slides Assembly; Fabricated Tee Fig #436A
.5 Acceptable material for hot water piping NPS 250 mm and larger: Anvil
Structural “H” Slide Assembly Complete Fig #439 (for 250mm pipes and larger).
.6 Exterior
.7 As indicated on drawings.
3.3.2. Alignment guides:
.1 Provide as per manufacturers recommendations and indicated on
drawings.
.2 To accommodate specified thickness of insulation,
.3 Vapor barriers, jackets to remain uninterrupted.
.4 Standard of Acceptable: Anvil Pipe Slides Assembly, Structural Tee
Slide Fig. #257, Type 3 or Anvil Structural “H” Slide Assembly Complete Fig #439,
3.3.3. Pipe Slides
.1 For longitudinal and lateral movement as indicated with carbon steel
base with PTFE and/or bonded slide plates (with counter sunken screws) covering full face of saddle.
.2 Slide material will be suitable for the service temperature, with low
thermal conduction properties.
.3 Vapor barriers, jackets to remain uninterrupted.
3.3.4. Fiberglass specialty shear collars:
.1 Bonded to pipe with compatible resin.
.2 Use with anchors, guides and pipe riser restraints.
3.4 V
IBRATIONI
SOLATION3.4.1. All piping risers to be supported using acoustics vibration isolation pads as
per drawing detail.
3.4.2. Contractor to make any adjustments requested by supplier.
3.4.3. Provide pre-engineered spring hangers as indicated.
3.4.4. Provide spring hangers on all pipes connected to rotating equipment at
positions as specified below:
.1 Piping NPS up to and including 8” without flexible connections at pipe
connections to equipment: provide spring hanger supports for four points of isolation.
.2 Piping NPS up to and including 8” with flexible connections at pipe
CITY OF VANCOUVER PIPE HANGERS AND SUPPORTS
NEUETSEXPANSION SECTION 15061 PAGE 9 OF 9
PROJECT NO.210243 JUNE 23,2010
.3 Piping NPS greater than and equal to 10” without flexible connections
at pipe connections to equipment: provide spring hanger supports for six points of isolation.
.4 Piping NPS greater than and equal to 10” with flexible connections at
pipe connections to equipment: provide spring hanger supports for two points of isolation.
3.4.5. Manufacturer of Vibration Isolation Material to review shop drawings and
detailed piping drawings for each piece of rotating equipment or other equipment identified as required isolation. Based on these shop drawings the manufacturer will make the final isolation equipment selection.
3.4.6. The manufacturer of Vibration Isolation Material will be required to visit site
during construction to review the installations and ensure compliance with their requirements. At project completion, the supplier will inspect the complete installation and supply a letter of compliance to the Engineer.
CITY OF VANCOUVER IDENTIFICATION
NEUETSEXPANSION SECTION 15075 PAGE 1 OF 8
PROJECT NO.210243 JUNE 23,2010
SECTION 15075 IDENTIFICATION
1
PART 1. - GENERAL
1.1 S
UMMARY1.1.1 This section includes materials and requirements for the identification of
piping systems, duct work, valves and controllers, including the installation and location of identification systems.
1.1.2 Related Sections:
.1 Section 15061 – Pipe Hangers and Supports
.2 Section 15142 – Domestic Water Supply Piping – Copper
.3 Section 15180 – District Heating Primary Piping.
.4 Section 15513 – Secondary Piping.
1.2 R
EFERENCES1.2.1 Canadian Gas Association (CGA)
.1 CSA/CGA B149.1, Natural Gas and Propane Installation Code.
1.2.2 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-1.60, Interior Alkyd Gloss Enamel.
.2 CAN/CGSB-24.3, Identification of Piping Systems.
1.2.3 National Fire Protection Association (NFPA)
.1 NFPA 13, Standard for the Installation of Sprinkler Systems.
.2 NFPA 14, Standard for the Installation of Standpipe and Hose
Systems.
1.3 S
UBMITTALS1.3.1 Submittals: in accordance with Section 01330 - Submittals.
1.3.2 Product Data:
.1 Submit for approval: manufacturer's printed product literature,
specifications and datasheet in accordance with Section 01330 – Submittals. Include product characteristics, performance criteria and limitations.
1.3.3 Shop Drawings:
.1 Submit shop drawings in accordance with Section 01330 - Submittals
.2 Shop drawings: submit lists of proposed wording for approval before
labeling and/or engraving.
1.4 S
AMPLES1.4.1 Submit samples in accordance with Section 01330: Submittal Procedures.
1.4.2 The Contractor to verify with the Consultant regarding the equipment, wiring,
CITY OF VANCOUVER IDENTIFICATION
NEUETSEXPANSION SECTION 15075 PAGE 2 OF 8
PROJECT NO.210243 JUNE 23,2010
2
PART 2. - PRODUCTS
2.1 M
ANUFACTURERS’
N
AMEPLATES2.1.1 Metal
2.1.2 Nameplate mechanically fastened on each piece of equipment.
2.1.3 Letters and numbers raised or recessed letters.
2.1.4 Information to include as appropriate:
2.1.5 Equipment: Manufacturer’s name, equipment model, size, manufacturer's
name, serial number, and capacity.
2.1.6 Motor: Voltage, Hz, phase power factor, duty, frame size.
2.1.7 Provide UL, ULC, FM, CSA, National Board, and Registration Plates as
required by the authority having jurisdiction.
2.1.8 Locate nameplates so that they can be easily read. Do not insulate or paint
over plates. Provide stand-offs on insulated equipment as required.
2.2 S
YSTEMN
AMEPLATES2.2.1 Color:
.1 Hazardous: red letters, white background.
.2 Elsewhere: black letters, white background (except where required
otherwise by applicable codes). 2.2.2 Construction:
.1 1.5mm (1/16”) thick, laminated plastic or white anodized aluminum,
matte finish, square corners, letters accurately aligned and machine engraved into core.
2.2.3 Sizes:
.1 Conform to following:
.i 2.5 mm thick, 6 mm lettering
2.2.4 The following equipment will require nameplates:
CITY OF VANCOUVER IDENTIFICATION
NEUETSEXPANSION SECTION 15075 PAGE 3 OF 8
PROJECT NO.210243 JUNE 23,2010
.12 Strainers
.13 Check Valves
2.3 S
YSTEMN
AMEPLATES2.3.1 Colour:
.1 Black lettering, white background, except where required otherwise by
applicable codes.
.2 For hazardous warnings use red lettering, white background.
2.3.2 Construction:
.1 3.0 mm [1.5 mm] laminated plastic or white anodized aluminum, matte
finish with square corners, letters accurately aligned, and machine engraved into core.
2.3.3 Sizes:
.1 Lettering to be 6 mm tall, 2.5 mm thick.
.2 Conform to following table:
Size # Sizes (mm) No. of Lines Height of Letters (mm) #1 10 x 50 1 3 #2 13 x 75 1 5 #3 13 x 75 2 3 #4 20 x 100 1 8 #5 20 x 100 2 5 #6 20 x 200 1 8 #7 25 x 125 1 12 #8 25 x 125 2 8 #9 35 x 200 1 20
.3 Use maximum of 25 letters/numbers per line.
2.3.4 Locations:
.1 Terminal cabinets, control panels, power transformers, disconnects,
including junction boxes for leak detection and communication systems: use size # [5].
.2 Equipment; heat exchangers, pumps, boilers, chillers, cooling towers,
compressors, tanks and vessels, fans, standby generators, compressed gas systems, glycol packaged systems, unit heaters, air conditioning units actuated dampers: use size # [9].
.3 Valves, piping and control devices; control valves, safety valves,
sensors and/or instrumentation, transmitters, controllers, energy meters, flow meters, strainers, check valves: use size # [6].