• No results found

15.2.1-Interface Management Plan_ R3

N/A
N/A
Protected

Academic year: 2021

Share "15.2.1-Interface Management Plan_ R3"

Copied!
31
0
0

Loading.... (view fulltext now)

Full text

(1)

SADARA PROJECT

LSPB CONTRACT

TECHNICAL DATA BOOK

ATTACHMENT IV TO SCHEDULE B

15.2.1 BUILD INTERFACE MANAGEMENT

PLAN

Document No: A554-R-730-IN-GEN-INT-001

RTIP Rev: 1 2 3 3 FW Prepared by: Majid M Alghamdi Majid M Alghamdi Majid M Alghamdi FW Approved

by: Mike Dowden Mike Dowden Mike Dowden Owner

Approved by: Daniel Abanto Daniel Abanto Daniel Abanto

Revision Date: 11 July 2012 28 Aug 2012 10 Sept 2012

Issue

Purpose: ITB IFT IFT

This document contains technical information that may be subject to the export control regulations of the United States and/or other jurisdictions. It may not be exported or re-exported except as authorized under applicable U.S. or other export control regulations.

(2)

SUMMARY OF DOCUMENT REVISIONS Rev. No. Date Revised Section

Revised Revision Description

1 3 July-12 Issued for Client Review

2 28 Aug-12 Attachment 2 Interface Dependency Table Update 3 10-Sept-12 Attachment 2 Interface Dependency Table Update

(3)

TABLE OF CONTENTS Section Topic 1.0 PURPOSE ... 4 2.0 SCOPE ... 4 3.0 DEFINITIONS ... 4 4.0 RESPONSIBILITIES ... 5 4.1 INTERFACE PARTIES ... 6 4.2 CONTRACTOR F ... 6 4.3 CONTRACTOR O ... 7

4.4 PROGRAM INTERFACE MANAGEMENT TEAM (PIMT) ... 8

5.0 INTERFACE TYPES ... 8

5.1 EXTERNAL INTERFACE ... 8

5.2 INTERNAL INTERFACE ... 9

6.0 INTERFACE NUMBERING ... 9

7.0 COMMUNICATION ... 10

7.1 INTERFACE QUERIES (IQS) ... 11

7.2 IQ NUMBERING ... 11

7.3 TRANSMISSION OF DOCUMENTATION ... 11

8.0 INTERFACE GUIDELINES ... 11

8.1 PIPING ... 12

8.1.1 ABOVE GROUND PIPING INTERFACES ... 12

8.1.2 UNDERGROUND PIPING INTERFACES ... 12

8.2 CIVIL INTERFACES ... 13

8.2.1 ROAD INTERFACE ... 13

8.2.2 PAVING INTERFACES ... 14

8.2.3 DITCH INTERFACES ... 14

8.2.4 TELECOMMUNICATION CONCRETE ENCASED DUCT BANKS ... 15

8.3 TELECOMMUNICATIONS ... 16

8.4 ELECTRICAL ... 16

ATTACHMENT 1 – IQ GUIDELINES ... 17

(4)
(5)

1.0 PURPOSE

This document defines how interfaces are to be managed by the Packages Contractors. It defines the role and responsibilities of each interface Party. It does not define the engineering requirements of each interface.

This document is intended to:

• Ensure all interfaces are identified

• Define clear responsibilities for each Party • Ensure there are no interface gaps or overlaps

• Define the physical method of making the interface (flange, junction box, etc) • Ensure schedule compatibility, relating to interfaces

2.0 SCOPE

This document defines the requirements for the management of interfaces during construction phase

The physical interface definition includes the following connections: • Piping (above and underground)

• Civil (roads, paving, ditches, ducts) • IT/Telecoms

• Electric power cable and Control Cable 3.0 DEFINITIONS Title Definition BL Battery limit Contractor “Package A, B, C, Or D Contractor”

The SDL Building Project is divided into four Packages, A, B,C and D. Each Package will be constructed by a Package contractor

Package contractor The Contractor responsible for Construction of a Package. Finalization

Contractor “Contractor F”

Contractor F effectively will accept the works of Contractor O and will complete the Interface Point works. Contractor F will maintain responsibility for the Interface Point until construction turnover.

Originator

Contractor “ Contractor O”

Contractor O is the Contractor who initiates the works at an IP. Contractor O will provide Contractor F the required support to allow Contractor F to complete the works at subject interface point.

(6)

3rd Party contractor Contractors nominated for works outside of the building battery limit or not included in Contractor A,B,C& D scope of work

ICF Interconnecting Facilities Contractor ITC Information Technology Contractor

EW Early Work Contractor

IDT Interface Dependency Table

External Interface External Interface is an interface between any Package Contractor and a third party contractor e.g. between Package C Contractor and ICF Contractor

Internal Interface An Internal Interface is an interface between any two Package Contractors

IP Interface Point

IQ Interface Query

ISBL Inside Battery Limit. A category of work scope for facilities inside a process Unit BL

OSBL Outside Battery Limits. Outside the Process Unit BL but within the Site boundary

PMT Project Management Team

SPOC Single Point of Contact

4.0 RESPONSIBILITIES

This section outlines the respective responsibilities of the Project Management Team and the Packages Contractors.

Package Contractors are wholly responsible for the completion of all Interface Points within the parameters of the contract price. Package Contractor shall be responsible to communicate with any other Package Contractor as required to complete all works relating to the Interface Points. Package Contractor shall also be responsible for all documentation and communication with the PMT.

The following is the general frame of responsibilities

I. PMT will: Oversee the interface process and nominate contractor (F) Finalization Contractor or (O) Originator Contractor in each IP.

II. It is the responsibility of a Package Contractors to coordinate with the other Package Contractors to establish schedule of activities at each Interface Point (IP). Agreeing to the sequence of activities, and finalizing the proper sign off and required testing for each (IP) based

(7)

on the role they will be assigned to as an Originator contractor Or Finalization contractor.

III. Contractor O will be the first contractor to install their works in a condition that Contractor F will be able to complete the IP per the Contract Documents.

IV. Contractor F prior to starting any works at an IP shall confirm Contractor O installation is acceptable to complete the IP per the terms of the contract documents. This is to include layout and elevations and general soundness of the installation.

V. Contractor O shall facilitate Contractor F as required to complete the IP, providing required access or traffic control, etc. etc.

VI. Upon completion of any irregularities and acceptance of Contractor O IP works, Contractor F shall complete the IP per the requirements of the contract documents.

VII. Contractor F shall be responsible for future protection of the IP and all snag list works associated with the said IP.

VIII. It is the responsibility of the parties involved to ensure that the appropriate Non-Disclosure Agreements are in place where the exchange of information and / or drawings & documents as specified in this document.

4.1

Interface Parties

There are four parties involved in the management of interface points: • Finalization Contractor “ Contractor F”

• Originator Contractor “ Contractor O” • 3rd party Contractor

• Project Management Team

For each IP, Contractor F and Contractor O will be identified by the PMT.

4.2

Contractor F Contractor F shall:

1. Be the contractor that finalizes the works at an IP

2. Participate in the creation and maintenance of the IDT Interface Dependency Table

3. Participate in all requested IP coordination meetings

4. Mutually agree with Contractor O that the IP and associated data is correct, consistent and complete.

(8)

6. Populate interfaces completion dates in the Interface Dependency Schedule (See Attachment 2) and update regularly to manage and monitor the timing of completion of interface points and gates. Copy to be provided to PMT. 7. Reach agreement on interfaces with other Contractors in a timely manner to

support the overall Project schedule.

8. Identify and agree with Contractor O the inspections, tests and construction and pre-commissioning records that are required to be performed and/or maintained by itself and Contractor O. This applies to situations where both Contractors have an overlap of activities at the interface such as the joint hydrotest of both sides of an interface point at the same time. Otherwise the Contractors shall each be responsible for their 'side' of the interface.

9. Identify and agree with Contractor O any inspections, tests, drying and any other requirements to be witnessed by itself and Contractor O.

10. Prior to starting any interface works, confirm the acceptability of the in-place works instated by Contractor O. This confirmation shall include the overall acceptability of the in place IP works, including: layout, alignment elevation and the integrity of the elements being attached to or abutted. If any unacceptable conditions are identified then an equitable resolution shall be sought with Contractor O and the PMT. If Contractor F connects to an IP without identifying any deficiencies then Contractors O IP works will be considered as accepted without exception. This will not include any “latent or impossible to identify” problems. The PMT will act as arbitrator as required. 11. Upon acceptance of Contractor O works at IP Contractor F shall complete the

IP works and provide protection until final turnover of the works. 12. Complete all Snag list works associated with the IP

13. Be fully responsible for the procurement and construction of the part of system within its own area.

14. Identify IPs that are no longer relevant, and communicate such to Contractor O and the PMT in a timely manner. .

4.3

Contractor O Contractor O shall:

1. Be the contractor that starts the works at an IP

2. Participate in the creation and maintenance of the IDT Interface Dependency Table

3. Participate in all requested IP coordination meetings

4. Mutually agree with Contractor F that the IP and associated data is correct, consistent and complete.

5. Provide all necessary input and support to the PMT

6. Populate interfaces completion dates in Interface Dependency Schedule (See Attachment 2) and update regularly to manage and monitor the timing of completion of interface points and gates. Copy to be provided to PMT. 7. Reach agreement on interfaces with other Contractors in a timely manner to

support the overall Project schedule.

8. Identify and agree with Contractor F the inspections, tests and construction and pre-commissioning records that are required to be performed and/or maintained by itself and Contractor F. This applies to situations where both Contractors have an overlap of activities at the interface such as the joint

(9)

hydrotest of both sides of an interface point at the same time. Otherwise the Contractors shall each be responsible for their 'side' of the interface.

9. Identify and agree with Contractor F any inspections, tests, drying and any other requirements to be witnessed by itself and Contractor O.

10. Complete the first stage of the works relating to subject IP per the documented agreements made with Contractor F.

11. Facilitate all requested inspections of the IP with Contractor F and or the PMT to confirm installation is installed per the contract requirements, position and elevation. Any and all unacceptable conditions shall be rectified promptly to prevent any schedule disruption of Contractor F and the overall program schedule.

12. Provide all required interface assistance including access, traffic control and any other reasonable or required assistance to allow Contractor F complete the IP.

13. Identify IPs that are no longer relevant, and communicate such to Contractor F in a timely manner. Also communicate to PMT.

14. Be fully responsible for the procurement and construction of the part of a System within its own area.

4.4

Project Management Team (PMT) will:

1. Develop, communicate and maintain the Interface Management Plan and associated guidelines for:

• Identifying and defining interface points

• Assigning responsibilities of parties at each IP

• Data required to define each interface point construction phase 2. Provide Final resolution of any queries at interface points

5.0 INTERFACE TYPES

5.1

External Interface

External Interface specifically refers to 3rd parties outside of the contractors nominated for the building envelope.

(10)

5.2

Internal Interface

Internal Interface is an interface between Package Contractors nominated for the Building scope.

6.0 INTERFACE NUMBERING

The IP number will be assigned as follow

IP-d-w/u-nnnn Where:

Internal Interface Point Unit 1

Unit 2

Unit 3

Envelope

Internal Interface Point Package A

Package C

Package B

Unit

External Interface Point Unit 1

Unit 2

Unit 3

Envelope

External Interface Point Package A

Package C

Package B

(11)

d Discipline code, see below w/u Package Contractors Code

The first number shown (w) is Contractor O and the second number (u) is Contractor F.

nnnn Serial number (a unique number will be assigned for each discipline)

Discipline codes:

CAE Cable Tray - Electrical CAT Cable Tray – IT

CBE Cable Trench – Electrical CBT Cable Trench/Duct Bank - IT CC Civil Open Ditch

CF Civil Fence Crossing CR Civil Road CRT Road Crossing - IT E Electrical Cable F Firewater P Piping S Structural T Telecommunications Cable

TS Miscellaneous IT (Supplementary Interface Table) U Underground Piping (gravity flow only)

The following is the specific Package Contractors Codes, which will be used to provide clarity.

A Package A Contractor B Package B Contractor C Package C Contractor D Package D Contractor

For example: “IP-P-A/B-000004” would be a piping IP between the Package A Contractor and Package B Contractor.

(12)

7.0 COMMUNICATION

Packages Contractors shall communicate directly with each other to agree definition and completion of interfaces. PMT will maintain, the master SPOCs List which will include the names and contact details of the interface coordinators (Single Points of Contact) for all parties.

Communication may take place in a combination of the following formats: • Interface Queries (IQs)

• Transmission of documentation

• Meetings (with decisions subsequently recorded by IQs using MOM as a proof of agreements)

• Emails

Each Package Contractor shall appoint a SPOC to efficiently manage such communications. Each Package Contractor shall maintain a log of all IQs sent/received. IQs raised by any Contractor shall be addressed to the other Party’s Contractor SPOC’ and shall also be copied to the ‘PMT SPOC – additional people may be copied but all IQs must be sent only ‘To’ the Package Contractor SPOC’

7.1

Interface Queries (IQs)

Interface Queries (IQs) may be raised by any Party to make a query, provide or request information or to confirm an agreement, using the form in Attachment P,

Contractors shall communicate directly with all other Contractors having an interest in the interface. All formal agreements and requests shall be recorded in an IQ.

7.2

IQ Numbering

IQs shall be numbered in the form:

IQ-x-y-nnnn Where:

x Querying Party code y Responding Party code

nnnn Serial number (assigned by the querying Party)

The Party codes are included within the ‘SPOCs List’ which is maintained by PMT and regularly issued to all parties. The ‘SPOCs List’ also identifies which units are associated with each Party. For example, the second IQ from Package B Contractor to Package C contractor would be numbered IQ-B-C-002.

(13)

7.3

Transmission of Documentation

A record shall be kept of all documentation (documents and drawings) transmitted between Contractors and IQs shall be used for the transmittal.

8.0 INTERFACE GUIDELINES

The following defines the split of responsibilities between Contractors during construction at IPs and provides guidance on how to implement interfaces for different situations that may arise. The engineering requirements are defined in the relevant Program documents and drawings. The list of IPs are listed in Attachment 2

The following is general guidance

• For external interfaces between a Package and a 3rd Party contractor, then

the Package Contractor will be Contractor F.

• For internal interfaces between Packages, then Contractor F will be assigned by the Project Management Team.

8.1

Piping

8.1.1 Above Ground Piping Interfaces 8.1.1.1 General

1. The default position shall be that Contractor F shall provide the required isolation, based on the service, at the IP for commissioning and operating purposes. This isolation could be blind flanges, figure 8 blinds, valves or other means. Contractor F shall provide any final spacers, gaskets and bolts required for the final closure of the IP.

2. Contractor F and Contractor O shall each provide their own test gaskets, blind flanges and bolts to allow testing of the piping within their respective scope. 3. After completion of flushing, testing, etc by each Contractor of his own

section of piping, Contractor F, after agreement with the other Contractor, remove the blind, install the spacer, and bolt up the flanges to complete the joint.

4. Each Contractor shall be responsible for the design and installation of insulation up to the Interface Point with Contractor F responsible for final closure of the joint.

CONTRACTOR F CONTRACTOR O

(14)

8.1.2 Underground Piping Interfaces 8.1.2.1 Firewater

1. Contractor O shall provide fire mains and appurtenances along the main roads for the overall firemain outside Buildings area and provide spurs off the ring main at the indicated on the drawings

2. The IP, which consists of a valve supplied by Contractor O will be installed in a valve box constructed by Contractor O. Contractor F will be responsible for grouting and sealing the valve box where his pipe protrudes.

3. Contractor O shall install and test the fire main up to the IP.

4. Contractor F shall install and test his fire main up to the isolation valve. 5. Contractor F shall provide the gaskets, bolts etc to make the final closure. 8.1.2.2 Other services

1. Each contractor shall construct, test, flush, clean, and back fill their piping up to their respective battery limits. Contractor F will then complete the system with a short section of pipe. These final joints will be considered “Golden Joints” followed by service test before backfilling.

8.2

Civil Interfaces 8.2.1 Road Interfaces

1. Contractor O shall lay and compact the pavement materials to an acceptable stable slope beyond the extent of his wearing surface slope.

2. Contractor F shall ensure the soundness of this material prior to laying all subsequent layers.

CONTRACTOR F ANCHOR

ANCHOR TEMPORARY END

PIECES FOR TESTING

FINAL SPOOL, JOINTS & TESTING BY CONTRACTOR O

ANCHOR

ANCHOR TEMPORARY END

PIECES FOR TESTING

FINAL SPOOL, JOINTS & TESTING BY CONTRACTOR F

(15)

It is the responsibility of Contractor F to complete the interface, unless PMT instructed otherwise, recognizing that the edge of the courses, shown above, may have worn during the interim period. They will be responsible for rectification work to the edge.

8.2.2 Paving Interfaces

1. Paving interface shall typically be at the high point of paving.

2. Contractor O shall lay and compact the pavement materials to an acceptable stable slope beyond the extent of his wearing surface slope.

3. Contractor F shall ensure the soundness of this material prior to laying all subsequent layers.

CONTRACTOR O CONTRACTOR ICF

1.0m* 1.0m*

*Dimensions to be confirmed by CONTRACTOR F Asphalt/concrete paving

Base course

Interface

Centreline of Road

Interface

CONTRACTOR F CONTRACTOR ICF

*Dimensions to be confirmed by CONTRACTOR F 1.0m*

1.0m*

Surface wearing course Base course

Sub –base (if required) Sub -grade Interface Interface PLAN PLAN CONTRACTOR F CONTRACTOR F

CONTRACTOR ICF CONTRACTOR ICF

(16)

8.2.3 Ditch Interfaces

1. If the IP is a direct tie-in to the Contractor O ditch, Contractor O will Construct the ditch without provision for Contractor F, who will tie-in in accordance with Project Specifications.

2. If the IP is not a direct tie-in to the Contractor O ditch, Contractor O shall extend the reinforcement to permit continuity by Contractor F. 3. Contractors O & F shall provide initial construction joint with

Water stops.

8.2.4 Telecommunication Concrete Encased Duct Banks

1. The Contractor O ensures the integrity of the conduits to be free from damage. 2. Conduit ends shall be cap and plugged at the interface point to ensure that no

un-desired material will enter into the conduits.

3. The Contractor O shall leave at least 300mm of the conduit, free of concrete for the Contractor F to conveniently place the couplings.

4. Contractor F shall provide and install the couplings to properly connect the conduits. 5. Contractor F shall provide and install the completion of concrete encasement for the

conduit protection.

6. Contractor F shall coordinate with the Contractor O to execute mandrel throughout the length of the involved duct bank

CONTRACTOR F CONTRACTOR O 0.5m * exposed reinforcement Expansion Joint Slope Plan Elevation Section

(17)

8.3

IT/ Telecom Interface

All telecommunication cables inside buildings will be supplied and installed by Package Contractors as per Package Contractor scope, however ITC will terminate the cables at the wall faceplates and at the building interface terminal strip; Package Contractor will supervise terminations within the building.

8.4

Electrical Interface

(18)

ATTACHMENT 1 – INTERFACE QUERY FORM

(19)
(20)

No. Interface Point O F Type IP Status Days

ELECTRICAL 

1  IP‐CBE‐B/A‐0001 

Electrical Trench 

2  IP‐CBE‐B/A‐0002 

Electrical Trench 

3  IP‐CBE‐B/A‐0003 

Electrical Trench 

4  IP‐CBE‐B/ICF‐0004 

ICF 

Electrical Trench 

5  IP‐CBE‐B/ICF‐0005 

ICF 

Electrical Trench 

6  IP‐CBE‐B/ICF‐0006 

ICF 

Electrical Trench 

7  IP‐CBE‐B/C‐0007 

Electrical Trench 

8  IP‐CBE‐B/C‐0008 

Electrical Trench 

9  IP‐CBE‐D/C‐0009 

Electrical Trench 

10  IP‐CBE‐B/C‐0010 

Electrical Trench 

11  IP‐CBE‐D/A‐0011 

Electrical Trench 

12  IP‐CBE‐C/A‐0012 

Electrical Trench 

13  IP‐CBE‐D/C‐0013 

Electrical Trench 

14  IP‐CBE‐D/C‐0014 

Electrical Trench 

15  IP‐CBE‐D/C‐0015 

Electrical Trench 

16  IP‐CBE‐C/A‐0016 

Electrical Trench 

17  IP‐CBE‐C/A‐0017 

Electrical Trench 

18  IP‐CBE‐C/A‐0018 

Electrical Trench 

19  IP‐CBE‐C/A‐0019 

Electrical Trench 

(21)

Tray 

21  IP‐CAE‐A/ICF‐0002 

ICF 

Electrical Cable 

Tray 

22  IP‐CAE‐A/ICF‐0003 

ICF 

Electrical Cable 

Tray 

IT 

1  IP‐CBT‐ B/A‐0001 

IT Duct Banks 

2  IP‐CBT‐ B/A‐0002 

IT Duct Banks 

3  IP‐CBT‐ A/ICF‐0003 

ICF 

IT Duct Banks 

4  IP‐CBT‐A /ICF‐0004 

ICF 

IT Duct Banks 

5  IP‐CBT‐ A/ICF ‐0005 

ICF 

IT Duct Banks 

6  IP‐CBT‐B/C‐0006 

IT Duct Banks 

7  IP‐CBT‐D/C‐0007 

IT Duct Banks 

8  IP‐CBT‐ D/C‐0008 

IT Duct Banks 

9  IP‐CBT‐D/C‐0009 

IT Duct Banks 

10  IP‐CBT‐ D/C‐0010 

IT Duct Banks 

11  IP‐CBT‐ D/C‐0011 

IT Duct Banks 

12  IP‐CBT‐B/C‐0012 

IT Duct Banks 

  

13  IP‐CBT‐ B/ICF‐0013 

ICF 

IT Duct Banks 

14  IP‐CBT‐ B/A‐0014 

ICF 

IT Duct Banks 

15  IP‐CBT‐C/A‐0015 

IT Duct Banks 

  

16  IP‐CBT‐D/A‐0016 

IT Duct Banks 

(22)

18  IP‐CBT‐ D/C‐0018 

IT Duct Banks 

19  IP‐CBT‐D/C‐0019 

IT Duct Banks 

20  IP‐CBT‐ A/C‐0020 

IT Duct Banks 

21  IP‐CBT‐ C/ICF‐0021 

ICF 

IT Duct Banks 

22  IP‐CBT‐D/A‐0022 

IT Duct Banks 

  

23  IP‐CBT‐ B/C‐0023 

IT Duct Banks 

24  IP‐CBT‐ B/D‐0024 

IT Duct Banks 

25  IP‐CBT‐D/C‐0025 

IT Duct Banks 

  

26  IP‐CBT‐B/ICF‐0026 

ICF 

IT Duct Banks 

  

27  IP‐CBT‐B/ITC‐0027 

ITC 

IT Duct Banks 

  

28  IP‐CBT‐B/ITC‐0028 

ITC 

IT Duct Banks 

  

29  IP‐CBT‐B/ITC‐0029 

ITC 

IT Duct Banks 

  

30  IP‐CBT‐B/ICF‐0030 

ICF 

IT Duct Banks 

  

31  IP‐CBT‐/‐0031 

  

  

  

Intentionally  

Not Used 

32  IP‐CBT‐D/A‐0032 

IT Duct Banks 

  

33  IP‐CBT‐ C/EW‐0033 

EW 

IT Duct Banks 

  

  

  

  

34  IP‐CBT‐ C/EW‐0034 

EW 

IT Duct Banks 

  

  

  

  

35  IP‐CBT‐ D/EW‐0035 

EW 

IT Duct Banks 

  

  

  

  

36  IP‐CBT‐ D/EW‐0036 

EW 

IT Duct Banks 

  

  

  

  

37  IP‐CBT‐ D/EW‐0037 

EW 

IT Duct Banks 

  

  

  

  

38  IP‐CBT‐ D/EW‐0038 

EW 

IT Duct Banks 

  

  

  

  

3 3

(23)

40  IP‐CBT‐ D/EW‐0040 

EW 

IT Duct Banks 

  

  

  

  

41  IP‐CBT‐ D/EW‐0041 

EW 

IT Duct Banks 

  

  

  

  

42  IP‐CBT‐ D/EW‐0042 

EW 

IT Duct Banks 

  

  

  

  

43  IP‐CBT‐ D/EW‐0043 

EW 

IT Duct Banks 

  

  

  

  

CIVIL 

1  IP‐CR‐A/ICF‐0001 

ICF 

Road 

2  IP‐CR‐A/ICF‐0002 

ICF 

Road 

3  IP‐CR‐A/ICF‐0003 

ICF 

Road 

4  IP‐CR‐A/ICF‐0004 

ICF 

Road 

5  IP‐CR‐A/ICF‐0005 

ICF 

Road 

6  IP‐CR‐A/ICF‐0006 

ICF 

Road 

7  IP‐CR‐A/ICF‐0007 

ICF 

Road 

8  IP‐CR‐A/ICF‐0008 

ICF 

Road 

9  IP‐CR‐A/ICF‐0009 

ICF 

Road 

10  IP‐CR‐B/ICF‐0010 

ICF 

Road 

11  IP‐CR‐A/B‐0011 

Road 

12  IP‐CR‐A/B‐0012 

Road 

13  IP‐CR‐A/B‐0013 

Road 

14  IP‐CR‐A/B‐0014 

Road 

15  IP‐CR‐A/B‐0015 

Road 

16  IP‐CR‐A/B‐0016 

Road 

17  IP‐CR‐A/B‐0017 

Road 

18  IP‐CR‐A/B‐0018 

Road 

3 3

(24)

19  IP‐CR‐B/ICF‐0019 

ICF 

Road 

20  IP‐CR‐B/ICF‐0020 

ICF 

Road 

21  IP‐CR‐B/ICF‐0021 

ICF 

Road 

22  IP‐CR‐C/ICF‐0022 

ICF 

Road 

23  IP‐CR‐D/C‐0023 

Road 

24  IP‐CR‐D/C‐0024 

Road 

25  IP‐CR‐D/C‐0025 

Road 

26  IP‐CR‐D/C‐0026 

Road 

27  IP‐CR‐A/C‐0027 

Road 

28  IP‐CR‐A/C‐0028 

Road 

29  IP‐CR‐A/C‐0029 

Road 

30  IP‐CR‐A/C‐0030 

Road 

31  IP‐CR‐D/C‐0031 

Road 

32  IP‐CR‐D/PREP‐0032 

PREP 

Road 

33  IP‐CR‐D/PREP‐0033 

PREP 

Road 

34  IP‐CR‐D/PREP‐0034 

PREP 

Road 

35  IP‐CR‐D/PREP‐0035 

PREP 

Road 

36  IP‐CR‐D/C‐036 

Road 

37  IP‐CR‐C/ICF‐0037 

ICF 

Road 

  

  

  

  

38  IP‐CR‐C/ICF‐0038 

ICF 

Road 

  

  

  

  

39  IP‐CR‐D/ICF‐0039 

ICF 

Road 

  

  

  

  

40  IP‐CR‐D/PREP‐0040 

PREP 

Road 

  

  

  

  

3 3

(25)

42  IP‐CR‐D/PREP‐0042 

PREP 

Road 

  

  

  

  

43  IP‐CR‐D/PREP‐0043 

PREP 

Road 

  

  

  

  

44  IP‐CR‐D/ICF‐0044 

ICF 

Road 

  

  

  

  

37  IP‐CC‐A/B‐0001 

Storm Ditches 

38  IP‐CC‐A/B‐0002 

Storm Ditches 

39  IP‐CC‐A/ICF‐0003 

ICF 

Storm Ditches 

40  IP‐CC‐A/ICF‐0004 

ICF 

Storm Ditches 

41  IP‐CC‐A/ICF‐0005 

ICF 

Storm Ditches 

42  IP‐CC‐B/ICF‐0006 

ICF 

Storm Ditches 

43  IP‐CC‐C/PREP‐0007 

Storm Ditches 

44  IP‐CC‐D/C‐0008 

Storm Ditches 

45  IP‐CC‐ ‐0009 

Intentionally  Not  Used 

46  IP‐CC‐D/C‐0010 

Storm Ditches 

47  IP‐CC‐C/A‐0011 

Storm Ditches 

48  IP‐CC‐A/C‐0012 

Storm Ditches 

49  IP‐CC‐ 0013 

Intentionally  Not 

Used 

50  IP‐CC‐C/A‐0014 

Storm Ditches 

51  IP‐CC‐A/RC‐0015 

RC 

Storm Ditches 

52  IP‐CC‐D/C‐0016 

Storm Ditches 

53  IP‐CC‐D/C‐0017 

Storm Ditches 

54  IP‐CC‐C/RC‐0018 

RC 

Storm Ditches 

(26)

55  IP‐CC‐D/C‐0019 

Storm Ditches 

56  IP‐CC‐D/C‐0020 

Storm Ditches 

57  IP‐CC‐B/C‐0021 

Storm Ditches 

58  IP‐CC‐B/RC‐0022 

RC 

Storm Ditches 

59  IP‐CC‐B/C‐0023 

Storm Ditches 

60  IP‐CC‐B/C‐0024 

Storm Ditches 

61  IP‐CC‐C/ICF‐0025 

ICF 

Storm Ditches 

  

  

  

  

62  IP‐CC‐C/ICF‐0026 

ICF 

Storm Ditches 

  

  

  

  

PIPING 

1  IP‐P‐B/A‐0001 

Sanitary System 

2  IP‐P‐B/A‐0002 

Return ‐ Chilled 

Water 

3  IP‐P‐B/A‐0003 

Supply ‐ Chilled 

Water 

4  IP‐P‐ ‐0004 

  

  

  

Intentionally  

Not Used 

5  IP‐P‐ ‐0005 

  

  

  

Intentionally  

Not Used 

6  IP‐P‐ ‐0006 

  

  

  

Intentionally  

Not Used 

7  IP‐P‐ ‐0007 

  

  

  

Intentionally  

Not Used 

8  IP‐P‐B/A‐0008 

Potable Water 

9  IP‐P‐B/A‐0009 

Compressed Air 

(27)

10  IP‐P‐B/A‐0010 

Return ‐ Chilled 

Water 

11  IP‐P‐B/A‐0011 

Supply ‐ Chilled 

Water 

12  IP‐P‐B/A‐0012 

Sanitary System 

13  IP‐P‐B/C‐0013 

Return ‐ Chilled 

Water 

14  IP‐P‐B/C‐0014 

Supply ‐ Chilled 

Water 

15  IP‐P‐B/C‐0015 

Potable Water 

16  IP‐P‐B/C‐0016 

Potable Water 

17  IP‐P‐B/C‐0017 

Sanitary System 

18  IP‐P‐B/C‐0018 

Sanitary System 

19  IP‐P‐D/C‐0019 

Sanitary System 

20  IP‐P‐D/C‐0020 

Potable Water 

21  IP‐P‐B/C‐0021 

Utility Water 

22  IP‐P‐B/C‐0022 

Compressed Air 

23  IP‐P‐B/C‐0023 

Potable Water 

24  IP‐P‐C/A‐0024 

Potable Water 

25  IP‐P‐C/A‐0025 

Utility Water 

26  IP‐P‐C/A‐0026 

Sanitary System 

27  IP‐P‐D/C‐0027 

Supply ‐ Chilled 

Water 

(28)

Water 

29  IP‐P‐ ‐0029 

  

  

  

Intentionally  

Not Used 

30  IP‐P‐D/C‐0030 

Potable Water 

31  IP‐P‐ ‐0031 

  

  

  

Intentionally  

Not Used 

32  IP‐P‐A/C‐0032 

Potable Water 

33  IP‐P‐A/C‐0033 

Return ‐ Chilled 

Water 

34  IP‐P‐A/C‐0034 

Supply ‐ Chilled 

Water 

35  IP‐P‐ ‐0035 

  

  

  

Intentionally  

Not Used 

36  IP‐P‐D/C‐0036 

Sanitary System 

37  IP‐P‐D/C‐0037 

Sanitary System 

38  IP‐P‐D/C‐0038 

Potable Water 

39  IP‐P‐D/C‐0039 

Sanitary System 

40  IP‐P‐D/C‐0040 

Sanitary System 

41  IP‐P‐D/B‐0041 

Potable Water 

42  IP‐P‐ ‐0042 

Intentionally  Not  Used 

43  IP‐P‐B/C‐0043 

Sanitary System 

44  IP‐P‐ ‐0044 

Intentionally  Not  Used 

(29)

Used 

46  IP‐P‐ ‐0046 

Intentionally  Not  Used 

47  IP‐P‐ ‐0047 

Intentionally  Not  Used 

48  IP‐P‐ ‐0048 

Intentionally  Not  Used 

49  IP‐P‐ ‐0049 

Intentionally  Not  Used 

50  IP‐P‐B/A‐0050 

Sanitary System 

  

51  IP‐P‐B/A‐0051 

Potable Water 

  

52  IP‐P‐B/A‐0052 

Compressed Air 

  

53  IP‐P‐C/A‐0053 

Potable Water 

  

54  IP‐P‐C/A‐0054 

Compressed Air 

  

55  IP‐P‐C/A‐0055 

Utility Water 

  

56  IP‐P‐C/EW‐0056 

EW 

Sanitary System 

MUSSALA & CAFÉ 

57  IP‐P‐C/EW‐0057 

EW 

Potable Water 

MUSSALA & CAFÉ 

58  IP‐P‐D/BRINE‐0058 

BRINE 

Sanitary System 

GATE 4 

59  IP‐P‐D/BRINE‐0059 

BRINE 

Potable Water 

GATE 4 

60  IP‐P‐D/EW‐0060 

EW 

Potable Water 

GATE 5 

61  IP‐P‐D/ICF‐0061 

ICF 

Sanitary System 

GATE 5 

62  IP‐P‐D/ICF‐0062 

ICF 

Sanitary System 

GATE7 

63  IP‐P‐D/ICF‐0063 

ICF 

Potable Water 

GATE 7  3

3 3 3

(30)

64  IP‐P‐D/ICF‐0064 

ICF 

Sanitary System 

PEDESTRIAN 

SOUTH 

65  IP‐P‐D/ICF‐0065 

ICF 

Potable Water 

PEDESTRIAN 

SOUTH 

66  IP‐F‐B/A‐0001 

Firewater 

67  IP‐F‐ ‐0002 

  

  

  

Intentionally  

Not Used 

68  IP‐F‐ ‐0003 

  

  

  

Intentionally  

Not Used 

69  IP‐F‐ ‐0004 

  

  

  

Intentionally  

Not Used 

70  IP‐F‐ ‐0005 

  

  

  

Intentionally  

Not Used 

71  IP‐F‐B/C‐0006 

Firewater 

72  IP‐F‐B/C‐0007 

Firewater 

73  IP‐F‐ ‐0008 

  

  

  

Intentionally  

Not Used 

74  IP‐F‐ ‐0009 

  

  

  

Intentionally  

Not Used 

75  IP‐F‐C/A‐0010 

Firewater 

76  IP‐F‐B/C‐0011 

Firewater 

77  IP‐F‐ ‐0012 

  

  

  

Intentionally  

Not Used 

78  IP‐F‐ ‐0013 

  

  

  

Intentionally  

Not Used 

3

(31)

Not Used 

80  IP‐F‐ ‐0015 

  

  

  

Intentionally  

Not Used 

81  IP‐F‐ ‐0016 

Intentionally  Not  Used 

82  IP‐F‐ ‐0017 

Intentionally  Not  Used 

83  IP‐F‐A/PREP‐0018 

Intentionally  Not  Used 

84  IP‐F‐ ‐0019 

 

 

  

Intentionally  

Not Used 

85  IP‐F‐B/C‐0020 

Firewater 

86  IP‐F‐B/A‐0021 

Firewater 

87  IP‐F‐C/A‐0022 

Firewater 

88  IP‐F‐B/C‐0023 

Firewater 

References

Related documents

The Project Manager is responsible for negotiating with management to ensure that resources are allocated to the project when required to complete the next phase.. Project

CONTRACTOR SHALL PROVIDE QUALITY CONTROL IN ACCORDANCE WITH SUDAS SECTION 7010 3.7, AND SHALL BE THE RESPONSIBLE PARTY FOR ALL REQUIRED TESTING AND RE-TESTING OF P.C..

monitor, control and communicate risks that threaten the success of a project. This process is comprised of two required templates the: Risk Management Plan and Risk

Such a master HVACR contractor shall be required to complete one hour of continuing education in the statutes and rules governing the practice of heating, ventilating, air

3.2.8.1 The Agency shall credit the account of the Contractor to its benefit and to the benefit of its subcontractors. 3.2.8.2 The Contractor shall be responsible for paying

Insurance of the works : The contractor shall within 7 days from the date of commencement of the works at his cost and keep them insured until one month after

The Contractor Project Manager shall be responsible for ensuring required Maricopa County Public Defense Services approval of applicable deliverables.. The Maricopa County

The subcontractor Project Manager is responsible to the Contractor Project Manager for the timely delivery of all Software AG products required under this contract and the