• No results found

Maintaining value for money in the operational phase of PPP contracts

N/A
N/A
Protected

Academic year: 2021

Share "Maintaining value for money in the operational phase of PPP contracts"

Copied!
17
0
0

Loading.... (view fulltext now)

Full text

(1)

Maintaining value for money in the operational phase of PPP contracts

Michael Burnett, Director, European PPP Forum, European

Institute of Public Administration, OECD meeting of Senior PPP Officials, 18 February 2014

(2)

Scope

PPP contract management – The challenge

PPP contract management – Common mistakes

PPP contract execution – What can go wrong

PPP contract execution – What to do if contracts go

wrong

PPP contract execution – Examples of responses to

challenges

Contract execution – Challenges in the new EU

(3)

Introduction – Michael Burnett

Chartered Accountant (c.20 years working in public

procurement)

Assistant Director, KPMG

Director, EIPA European PPP Forum (9 years)

Member, European Commission Stakeholder Expert

Group on Public Procurement since 2012

Member, Editorial Board, European Procurement and

(4)

Contract management and the award process

Clear specification of contract objectives (including

KPIs, targets for KPIs and how measured)

Robust performance management régime to verify if

contract objectives being met

Change protocols for planned/unforeseen change

Contract conditions giving access to necessary

information

Means to verify continuing value for money (VFM)

during contract

(5)

Challenges in realising procured VFM

Deals skilfully tendered and astutely negotiated by the

public sector still have to be managed effectively: - Maintaining procured VFM when change needed - Combatting bargaining weakness when change

needed

- Combatting information asymmetry

- Application of performance monitoring régime

Important to have the right resources and skills in

contract management team (economic operators will usually have more experience)

(6)

PPP contract management – Common mistakes

Failure to plan contract management during

procurement phase

The “sigh of relief” factor

Failure to transfer procurement knowledge to contract

management team

Inadequate contract management resources

Poor match to required skill set (e.g. training, past

experience)

Senior management switch off/demotivation of

(7)

PPP contract execution – What can go wrong (1)

Ineffective contract management is often a major cause of difficulties in contract execution

BUT ALSO

Procurement errors by Contracting Authority

Demand forecast errors

General economic shocks

Force majeure event

Mismanagement/under-resourcing by private partner

(8)

PPP contract execution – What can go wrong (2)

Legislative change (controllable/non-controllable)

Technological change

Professional practice change

Public acceptance change

Change of political control/orientation

(9)

PPP Contract execution – Options if things go

wrong

Change contract in favour of private partner (e.g.

length, scope, performance targets, payment amounts, payment flow, shift to partial or full availability basis, future revenue/refinancing guarantees, partial debt re-financing, hand-back terms, lower DSCRs subject to lender approval, other risk re-acceptance etc)

Don’t change and leave responsibility for recovery

with private partner

Rebalance the contract on the “something for

something” principle

(10)

Evaluating options if things go wrong

Determine approach on case by case basis based on:

Responsibility for specific contract issues arising

Responsibility in original contract for risk materialising

Partnering behaviour of private partner

Scale of recovery needed

Scope for change (affordable?, foreseen in contract

review clauses? legally permissible?)

Consequences of failure for public sector

(11)

PPP Contract execution – Options for

rebalancing the contract

Activate LGTT, Europe 2020 Project Bond Guarantees

or other guarantee options (if relevant)

Portfolio/territorial re-negotiation

Compensating adjustments by SPV (e.g. more sponsor

equity, new equity investor, acceptance of public sector equity/board representative in SPV, future public sector gain sharing, refinancing with gain sharing, future

enhanced monitoring/certification/audit, future

requirement for performance bond/sponsor parent company guarantees, earlier recovery of asset, lower user tariff, pass through of energy/insurance/sub-letting shared savings etc)

(12)

PPP contract execution – Examples of

responses to challenges (1)

Example 1 – NATS

Causes of problem: General economic shock

(September 11th) and over-optimistic demand forecasts

(but NB also risks in initial financing structure of NATS)

Nature and scale of problem:

- Project company loan covenants in danger of being breached - Lenders threat to withdraw funding from project company

- Investors unable to provide sufficient extra finance - Threat to functioning of UK Air Traffic Control system

(13)

PPP contract execution – Examples of

responses to challenges (1) continued

Result:

– Need for short-term emergency funding facility of £60m (£30 million from government, matching £30 million loan from NATS bankers)

– Financial restructuring (BAA as new private investor invested £65 million, government capital injection of £65 million, lower overall price cap, upside and downside volume risk sharing mechanism through price adjustments, planned cost reductions, significant replacement of bank debt by bond finance, less tight bank

oversight, less onerous debt covenants, tighter monitoring of future distributions, safeguards re conflict on interest for new shareholder, no need for government takeover)

– No major financial shocks since refinancing, no further public

(14)

PPP contract execution – Examples of

responses to challenges (2)

Example 2 – London Underground PPP

Cause of problem: Ineffective contract management by

Contracting Authority and mismanagement by private partner (but NB also contract strategy errors by

Contracting Authority)

Nature and scale of problem (Part 1):

– One of the two private partners (Metronet) went into

administration in 2007 (after cost overspends and threat by lenders to withdraw access to loan facilities) and the PPP Arbiter granted only £121 million of requested interim £551 million UP increase for 2007-08

(15)

PPP contract execution – Examples of

responses to challenges (2) continued

Nature and scale of problem (Part 2):

– Three years later the other private partner (Tube Lines) requested £1.3 billion for additional expenditure for upgrades required

compared to estimates of the PPP Arbiter

Result:

– Termination of PPP and public sector takeover of Metronet and Tube Lines contracts

– In Metronet’s case, public sector paid £1.7 billion to meet guarantee to lenders on early termination

– In Tube Lines case, public sector paid £310 million to acquire shares of project company and assumed £1.3 billion of project company’s debt

(16)

PPP Contract execution – Challenges in the new

EU Directives

Possibility to change contracts to greater extent/more

easily and frequently to include additional works,

services or supplies (Art.72(1)(b) Public Procurement Directive, Art.43(1)(b) Concessions Directive)

- Removal of the “unforeseen circumstances” test - Removal of cumulative limit on total value

- No limit on number/frequency of changes

Step-in rights for lenders unambiguous? (Art.72(1)(d)

Public Procurement Directive, Art.43(1)(d) Concessions Directive)

Impact of legislative provisions on number of

(17)

European PPP Forum

WEB SITE

http://www.eipa.eu then search for PPP

CONTACT DETAILS

Mr Michael Burnett

Director, European PPP Forum

European Institute of Public Administration Maastricht, the Netherlands

Tel +31-43-32 96 286 E-mail: [email protected]

References

Related documents