Maintaining value for money in the operational phase of PPP contracts
Michael Burnett, Director, European PPP Forum, European
Institute of Public Administration, OECD meeting of Senior PPP Officials, 18 February 2014
Scope
PPP contract management – The challenge
PPP contract management – Common mistakes
PPP contract execution – What can go wrong
PPP contract execution – What to do if contracts go
wrong
PPP contract execution – Examples of responses to
challenges
Contract execution – Challenges in the new EU
Introduction – Michael Burnett
Chartered Accountant (c.20 years working in public
procurement)
Assistant Director, KPMG
Director, EIPA European PPP Forum (9 years)
Member, European Commission Stakeholder Expert
Group on Public Procurement since 2012
Member, Editorial Board, European Procurement and
Contract management and the award process
Clear specification of contract objectives (including
KPIs, targets for KPIs and how measured)
Robust performance management régime to verify if
contract objectives being met
Change protocols for planned/unforeseen change
Contract conditions giving access to necessary
information
Means to verify continuing value for money (VFM)
during contract
Challenges in realising procured VFM
Deals skilfully tendered and astutely negotiated by the
public sector still have to be managed effectively: - Maintaining procured VFM when change needed - Combatting bargaining weakness when change
needed
- Combatting information asymmetry
- Application of performance monitoring régime
Important to have the right resources and skills in
contract management team (economic operators will usually have more experience)
PPP contract management – Common mistakes
Failure to plan contract management during
procurement phase
The “sigh of relief” factor
Failure to transfer procurement knowledge to contract
management team
Inadequate contract management resources
Poor match to required skill set (e.g. training, past
experience)
Senior management switch off/demotivation of
PPP contract execution – What can go wrong (1)
Ineffective contract management is often a major cause of difficulties in contract execution
BUT ALSO
Procurement errors by Contracting Authority
Demand forecast errors
General economic shocks
Force majeure event
Mismanagement/under-resourcing by private partner
PPP contract execution – What can go wrong (2)
Legislative change (controllable/non-controllable)
Technological change
Professional practice change
Public acceptance change
Change of political control/orientation
PPP Contract execution – Options if things go
wrong
Change contract in favour of private partner (e.g.
length, scope, performance targets, payment amounts, payment flow, shift to partial or full availability basis, future revenue/refinancing guarantees, partial debt re-financing, hand-back terms, lower DSCRs subject to lender approval, other risk re-acceptance etc)
Don’t change and leave responsibility for recovery
with private partner
Rebalance the contract on the “something for
something” principle
Evaluating options if things go wrong
Determine approach on case by case basis based on:
Responsibility for specific contract issues arising
Responsibility in original contract for risk materialising
Partnering behaviour of private partner
Scale of recovery needed
Scope for change (affordable?, foreseen in contract
review clauses? legally permissible?)
Consequences of failure for public sector
PPP Contract execution – Options for
rebalancing the contract
Activate LGTT, Europe 2020 Project Bond Guarantees
or other guarantee options (if relevant)
Portfolio/territorial re-negotiation
Compensating adjustments by SPV (e.g. more sponsor
equity, new equity investor, acceptance of public sector equity/board representative in SPV, future public sector gain sharing, refinancing with gain sharing, future
enhanced monitoring/certification/audit, future
requirement for performance bond/sponsor parent company guarantees, earlier recovery of asset, lower user tariff, pass through of energy/insurance/sub-letting shared savings etc)
PPP contract execution – Examples of
responses to challenges (1)
Example 1 – NATS
Causes of problem: General economic shock
(September 11th) and over-optimistic demand forecasts
(but NB also risks in initial financing structure of NATS)
Nature and scale of problem:
- Project company loan covenants in danger of being breached - Lenders threat to withdraw funding from project company
- Investors unable to provide sufficient extra finance - Threat to functioning of UK Air Traffic Control system
PPP contract execution – Examples of
responses to challenges (1) continued
Result:
– Need for short-term emergency funding facility of £60m (£30 million from government, matching £30 million loan from NATS bankers)
– Financial restructuring (BAA as new private investor invested £65 million, government capital injection of £65 million, lower overall price cap, upside and downside volume risk sharing mechanism through price adjustments, planned cost reductions, significant replacement of bank debt by bond finance, less tight bank
oversight, less onerous debt covenants, tighter monitoring of future distributions, safeguards re conflict on interest for new shareholder, no need for government takeover)
– No major financial shocks since refinancing, no further public
PPP contract execution – Examples of
responses to challenges (2)
Example 2 – London Underground PPP
Cause of problem: Ineffective contract management by
Contracting Authority and mismanagement by private partner (but NB also contract strategy errors by
Contracting Authority)
Nature and scale of problem (Part 1):
– One of the two private partners (Metronet) went into
administration in 2007 (after cost overspends and threat by lenders to withdraw access to loan facilities) and the PPP Arbiter granted only £121 million of requested interim £551 million UP increase for 2007-08
PPP contract execution – Examples of
responses to challenges (2) continued
Nature and scale of problem (Part 2):
– Three years later the other private partner (Tube Lines) requested £1.3 billion for additional expenditure for upgrades required
compared to estimates of the PPP Arbiter
Result:
– Termination of PPP and public sector takeover of Metronet and Tube Lines contracts
– In Metronet’s case, public sector paid £1.7 billion to meet guarantee to lenders on early termination
– In Tube Lines case, public sector paid £310 million to acquire shares of project company and assumed £1.3 billion of project company’s debt
PPP Contract execution – Challenges in the new
EU Directives
Possibility to change contracts to greater extent/more
easily and frequently to include additional works,
services or supplies (Art.72(1)(b) Public Procurement Directive, Art.43(1)(b) Concessions Directive)
- Removal of the “unforeseen circumstances” test - Removal of cumulative limit on total value
- No limit on number/frequency of changes
Step-in rights for lenders unambiguous? (Art.72(1)(d)
Public Procurement Directive, Art.43(1)(d) Concessions Directive)
Impact of legislative provisions on number of
European PPP Forum
WEB SITE
http://www.eipa.eu then search for PPP
CONTACT DETAILS
Mr Michael Burnett
Director, European PPP Forum
European Institute of Public Administration Maastricht, the Netherlands
Tel +31-43-32 96 286 E-mail: [email protected]