• No results found

Project Planning

N/A
N/A
Protected

Academic year: 2021

Share "Project Planning"

Copied!
35
0
0

Loading.... (view fulltext now)

Full text

(1)

Group No: 4

Group No: 4

Aman

Amanii Abd

Abdalg

algadir

adir

Saf

Safaa

aa Ha

Hashi

shim

m

Lee

Leena

na Fa

Faro

roug

ug

Al

Alia

iaa

a Sa

Saye

yed

d A.

A.Al

Alaa

aall

Els

Elsadi

adig

g Mu

Munee

neerr

Asia M. Ali

Asia M. Ali

Afr

Afrah

ah A. A

A. Alaz

laziz

iz

Mustafa Kamil

Mustafa Kamil

(2)
(3)

 IntroductionIntroduction

 DEVELOPING THE PROJECT SCOPEDEVELOPING THE PROJECT SCOPE

 Develop WBSDevelop WBS

 Scheduling:Scheduling:

 Define work activitiesDefine work activities

 Sequence Work activitiesSequence Work activities

 Activities resources estimatingActivities resources estimating

 Estimate activities durationEstimate activities duration

 Risk management planningRisk management planning

 Quality planningQuality planning

 Budget planningBudget planning

 Establish human resource planEstablish human resource plan

 Establish communication planEstablish communication plan

 Establish Procurement planEstablish Procurement plan

  ConclusionConclusion

Presenter (1)

Presenter (1)

Am

Am

an

an

i

i

Ab

Ab

d

d

Al

Al

g

g

ad

ad

ir

ir

Introduction

Introduction

(4)

Introduction

Introduction

 After the initiation stage, the projecAfter the initiation stage, the project is t is planned to an appropriateplanned to an appropriate

level of detail. level of detail.

 The main purpose is to plan The main purpose is to plan timetime, cost and , cost and resources adequately toresources adequately to

estimate the work needed and to

estimate the work needed and to effectiveeffectively manage risk duringly manage risk during project execution.

project execution.

 As with the Initiation process group, a failure to adequately planAs with the Initiation process group, a failure to adequately plan

greatly reduces the project's chances of successfully accomplishing its greatly reduces the project's chances of successfully accomplishing its goals.

goals.

Introduction

Introduction

When carrying out a root cause analysis on

When carrying out a root cause analysis on a client complaint

a client complaint

you might hear the following symptomatic expression:

you might hear the following symptomatic expression:

“I didn’

“I didn’t have the time t have the time to plan, the cto plan, the client needed it urgently and Ilient needed it urgently and I

had to get it into production immediately”.

had to get it into production immediately”.

How

However this serves to illustrate the t

ever this serves to illustrate the true value of p

rue value of project planning

roject planning

in saving time, money and problems.

(5)

Introduction

The key to a successful project is in planning

Planning is the first thing you do when undertaking a project

Often project planning is ignore to rush in for the work

The value of project planning

saving money

saving time

saving many problems

Remember: If you fail to plan, you plan to fail

Importance of project planning

1.

Broadening

the core team‘s understanding of the project

scope

2.

Determining delivery sequence and priorities

3.

Providing access to product-specific know-how

4.

Managing the expectations of product developers in order to

minimize last minute scope changes

5.

Establishing the optimum process and schedule

6.

Risk analysis, contingency planning and stress-testing of

(6)

Importance of project planning

8.

Defining communication, escalation channels and managing

the client‘s expectations

9.

Ensuring Quality Assurance at all stages

10.

Allocating and managing to budget

Planning stepes

 Developing the project scope:  Setting objectives  Identify deliverables  Develop WBS

 Scheduling:

 Define work activities  Sequence Work activities  Activities resources estimating  Estimate activities duration  Risk management planning

 Quality planning  Budget planning

 Establish human resource plan  Establish communication plan

(7)

Safaa Hashim

DEVELOPING THE PROJECT SCOPE

Project scope

The project scope statement is the definition of the project

 — 

what needs to be accomplished.

The Develop Preliminary Project Scope Statement process

addresses and documents the characteristics and boundaries of

the project and its associated products and ser vices, as well as

the methods of acceptance and scope control.

(8)

project scope

The preliminary project scope statement is developed from

information provided by the initiator or sponsor.

The project scope statement content may vary depending upon

the application area and complexity of the project but it must

contain:

Project objectives

Required deliverables

Project scope development tools and techniques

1 – Project Management Methodology:

The project management methodology defines a process that aids a project management team in developing and controlling changes to the preliminary project scope statement.

2 – Project Management Information System:

The project management information system, an automated system, is used by the project management team to support generation of a preliminary project scope statement, facilitate feedback as the document is refined, control changes to the project scope statement, and release the approved document.

3 – Expert Judgment:

Expert judgment is applied to any technical and management details to be included in the preliminary project scope statement.

(9)

Project objectives

 A project is successful when the needs of the stakeholders have been

met.

A stakeholder is anybody directly, or indirectly impacted by the project.

 As a first step, it is important to identify the stakeholders in your

project.

 It is not always easy to identify the stakeholders of a project,

particularly those impacted indirectly.

 Examples of stakeholders are:  The project sponsor.

 The customer who receives the deliverables.  The users of the project outputs.

 The project manager and project team.

Project objectives

 Once you understand who the stakeholders are, the next step is to

find out their needs.

 The best way to do this is by conducting stakeholder interviews.  Take time during the interviews to draw out the true needs that

create real benefits.

 Often stakeholders will talk about needs that aren't relevant and

don't deliver benefits. These can be recorded and set as a low priority.

(10)

Project objectives

The next step, once you have conducted all the inter views, and

have a comprehensive list of needs is to prioritise them.

From the prioritised list, create a set of goals that can be

easily measured.

A technique for doing this is to review them against the SMART

principle.

This way it will be easy to know when a goal has been

achieved.

Project objectives

Once you have established a clear set of goals, they should be

recorded in the project plan.

It can be useful to also include the needs and expectations of

your stakeholders.

This is the most difficult part of the planning process

completed.

(11)

Project deliverables

Using the goals you have defined, create a list of things the

project needs to deliver in order to meet those goals.

Specify when and how each item must be delivered.

Add the deliverables to the project plan with an estimated

delivery date.

More accurate delivery dates will be established during the

scheduling phase.

Presenter (3)

Leena Faroug Hassan

(12)

Develop WBS

 A work breakdown structure (WBS) is a tool used to define and

group a project's discrete work elements in a way that helps organize and define the total work scope of the project.

 A work breakdown structure element may be a product, data, a

service, or any combination.

 A WBS also provides the necessary framework for detailed cost

estimating and control along with providing guidance for schedule development and control.

 Additionally the WBS is a dynamic tool and can be revised and

updated as needed by the project manager.

Develop WBS

 The WBS provides a common framework for the natural development

of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established.

 A WBS permits summing of subordinate costs for tasks, materials,

etc., into their successively higher level ―parent‖ tasks, materials, etc.

 For each element of the WBS, a description of the task to be

performed is generated. This technique (sometimes called a System Breakdown Structure) is used to define and organize the total scope of a project.

(13)

Develop WBS

 The Work Breakdown Structure is a tree structure, which shows a

subdivision of effort required to achieve an objective; for example a program, project, and contract.

 In a project or contract, the WBS is developed by starting with the

end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g.,

systems, subsystems, components, tasks, subtasks, and work packages) which include all steps necessary to achieve the objective.

Develop WBS

 The WBS is organised around the primary products of the project (or

planned outcomes) instead of the work needed to produce the products (planned actions).

 Since the planned outcomes are the desired ends of the project, they

form a relatively stable set of categories in which the costs of the planned actions needed to achieve them can be collected.

 A well-designed WBS makes it easy to assign each project activity to

one and only one terminal element of the WBS.

 In addition to its function in cost accounting, the WBS also helps map

(14)

Presenter (4)

Aliaa Sayed Abdalaal

(15)

Define work activities

 Activity definition refers to the process of parsing a project into a

number of individual tasks which must be completed before the deliverables can be considered completed.

 Activity definitions rely on a number of specific input processes. These

include enterprise environmental factors, organizational process, the project scope statement, the work breakdown structure, the project management plan.

Scheduling:

Define work activities

 Through use of these inputs, the activities that will need to ultimately

be completed in order to compete all of the project objectives can be readily defined, and the activity definition can be further accomplished through the utilization of a number of tools and techniques including templates, rolling wave planning, expert judgment, and planning components.

 The four ultimate outputs of the activity definition process are the:  Activity list

 The resulting activity attributes  All requested changes,

(16)

Sequence Work activities

 The term activity sequencing refers within the context of project

management to a dual process.

 Initially, activity sequencing involves a specific process of the

identification of dependencies among a series of schedule activities.

 The next step of activity sequencing involves the

documentation of the said series of dependencies among those schedule activities.

 More specifically, activity sequencing involves the chronicling the

dependencies among these schedule activities and putting them into a logical order.

Scheduling:

Activity resource estimating

 Activity resource estimating is a process in which the project team

carefully compiles a thorough listing of the resources that will be needed in completing a project.

 There are six inputs that are to be used in the process of activity

resource estimating. Those six inputs are:

1. The activity list

2. The activity attributes 3. The organizational process

4. The enterprise environmental factors 5. The resource availability.

(17)

Activity resource estimating

 There are a number of tools that can also be utilized in most

effectively estimating the required activity resources. Those tools include:

 Expert Judgment,

 A Complete Alternatives Analysis,  The Use Of Published Estimating Data,  Project Management Software,

 The Use Of Bottom-up Estimating. 

Scheduling:

Activity resource estimating

 The resulting outputs from this process include:  Activity Resource Requirements,  Activity Attributes Updates,  Requested Changes,

 A Resource Breakdown Structure,

 The Development Of a resource calendar.

 The successful utilization of activity resource estimates will help

(18)

Estimate activity duration

 Activity duration estimating represents the act of quantifying the

amount of time that it is anticipated the activity will take to complete.

 This phase of the project, that which consists of the estimating of the

amount of time needed to complete all individual schedule activities, typically and traditionally takes place before a project is kicked off, during the conception phase, however, it is possible for the actual activity duration estimating period to take place later, perhaps close to or even slightly after the project has officially kicked off, however, even in those cases a draft or preliminary estimation has typically been made.

Scheduling:

Estimate activity duration

 Estimations can be made in any calendar unit that seems

appropriate, such as months, weeks, days, etc., the entirety of the activity duration estimate can be further broken down into subparts or milestones at which certain elements, or deliverables, of the activity are to have been completed in final or draft form.

(19)

Alsadig Muneer

RISK MANAGEMENT PLANNING

Risk management planning

 Despite the most careful efforts, sometimes risk cannot be avoided.  There will be a number of times over the course of the project‘s

respective life cycle that the project management team and or the project management team leader will find themselves in a position in which they realize that a particular component as to the project and or a particular facet of that project does in fact come with a set or series of inherent risk.

 After all of these likely and potential risks have been properly

organized and categorized, it is up to the project management team and or the project manager to effectively determine the best way to deal with these risks.

(20)

Risk management planning

 The most effective means with risks is through the establishment of an

effective risk management plan.

 A risk management plan is an input output document that outlines

exactly how risk management will be performed on a given project. It can be an informal document, or it can be very specific and very formalized in nature, depending on what exactly is required.

 Information in these plans can vary widely depending on the project

application area and or project size.

Quality planning

 Quality planning refers specifically to the actions of the project

management team and or the project management team leader to engage in the action of establishing and conducting a process for the purposes of identifying and determining exactly which standards of quality are in fact relevant to the project as a whole, and also in making an effective determination as to how to satisfy them.

 The concept of quality refers specifically to the degree or amount

toward which an inherent or embedded number of traits fulfills a number of predetermined requirements that have been deemed necessary.

(21)

Quality planning

 In quality planning, it is determined how vigilant to be in regards to

monitoring these traits, how stringent to be in the management process in redirecting energies that have lost focus and are causing deviations in the focus from these inherent traits,. Quality planning is typically best done at the onset of the project, but can of course be tweaked as necessary,

Presenter (6)

Asia M. Ali

(22)

Budget planning

 The project budget is a detailed estimate of all the costs required to

complete project tasks.

 It is much more detailed than the high-level budget developed in the

Initiate Stage.

 The typical budget specifies:  Costs for staff labor  Materials procurement  Ongoing operating costs

 Other direct costs such as travel or training.

Budget planning:

Rationale

 The detailed budget provides the project sponsor with a best

estimate of how much the project will cost.

 The detail budget helps manage expectations and gives the project

sponsor information to develop a cost/benefit for the project.

 The budget is also used in the Execute and Control stage to help

(23)

Budget planning

 Who is involved?  Project Manager  Project Sponsor  Project Team  Results

This information is included in a separate section of your project plan

often referred to as ―Project Budget.‖

Budget planning:

(24)

Afrah A. Alaziz

Human resource planning

Human resource planning

The term human resource planning refers specifically to a

project management process that involves the careful and

deliberate identification, categorization, and ultimately,

documentation of the entirety of all project roles assigned to all

individual members of the project work team.

Included among this documentation process is a careful

delineation of all of the individual project team members‗

personal responsibilities in regards to management of the

project, as well as all the specific reporting relationships among

all members of the project team.

(25)

Human resource planning

Human Resources Planning Inputs:

-Enterprise environment factors.

organizational factors.

Technical factors.

Interpersonal factors.

Location factors.

Political factors.

-Organizational process assets.

-Project management plan (particularly the activity

resource requirements)

Human resource planning

Types of documentations:

- project descriptions

-organizational chart

-performance appraisals

The organization‘s conflict management process

Elements like training requirement

Projects roles and responsibilities

(26)

Human resource planning

Human Resources Planning outputs:

Roles and responsibilities

- Roles

- Authority

- responsibilities

- Competency

Staffing management plan

- staffing acquisition

Human resource planning

- Time table

Release criteria

Training needs

Rercognition and rewards

Complains

(27)

Human resource planning

Presenter (8)

Mustafa Kamil

(28)

Communication management plan

The communication management plan is the written document

that outlines, highlights, and details the communications needs

and expectations for the entire project.

This can include specific communications technologies that are

required, such as need for dedicated cell phones so that the

project team members can keep in touch, as well as specific

update formats, such as the need for a weekly email update, or

perhaps the need for a weekly conference call.

Communication management plan

The communication management plan also includes mention of

the specific party or parties who are to be responsible for

each format of communication.

Communication management plans come in a wide variety of

shapes and sizes.

Some can be formally written, others can be more informal

drafts. They can be extremely detailed, or can be written very

broadly, meant more to steer project team members in a

general direction (i.e., ―Send the team a weekly email to

update) as opposed to providing specific rigid instruction (i.e.,

―Send a weekly email to these specific members on this specific

(29)

Communication management plan

Project Communications Management plays a key role in

keeping all members of the project management team on the

same page.

Without communication among all team members and project

stakeholders there can be a breakdown in processes which

could have a negative impact on the final product.

The project manager must know the communication processes

involved in effective project management.

Communication management plan

First of all there should be planning to determine what

information needs to be communicated to all stakeholders in the

project.

Next, that information must be made readily available to the

stakeholders and generated in a timely fashion.

Performance must also be accounted for by reporting the

project status, measuring progress and forecasting.

Finally, communication with project stakeholders must be

managed so that all requirements are met and issues are

promptly resolved.

(30)

NuhaA.Alaziz

Communication management

Interactions and overlap among the communication processes

are inevitable and expected throughout all phases of project

management

Project Communications Management can be broken down into

(31)

Communication management

1.

Managing a meeting by having an agenda as well as

resolving conflict

2.

Writing style to be used

3.

Method of communication; written or oral, informal memo or

formal report, face-to-face or email, all of which are

dependent on the situation at hand

4.

Techniques for presentation including whether to use visual

aids and effective use of body language

5.

Possible barriers or feedback loops that influence

communication

Communication management

There are also several key components in project communication

management which should be considered:

Encoding or translation makes sure everyone understands

what is said.

The output of that encoding is the message which is

conveyed through a medium.

Interference with the message is called noise and finally,

the message must be decoded to have meaning for all

involved.

(32)

Procurement planning

As is the case with almost every aspect of the project

management process, it is essential and imperative that the

project management team and or the project management

team leader implement an effective and succinct plan when it

comes to the various components of procurement throughout the

project‘s life cycle.

Specifically speaking, the procurement management plan refers

to the plan that has been put into place that is meant to dictate

and describe the entirety of the procurement process and how

it is means to relate to and with the developing procurement

documentation, and how contract closure will relate to all.

Procurement planning

The procurement management plan should be implemented

and developed as early in the project life cycle as possible to

assure that, to the extent possible, the procurement process is

consistent throughout, however, in some cases, the plan may be

altered once the project begins, particularly if budgetary

reasons dictate.

(33)

Hatim Abbas Mudawi

(34)

What Exactly Is a “Successful” Project?

“Successful” Project

successful project would be defined as a project that:

Delivered as promised: Project produced all the stated

deliverables.

Completed on-time: Project completed within the approved

schedule.

Completed within budget: Project completed under the

approved budget.

Delivered quality: Project deliverables met all functional,

performance,

(35)

“Successful” Project

Achieved original purpose: The project achieved its original

goals, objectives, and purpose.

Met all stakeholder expectations: The complete expectations of

each key stakeholder were met, including all client acceptance

criteria, and each key stakeholder accepts the project results

without reservation.

■ Maintains ―win

-

win‖ relationships

:The needs of the project

are met with a ―people focus‖ and do not require sacrificing the

needs of individual, team members or vendors. Participants

on successful projects should be enthusiastic when the project is

complete and eager to repeat a similar experience.

Tip

An excellent technique is to identify,

document, review, and approve any

criteria that will be used to measure the

success of the project during the project

definition and planning processes.

References

Related documents

Rationale. The essence of ownership is control. Yet small shareholders have no control over the activities of the company they “own” and lack protection from

Since our objective is to forecast the performance of a given production unit in terms of its productivity, we would like to forecast the Malmquist productivity index

Nursing Topics Discussed During Rounds The Society of Critical Care Medicine & Sutter Health (2015) highlight the importance of members of the interprofessional team

The proof of the following Lemma is partially similar to that of [7, Theorem 3.1]: Lemma 4.6 The fibrewise foliation associated to a thick foliated bundle with taut fibre and

The technical potential for variable renewable electricity generation in Czechia is more than twice as high as the estimated electricity consumption in 2030, which constitutes

El reuso del agua en la Ciudad de México ha sido importante para la diminución de agua potable en el sector industrial y el sector agrícola (JIMENEZ,2011). El reuso de

The West Virginia Department of Education, in collaboration with SREB, revived and refocused the High Schools That Work initiative in the state, resulting in 26 schools focused

While the municipality’s appraisal expert’s determination concerning the interrelationship of the subject’s retail and warehouse areas is more reliable than taxpayer’s analysis,