• No results found

Rabai Case Study. May, 2009

N/A
N/A
Protected

Academic year: 2021

Share "Rabai Case Study. May, 2009"

Copied!
14
0
0

Loading.... (view fulltext now)

Full text

(1)

Rabai Case Study

(2)

Rabai Location

The Project is a 90MW Fuel Oil fired power plant

located at Rabai, 20 km inland from the port of Mombasa. The site is

adjacent to the KPLC high voltage substation.

(3)

0 2 0 0 4 0 0 6 0 0 8 0 0 10 0 0 2 0 0 4 2 0 0 5 2 0 0 6 2 0 0 7 GDP /Capita

Kenya is generally regarded, notwithstanding the recent civil unrest, as the business hub of East Africa and one of the more stable business environments on the African Continent. Over the last few years the country has enjoyed sustained growth benefiting from a pro business, pro private sector Government.

Subject Descriptor Units Scale 2004 2005 2006 2007 2008 2009 Gross domestic product Annual percent change 4.60% 5.8 6.10% 7% 2.50% 3.40% Gross domestic product per capita U.S. dollars Units 495 572 670 845 860 921 Inflation, average consumer prices Annual percent change 11.60% 10.30% 14.40% 9.76% 12.34% 7.01% Population Persons Millions 32.8 33.4 34 34.6 35.3 35.9 International Monetary Fund, World Economic Outlook Database, April 2008

(4)
(5)
(6)

 Rabai was recognized by both Project Finance International and

Project Finance Magazine as ‘Africa Power Deal of the Year’

 Why is this Project of interest?

 It was structured in the midst of a period of considerable unrest in

Kenya

 Following the Dec 2007 Presidential elections a dispute over the result

led to violence which resulted in the deaths of over 1,000 people and the displacement of over 300,000 people

 At this time we had to work closely with our financing partners to

determine the conditions upon which they would continue with the transaction

 There was much discussion with the Government of Kenya regarding

risks associated with political violence

 The financing was ‘firmed up’ following the announcement of a

power sharing deal brokered by Kofi Annan

(7)

 The Project reached Financial Close on October 8th 2008

 This was less than one month after the collapse of Lehman Brothers

 The debt terms including margin were unaffected by the crisis

 The project was to some extent insulated from the crisis by the

nature of its lenders

 The Development Finance Institutions lending to Rabai were

prepared to continue

 The success of the financing to some extent also reflects the extent

to which Africa has been insulated from some of the effects of the crisis

 Growth in many parts of Africa has moved from the 7%pa to the

5%pa range

 This is in contrast to the negative growth being experienced in

much of the developed world

(8)



Clear transparent process



Built on a platform of a reformed energy sector

 New Electricity Act enabling private sector participation

 An independent pro-investment Energy Regulatory Commission

 A cost reflective tariff

 A track record; success breeds success



Use of standard documentation reflecting risk allocation

designed to facilitate project financing



Clear decisive leadership within the Energy Sector



Co-operation and full involvement of officials from the

Attorney General’s Office and the Ministry of Finance



Development Finance Institutions being somewhat less

affected by the banking crisis

Reasons for Success

(9)

 Recognition of the need for Government Support

 A willingness to learn from previous deals inside and outside

Kenya

Reasons for Success II

Government Support Sector Reform Guarantees Requested Comfort Letter Requested

(10)

Private Sector Participation

Public

 Amount of cash is finite and is

required for uses such as health and education

 The utility has to be in a

position to raise the capital required to complete any given project

 Public projects have a

tendency to run over time and over budget

Private

 Funds are readily available for

well structured projects

 The utility has only to pay

electricity and not to raise the capital for any given project

 Performance levels are

typically high

 The private sector takes

performance risk

 Government does, however, have the option to complete projects in

(11)

Equity and Debt Participants

34.5%(€9.2m) 20%(€5.3m) 25.5%(€6.8m)

100% (99% Prefs. 1% Ords.)

Aldwych FMO BWSC IFU

Rabai Power Holdings UK

Rabai Power Ltd. DEG FMO EAIF Proparco 15% (€12.0m) 25%* (€19.8m) 25%* (€19.8m)

* Both EAIF and Proparco are investing in senior and subordinated debt $2.8m each

Equity

Debt 20%(€5.3m)

25% (€19.8m)

(12)

KPLC Aldwych Const. Kenya Government of Kenya

Rabai Power Ltd.

Power Purchase Agreement, Direct Agreement & Sub Lease Construction Period Management Agreement BWSC Fuel Supplier Fuel Supply Agreement EPC Contract (onshore and offshore) a Spare Parts & Technical Services Agt.

Lenders

Financing Agreements

Rabai O&M Co.

Operations and Maintenance Agreement

Government of Kenya Letter

(13)

Ken Gen

Energy Regulatory Commission

Policy Direction

Recommend Licence Issue

KPLC Ministry of Energy Policy Licence Imports IPPs Retail Customers R E G U L A T I O N Enforce Licence Requirements Retail Tariff Approval PPA & Bulk Tariff Approval

Customer Complaints

Sector and Customer Information – Sector

Overview

(14)

Aldwych International Ltd. Burmeister & Wain Scandinavian Contractors A/S

Emerging Africa Infrastructure Fund

Nederlandse Financierings-Maatschappij voor Ontwikkelingslanden N.V.

Promotion et Participation pour la Coopération économique

Nederlandse Financierings-Maatschappij voor Ontwikkelingslanden N.V.

Deutsche Investitions- und Entwicklungsgesellschaft mbH

Bank of New York Mellon

Allen & Overy LLP

The Industrialization Fund for Developing Counties A joint venture

of

and

Rabai Power Holdings Limited

€84,600,000 Project Financing facility for

Lead Arrangers

Barclays Kenya Limited

Trinity International LLP Lenders Legal Advisor Sponsor Legal Advisor Facility Agent And Security Trustee Kenyan Security Trustee

Rabai Power Limited

References

Related documents

It consist of 5 modules ,evaluation based filtering, time domain unfair rating detector, suspicious user correlation analysis, trust analysis based on Dempster-Shafer

With the definition of MDA (Model- Driven Architecture) and the acceptance of MDE (Model-Driven Engineering) techniques in this environment, some groups are working in the use

The Midwest Association of Higher Education Facilities Officers (MAPPA) invites you to the Educational and Pro- fessional Conference held at the Kingsgate Marriott Con- ference

mental health problem mental disorder psych* illness psych* disorder psych* diagnosis psych* problem distress schizophrenia depression anxiety self-help intervention

(There will in such studies be a need to consider the impact of policies which affect the movement of freight within the urban area, such as lorry restrictions or time-specific

[9] has divided pronoun into demonstrative pronoun (ﯼﺮﻴﻤﺿ ﺖﻔﺻ), personal pronoun ( ﺮﻴﻤﺿ ﯽﺼﺨﺷ), relative pronoun (ہﻟﻮﺻﻮﻣ ﺮﻴﻤﺿ), correlative pronoun (لﻮﺻﻮﻣ

The purpose of this lab is to construct a relationship between frictional forces and the normal force on an object, to calculate the kinetic and static coefficients of friction

 Permits a county law library resources board to accept payment of fees for services or receive gifts by a financial transaction device, such as a credit or debit card, if the board