ECE 6606PD Distribution Systems Engineering
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Assignment
1
Distribution
System
Load
Characteristics
1-a)Average Power= total annual8760 energy 107
=8760=1141kW
1-b)Annual Load Factor= F = Average demand
LD Peak demand = 1141 =0.326 3500 2-a) Transformer kW= 1800+2000+2000 =5043.48 kW 1.15
To Calculate Transformer S, calculate Q first Q=Ptancos-1 (power factor)
Q =1800tancos-1 (0.95)=591.63 kVAR Similarily
Q2 =1239.49 kVAR Q3 =968.64 kVAR
Transformer kVAR= Q1 +Q2 +Q3 =2434.578 kVAR
1.15
Transformer kVA= P2 +Q2 = 5043.482 +2434.5782 =5600.34 kVA 2-b)Load diversity=(1800+2000+2000)-(5043.48)=756.52 kW
2-c) First transformer's emergency rating =3125×1.25=3906.25 kVA (Not Suitable) Second transformer's emergency rating =4687×1.25=5858.75 kVA (Suitable) Choose second transformer
ECE6606PD
Distribution Systems Engineering
Assignment # 2
Distribution System Load Forecasting
1. Explain briefly the main difference between the extrapolation, the simulation, and the econometric methods for load forecast. Your answer should address the following:
a. Their use for distribution system load forecast. b. The data requirements.
c. The accuracy of their results.
[30 marks] Lecture 2, Section 4
2. For the demand data given in Table 1, forecast the nearest three future points and calculate the MAE the RMSE over the historical data points sets using the following forecasting techniques:
a. 4-order weighted moving average (WMA) b. ARIMA (2,0,0)
Table 1 Hourly demand data variation
[70 marks] Hour 1 2 3 4 5 6 Power (kW) 28969.26 26392.32 24254.58 22707.33 21787.5 21642.96 Hour 7 8 9 10 11 12 Power (kW) 22187.94 22463.73 22850.31 24301.62 26440.89 28536.93 Hour 13 14 15 16 17 18 Power (kW) 29886.12 30487.05 30160.56 30874.11 33837.27 37946.61 Hour 19 20 21 22 23 24 Power (kW) 37448.58 36800.67 35871.45 34722.09 32497.41 28453.05 Solution:
i) 4-order weighted moving average (WMA)
The mathematical expression for the 4-order moving average model can be re-written as follows 4 Yˆ
i
Wm Y
i m
W1 Y
i 1
W2 Y
i 2
W3 Y
i 3
W4 Y
i 4
m1 i 4The chosen weights are 0.4, 0.3, 0.2, and 0.1, respectively.
Table 2 and Fig. 1 present the generated results when using the 4-order weighted moving average. These results reveal that the MAE is 2314.41 kW and the RMSE is 2848.89 kW.
Table 2 Load forecasting using 4-order weighted moving average
Hour (i) Power (kW) {e(i)}^2
Actual Forecasted e(i)
1 28969.26 2 26392.32 3 24254.58 4 22707.33 5 21787.5 24534.696 2747.20 7547085.86 6 21642.96 23017.347 1374.39 1888939.63 7 22187.94 22160.358 27.58 760.77 8 22463.73 21996.297 467.43 218493.61 9 22850.31 22149.216 701.09 491532.80 10 24301.62 22481.127 1820.49 3314194.76 11 26440.89 23287.281 3153.61 9945249.72 12 28536.93 24683.277 3853.65 14850641.44 13 29886.12 26492.394 3393.73 11517376.16 14 30487.05 28233.867 2253.18 5076833.63 15 30160.56 29512.131 648.43 420460.17 16 30874.11 30041.256 832.85 693645.79 17 33837.27 30483.834 3353.44 11245533.01 18 37946.61 31877.958 6068.65 36828537.10 19 37448.58 34520.703 2927.88 8572463.73 20 36800.67 36218.28 582.39 339178.11 21 35871.45 36927.891 1056.44 1116067.59 22 34722.09 36673.158 1951.07 3806666.34 23 32497.41 35755.263 3257.85 10613606.17 24 28453.05 34269.948 5816.90 33836302.34 25 28453.05 31662.006 26 28453.05 29888.826 27 28857.486 2
40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Time Intervals (hours)
Actual Forecasted
ii) ARIMA
(2,0,0)
Fig. 1 Load forecasting using 4-order weighted moving average
The forecasting model for the ARIMA (2,0,0) is expressed mathematically by,
Yˆ
i
a b1 Y
i 1
b2 Y
i 2
i 3, 4, 5,... where a , b1 ,
and
b2 represent the model coefficients that can be estimated using the Least Square Method as follows,
⎡a ⎤ A ⎢b ⎥
T .
1.T Y ⎢1 ⎥ ⎢⎣b2 ⎥⎦ ⎡1 ⎢ ⎢1 ⎢ ⎢ Y
2
Y
3
Y
1
⎤ Y
2
⎥ ⎥ ⎥ ⎣1 Y (n 1) Y (n 2)⎦ ⎡Y
3
⎤ ⎢ ⎥ Y ⎢⎢Y
⎥4
⎥ ⎢
n
⎥There for this problem the model coefficients are
⎡a ⎤ ⎡3009.50⎤ ⎢ ⎥ ⎢ ⎥ A ⎢b1 ⎥ ⎢ ⎦ D e m an d ( ⎥ ⎣
1.726
⎥ ⎢⎣b
2 ⎥⎦ ⎢⎣- 0.8318⎥⎦
Table 3 and Fig. 2 present the generated results when using the ARIMA (2,0,0). These results reveal that the MAE is 796.71 kW and the RMSE is 1134.88 kW.
45 40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Time Intervals (hours)
Actual Forecasted
Fig. 2 Load forecasting using ARIMA (2,0,0) Table 3 Load forecasting using ARIMA (2,0,0)
Hour (i) Power (kW) {e(i)}^2
Actual Forecasted e(i)
1 28969.26 2 26392.32 3 24254.58 24466 211.42 44698.42 4 22707.33 22920 212.67 45228.53 5 21787.5 22028 240.50 57840.25 6 21642.96 21727 84.04 7062.72 7 22187.94 22243 55.06 3031.60 8 22463.73 23303 839.27 704374.13 9 22850.31 23326 475.69 226280.98 10 24301.62 23764 537.62 289035.26 11 26440.89 25947 493.89 243927.33 12 28536.93 28433 103.93 10801.44 13 29886.12 30271 384.88 148132.61 14 30487.05 30856 368.95 136124.10 15 30160.56 30771 610.44 372636.99 16 30874.11 29708 1166.11 1359812.53 17 33837.27 31211 2626.27 6897294.11 18 37946.61 35732 2214.61 4904497.45 19 37448.58 40360 2911.42 8476366.42 20 36800.67 36082 718.67 516486.57 21 35871.45 35378 493.45 243492.90 22 34722.09 34313 409.09 167354.63 23 32497.41 33102 604.59 365529.07 24 28453.05 30218 1764.95 3115048.50 25 28453.05 25088 26 28453.05 28452 27 28452 4 D e m an d (
ECE 6606PD
Distribution Systems Engineering
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Assignment
3
Distribution
System
Planning
Q1) Lecture 3, Sections 1, 3 and 4
Q2) it is required to calculate the cost function between different sections
Since it is a transportation problem, then we assume a separate cable is extended from each substation to each load point, no tapping‐of is allowed (tapping of is considered only in a transhipment problem)
Also since there is no limit to the power that could be supplied by each substation, each substation is assumed to supply the full load of a load point if associated with the least cost function for this load point For straight distance: cost function is 1 pu.
For straight river crossing: cost function is 10 pu. Thus the following table can be constructed
Load center Shortest distance from Shortest distance from 1 1 4 (4‐1) (9‐8‐7‐4‐1) 2 2 3 (4‐1‐2) (9‐8‐5‐2) 3 5 2 (4‐7‐8‐9‐6‐3) (9‐6‐3) 4 0 3 (9‐8‐7‐4) 5 1 2 (4‐5) (9‐8‐5) 6 4 1 (4‐7‐8‐9‐6) (9‐6) 7 1 2 (4‐7) (9‐8‐7) 8 2 1 (4‐7‐8) (9‐8) 9 3 (4‐7‐8‐9) 0
The minimum distance table is constructed for each load point
Load point Closest substation Cost function
1 SS1 1 2 SS1 2 3 SS2 2 4 SS1 0 5 SS1 1 6 SS2 1 7 SS1 1 8 SS2 1 9 SS2 0
Total cost function is 9
SS1 is used to supply load points: 1, 2, 4, 5, and 7 SS2 is used to supply load points 3, 6, 8 and 9 Rating of
SS1=2+4+1+5+2=14 MVA
Rating of SS2=4+6+5+5=20 MVA Results are illustrated in following table
Substation SS1 SS2
Fed load points 1 2 4 5 7 3 6 8 9
Distribution Systems Engineering
ECE6606PD
Assignment # 4 Solution
Distribution System Automation &
Demand Side Management
1. Discuss the main factors influencing efficient and reliable load supply to customers.
Lecture 4, Section 1 [30 marks]
2. Explain briefly the main basic areas required to be developed in order to implement distribution system automation.
Lecture 4, Section 6 [30 marks]
3. Discuss the different requirements of successful load management and its possible impacts
Lecture 4, Section 8 [40 marks]
Assignment # 5 Solution
Sub-Transmission Lines and Non-Technical
Distribution Substations Design Factors
1. Discuss briefly the different types of sub-transmission circuit’s configurations. Your answer should address the following:
a. The one line diagram of the electric circuit. b. The reliability of the configuration.
c. The relative cost of each configuration. d. The main drawbacks of each configuration.
Lecture 5, Section 2.1
2. Discuss briefly how the most optimal substation locations (sites) are determined and the different factors affecting the selection process.
Assignment # 6 Solution
Distribution Substation Design
Aspects
1. Discuss briefly the different types of substation bus configurations. Your answer should address the following:
a. The one line diagram of the electric circuit.
b. The possible operating voltages for each configuration. c. The main drawbacks of each configuration.
d. The main advantages of each configuration
Lecture 6, Section 3
2. A distribution substation services a square area with the substation at the center of the square. Assume that the substation is served by four three phase four wire 13.2/22.9 KV grounded-wye primary feeders. The feeder mains are made of either #2 AWG copper or #1/0 ACSR conductors. The three phase open wire overhead lines have a geometric mean spacing of 37 in between phase conductors. Assume a lagging-load power factor of 0.9 and a 1000 KVA/mi2 uniformly distributed load density.
From tables, the conductor ampacity for #2 AWG copper is 230A. (a) Consider thermally loaded feeder mains:
Since, the thermally limited case is considered, therefore, the feeder conductor is equal to its current carrying capacity, i.e. I = Imax = 230 A.
(i) Maximum load per feeder.
S feeder 3 x
VLL
x I max
x 22.9 x 230
9122.7 KVA (ii) Substation size.
Ssubstation 4 x S feeder 4 x 9122.57 36490.8 KVA
(iii) Substation spacing, both ways.
S feeder Afeeder x D
9122.7 l 2 x 1000
l4 3.02 mi
Substation Spacing, both Ways 2 l4 6.04 mi
(iv) Total percent voltage drop from the feed point to the end of the main. From Fig. 1, k for #2 AWG copper at 22.9 kV is 0.00025
%VD 2 x k x D x l 3 4 3 4 2 x 0.0025 x 1000 x (3.02)3 3 4.59 %
(b) Consider voltage drop-limited feeders which have 3% voltage drop and find: (i) Substation spacing, both ways.
%VD 2 x k x D x l 3 4 3 4 3 2 x 0.00025 x 1000 x l 3 3 4 l4 2.621 mi
Substation Spacing, both Ways 2 l4 5.242 mi (ii) Maximum load per feeder.
2 S feeder Afeede r x D l4 2 x 1000 S feeder (2.621) x 1000 6869.641 KVA (iii) Substation size.
Ssubstation 4 x S feeder 4 x 6869.641 27.47856 MVA
(iv) Ampere loading of the main in per unit of conductor ampacity.
S feeder I 6869.941 173.196 A 4 3 x VLL 3 x 22.9
I pu I I max 173.19 6 230 0.753
---
---ECE 6606PD
Distribution Systems Engineering
Assignment
7
Primary
Distribution
Systems
Design
and Operation
1)
(40 marks) Explain briefly the diferent primary
distribution system configurations. Your answer should
address the following:
a)
The single line diagram of each configuration.
b)The main advantage of each configuration.
c)The disadvantages of each configuration.
d)
The degree of reliability of each configuration.
Lecture 7, Section 3
2)
(60 Marks)
-
First, determine the k factor for the main and the
lateral
From Figure 2, The K factor for the main = 0.0004 and
for the lateral = 0.001
-
Then calculate the maximum diversified demand
-
Determine the peak load for each substation as
follows
-
For design A: The voltage drop will be the
-
For design B: The voltage drop will be summation of
the voltage drop of the shown three lines
Total Voltage Drop
1.6
1.6
0.0625
3.2625%
Distribution Systems Engineering
ECE6606PD
Assignment # 8 Solution
Secondary Distribution Systems Design, Services
and Metering
1. Explain briefly the different secondary distribution system configurations. Your answer should address the following:
a. The single line diagram of each configuration. b. The main advantage of each configuration. c. The disadvantages of each configuration. d. The degree of reliability of each configuration.
Lecture 8, Section 1.2
2. Discuss the main components of the secondary distribution system. Your answer should consider the following issues:
a. The secondary system voltage level.
b. The design consideration of the secondary system.
c. The degree of reliability of each component in the secondary system.
Assignment # 9 Solution
Voltage Drops and Power Loss
Calculations
1. Figure #1 shows a square-shaped service area (A = 4 mi2) with a uniformly distributed load density
of D kVA/mi2 and 2 mi of #4/0 AWG copper overhead main from a to b. There are many closely spaced primary laterals, which are not shown in the square-shaped service area of the figure.
In this voltage-drop study, use the precalculated voltage-drop curves of Figure #2 when applicable. Use the nominal primary voltage of 19,920/34,500 V for a three-phase four-wire wye-grounded system. Assume that at peak loading the load density is 1000 kVA/mi2 and the lumped load is 2000 kVA, and that at off-peak loading the load density is 333 kVA/mi2 and the lumped load is still 2000 kVA, The lumped load is of a small industrial plant working three shifts a day. The substation bus voltages are 1.025 pu V of 19,920 base volts at peak load and 1.000 pu V during off-peak load. The transformer located between buses c and d has a three-phase rating of 2000 kVA and a delta-rated high voltage of 34,500 V and grounded-wye- delta-rated low voltage of 277/480 V. It has 0 + j0.05 per unit impedance based on the transformer ratings. It is tapped up to raise the low voltage 5.0 percent relative to the high voltage, i.e., the equivalent turns ratio in use is (19,920/277) x 0.95. Use the given information and data for peak loading and determine the following:
a- The percent voltage drop from the substation to point a, from a to b, from b to c, and from c to d on the main.
b- The per unit voltages at the points a, b, c, and d on the main. c- The line-to-neutral voltages at the points a, b, c, and d.
Figure #2, Question #1
Solution:
a- The kVA rating of the square-shaped service area is
Ssquare = Dsquare x Area = 1000 x 4 = 4000 kVA.
The total kVA load on the main feeder is
Stotal = Ssquare + Slumped = 4000 + 2000 = 6000 kVA.
Using Fig. 2 the K constant for # 4/0 Copper is 0.000065 and that for # 4 Copper is 0.00017. Then, the %VD from the substation to bus A is
%VDOA = K x Stotal x l = 0.000065 x 6000 x 1 = 0.4 % .
%VDAB = (K x Ssquare x l ) + (K x Slumped x l) 2 = (0.000065 x 4000 x 1) + (0.000065 x 2000 x 2) = 0.52 % .
The %VD from bus B to bus C is
%VDBC =K x Slumped x l =0.00017 x 2000 x 2 = 0.68 % .
The %VD from bus O to bus C is
%VDOC =%VDOA +%VDAB +%VDBC = 0.4 + 0.52 + 0.68 = 1.6 % .
The per unit voltage at bus C (similarly at the lumped load terminal) is:
Vc = Vo - VDOC = 1.025 -0.016 = 1.009 pu
To find the %VD from bus C to bus D: The lumped load current is
I 2000 kVA
3 x
1.009 x 34.5 kV
33.17 A
The base load current is
Ibase S lumped 3 x VC ,LL 2000 kVA 3 x 34.5 kV 33.47 A
The per unit lumped load current is
I pu I I base
33.17 0.99 pu 33.47
Since pf = 0.9, therefore = 25.84and sin = 0.4359.
and the low voltage side has been tapped up 5%
x VC ,LL
3
Then the %VD from bus C to bus D is %VD = I (R cosX sin ) Vbase 0.05 0.99 x 0.05 x 0.4359 1 0.0 5 = -2.84 % . C
b- The per unit values for the voltages at buses A, B, C, and D on the main: VA = V0 – V0A = 1.025 – 0.004 = 1.021 pu VBB = VA – VAB = 1.021 – 0.0052 = 1.0158 pu VC = VBB – VBC = 1.0158 – 0.0068 = 1.009 pu VD = VC – VCD = 1.009 – (-0.0284) = 1.0374 pu
c- The line-to-neutral voltages at buses A, B, C, and D on the main:
VA = 19,920 x 1.021 = 20,338.32 V
VBB = 19,920 x 1.0158 = 20,234.73 V
VC = 19,920 x 1.009 = 20,099.28 V
VD = 277 x 1.0374 = 287.36 V
2. Figure 3 show a single-line representation of a three-phase, 69 kV network. Substation 1 supplies substations 2 and 3. Substations 2 and 3 are connected via a tie line. Calculate:
a. The voltage difference between substations 2 and 3 when the tie line is open. b. The line currents when the tie line is connected.
c. The total power loss when the tie line is connected.
Figure #3, Question #2
Solution:
For the 125 A, PF = 0.9 load;
I L1 112.5 j 54.49 125 25.84 A
For the 195 A, PF = 0.85 load; I L2 165.75 j 102.72 195 31.78 A a. when the tie line is open as shown in Figure # 4 we have;
I1 I L1 112.5 j 54.49 125 25.84
A
I 2 I L2 165.75 j 102.72 195 31.78 A
Figure # 4, Question #2 The voltage at substation 2 (V2) can be expressed by;
V2 V1 I1 x Z12 V1
112.5 j 54.49
x
0.9 j 1.8
V1
199.332 j 153.459
Similarly, the voltage at substation 3 (V3) can be expressed by;
V3 V1 I 2 x Z13 V1
165.75 j 102.72
x
1 j 1
V1
268.47 j 63.03
Subtract the last two equations from each other, the voltage difference between substations 2 and 3 (V23) can be found as
V23 V2 V3
199.332 j 153.459
268.47 j 63.03
69.138 j 90.429113.8 52.6 V
ECE6606PD
Distribution Systems Engineering
I1 I 3 I L1 112.5 j 54.49 125 25.84 A I 2 I3 I L2 165.75 j 102.72 195 31.78 A and Therefore, I1
112.5 j 54.49
I3 I 2
165.75 j 102.72
I3 and Using kVL, we get; I1 x Z12 I 2 x Z13 I 3 x Z 23 0Substituting by I1 and I2 in the last equation we get;
112.5 j 54.49
I3
x
0.9 j 1.8
165.75 j 102.72
I3
x
1 j 1
I 3 x
1 j 2
0 Therefore,
112.5 j 54.49
x
0.9 j 1.8
165.75 j 102.72
x
1 j 1
I 3
0.9 j 1.8
1 j 1
1 j 2
I 3 7.43 j 18.89 20.368.54 A I1
112.5 j 54.49
7.43 j 18.89
105.07 j 73.38 128.1634.9 A I 2
165.75 j 102.72
7.43 j 18.89
173.18 j 83.83 192.4025.83 Ac. The total power loss when the tie line is connected can be calculated as follows;
ECE6606PD
Distribution Systems Engineering
3 x
I 2 x r12 I 2 x r 13 I3 x r23
3 x
128.16
2 x 0.9
192.4
2 x 1
20.3
2 x 1
156.64 kW 1---
---ECE 6606PD
Distribution Systems Engineering
Assignment
10
Application
of
Capacitors
for
Distribution Systems
1)
(20 marks) Power capacitors are used to improve
distribution system performance. Discuss the benefits
for using power capacitor in distribution systems.
(Lecture 10, Sections 4.3
& 4.4) (20 marks) Explain the main diference between
applying series and shunt capacitors to distribution
system and also identify the main functions and the
target applications of each capacitor.
(Lecture 10, Sections 5
& 6)
2)
(60 marks) Assume that a three – phase 400-hp,
50-Hz, and 4160-V star connected induction motor has a
full load efficiency of 85%, a lagging pf of 0.75, and
is connected to a feeder. If it is desired to correct the
power factor of the load to 0.88 lagging, by
connecting three capacitors at the load, determine
following:
a)
The rating of capacitors
bank
in
Kilovars
(without
any approximations).
b)
The capacitance of each unit if capacitors are
connected in delta (in microfarads).
c)
The capacitance of each unit if capacitors are
connected in star (in microfarads).
Solution
a)
The input power of the induction motor can be found
as:
P
(400
hp
)(0.7457
kW
/
hp
)
0.85
350.92 kW
The reactive power of the motor at the uncorrected power
factor is:
---
---ECE 6606PD
Distribution Systems Engineering
Q
P
tan
350.92 tan(cos
10.75)
1 1Q
1
350.92
0.8819
309.48 k var
The reactive power of the motor at the corrected power
factor is
Q
P
tan
350.92 tan(cos
10.88)
2 2Q
2
350.92
0.5397
189.41k var
Thus, the reactive power provided by the capacitor equals
Q
c
Q
1
Q
2
309.48
189.41
120.07 k var
b)
The capacitor reactance can be calculated as
X
c,phase
V
21
phase
Q
c, phase2
fC
Thus, the capacitance of the capacitor is calculated as
C
Q
c, phase2 phaseWhere
Q
Q
c
120.07
k var
c, phase3
3
For delta connected capacitor, V
phaseis equal to 4160 V
(The voltage across each individual capacitor is the
total line voltage) as shown in Figure 1
f
V
2
Substituti
ng
Figure 1
C
120.07
3
2
50
1000
4160
27.36
F
c)
In this case, V
phasewill be equal to (4160/sqrt(3))
as shown in Figure 2
Substituti
ng
C
120.07
1000
22.09
F
3
2
60
(
4160
)
23
Comment: Most utilities prefer to install delta connected
capacitors as the capacitance required in this case is
(1/3) the capacitance required for star connected
capacitors. However, it has to be noted that delta
connected capacitors are subjected to (sqrt (3)) more
voltage than star connected capacitors
Assignment
11
Distribution
System Voltage
Regulation
1)
(30 marks) Voltage regulators are used to improve the
quality of the distribution system performance. Discuss
briefly the main components of the automatic voltage
regulator and their main functions. Also explain the
main function of the line drop compensator (LDC) and
the electric circuit of the LDC.
[Sections 6 & 7]
2)
(70 marks) An industrial customer’s bus is located at
the end of a 3 mile primary line with a resistance of
0.3 Ω/mi and an inductive reactance of 0.8 Ω/mi. The
customer’s transformer is rated 5000 kVA with
transformer impedance of 0 + j0.05 pu Ω based on
the rated kVA. Assume that the industrial load is at
the annual peak of 4000 kVA at 80 % lagging power
factor. Select a proper three-phase capacitor bank size
to be connected to the industrial load 4 kV bus to
achieve the following goals:
a)
Produce a voltage rise of at least 0.02 pu.
b)
Raise the ON-peak power factor to at least 88 %
lagging power factor.
Hint:
-
Use multiples of three-phase, 150 kvar capacitor units
in sizing the
required capacitor bank.
-
The primary voltage of the transformer is 12.8 kV.
Solution
For the original load (4000 kVA at 80 % lagging power factor),
S
4000
cos
1(0.8)
4000
36.87
kVA
After correcting the load power factor to 88 % lagging, the
active power
P
n
P
o
S
o
pf
o
4000
0.8
3200 kW
Howeve
r
P
n
S
n
pf
n
3200
S
n
0.88
S
n
3636.364 kVA
Then, it is required to find the old and new reactive powers
Q
(S
)
2
(P )
2
2400 kVAR
o o oQ
(S
)
2
(P )
2
1727.17 kVAR
n n nTherefore, the additional reactive power required by
installing the capacitor bank to raise the ON-peak power
factor to at least 88 % lagging power factor is
Q
c
Q
o
Q
n
2400
1727.17
672.83 kVAR
Using multiples of three-phase 150 kvar capacitor units,
then the required reactive power of the capacitor bank is
750 kVAR (this value will raise the power factor to 88.88 %)
Considering the transformer primary voltage as 12.8 kV,
the transformer impedance can be calculated as follows;
X
X
( pu)
X
(12.8
10
3)
2(base)
0.05
1.6384
tr tr tr5000
10
3The resultant voltage rise from installing the 750 kVAR
capacitor bank is
VR( pu)
Q
X
L
3636.36
2
3200
21000 (kV
B,LL)
750
(0.8
3
1.6384)
1000 (12.8)
0.018486 pu
2This is less than the required 2%
Thus, 750 KVAR don’t meet the design specifications
Increase the capacitor size to 900 KVAR
VR( pu)
Q
X
L1000 (kV
B,LL)
900
1000 (12.8)
(0.8
3
1.6384)
2
0.0222 pu
Check for the new power factor
pf
cos(tan
1(
Q
n))
cos(tan
1(
Q
o
Q
c)
cos(tan
1(
2400
900
)
npf
n
0.905
P
nP
n3200
2Assignment
12
Distribution
Service
Reliability
1)
(50 marks) Improvement of electric power delivery
reliability is an important task that is carried out by
the electric utility due to the high cost of customer
outages. Explain briefly the main reliability indices
that are commonly used in measuring distribution
system reliability. Also explain the widely used
reliability practices in distribution systems. Your answer
should address this subject for the following customer’s
type: Residential, light load commercial, commercial,
industrial, and agricultural.
[Sections 3 & 5]
2)
(50 marks) Each component in the system has its
internal risk of failure along with the external factors.
Discuss briefly how the diferent existing components
in the distribution system can afect the system
reliability.
[Section 6.1]
Notes
-