• No results found

Reliability Analysis of Randu Garut 3 Distribution System Using Section Technique Method

N/A
N/A
Protected

Academic year: 2021

Share "Reliability Analysis of Randu Garut 3 Distribution System Using Section Technique Method"

Copied!
6
0
0

Loading.... (view fulltext now)

Full text

(1)

Reliability Analysis of Randu Garut 3 Distribution

System Using Section Technique Method

Jimmy Trio Putra

Department of Electrical Engineering and Informatics Universitas Gadjah Mada

Yogyakarta, Indonesia [email protected]

Raka Trialviano Bagus

Department of Electrical Engineering and Informatics Universitas Gadjah Mada

Yogyakarta, Indonesia [email protected] Abstract— In a distribution system, reliability index is

significant to calculate system performance in continuosly distribute the electricity power to consuments. Fedeer analysed by researcher is the main electricity distributor in Tambak Aji industrial area, a developing industrial area. This research is needed to be conducted to ensure the frequent blackout is known and minimalized along with increasement of load number in the feeder. Using section technique method which divides feeder section based on sectionalizer number and detailed calculation in each load point, device failure rate, the length of conductor, and disturbance repairement duration. It was obtained Randu Garut 3 feeder reliability index of SAIFI of 1.759 faults/year, SAIDI of 4.547 hours/year as CAIDI of 2.585 hours/year.

Keywords—CAIDI, reliability, SAIDI, SAIFI, Section Technique

I. INTRODUCTION

Electrical power system’s ability to provide sufficient supply with satisfying quality is main role of electrical producer [1]. As the demand of electrical power goes higher, the system is demanded to has reliability in electrical power providing and distribution. Disturbance or damage in system will widely affect reliability value and also make load released thus black out is happened.

To determine reliability level of electrical power distribution, medium voltage network’s role is crucial. The electric power distribution systems contributes about 80-90% of the customer reliability problems in general [1-3]. There are some number of factors that may cause abnormal system conditions (or fault conditions) and result in customer interlude, for example contact of animals and trees with distribution equipment, lightning and wind storms as examples of bad weather, distribution equipments with aging condition and lack of maintenance and traffic accidents [4-7].

Electrical system disturbance that resulted in blackout gives losses in consument’s side. According to PT PLN (Persero) West Semarang region data, there is big growth of customer number from 2016 until February 2018 as many as 3645 customer or 3,7%. This is caused by increasement of people’s life rate and batch of developments in industrial sector by goverment, especially West Semarang Goverment. Thus, there is demand of electrical power system that is standard-fulfilled quality by electrical provider.

This research is done in electrical power main feeder in industrial and office complex region with small number of customer and big number of devices. Beside that, load of Randu Garut 3 feeder will increase in the next few years caused by development of industrial sector in Tambak Aji

region.. This industry will suffer considerable losses if black out occurs, in which the activities will be halt and the product will be damaged or defect. Types of customer are divided in to two: medium and low voltage customer. Furthermore, Randu Garut 3 feeder is frequently disrupted causing circuit breaker in substation works/trips, then 19 blackouts occurr during 2017.

Some studies proposed methods for evaluating the reliability of distribution system, for example [8] with quantitative method based on the reliability characteristics of basic system components. There were also a three-state Markov model composed post-fault switching actions [9], a Markov modelling approach by researcher [10]. Researcher [12] with restoration times models for distribution systems faults, meanwhile [11] with a Failure Modes and Effects Analysis (FMEA) technique, and [13] with models for equipment aging. To improve the accuracy of the reliability assessment, historical outage data were directly incorporated into some algorithms [14].

Nowadays, studies to assess reliability of power distribution system with distributed generation [20], [21]. Reference [15] proposed an assessment of reliability that take in to consideration the characteristics of energy released by renewable energy generation such as solar and wind generation. Reference [16] used clustering algorithm using clustering algorithm, output of the unconventional units were correlated with hourly load and designated into certain states. Reference [17] proposed a method to evaluate reliability of a distribution system with wind turbine generators using a simulation of time sequential A six state model of WTG with joint effects of wind speed and forced outage is developed by authors.

This research used section technique method in calculating load point reliability index and analyze reliability index of distribution system in Randu Garut 3 feeder, PT PLN (Persero) west Semarang Region. This method is similar to FMEA method which counts reliability of a system based on effects of failure with the system and how it will affect the load point. This method is similar to FMEA method, system reliability determined by measuring and observing the impact of detoriation in system and load point. Identification of aftermath of an individual failure is conducted systematically by analysing the situation of occurred problem [18]. Section method divides calculation in every section thus analysis was done in detail, fast, simple and accurate. Beside that, obtained system reliabilty index will be compared with SPLN 68-2-1986 standard and 2018 PT. PLN (Persero) West Semarang’s target. Used indexes were SAIFI (System Average Interruptions Frequency Index), SAIDI (System Average Interruption Duration Index) and CAIDI (Costumer Average Interruption Duration Index).

(2)

II. SECTION TECHNIQUE METHOD A. Section Technique

Section Technique Method is a structured method to analyse and evaluate system that can be used to find reliability index of distribution system. In this method, system is divided in to several smaller parts or sections first, thus the probability of miscalculation will be minimized and time cost will be reduced [18].

Reliability of a distribution system is based on how is the failure effect from an individual device will affect the system operation. This effect is identified systematically by analysing how is the consequences toward all of the customers in distribution network. Then each of the device failure will be analysed in one load point in the system thus the load point that is disturbed frequently will be found. Flowchart of section technique method is attached in Fig. 1.

Fig. 1. Flowchart of Section Technique Method

B. Reliability Index

Reliability of consument service is able to be stated in several indexes, which the three most often used are SAIFI, SAIDI and CAIDI. Below are needed data to find the three indexes, such as:

1) Failure Rate

Failure rate is average value from number of failures in a certain observed time (T), and is stated in failure rate in a year. In an observation, failure rate is stated as below:

f

λ=

T

(1)

a) Load point Failure Rate

The sum of all equipment failure rates will affect the load point, is calculated by the equation:

λLP

i

i k

λ

=

=

(2) b) Load point Disturbance Duration

The sum of the repairing/switching duration with multiplying the rate of failure of all the equipment affecting the load point, calculated by the equation:

ULP

i

.

i k

rj

λ

=

=

(3)

2) System Average Interruption Frequency Index SAIFI is defined as the average number of system failures that occur per customer served by the system per unit time (generally per year), calculated by the equation:

.

SAIFI

NLP LP

N

λ

=

(4)

3) System Average Interruption Duration Index

SAIDI is the average value index of the duration of system disruption for each consumer for a year, calculated by the equation: . SAIDI= NLPULP N   (5)

4) Customer Average Interruption Duration Index.

CAIDI is an index value of the average duration of consumer disturbance each year, informing the average time to normalize the interruption of each customer within a year. Equation in calculating CAIDI:

SAIDI CAIDI=

SAIFI (6)

III. TEST SYSTEMS

The data needed in finding the reliability value of the distribution system include outage and repair duration. Both values are obtained with reference to SPLN No. 59 of 1985 as in Table I and Table II. Whereas, the feeder shown in Fig. 2. is supplied from Randu Garut with an installed transformer of 60 MVA. The load served by these feeders are industrial, commercial and residential. There are 43 load points of 1 phase and 3 phase distribution transformer which are low voltage customer type with power below 197 kVA and 25 circuit breaker. The total load of both low and medium voltage is 138 customers. This feeder is divided into 95 lines with a total length of 8.72 km. The data used in this study based on real data taken at PT. PLN (Persero) West Semarang.

(3)

TABLE I. FAILURE INDEX AND REPAIR TIME OF MEDIUM VOLTAGE

Overhead Medium Voltage

Sustained failure rate (λ/km/yr) 0.2 r (repair time) (hour) 3 re (switching time) (hour) 0.25

TABLE II. DATA OF DEVICE OUTAGE,REPAIR AND SWITCHING

Devices λ (unit/year) r (hr) rs (hr)

Transformer 0.005 10 0.15

Circuit Breaker 0.004 10 0.25

Sectionalizer 0.003 10 0.15

Recloser 0.005 10 0.25

Fig. 2. Single line diagram of Randu Garut 3

A. Area Limit with Sectionalizer

The distribution network of Randu Garut 3 is divided based on the number of sectionalizers attached. The feeder has 3 sectionalizers in the form of 2 load break switches; mounted in normally close and 1 reclose. Thus, the feeder has 2 sections with a radial configuration as shown in Fig. 3. and Fig. 4.

Fig. 3. Section 1 Randu Garut 3

Fig. 4. Section 2 Randu Garut 3

IV. RESULTS AND DISCUSSION

Reliability analysis was conducted based on data that has been obtained by using data length of lines and data of customer number per load point. The reliability of each section is described as follows:

A. Section 1

The effect of a device failure in the system can be seen in the list of failure modes Table III.

TABLE III. SECTION IFAILURE MODE LIST

Disturbance Numbers

Device

Load Point affected by Repair Time Load Point affected by Switching Time 1 ABSW CB 1-CB 25 + LP 1-LP 43 - 2 Recloser CB 1-CB 25 + LP 1-LP 43 - 3 CB 1 CB 1 - 4 T1 LP 1 - 5 L1 CB 1-CB 25 + LP 1-LP 43 -

TABLE IV. FAILURE DURATION AND RATE LOAD POINT SECTION I

Load Point

Failure Duration and Rate Load Point λ (fault/year) U (hours/year) CB 1 0.982 3.03 ~ CB 11 0.982 3.03 CB 12 0.978 2.99 ~ CB 25 0.978 2.99 LP 1 0.983 3.04 ~ LP 23 0.983 3.04 LP 24 0.978 2.99 ~ LP 40 0.978 2.99 LP 41 0.978 2.99 LP 42 0.978 2.99 LP 43 0.978 2.99

(4)

Table III. shows some samples because the number of equipment that had CB as many as 11, 23 transformers, and 54 lines. Next, calculate the value of failure rate and the duration of failure of each load point. Failure rate and failure duration can be seen in Table IV.

From Table IV. It was obtained λ for CB1 to CB12 of 0.982 fault/year and λ for CB12-CB25 of 0.978, the meaning of CB here is that the load point failure rate is in medium voltage customers, whereas LP is low voltage customers and the difference in value of 0.005 was caused by section difference, because the calculation occurred in section 1 then the failure of load point in section 2 in the form of CB and LP was not counted.

Taken one case on CB1, λ CB1 was obtained from the sum of equipment failure rate affecting CB1 and multiplication of failure rate with length of lines. From Table IV. also obtained the value of U for CB1 of 3.03 faults/year. ULP1 is obtained from the sum of multiplication product λ of equipment with repair time or switching time in which the equipment is affecting CB1. Multiplication by repair time or switching time depends on the condition of the equipment, whether the equipment must be off or only experience switching time condition during interruption. This can be seen in Table V.

In section 1, the conditions experienced by all existing equipment are only repair conditions and no equipment was subject to switching time conditions, due to the equipment and the substation were close in distance so that if an interruption happened, it cannot be backed up and the disturbance must be repaired first to the voltage from the new substation can be supplied again, so to find U in Table IV. condition used is repair time condition. By knowing index of reliability of load point can be obtained index of reliability section.

Based on Table VI, it was obtained SAIFI and SAIDI in section I with value 0.9798043 fault/year for SAIFI and 3.00804 hours/year for SAIDI. SAIFI for CB1 was obtained from multiplying the number of consumers on the load point by λ CB1 then dividing it by the total customer.

TABLE V. DISTURBANCE DURATION AND FAILURE RATE SECTION I

Device SPLN λ Lenght of lines (fault/year) λLP SPLN r (hr/year) ULP

ABSW 0.003 - 0.003 10 0.03 Recloser 0.005 - 0.005 10 0.05 LP (T) 0.005 - 0.005 10 0.05 L1 0.2 0.21 0.042 3 0.126 ~ L47 0.2 0.05 0.01 3 0.03 L48 0.2 0.1 0.02 3 0.06 L49 0.2 0.03 0.006 3 0.018 L50 0.2 0.2 0.04 3 0.12 L51 0.2 0.04 0.008 3 0.024 L52 0.2 0.15 0.03 3 0.09 L53 0.2 0.05 0.01 3 0.03 L54 0.2 0.04 0.008 3 0.024 TOTAL λLP 0.983 TOTAL ULP 3.04

TABLE VI. SAIFI AND SAIDIPER LOAD POINT SECTION I

Load Point Numbers of Cons. Numbers Of Cons. x λLP Numbers Of Cons.

x ULP SAIFI SAIDI

CB 1 1 0.982 3.03 0.007116 0.021957 CB 2 1 0.982 3.03 0.007116 0.021957 CB 3 1 0.982 3.03 0.007116 0.021957 ~ CB 25 1 0.978 2.99 0.007087 0.021667 LP 1 1 0.983 3.04 0.007123 0.022029 LP 2 3 2.949 9.12 0.02137 0.066087 LP 3 1 0.983 3.04 0.007123 0.022029 ~ LP 36 5 4.89 14.95 0.035434 0.108333 LP 37 1 0.978 2.99 0.007086 0.021666 LP 38 15 14.67 44.85 0.106304 0.325000 LP 39 4 3.912 11.96 0.028347 0.086666 LP 40 1 0.978 2.99 0.007086 0.021666 LP 41 1 0.978 2.99 0.007086 0.021666 LP 42 10 9.78 29.9 0.070869 0.216666 LP 43 1 0.978 2.99 0.007087 0.021667 Total 0.979804 3.00804 B. Section 2

The effect of system device failure in section 2 is shown in failure mode list in Table VII.

TABLE VII. FAILURE MODE LIST OF SECTION 2

Disturbance Numbers Device LP affected by Repair Time LP affected by Switching Time 1 Recloser CB 12-CB 25 + LP 24-LP43 CB 1-CB 11 + LP 1-LP23 2 CB 12 CB 12 - 3 T24 LP 24 - 4 L55 CB 12-CB 25 + LP 24-LP43 CB 1-CB 11 + LP 1-LP23

Table VII. are some of the only equipment samples that can be displayed because the tables are too long, in fact that there are 14 CB, 20 Transformers and 40 lines. Next, calculate the value of failure rate and the duration of failure of each load point. The value of failure rate and duration of failure can be viewed in Table VIII.

(5)

TABLE VIII. LOAD POINT FAILUREDURATIONANDRATEOF SECTION 2

Load Point Load Point Failure Duration And Rate λ (fault/year) U (hours/year) CB 1 0.777 0.19425 ~ CB 11 0.777 0.19425 CB 12 0.781 2.392 ~ CB 25 0.781 2.392 LP 1 0.777 0.19425 LP 22 0.777 0.19425 ~ LP 23 0.777 0.19425 LP 24 0.782 2.402 ~ LP 43 0.782 2.402

By knowing load point reliability index, section 2 reliability index can be obtained and is shown in Table IX.

TABLE IX. SAIFI AND SAIDI PER LOAD POINT IN SECTION 2

Load Point Numbers of Cons. Numbers of Cons. x λLP Numbers of Cons.x

ULP SAIFI SAIDI

CB 1 1 0.777 0.19425 0.005630 0.001407 CB 2 1 0.777 0.19425 0.005630 0.001407 CB 3 1 0.777 0.19425 0.005630 0.001407 ~ CB 25 1 0.781 2.392 0.00565 0.017333 LP 1 1 0.777 0.19425 0.005630 0.001407 LP 2 3 2.331 0.58275 0.016891 0.004222 LP 3 1 0.777 0.19425 0.005630 0.001407 ~ LP 43 1 0.782 2.402 0.005666 0.017405 Total 0.78001 1.5398

Based on Table IX, SAIFI and SAIDI in section 2 can be obtained with a value of 0.78001 fault/year for SAIFI and 1,5398 hours/year for SAIDI. After knowing the reliability index value of each section, value of index reliability of feeder network system can be obtained by summing index reliability of each section. The calculation can be seen in Table X.

TABLE X. INDEX OF TOTAL RELIABILITY

Section Index of Total Reliability SAIFI SAIDI

I 0.979804 3.0080

II 0.78001 1.5398

Total 1.759814 4.5478

The value of SAIFI and SAIDI was obtained by summing the magnitude of the reliability index of each section. For analyzed feeder, it was obtained SAIFI value of 1.759814 faults/year and SAIDI value of 4.5478 hours/year. The value of CAIDI was obtained by dividing the SAIDI value by SAIFI, so the result of the calculation is shown in Table XI.

TABLE XI. CAIDI VALUE

Section Index of Reliability (CAIDI)

I 3.07004504 II 2.01160328 Total 2.58427267

Furthermore, to determine whether the analyzed that is Randu Garut 3 included in the category of reliable feeder or not, the researcher did two comparison of reliability values that have been obtained with certain standard reliability values, among others:

a) Standards established by PT. PLN (Persero) in accordance with SPLN No. 68-2 Year 1986 on "Level of Security Guarantee of Power System Part Two" which states that the radial configuration network system with PBO (Recloser).

b) Target of Rayon Semarang Barat 2018.

Fig. 5. Comparison of Section Technique, SPLN and Target of Rayon Shown in Fig. 5. Comparison of section technique method with SPLN No. 68-2 in 1986 and 2018 Target of West Semarang Region, SAIFI and SAIDI reliability index obtained by section technique method was smaller, it means that the reliability value of Randu Garut was higher. While the value of CAIDI obtained was lower than SPLN No. 68-2 in 1986 and higher than the 68-2018 target.

(6)

V. CONCLUSION

Section technique method is used to analyze distribution system reliability in Randu Garut 3 feeder, total reliability values obtained were SAIFI INDEX of 1.75981884 faults/year, SAIDI index of 4.57712319 hours/year and CAIDI index 2.58427267 hours/fault.

Obtained overall reliability index using section technique method was better from PLN standard and target of West Semarang Region in 2018, except for CAIDI value which surpass target of West Semarang Region in 2018. Thus, section technique method is able to become solution in determining reliability index of particular distribution system. In addition, it can be concluded that the longer the lines of the distribution network and the more components of the equipment on the system, the greater the likelihood of failure occurring resulting in blackout at the load point which may decrease the reliability of the feeder.

REFERENCES

[1] R. Billinton, R. N. Allan, “Reliability Evaluation of Power Systems”, Plenum Press, Second Edition, 1996.

[2] R. E. Brown, A. P. Hanson, H. L. Willis, F. A. Luedtke, M. F. Born, “Assessing the Reliability of Distribution Systems”, IEEE Computer Applications in Power, January 2001, pp. 44-49.

[3] R. E. Brown, “Electric Power Distribution Reliability”, Marcel Dekker, Second Edition, 2009.

[4] Chow 95 M-y. Chow and L.S. Taylor. “Analysis and Prevention of Animal-Caused Faults in Power Distribution Systems.” IEEE Transactions on Power Delivery, Vol. 10, No. 2. 1996. pp.995-1001. [5] C. M. Warren, 'The Effect of Reducing Momentary Outages on

Distribution Reliability Indices.' IEEE Transactions on Power Delivery, Vol. 14, No. 1, January 1999, pp. 250-255.

[6] D. E. Parrish, 'Lightning Faults on Distribution Lines,' IEEE Transactions on Power Delivery, Vol. 4, No. 4, October 1989. pp. 2179-2186.

[7] Brow 97 E. Brown, S. Gupta. R. D. Christie, S. S. Venkata, and R. Fletcher, Distribution System Reliability Assessment: Momentary Interruptions and Storms.' IEEE Transactions on Power Delivery, Vol. 12, No. 4, October 1997. pp. 1569-1575.

[8] P. Gaver, F. E. Montmeat. and A. D. Patton, Power System Reliability: I Measures of Reliability and Methods of Calculation.' IEEE Transactions on Power Apparatus and Systems, Vol. PAS-83, No. 7, July 1964, pp. 727-737.

[9] J. Endrenyi, 'Three state models in power system reliability evaluation,' IEEE Transactions on Power Apparatus and Systems, Vol. 90, No. 4. July/August 1971, pp. 1909-1916.

[10] D. O. Koval and R. Billinton. "Evaluation of Distribution Circuit Reliability.' IEEE Transactions on power Apparatus and Systems, Vol. PAS-98. No. 2. March/April 1979. pp. 509-518.

[11] S. J. Kostyal, T. D. Vismor and R. Billinton, "Distribution System Reliability Handbook. ' Final Report. EPRI EL-81-16-LD. Project 136-1. Electric Power Research Institute. September 1981.

[12] M.-y. Chow, L. S. Taylor, and M.-s.Chow, 'Time of Outage Restoration Analysis in Distribution Systems,* IEEE Transactions on Power Delivery, Vol. II. No. 3, July 1996, pp. 1652-1658. [13] S. Asgarpoor and M. J. Mathine, 'Reliability Evaluation of

Distribution Systems with Non-Exponential Down Times,' IEEE Transactions on Power Systems. Vol. 12, No. 2, May 1997, pp. 579-584.

[14] R. Billinton and R. Goel, 'An Analytical Approach to Evaluate Probability Distributions Associated with the Reliability Indices of Electric Distribution Systems,' IEEE Transactions on Power Delivery. Vol. 1, No. 3, July 1986, pp. 245-251.

[15] C. Singh and A. Lago-Gonzalez, “Reliability modeling of generation systems including unconventional energy sources,” IEEE Transactions on Power Apparatus and Systems, vol. 104, no. 5, May 1985.

[16] C. Singh and Y. Kim, “An e cient technique for reliability analysis of power systems including time dependent sources,” IEEE Transactions on Power Systems, vol. 3, no. 3, pp. 1090–1096, Aug. 1988.

[17] P. Wang and R. Billinton, “Time-sequential simulation techniques for rural distribution system reliability cost/worth evaluation including wind generation as alternate supply,” in IEE Proc. Transmission, Distribution, and Generation, vol. 148, no. 4, July 2001, pp. 355–360.

[18] Jamaris, “Analisis Keandalan Sistem Jaringan Distrikbusi 20kV di PT. PLN (Persero) Rayon Panam Penyulang 4 Lobak Menggunakan Metode Section Technique dan Metode Reliability Index Assessment (RIA)”, Tugas Akhir UIN SUSKA – Pekanbaru, 5 Januari 2016.

[19] Santoso, R. “Evaluasi Tingkat Keandalan Jaringan Distribusi 20 kV pada Gardu Induk Bangkinang dengan menggunakan Metode FMEA, Jurnal Fakultas Teknik Universitas Riau, 2016. pp 1-7. [20] Abdulaziz. A. Alkuhayli, Srinath Raghavan, Badrul H. Chowdhury,

"Reliability evaluation of distribution systems containing renewable distributed generations", North American Power Symposium (NAPS) 2012, pp. 1-6, 2012.

[21] S. Mostafa Elmi, Mojtaba Rafiei, "Effects of reclosing devices and distributed generation (DG) to improve reliability indices in radial distribution lines", Electrical Power Distribution Networks (EPDC) 2012 Proceedings of 17th Conference on, pp. 1-5, 2012.

References

Related documents

Writing is a process of thinking to express the ideas through letters word, phrases and clauses to forms of a series related sentences Students are able to:

• Consumers want such earlier disclosure and when it is provided they report higher levels of confidence about their choices of product. • These confidence levels are mostly

Výsledný model odpovídá jednak minimalizaci statického napětí uvnitř materiálu způsobeného struna- mi, a také umožňuje velice efektivní kmitání horní rezonanční desky

The reflectivity spectrum informs more about the free excitons peaks positions than the photoluminescence. Because of the pre-eminence of the bound excitons B. Lo and

As shown in the Fig.2, there are three main components to Docker’s architecture – Docker Daemon, Docker CLI and a REST API [23]. Docker daemon handles all the tasks for

Cumulative flipping is the fraction of block (10,000 shares or more) sell- signed volume from days 3 through 25 to total volume. Returns are calculated starting on the 26th day of

You must meet normal University requirements for admission to an undergraduate program or hold qualifications deemed to be equivalent.. SELECTION

[r]