Safe Work Method Statement
Prepared By: Paul Sefton-Rowston
Document Owner(s)
Organisation Role
Paul Sefton-Rowston Director
Version Control
Version
Date
Author
Reviewer
Change Description
0.1 05/09/12 Kirsty McInnes Paul Sefton-Rowston Draft
1.0 06/09/12 Kirsty McInnes Paul Sefton-Rowston Final
External Distribution List
Version
Date
To
Company
SAFE WORK METHOD STATEMENT – Part 1
Company details
Company Name: Gawled Pty Ltd Contact Name:
Position: Phone number:
Paul Sefton-Rowston Director
0423 254 114
ABN: 80 111 599 921
Address: 1/6 Aristos Place Winnellie NT 0820
Project details
Project: Charles Darwin University Accommodation Block Area: Darwin
Job Address: Ellengowan Drive, Brinkin NT Principal Contractor: Sunbuild Pty Ltd Job Description: Mechanical Services
Activity:
Air Conditioner Installation
This SWMS has been developed in consultation with: SWMS Approved by: Name: Paul Sefton-Rowston Signature:
Date:
Name: Signature: Job Title: Date:
Paul Sefton-Rowston
Construction Manager 06/08/12
Daniel Banks Apprentice Refrigeration
Mechanic
Joseph Gallez Electrician
Luke Comber Refrigeration Mechanic
Personnel responsible for monitoring and managing activity: Paul Sefton-Rowston
Overall Risk Rating After Controls Implemented (Refer to Part 3: Risk Assessment)
M8 Moderate
ALL PERSONS INVOLVED IN TASK MUST HAVE THIS SWMS COMMUNICATED TO THEM PRIOR TO WORK COMMENCING
Regular inspections and observations will be conducted by Paul Sefton-Rowston to ensure SWMS is being complied with.
Daily Tool Box Talks will be undertaken to identify, control and communicate additional site hazards.
Work must cease immediately if incident or near miss occurs. SWMS must be amended in consultation with relevant persons.
Personal Protective Equipment
Green 204
Day Operations – Normal Requirements:
Safety footwear (non-slip boots), hearing protection, high visibility shirt or vest, hard hat and sun protection if required, hand protection (gloves), protective clothing.
Foot
Protection
Hearing
Protection
High
Visibility
Head
Protection
Hand
Protection
Protective
Clothing
Emergency Procedures
1. Work under Sunbuild emergency procedures 2. Site induction in accordance with Sunbuild
3. First aid kits to be available on site and in vehicles 4. Qualified first aid personnel on site (Sunbuild) 5. Participate in trial evacuation, as required
Purpose of SWMS:
This SWMS covers risks associated with general installation of air conditioning systems.
Ensure the manufacturer’s installation manual/guide is available for specific information on all installation works.
Main risks:
-
Falls from height
-
Electrocution/electric shock
Activities
Possible Safety or
Environmental
Hazards
RB
Control Measures to Reduce risk
Risk is to be controlled using hierarchy of control measures:1. Elimination (completely remove from hazard); 2. Substitution (replace the hazard with a lesser hazard); 3. Isolation/ Engineering controls (make a structural change to
the work environment or work process) 4. Administration controls (procedures);
5. Personal protective equipment.
RA
Responsible
Officer
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Hazardous
substances on site
Hazardous materials 3 D H:18 Refrigerant Gases:
o Ensure restrained adequately on transport vehicle.
o Avoid storing inside cabin of vehicles
o Keep minimum quantities
o Ensure Material Safety Data Sheet available (within 5 year issue date)
o Inspect cylinders regularly to ensure no damage or leaks
Take care not to kink copper pipes.
Expel air from system as required by manufacturer.
Check for refrigerant leakage from pipe connectors. Use appropriate gas detector, or soapy water in a spray bottle. If bubbles form, tighten all fittings and recheck.
Ensure adequate ventilation
1 D M: 10 PSR
Carrying materials onto site
Manual handling injury 3 C M:13 Avoid working in static or awkward postures (such as bending or working with arms raised above head height) for more than 30 minutes at a time and/or 2 hours over entire shift.
Ensure regular rest breaks are taken.
2 C M:9 PSR
Slips/ Trips 4 B M:12 Clear any obstructions from the access path 1 B L:3 PSR Traffic management 3 D M:13 Wear high-visibility clothing at all times.
Unload only in areas which are declared as safe by the principal contractor.
Activities
Possible Safety or
Environmental
Hazards
RB
Control Measures to Reduce risk
Risk is to be controlled using hierarchy of control measures:1. Elimination (completely remove from hazard); 2. Substitution (replace the hazard with a lesser hazard); 3. Isolation/ Engineering controls (make a structural change to
the work environment or work process) 4. Administration controls (procedures);
5. Personal protective equipment.
RA
Responsible
Officer
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Unloading
heavy materials
Manual handling injury 5 C M:20 Use hand trucks, cable trolleys to move materials
Use mechanical aids to lift and hold pipes in position (such as duct lifters)
Lift heavy materials as a team
All team members must undergo manual handling training
Ensure duct lifters have safety gears capable of holding the load in the event of a failure of hoisting rope)
Lifting equipment has suitable SWL.
Use smaller sized cable drums
2 C M: 9 PSR
Slips/ Trips 4 B M:12 Ensure work areas are cleared of off-cuts/ tripping hazards regularly.
1 B L:3 PSR
Traffic management 3 D M:13 Wear high-visibility clothing at all times.
Be aware of the traffic management requirements.
Activities
Possible Safety or
Environmental
Hazards
RB
Control Measures to Reduce risk
Risk is to be controlled using hierarchy of control measures:1. Elimination (completely remove from hazard); 2. Substitution (replace the hazard with a lesser hazard); 3. Isolation/ Engineering controls (make a structural change to
the work environment or work process) 4. Administration controls (procedures);
5. Personal protective equipment.
RA
Responsible
Officer
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Working on
roof
Working at heights 5 E E:25 Check type of roof (pitched, tile, skylights etc)
Check condition of roof (fragile, brittle etc)
Ensure support walls, ceiling and roof have sufficient load bearing capacity.
Ensure work area is of the required height.
Check the number of persons expected on roof/ceiling space.
Ensure scissor lift or step platforms are used. If ladders are only option, ensure they are industrial, good condition, set-up correctly and secured both top and bottom.
Where a roof pitch exceeds 35 degrees, do not stand on the roof. Work from a cherry picker, scaffold or travel restraint system.
If using travel restraint or fall arrestors, ensure harness and clips are compatible, anchor points have been assessed by qualified persons, training undertaken and emergency plan in place for rescue.
2 C M: 9 PSR
Working in ceiling spaces
Working in
ceiling/confined space
3 D H:18 Avoid entering ceiling space – work from solid platform. If required to enter, ensure joists/purlins are capable of holding weight of person and equipment and tested for load capacity
Don’t stand on fragile areas – such as plasterboard
Walk along planks and crawl if required.
Ensure regular rest breaks are taken
Activities
Possible Safety or
Environmental
Hazards
RB
Control Measures to Reduce risk
Risk is to be controlled using hierarchy of control measures:1. Elimination (completely remove from hazard); 2. Substitution (replace the hazard with a lesser hazard); 3. Isolation/ Engineering controls (make a structural change to
the work environment or work process) 4. Administration controls (procedures);
5. Personal protective equipment.
RA
Responsible
Officer
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Air
conditioning cabling installation
Electric shock 3 D H:18 Check proximity to power lines
Power supply off
Ensure equipment has been checked regularly.
Check the equipment register is up to date.
Inspect wiring before each use.
Do not operate Electrical equipment near water or chemicals.
1 D M:10 PSR
Working outside
Hazardous atmosphere. (e.g. Dust)
3 C M:13 Avoid placing unit in direct sun or under drains etc (if possible)
Leave sufficient space between front, rear and sides (as specified by manufacturer)
Keep away from hazardous atmospheres or ignition sources
Ensure base and supporting frame is secure and capable of holding unit
Located in area where there is fresh air.
Wear high-visibility clothing to avoid collisions with moving vehicles.
1 C M:6 PSR
Slips and trips 3 B M:8 Ensure work areas are cleared of off-cuts/ tripping hazards regularly.
1 B L:3 PSR
Working inside
Hazardous atmosphere. (e.g. Dust)
3 C M:13 No heating or steam sources nearby
No hazardous materials nearby
Check anchor points (suitable work load and position)
Location of existing services (heating, water, pipes, electrical leads)
Good air circulation
Not too near doorways
Positioned where vents will not be blocked.
Activities
Possible Safety or
Environmental
Hazards
RB
Control Measures to Reduce risk
Risk is to be controlled using hierarchy of control measures:1. Elimination (completely remove from hazard); 2. Substitution (replace the hazard with a lesser hazard); 3. Isolation/ Engineering controls (make a structural change to
the work environment or work process) 4. Administration controls (procedures);
5. Personal protective equipment.
RA
Responsible
Officer
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
Likel
iho
od
C
on
se
qu
en
ce
R
isk
R
at
ing
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented. Slips and trips 3 B M:8 Ensure work areas are cleared of off-cuts/ tripping
hazards regularly.
1 B L:3 PSR
Using power tools
Electric shock from tools
3 D H:18 Guards in place
Electrical leads in good condition and tested/tagged, RCDs in use
Correct for job/used for purpose
1 D M: 10 PSR
Laceration 4 D H:21 Avoid putting face too close to work. Stand to side when tightening with pipe wrenches, strip cable away from body.
Cover sharp edges of duct. Ensure protective caps are placed into end of thread droppers.
Use pipe cutters and cable strippers rather than hacksaws and knives.
2 C M:9 PSR
Manual handling 5 C M:20 Avoid working in static or awkward postures (such as bending or working with arms raised above head height) for more than 30 minutes at a time and/or 2 hours over entire shift.
Ensure regular rest breaks taken.
C A M:9 PSR
Cutting into structures
Hazardous materials (e.g. Asbestos)
3 D H:18 Determine material type before cutting.
Provide suitable personal protective equipment for short term works.
SAFE WORK METHOD STATEMENT – Part 2
Only undertake work which is allowable under the specific licence held. For example, an electrical license is required in order to perform electrical installations. A refrigerant mechanic with a restricted license cannot perform electrical installation work, but they can disconnect and connect electrical equipment and replace with like components of the a/c and refrigerant equipment.
Employee
Personal Qualifications,
Licenses and Experience
required for the job:
Duties and Responsibilities of
those employees undertaking the
task:
Training Required to Complete
the Work:
(All employees must be trained in relevant procedures.)
Paul Sefton-Rowston A9040 NT Electrical Licence (A9040) Electrical, Management
White Card - Industry standard safety induction.
Site specific inductions. Training in this SWMS Daniel Banks NT Refrigeration Licence (L075814) Air conditioning & Refrigeration
White Card - Industry standard safety induction.
Site specific inductions. Training in this SWMS Joseph Gallez NT Electrical Licence (A9714) Electrical
White Card - Industry standard safety induction.
Site specific inductions. Training in this SWMS Luke Comber NT Refrigeration Licence (L013997) Air conditioning & Refrigeration
White Card - Industry standard safety induction.
Site specific inductions. Training in this SWMS
Details of regulatory permits/licenses required:
Engineering Details/Certificates/Work Cover Approvals:
NT Electrical licence.
Attain any necessary permits from Sunbuild.
N/A
Legislation
The following legislation is applicable to this project:
Work Health and Safety [National Uniform Legislation]Act 2011 (as in force at 1st January 2012)
Work Health and Safety [National Uniform Legislation]Regulations 2011 (as in force at 1st January 2012) Workplace Health and Safety Act 2011
Workplace Health and Safety Regulations 2011
Codes of Practice
The following codes of practice are applicable to this project: National
National Code of Practice: First Aid in the workplace National Code of Practice: Construction Work National Code of Practice: Hazardous manual tasks
National Code of Practice: How to manage work health and safety risks National Code of Practice: Managing the risk of falls at workplaces National Code of Practice: Managing the work environment and facilities National Code of Practice: Managing noise and preventing hearing loss at work National Code of Practice: Confined spaces
National Code of Practice: Labelling of workplace hazardous chemicals National Code of Practice for Induction for Construction Work May 2007
Adopted National Exposure Standards for Atmospheric Contaminants in the Occupational Environment [NOHSC:1003(1995)]
Standards Applicable
The following standards are applicable to this project:
National Standard for Licensing Persons Performing High Risk Work 2006 National Standard for Manual Tasks 2007
ISO 31000 Risk Management AS 3000 2007 Wiring Rules
AS 3001 2008 Electrical installations – Relocatable premises
AS 3012 2010 Electrical Installations – Construction and demolitions sites AS3760 2010 In-service safety inspection and testing of electrical equipment
AS3100 Approval & Test Specification – General requirements for electrical equipment AS1269.2 Occupational Noise Management – Noise Control Management
AS1336 Recommended Practices for Occupational Eye Protection AS1800 Occupational Protective Helmets – selection, care and use
AS2210 Occupational Protective Footwear Part 1 – Guide to selection, care and use AS2161.1 Occupational Protective Gloves – Selection, use & maintenance
AS4602 High Visibility Garments
Plant/Tools/Equipment:
(List plant and equipment tobe used on the job.)
Calibration Certificate:
(Current / N/A)Maintenance Details:
(Include maintenance on cranes, forklifts, electrical equipment etc.)Refer to attached “Detailed Asset List”. No Calibration Required. All equipment to be checked for appropriate tags prior to use.
Part 3- RISK ASSESSMENT
Risk Management Code of Practice 2007, AS/NZS 31000 -2009 Risk Management Principles and guidelines
Step 1 Determine Likelihood – What is the possibility that the effect will occur? Step 2 Determine Consequence - What will be the expected effect?
Criteria Description
Almost certain
Expected in most circumstances.
Effect is a common result Likely Will probably occur in
most circumstances.
Effect is known to have occurred at this site or it has happened
Possible Might occur at some time Effect could occur at the site or I’ve heard of it happening
Unlikely Could occur at some
time
Effect is not likely to occur at the site or I have not heard of it happening
Rare May occur only in
exceptional circumstances
Effect is practically impossible.
Step 3 Determine the risk score Step 4 Record risk score on worksheet (Note – Risk scores have no
absolute value and should only be used for comparison and to engender discussion.) Level of Effect Example of each level
Insignificant/Acceptable No effect – or so minor that effect is acceptable
Minor First aid treatment only; spillage contained at
site.
Moderate Medical treatment; spillage contained but with
outside help.
Major Extensive injuries; loss of production
Catastrophic Death; toxic release of chemicals
Consequence
Likelihood A:
Insignificant
B: Minor
C: Moderate
D: Major
E: Catastrophic
5: Almost certain
M11 H16 H20 E23 E25
4: Likely M7 M12 H17 H21 E24
3: Possible M4 M8 M13 H18 H22
2: Unlikely L2 M5 M9 H14 H19
1: Rare L1 L3 M6 M10 H15
Score Action
Extreme: 23-25 ACT NOW – Urgent - do something about the risks immediately. Requires immediate attention. High: 14-22
Highest management decision is required urgently. Moderate: 4-13
Follow management instructions.
Low: 1-3 OK for now. Record and review regularly, and if any equipment/ people/ materials/ work processes or procedures change.