PMP® Certification Course
(17 Contact Hours/PDUs)
Conducted by
PMI Lahore, Pakistan Chapter
Copyright PMI Lahore, Pakistan Chapter 2016
Learning Objectives of the course
• Learning Objectives of the course are as follows:
– Understand PMI methodology and Prepare for PMP® Certification exam.
• Books to consult
– Project Management Professional (PMP®) Handbook (free download from PMI website)
– Project Management Professional (PMP®) Exam Content Outline (free download from PMI website)
– PMBOK® 5thEdition (buy or print if you are a PMI member)
• It is recommended that candidates should have these three
books with them when they come for the course
Materials in this class are based on Project Management
Institute, A Guide to Project Management Body of
Knowledge (PMBOK® Guide), - Fifth Edition, Project
Management Institute, Inc., 2013
PMBOK is a registered trade mark of Project Management Institute, Inc.
3
Copyright PMI Lahore, Pakistan Chapter 2016
PMP® Certification Course Schedule (35 PDUs)
9am – 6:00pm
(1 hour Lunch/Tea breaks)
Day Title Time
1 Day 1 Morning Overview of PMI & Project Management Introduction 2 Hrs 2 Day 1 Morning Chapter 4, Integration Management 2 Hrs
4 Day 1 Afternoon Chapter 5, Scope Management 2 Hrs
6 Day 1 Afternoon Chapter 6, Time Management 2 Hrs
5 Day 2 Morning Chapter 7, Cost Mgt.; Chapter 8, Quality Mgt. 2 Hrs 6 Day 2 Morning Chapter 9, HR Mgt.; Chapter 10, Communication Mgt 2 Hrs
7 Day 2 Afternoon Chapter 11, Risk Management 2 Hrs
8 Day 2 Afternoon Chapter 12, Procurement Management 1 Hrs 9 Day 2 Afternoon Chapter 13, Stakeholders Management 1 Hrs
4
Copyright PMI Lahore, Pakistan Chapter 2016
Project Management Institute
Project Management Institute (PMI®) is a
Worldwide organization which was
established in 1969
“PMI is one of the world's largest not-for-profit
membership associations for the project
management profession, with more than
550,000 members and credential holders in more
than 185 countries”.
(PMI website) pmi.org
5
Copyright PMI Lahore, Pakistan Chapter 2016
PMP® Certification
Education
Experience
35 hours of Project Management Education
Pass the Exam
Certificate, valid for 3 years
Application Process
• Apply on-line at
www.pmi.org
• After the application is approved (5 days, if not audited) you
will be provided an authorization number from PMI to make
appointment for exam.
• After authorization you must take the exam within one year.
• Candidates have 3 opportunities to pass the exam in 1 year.
• After that if they do not pass then they have to wait for 1
year from the date of last attempt.
7
Copyright PMI Lahore, Pakistan Chapter 2016
INTRODUCTION
Project Management
8
Copyright PMI Lahore, Pakistan Chapter 2016
Introduction
Topic in this section
• Purpose of PMBOK® Guide
• What is a Project
• What is Project Management
• Role of Project Manager
• Project Management Body of Knowledge
Copyright PMI Lahore, Pakistan Chapter
2016 9
Chapter 1 > Introduction
Purpose of PMBOK® Guide - Fifth Edition.
• The book is a standard for Project Management from PMI
• This book is well recognized in the Project Management
industry.
• It describes 47 processes that are used in managing
projects.
• Chapter 1 &2: Introduction and key concepts in Project
Management
• Chapter 3: Project Management processes.
• Chapters 4 – 13: 10 Knowledge Areas
• The book is a useful guide for project management.
• It provides guidelines that can increase project success
• It uses vocabulary which can be commonly used in Project
Management
• However it is not totally complete as it may not contain
everything that is required in Project Management
• It can be considered as a reference guide.
• The processes given in the book can be used in nearly all
type of projects.
Purpose of PMBOK® Guide - Fifth Edition.
PMBOK 2
11
Copyright PMI Lahore, Pakistan Chapter 2016
What is a Project?
12
Copyright PMI Lahore, Pakistan Chapter 2016
What is a Project?
• Project is a temporary endeavour that is taken to produce a unique product, service or result
• Temporary means that project will end (Projects can last from a few days to many years)
• End of the project is reached when
– Project work is completed
– When it is clear that it is not possible to complete the project work. – There is no need for the project to be carried out.
• Unique means that the output of every project is different. • Project go through ‘progressive elaboration’.
PMBOK 3
13
Copyright PMI Lahore, Pakistan Chapter 2016
What is a Project deliverable?
• Projects deliverable could be a Product, Service or Result. For
example:
Product: Product is a deliverable which could be an end item, or it could be a component of another item. (e.g. complete house or just the grey structure)
Service: Service is a deliverable which has the capability to perform a business function. (e.g. business function to supports production, distribution, design; ERP computer system)
Result: Result is a deliverable in form of a document. (e.g. research paper, marketing survey result report)
Chapter 1 > Introduction
Examples of a Project
• Developing a new product
• Developing a new service
• Create a new department in an organization
• Implementing a new computer system
• Construction of a new metro-bus system
• Implementing a new business process
• Constructing a house
• Construction of road
15
Copyright PMI Lahore, Pakistan Chapter 2016
Examples
1. Developing a new product or service
2. Running 1122 centre
3. Change in structure, staffing, in an organisation
4. Implementing a new Computer system
5. Maintaining a email system
6. Constructing a building or plant
7. Campaign for a political office
8. Developing and implementing a new procedure
9. Arranging a function or event
10. Operation of a Fertilizer plant
P
O
X X X X X X X X X X 16Copyright PMI Lahore, Pakistan Chapter 2016
What is a Project
Management?
17
Copyright PMI Lahore, Pakistan Chapter 2016
What is Project Management?
Application of knowledge, skills, tools, and
techniques, to project activities to meet the
project requirements.
THIS IS DONE BY …
What is Project Management?
By applying
47 project management
processes, which are listed in
5 process groups and
10 knowledge areas
19
Copyright PMI Lahore, Pakistan Chapter 2016
What is Project Management?
• The five Process groups are:
1. Initiation
2. Planning
3. Executing
4. Monitoring and Controlling
5. Closing
PMBOK 5
20
Copyright PMI Lahore, Pakistan Chapter 2016
What is Project Management?
The 10 Knowledge Areas
1. Integration Management
2. Scope Management
3. Time Management
4. Cost Management
5. Quality Management
6. HR Management
7. Communication Management
8. Risk Management
9. Procurement Management
10. Stakeholders Management
All 47 processes are in these 10 knowledge areas
21
Copyright PMI Lahore, Pakistan Chapter 2016
What is Project Management?
Work within the 6 project constraints:
1. Scope (Work) 2. Time (Schedule) 3. Cost (Budget) 4. Resources 5. Risks 6. Quality
Change in any ‘one’ will have an effect on the others.
Scope
PMBOK 6
Resources Risks Quality
The Iron Triangle Primary
The Project Manager’s responsibilities
To be able to get the work done, the Project Manager should have the following: Knowledge – The project manager should have knowledge about the
project. i.e. what the project is about and what is required to be done. (Scope, Time and Cost) so that he is able to achieve the outcome of the project.
Performance – to be able to perform work in a manner that results are produced while applying the knowledge he/she has about the project and the deliverables to be produced.
Personal – Project Manager has to lead the team so that project work can be carried out effectively. To do this, Interpersonal skills or soft skills are required.
23
Copyright PMI Lahore, Pakistan Chapter 2016
PMBOK 17
Organizational Process Assets (OPAs)
Organizational Process Assets
These are documental assets that are available in the
organization.
These include documents such as plans, processes, policies,
templates, forms, procedures, work instruction and any type of
knowledge base or data that can be useful in planning and
execution of the project.
OPAs can be grouped in two categories:
1. Processes and Procedures
2. Knowledge base
PMBOK 27
24
Copyright PMI Lahore, Pakistan Chapter 2016
Organizational Process Assets (OPAs)
Examples of Processes and Procedures:
HR policies; e.g. medical policies, compensation policies Templates and forms (risk, schedule, WBS, others) Change control procedures,
Financial control procedure,
Issues and defect handling procedures
Communication procedures, Risk control procedures,
Work Instructions, evaluation criteria, performance measurement criteria
Audits, project evaluations, project validations, acceptance criteria
25
Copyright PMI Lahore, Pakistan Chapter 2016
PMBOK 27
Corporate Knowledge database examples:
Historical information of projects handled by the organization earlier Lessons learnt from previous projects
Issues and defect management database Project files from previous projects
Configuration management knowledge base Financial database
Organizational Process Assets (OPAs)
Enterprise Environmental Factors (EEFs)
These are conditions that are not under the control of the
project team what can have an effect on the project. These
conditions can help in the PM while developing the plan
and during the other stages of the project.
Generally EEFs are of two types:
1. Internal, that are within the organization
2. External, that are outside the organization
Enterprise Environmental Factors (EEFs)
PMBOK 29
27
Copyright PMI Lahore, Pakistan Chapter 2016
Organizational culture, structure Infrastructure facilities inside the
Company. HR administration
Company work authorization system
Stake holders risk tolerances Project Management
Information Systems used by the company
Market place conditions Government / Industry
standards Political situation
Human resources availability Communications systems Commercial databases availability General security Infrastructure Internal EEFs (related to organization)
Enterprise Environmental Factors (EEFs)
External EEFs
(related to the place of project)
28
Copyright PMI Lahore, Pakistan Chapter 2016
Stakeholders
Stakeholder is an individual, group, or organization who
may affect, be affected by, or perceive itself to be
affected by a decision, activity or outcome of a project.
Stakeholders can be directly or indirectly connected to
the project.
Project Stakeholders
PMBOK 30 See figure on PMBOK page 31 29Copyright PMI Lahore, Pakistan Chapter 2016
Stakeholders
30
Project Life Cycle:
The Project life cycle is divided into 4 stages from
the start to finish.
Project Life Cycle
PMBOK 38
31
Copyright PMI Lahore, Pakistan Chapter 2016
Characteristics of Project Life Cycle:
• 1 - Initiating Starting phase of the project. I.e. starting the work on the project (initiating)
2 - Planning
Preparation and planning for the work that is required to be done (planning)
3 - Execution
Executing the project work as per the plan (Execution) 4 - Closing
Accepting the deliverables and closing the project (Closing)
Project Life Cycle
PMBOK 39
32
Copyright PMI Lahore, Pakistan Chapter 2016
Characteristics of Project Life Cycle
Initiating Planning Executing Closing 1 2 3 4 33PMBOK 39 Copyright PMI Lahore, Pakistan Chapter 2016
What are Project Phases ?
Project may be divided into many number of phases. A phase
is a collection of logically related project activities that
culminates in the completion of one or ore deliverables.
The end of phase represents a natural point to reassess the
activities underway to change or terminate the project if
necessary.
This point may be referred as stage gate, milestone, phase
review, phase gate or kill point.
Project Life Cycle and Project Phases
Single Phase Project
PMBOK 42
35
Copyright PMI Lahore, Pakistan Chapter 2016
Three Phase Project
Front End Engineering Design Plant detail design Plant construction
PHASE I PHASE II PHASE III
PMBOK 43
36
Copyright PMI Lahore, Pakistan Chapter 2016
Overlapping Phase Project
Factory Design Construction PHASE I PHASE II PMBOK 43 37Copyright PMI Lahore, Pakistan Chapter 2016
Project Management Processes
Project Management Processes
• Project management is the application of knowledge,
skills, tools and techniques to project activities to
meet project requirements.
This is done by using the 47 processes which are in
10 knowledge areas and 5 process groups.
Copyright PMI Lahore, Pakistan Chapter
2016 39
PMBOK 47
Chapter 3 >
Project Management Processes
To succeed, the project team must:
Select processes that will meet objectives of the project
out of the 47 processes.
Define the approach to meet the project requirements
Ensure that they will meet the stakeholders needs
Balance the demands of scope, cost, time and quality.
PMBOK 47
40
Copyright PMI Lahore, Pakistan Chapter 2016
Project Management 5 Process Groups
Planning
Executing Monitoring & control ClosingInitiating
1 2 3 4 5
Processes performed to define and get authorization of a new
project. (2 processes)
Processes required to establish the scope of the project, and
define the course of action required to attain the objectives
(24 processes)
Processes performed to complete the work defined in the project management plan
(8 processes)
Processes required to track, review, and update the progress of the project
(11 processes)
Processes performed to finalize all activities and formally close
the project or phase
(2 Processes)
47
Processes
PMBOK 49
41
Copyright PMI Lahore, Pakistan Chapter 2016
Time
Planning Executing Monitoring &
Control Closing Initiating
Processes are not discreet, they overlap
13% 24% 30% 8% 25% PMBOK 51
Monitoring & Control Project Work Perform Integrated
Change Control Plan Scope Management
Collect Requirements Define Scope
Create WBS Plan Schedule Management
Define Activities Sequence Activities Estimate Activity Resources
Estimate Activity Duration Develop Schedule Plan Cost Management
Estimate Costs Determine Budget
8 ManagementQuality Plan Quality Management Perform Quality Assurance Control Quality Acquire Project Management Team Develop Project Management Team Manage Project Management Team 10 Communication
Management Plan Communication Management Manage Communication Control Communication Plan Risk Management
Identify Risks Conduct Qualitative Risk Analyses Conduct Quantitative Risk Analyses
Plan Risk Response 12 Procurement
Management Plan Procurement Management Conduct Procurements Control Procurements
Close Procurements 13 Stakeholders
Management Identity Stakeholders Plan Stakeholders Management
Manage Stakeholders Engagement
Control Stakeholders Engagement Risk
Management Control Risks
11 Scope Management Integration Management Validate Scope Control Scope Time
Management Control Schedule
Cost Management
9 HR Management Plan HR Management
Control Costs 4 5 6 7 Develop Project
Charter Develop Project Management Plan
Direct & Manage Project Work Close Project or Phase 47 Processes PMBOK 61 2 24 8 11 2 43
Copyright PMI Lahore, Pakistan Chapter 2016
Initiating Planning Executing Monitoring and Control Closing
Monitoring & Control Project Work Perform Integrated
Change Control Plan Scope Management
Collect Requirements Define Scope
Create WBS Plan Schedule Management
Define Activities Sequence Activities Estimate Activity Resources
Estimate Activity Duration Develop Schedule Plan Cost Management
Estimate Costs Determine Budget 8 Quality
Management Plan Quality Management
Perform Quality
Assurance Control Quality Acquire Project Management Team Develop Project Management Team Manage Project Management Team 10 Communication
Management Plan Communication Management Manage Communication Control Communication Plan Risk Management
Identify Risks Conduct Qualitative Risk Analyses Conduct Quantitative Risk Analyses
Plan Risk Response 12 Procurement
Management Plan Procurement Management Conduct Procurements Control Procurements
Close Procurements 13 Stakeholders
Management Identity Stakeholders Plan Stakeholders Management
Manage Stakeholders Engagement
Control Stakeholders Engagement Risk
Management Control Risks
11 Scope Management Integration Management Validate Scope Control Scope Time
Management Control Schedule
Cost Management
9 HR Management Plan HR Management
Control Costs Process Groups 4 5 6 7 Develop Project
Charter Develop Project Management Plan
Direct & Manage Project Work Close Project or Phase Knowledge Areas 47 Processes 2 24 8 11 2
While Managing Projects
44
Copyright PMI Lahore, Pakistan Chapter 2016
Monitoring & Control Project Work Perform Integrated
Change Control Plan Scope Management
Collect Requirements Define Scope
Create WBS Plan Schedule Management
Define Activities Sequence Activities Estimate Activity Resources
Estimate Activity Duration Develop Schedule Plan Cost Management
Estimate Costs Determine Budget
8 ManagementQuality Plan Quality Management Perform Quality Assurance Control Quality Acquire Project Management Team Develop Project Management Team Manage Project Management Team 10 Communication
Management Plan Communication Management Manage Communication Control Communication Plan Risk Management
Identify Risks Conduct Qualitative Risk Analyses Conduct Quantitative Risk Analyses
Plan Risk Response 12 Procurement
Management Plan Procurement Management Conduct Procurements Control Procurements
Close Procurements 13 Stakeholders
Management Identity Stakeholders Plan Stakeholders Management
Manage Stakeholders Engagement
Control Stakeholders Engagement Risk
Management Control Risks
11 Scope Management Integration Management Validate Scope Control Scope Time
Management Control Schedule
Cost Management
9 HR Management Plan HR Management
Control Costs 4 5 6 7 Develop Project
Charter Develop Project Management Plan
Direct & Manage Project Work Close Project or Phase 47 Processes 6 6 7 4 3 4 3 6 4 4 45
Copyright PMI Lahore, Pakistan Chapter 2016
PMI-Lahore, Pakistan Chapter
PMP® Certification Course
Project Integration Management
Chapter 4
Monitoring & Control Project Work Perform Integrated
Change Control Plan Scope Management
Collect Requirements Define Scope
Create WBS Plan Schedule Management
Define Activities Sequence Activities Estimate Activity Resources
Estimate Activity Duration Develop Schedule Plan Cost Management
Estimate Costs Determine Budget
8 ManagementQuality Plan Quality Management Perform Quality Assurance Control Quality Acquire Project Management Team Develop Project Management Team Manage Project Management Team 10 Communication
Management Plan Communication Management Manage Communication Control Communication Plan Risk Management
Identify Risks Conduct Qualitative Risk Analyses Conduct Quantitative Risk Analyses
Plan Risk Response 12 Procurement
Management Plan Procurement Management Conduct Procurements Control Procurements
Close Procurements 13 Stakeholders
Management Identity Stakeholders Plan Stakeholders Management
Manage Stakeholders Engagement
Control Stakeholders Engagement Risk
Management Control Risks
11 Scope Management Integration Management Validate Scope Control Scope Time
Management Control Schedule
Cost Management
9 HR Management Plan HR Management
Control Costs 4 5 6 7 Develop Project
Charter Develop Project Management Plan
Direct & Manage Project Work Close Project or Phase 47 Processes 2 24 8 11 2 6 47
Copyright PMI Lahore, Pakistan Chapter 2016
Project Integration Management
Why integrate: • Integration helps in:
Coordinating work between all areas for the success of the project. To make sure that the stakeholders’ needs regarding the project are
being met.
Determine how to get resources (HR and others) for the project. Anticipate future problems that can arise in the project (risk
management).
48
Copyright PMI Lahore, Pakistan Chapter 2016
Project Integration Management 4.0
Develop Project Charter 4.1
Develop Project Management Plan 4.2
Direct and Manage Project Work 4.3
Monitor and Control Project Work 4.4
Perform Integrated Change Control 4.5
Close Project or Phase 5.6
4.0 Project Integration Management
49
Copyright PMI Lahore, Pakistan Chapter 2016
Project Integration Management >
4.1 Develop Project Charter
Develop Process Charter is the process of
developing a document that formally authorizes
the existence of a project and provides the project
manager with the authority to apply organizational
resources to project activities.
Project Charter will give authority to the project
manager to start project related work by using
resources which have been assigned to the project.
Input, Tools and Techniques, Outputs
• Every process defined in PMBOK has inputs, tool & techniques
and outputs for the processes to be executed.
• Inputs is the information/data that is required to carry out the
process.
• Tools and techniques are actions required to complete the
process
• Output is the outcome of the process
• There 256 inputs, 209 tools and techniques and 153 outputs
in PMBOK. (total 618)
51
Copyright PMI Lahore, Pakistan Chapter 2016
Inputs
5
Tools & Techniques2
Outputs
1
4.1 Develop Project Charter
52
Copyright PMI Lahore, Pakistan Chapter 2016
1. Project statement of work (SOW)
The statement of work (SOW) is a written description of product, services, or result to be delivered by the project.
It describes what is to be produced by the project.
SOW is initiated within the organization or from outside the company.
E.g. Finance department asking the IT to develop a computer system for controlling inventory. IT would initiate this as a project and would develop a charter for it.
In case from outside, the SOW is generated by the customer or client asking a company to carry out work for them.
4.1 Develop Project Charter: Inputs
PMBOK 68
53
Copyright PMI Lahore, Pakistan Chapter 2016
2. Business case
Business case is a cost benefit analyses that is carried out to determine if the project is worth the investment.
This document becomes part of the Project Charter.
There are various ways benefit analyses can be carried out such as Example:
Return on Investment (ROI), Present Value (PV),
Internal rate of return (IRR)…etc.
3. Agreements
Any agreements between any two or more parties can generate a project and will require a Project Charter.
These can be Contracts, Memorandum of Understanding (MOU), Service Levels Agreements (SLA) Letter of Intent (LoI) Verbal agreements, emails or any other written agreements
4.1 Develop Project Charter: Inputs
55
Copyright PMI Lahore, Pakistan Chapter 2016
4. Enterprise environmental factors (EEFs)
EEFs is an input of the Project Charter as these will provide information on the local conditions both inside and outside the company Including:
Organizational structure Govt. standards, regulations Market conditions and others…
5. Organizational Process Assets (OPAs)
OPAs will help in developing Project Charter by providing: Standard operating procedures/processes
Templates/forms
Historical information from previous projects
4.1 Develop Project Charter: Inputs
56
Copyright PMI Lahore, Pakistan Chapter 2016
1. Expert Judgment
Expert judgement is used to asses the inputs to develop the project charter, to analyze the technical and others details of the project. This expertise can be provided by people inside and outside the
company. Paid or free. Such as: Consultants
• Stakeholders • Customers
• Technical professionals • Subject matter experts • PMO
4.1 Develop Project Charter:
Tool and Techniques
PMBOK 71
57
Copyright PMI Lahore, Pakistan Chapter 2016
2. Facilitation Techniques
These techniques are related to managing meeting
sessions for the development of project charter. These
meetings could have:
• Brainstorming sessions to generate ideas
• Conflict resolutions for resolving disagreements amongst the participants
• Problem solving sessions • Decision making sessions
The project manager will facilitate such meetings
4.1 Develop Project Charter:
Tool and Techniques
1. Project Charter
Project Charter is a written document which is issued by the initiator or the sponsor of the project.
It gives authority to the project manager to start work on the project and also give the PM the authority to start using resources on the project activities.
4.1 Develop Project Charter: Output
59
Copyright PMI Lahore, Pakistan Chapter 2016
Project charter will have:
Purpose of the project
• Project objectives which are measureable • Assumptions and constraints
• High-level description and boundaries • Summary milestones, budget.
• Stakeholders list • Approval requirements
• Project Manager, authority level • Name and authority of sponsors
4.1 Develop Project Charter >
Output
61 Charter Page-1 Sample Project Charter Page-2
Project Integration Management 4.0
Develop Project Charter 4.1
Develop Project Management Plan 4.2
Direct and Manage Project Work 4.3
Monitor and Control Project Work 4.4
Perform Integrated Change Control 4.5
Close Project or Phase 5.6
4.0 Project Integration Management
63
Copyright PMI Lahore, Pakistan Chapter 2016
4.2 Develop Project Management Plan
64
Develop Project Management Plan is the process
of defining, preparing, and coordinating all
subsidiary plans and integrating them into a
comprehensive project management plan
Inputs
4
Tools & Techniques2
Outputs
1
4.2 Develop Project Management Plan
65
Copyright PMI Lahore, Pakistan Chapter 2016
Develop Project Management Plan
Inputs
1. Project Charter
2. Outputs from Planning processes
All knowledge areas, (minus integration), has one management plan. Scope and Quality has two plans each.
1. Scope – Scope Mngt plan & Requirement Mngt Plans 2. Time – Schedule Mngt plan
3. Cost – Cost Mngt plan
4. Quality – Quality Mngt plan & Process Improvement plan 5. HR – HR Mngt plan
6. Communication Communication Mngt plan 7. Risk – Risk Mngt plan
8. Procurement – Procurement Mngt plan
9. Stakeholder – Stakeholder engagement Mngt plan
Develop Project Management Plan
Inputs
3. Enterprise Environmental factors (EEFs)
EEFs that will help in developing Project Management Plan Internal:
• Project management information systems
• Configuration management system, information collection and distribution
• Organization structure and culture • Personnel administration
External
• Government/Industry standards
• External conditions (Infrastructure, utilities, etc)
67
Copyright PMI Lahore, Pakistan Chapter 2016
Develop Project Management Plan
Input
4. Organizational process assets (OPAs)
Processes and procedures
Standard guidelines, work instructions, proposal evaluation criteria, performance evaluation criteria
Project management plan templates
• Guidelines and criteria for tailoring standard processes • Project closure guidelines
Change control procedures
Knowledge base
Project files from past projects
68
Copyright PMI Lahore, Pakistan Chapter 2016
Develop Project Management Plan
Tools and Techniques
1. Expert Judgment
For developing project management plan expert judgement is used to:
Asses which processes are required to meet the needs of the project and to what extent.
What technical and management expertise is required. What resources and skills are required
How much of configuration management is required How the change control will work
How the work will be prioritized.
PMBOK 76
69
Copyright PMI Lahore, Pakistan Chapter 2016
Develop Project Management Plan
Tools and Techniques
2. Facilitation Techniques
These techniques are related to managing meetings for
the development of project management plan.
Techniques include
• Brainstorming session to generate new ideas
• Conflict resolutions for resolving disagreements amongst the participants
• Problem solving sessions • Decision making sessions
Develop Project Management Plan
Output
• Project Management Plan
– Project Management Plan is a document that describes how the project will be executed, monitored, and controlled.
– It is used to integrate all the plans from the planning processes of the other knowledge areas:
– It contains 9+4+3 = 16 documents as follows: – 9 management plans from 9 knowledge areas
– 4 other plans (change control, configuration control, requirement management plan, process improvement plan)
– 3 baselines: Scope baseline; Schedule baseline; Cost baseline
PMBOK 77
71
Copyright PMI Lahore, Pakistan Chapter 2016
Develop Project Management Plan
Output
3 base-lines
1. Scope base line 2. Schedule base line 3. Cost base line
9 Management plans
1. Scope Management Plan 2. Schedule Management Plan 3. Cost Management Plan 4. Quality Management Plan 5. HR Management Plan
6. Communication Management Plan 7. Risk Management Plan
8. Procurement Management Plan 9. Stakeholder Management Plan
Components of Project Management Plan
See PMBOK 78 for details
4 other plans
1. Requirement Mngt. plan 2. Process improvement plan 3. Change control plan 4. Configuration Mngt. plans
72
Copyright PMI Lahore, Pakistan Chapter 2016
Project Integration Management 4.0
Develop Project Charter 4.1
Develop Project Management Plan 4.2
Direct and Manage Project Work 4.3
Monitor and Control Project Work 4.4
Perform Integrated Change Control 4.5
Close Project or Phase 5.6
4.0 Project Integration Management
73
Copyright PMI Lahore, Pakistan Chapter 2016
4.3 Direct and Manage Project Work
Direct and Manage Project Work is the process of
leading and performing the work defined in the
project management plan and implementing
approved changes to achieve project objectives.
Inputs
4
Tools & Techniques2
Outputs
5
4.3 Direct and Manage Project Work
75
Copyright PMI Lahore, Pakistan Chapter 2016
Direct and Manage Project Work
Inputs
1. Project management plan
– Contains all the subsidiary plans and the work to be done in the project. It has __ documents
2. Approved Change requests
– Approved change request is an output from the Integrated change control process.
– It is generated if any change is required in the project
– Changes in project could be due to Corrective action, Preventive action, Defect repair or Document change.
– All change requests are approved by the Integrated Change Control Process.
Next page ….
PMBOK 82
76
Copyright PMI Lahore, Pakistan Chapter 2016
4.3 Direct and Manage Project Work
Approved changes to the project will also be done in Direct and Manage Project Execution process. These will include the following:1. Corrective actions: An intentional activity that realigns the performance of the project work with the project
management plan.
2. Preventive actions: An intentional activity that ensures future performance of the project work is aligned with the project management plan.
3. Defect repair: An intentional activity to modify a non-conforming product or product component.
Direct and Manage Project Work
Inputs
3. Enterprise environmental factors (EEFs)
Some of the EEFs that would influence Direct and Manage project work would be:
Culture of the Company
Infrastructure of the organization HR administration
Stakeholders risk tolerance
Direct and Manage Project Work
Inputs
4. Organizational process assets (OPAs)
Some OPAs that will have influence on direct and manage project work would include:
Standards used for executing projects Communications requirements
Database for collecting performance data Management of Defects procedures Lessons learnt files
Previous project files
79
Copyright PMI Lahore, Pakistan Chapter 2016
Direct and Manage Project Work
Tools and Techniques
1. Expert judgment
Expert judgment is used to assess the input needed to direct and manage execution of the project management plan. Additional expertise is available from:
Other unit in the organization Consultant and subject matter experts Stakeholders, customers, suppliers, sponsors Technical associations
PMBOK 83
80
Copyright PMI Lahore, Pakistan Chapter 2016
Direct and Manage Project Work
Tools and Techniques
2. Project Management Information System
An Information system consisting of the tools and techniques to gather, integrate, and decimate the outputs of project
management processes can be used to manage the project work. It is used to support all aspects of the project from initiating to
closing, and can include both manual and/or automated systems
81
Copyright PMI Lahore, Pakistan Chapter 2016
Direct and Manage Project Work
Tools and Techniques
3. Meetings
Meetings are held to discuss and resolve problems and issues related to the project.
Meeting are attended by Project Manager, relevant team members, and stakeholders.
Meetings can be one of these types:
Information exchange
Brain storming, open evaluation Decision making
1. Deliverables
A unique and verifiable product, result or capability to
perform a service that must be produced to complete a
process, phase, or project.
Tangible components can include elements of the project management plan
83
4.3 Direct and Manage Project Work >
Outputs
2. Work performance data
Work performance data are the raw observations and
measurements identified during the activities being
carried out the project work. This includes:
• Work completed
• Key Performance Indicators • Technical Performance measures • Schedules
• Change requests • Defects
• Actual costs
84
4.3 Direct and Manage Project Work >
Outputs
3. Change requests
Change requests is a formal proposal to modify any
document, deliverable, or baseline.
May modify scope, cost, schedule, quality, etc.
• Corrective actions: An intentional activity that realigns the performance of the project work with the project management plan.
• Preventive actions: An intentional activity that ensures future performance of the project work is aligned with the project management plan.
• Defect repair: An intentional activity to modify a non-conforming product or product component.
• Updates: Changes in documents, plans, etc. to reflect changes
85
4.3 Direct and Manage Project Work >
Outputs
4. Project management plan updates
Plans that will be updated include
• Scope, Schedule, Cost, Quality, HR, Communication, Risk, Procurement, and project baselines
5. Project document updates
Documents that will be updated include
• Documents related to project Requirement documentation, issue log, risk register
4.3 Direct and Manage Project Work >
Outputs
Project Integration Management 4.0
Develop Project Charter 4.1
Develop Project Management Plan 4.2
Direct and Manage Project Work 4.3
Monitor and Control Project Work 4.4
Perform Integrated Change Control 4.5
Close Project or Phase 5.6
4.0 Project Integration Management
87
Copyright PMI Lahore, Pakistan Chapter 2016
4.4 Monitor and Control Project Work
88
Monitoring and Control is the process of tracking,
reviewing, and reporting the progress to meet the
performance objectives as defined in the project
management plan.
Inputs
7
Tools & Techniques4
Outputs
4
4.4 Monitor and Control Project Work
89
Copyright PMI Lahore, Pakistan Chapter 2016
4.4 Monitor and Control Project Work
Input
1. Project management plan 2. Schedule forecasts
– Derived from progress against the schedule baseline. – Expressed in terms of Schedule variance (SV) and Schedule
performance Indicator (SPI). 3. Cost Forecast
– Derived from progress against the cost baseline.
– Expressed in terms of cost variance (CV) and Cost Performance Indicator (CPI).
[Covered in Cost Management]
4.4 Monitor and Control Project Work
Inputs
4. Validated Changes
– Changes that have been carried out after approval from the Integrated Change Control Process are verified here. –
5. Work Performance Information
– Data collected and analyzed and converted into information. – Information is used to assess the project progress and make
decisions.
PMBOK 89
91
Copyright PMI Lahore, Pakistan Chapter 2016
4.4 Monitor and Control Project Work
Inputs
6. Enterprise environmental factors (EEFs)
– Government/Industry standards in the country – Shareholders risks tolerance
– Project Management Information System
7. Organizational process assets (OPAs)
– Communication procedures and requirements – Financial control procedures
– Risk control procedures – Lessons from previous projects
PMBOK 90
92
Copyright PMI Lahore, Pakistan Chapter 2016
Monitor and Control Project Work
Tools and Techniques
1. Expert Judgment:
Subject matter Experts in the team shall interpret the information available (raw data converted to information) for monitoring, control and purposes.
2. Analytical Techniques
Various analytical techniques are used to analyze the information to forecast future outcomes
PMBOK 92
93
Copyright PMI Lahore, Pakistan Chapter 2016
4.4 Monitor and Control Project Work >
Tools and Techniques
3. Project Management Information System
Project Management Information system consists of software that gather, integrate, and decimate the output for the project
management processes.
It is used to support all aspects of the project from initiating through closing, and can include both manual and automated systems
4. Meetings
– Meetings are held to monitor the project activities. These could are face to face, virtual, formal or informal.
– Objective of the these meetings is to review progress and analyze the information related to the project.
4.4 Monitor and Control Project Work >
Outputs
1. Change Requests
• After comparing planned results to actual results, change requests may be issued to expand, adjust or reduce project scope/product scope/quality requirements/cost baseline. These could result in:
• Corrective actions: An intentional activity that realigns the performance of the project work with the project management plan.
• Preventive actions: An intentional activity that ensures future performance of the project work is aligned with the project management plan.
• Defect repair: An intentional activity to modify a non-conforming product or product component.
95
4.4 Monitor and Control Project Work >
Outputs
2. Work performance reports
– Based on the information available work performance reports can be developed.
– These could be physical or electronic – Intended to generate decisions.
3. Project Management Plan Updates
• Updates will be made to Schedule plan, Cost plan, Quality plan, Scope baseline, Schedule baseline, Cost baseline, etc.
4. Project Document Updates
• Forecasts of the project
• Reports related to the project performance • Issues log
96
Copyright PMI Lahore, Pakistan Chapter 2016
Project Integration Management 4.0
Develop Project Charter 4.1
Develop Project Management Plan 4.2
Direct and Manage Project Work 4.3
Monitor and Control Project Work 4.4
Perform Integrated Change Control 4.5
Close Project or Phase 5.6
4.0 Project Integration Management
97
Copyright PMI Lahore, Pakistan Chapter 2016
4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process
of reviewing all change requests, approving
changes, and managing changes to the
deliverables, organizational process assets,
project documents, and the project management
plan; and communicating their results.
4.5 Perform Integrated Change Control
Change Control Changes in the project can take place anywhere from the start to the end of the project.
These changes could be due to changes in scope, changes in schedule, changes in budget, changes in specifications, corrective actions, preventive actions, defect repairs, etc.
Changes can be requested by any stakeholder. Change requests should be given in writing
All change requests should be logged in the ‘change log’.
All change requests pass through the ‘Perform Integrated change control procedure’ where they get approved or get rejected.
The final implemented status of the change is updated in the change log and is audited to ensure that the change is done.
PMBOK 96
99
Copyright PMI Lahore, Pakistan Chapter 2016
Inputs
5
Tools & Techniques3
Outputs
4
4.4 Perform Integrated Change Control
100
Copyright PMI Lahore, Pakistan Chapter 2016
4.5 Perform Integrated Change Control
Inputs
1. Project Management Plan
2. Work performance reports
– Information related to the work being carried out in the project. – How the project is performing
3. Change requests
– Change requests generated from the monitoring and controlling process is an input to this process.
PMBOK 97
101
Copyright PMI Lahore, Pakistan Chapter 2016
4.5 Perform Integrated Change Control
Inputs
4. Enterprise environmental factors
– Scheduling software
– Configuration management system – Information distribution system – and other related systems
4. Organization process assets
– Change control procedures – Policies and Standards
4.5 Perform Integrated Change Control
Tools and Techniques
1. Expert Judgment
A Change Control Board (CCB) will be formed to review all change requests. The change request will be analyzed by subject matter experts to determine if the change request should be approved or rejected. These experts will be from:
• Stakeholders • Consultants • Industry groups • Technical experts • PMO PMBOK 99 103
Copyright PMI Lahore, Pakistan Chapter 2016
4.5 Perform Integrated Change Control
Tools and Techniques
2. Meetings
Change Control Board (CCB) will review all requests for changes, and will either approve or reject the changes requested
All decisions taken by CCB will be documented.
Concerned department/stakeholder will be informed for follow-up
3. Change Control Tools
Manual or automated tools shall be used to manage change control system to assist CCB members.
104
Copyright PMI Lahore, Pakistan Chapter 2016
4.5 Perform Integrated Change Control
Outputs
1. Change request status updates
Change requests that have been approved by the CCB will be implemented and the status will be updated
2. Change log
Change log is used to document all change requests, both approved and also that are not-approved and their implementation status.
PMBOK 99
105
Copyright PMI Lahore, Pakistan Chapter 2016
4.5 Perform Integrated Change Control
Outputs
3. Project management plan updates
Project management plans will be updated including any subsidiary plans and baselines that are subject to change control process
4. Project document updates
Project documents that are related to changes shall be updated
Project Integration Management 4.0
Develop Project Charter 4.1
Develop Project Management Plan 4.2
Direct and Manage Project Work 4.3
Monitor and Control Project Work 4.4
Perform Integrated Change Control 4.5
Close Project or Phase 5.6
4.0 Project Integration Management
107
Copyright PMI Lahore, Pakistan Chapter 2016
4.6 Close Project or Phase
Close Project or phase is the process of finalizing
all activities across all of the Project Management
Process Groups to formally complete the project
or phase.
4.6 Close Project or Phase
The Close Project process will ensure that:
All actions required for the completion or exit criteria for the phase or project are taken.
Actions and activities required to transfer the products, services, or results to the next phase or operations are done
Activities to collect project or phase records, audit project success or failure gather lessons learned are carried out
Archiving of project information is done.
PMBOK 101
109
Copyright PMI Lahore, Pakistan Chapter 2016
Inputs
3
Tools & Techniques3
Outputs
2
4.6 Close Project or Phase
4.6 Close Project or Phase >
Inputs
1. Project management plan
2. Accepted deliverables
– These are deliverable that meet the acceptance criteria
and have been approved by the project sponsor or the
customer.
– Acceptance is based on formal documentation.
3. Organizational Process Assets (OPAs)
– Guidelines available in the data base for closing project
or phase. Forms, templates, etc.
PMBOK 102
111
Copyright PMI Lahore, Pakistan Chapter 2016
4.6 Close Project or Phase >
Tools and Techniques
1. Expert judgment
Experts with knowledge of administrative closing will advise in closing of project/phase.
Subject matter experts will ensure that project/phase closure is done as per the standard procedures
Experts will be taken from
Other project managers within the organization PMO
Professional and Technical associations
PMBOK 102
112
Copyright PMI Lahore, Pakistan Chapter 2016
4.6 Close Project or Phase >
Tools and Techniques
2. Analytical techniques
Some analytical techniques shall be used to determine the success or failure of the various processes of the project. E.g.
– Regression analyses
An analytical technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship.
– Trend analyses
An analytical technique that uses mathematical models to forecast future outcomes based on historical results.
3. Meetings
– Meetings can be Face to face or virtual. These could be formal or informal. – Meeting are held for lessons learned, closeout, reviews, etc.
113
Copyright PMI Lahore, Pakistan Chapter 2016
FLOW OF DELIVERABLE AFTER IT IS
COMPLETED IN EXECUTION PROCESS
Flow of Deliverable
8.3 Control Quality
->
5.5 Validate Scope ->
4.6 Close project or phase
Direct and Manage Project Work (Execution)
Deliverables Verified Deliverables Verified Deliverables Accepted Deliverables Accepted Deliverables Transitioned Deliverables Deliverables
8.3 Control Quality 5.5 Validate Scope
4.6 Close project or phase
Input Input Input
Output Output Output
Output
Quality Checks Verify Scope Acceptance
Deliverables are completed in the Execution Phase of the
project
115
Copyright PMI Lahore, Pakistan Chapter 2016
Flow of Deliverable
8.3 Control Quality
->
5.5 Validate Scope ->
4.6 Close project or phase
Direct and Manage Project Work
Deliverables Verified Deliverables Verified Deliverables Accepted Deliverables Accepted Deliverables Transitioned Deliverables Deliverables
8.3 Control Quality 5.5 Validate Scope
4.6 Close project or phase
Input Input Input
Output Output Output
Output
Quality Checks Verify Scope Acceptance Completed deliverable then goes to the Control Quality process (8.3) to see if it has been made as per
the quality requirements
116
Copyright PMI Lahore, Pakistan Chapter 2016
Flow of Deliverable
8.3 Control Quality
->
5.5 Validate Scope ->
4.6 Close project or phase
Direct and Manage Project Work
Deliverables Verified Deliverables Verified Deliverables Accepted Deliverables Accepted Deliverables Transitioned Deliverables Deliverables
8.3 Control Quality 5.5 Validate Scope
4.6 Close project or phase
Input Input Input
Output Output Output
Output
Quality Checks Verify Scope Acceptance
After being verified that the deliverable is as per specification it is sent to Validate Scope process (5.5)
to verify that it has been made as described in the
scope
117
Copyright PMI Lahore, Pakistan Chapter 2016
Flow of Deliverable
8.3 Control Quality
->
5.5 Validate Scope ->
4.6 Close project or phase
Direct and Manage Project Work
Deliverables Verified Deliverables Verified Deliverables Accepted Deliverables Accepted Deliverables Transitioned Deliverables Deliverables
8.3 Control Quality 5.5 Validate Scope
4.6 Close project or phase
Input Input Input
Output Output Output
Output
Quality Checks Verify Scope Acceptance If the deliverable is verified
that it is as per the scope, then it is passed on to Close
project or phase process (4.6) as an input where is
goes through the acceptance process and goes out as an output as transitioned deliverable
Flow of Deliverable
8.3 Control Quality
->
5.5 Validate Scope ->
4.6 Close project or phase
Direct and Manage Project Work
Deliverables Verified Deliverables Verified Deliverables Accepted Deliverables Accepted Deliverables Transitioned Deliverables Deliverables
8.3 Control Quality 5.5 Validate Scope
4.6 Close project or phase
Input Input Input
Output Output Output
Output
Quality Checks Verify Scope Acceptance
119
Copyright PMI Lahore, Pakistan Chapter 2016
Initiating Planning Executing Monitoring and Control Closing
Monitoring & Control Project Work Perform Integrated
Change Control Plan Scope Management
Collect Requirements Define Scope
Create WBS Plan Schedule Management
Define Activities Sequence Activities Estimate Activity Resources
Estimate Activity Duration Develop Schedule Plan Cost Management
Estimate Costs Determine Budget 8 Quality
Management Plan Quality Management
Perform Quality
Assurance Control Quality Acquire Project Management Team Develop Project Management Team Manage Project Management Team 10 Communication
Management Plan Communication Management Manage Communication Control Communication Plan Risk Management
Identify Risks Conduct Qualitative Risk Analyses Conduct Quantitative Risk Analyses
Plan Risk Response 12 Procurement
Management Plan Procurement Management Conduct Procurements Control Procurements
Close Procurements 13 Stakeholders
Management Identity Stakeholders Plan Stakeholders Management
Manage Stakeholders Engagement
Control Stakeholders Engagement Risk
Management Control Risks
11 Scope Management Integration Management Validate Scope Control Scope Time
Management Control Schedule
Cost Management
9 HR Management Plan HR Management
Control Costs Process Groups 4 5 6 7 Develop Project
Charter Develop Project Management Plan
Direct & Manage Project Work Close Project or Phase Knowledge Areas 47 Processes 2 24 8 11 2 120
Copyright PMI Lahore, Pakistan Chapter 2016
4.6 Close Project or Phase >
Outputs
1. Final Product, Services, or Result transition
– This is the handing over of the final deliverable(s) to the customer or sponsor or the transition to the next phase.
– This is done with a signed acceptance documentation from the Customer.
2. Organizational process assets (OPA) updates
Some of the documents that will be updated will include Project files
Project or phase closure documents Historical information
PMBOK 104
121
Copyright PMI Lahore, Pakistan Chapter 2016
PMI Lahore, Pakistan Chapter
PMP® Certification Course
Project Scope Management
Chapter 5
Monitoring & Control Project Work Perform Integrated
Change Control Plan Scope Management
Collect Requirements Define Scope
Create WBS Plan Schedule Management
Define Activities Sequence Activities Estimate Activity Resources
Estimate Activity Duration Develop Schedule Plan Cost Management
Estimate Costs Determine Budget
8 ManagementQuality Plan Quality Management Perform Quality Assurance Control Quality Acquire Project Management Team Develop Project Management Team Manage Project Management Team 10 Communication
Management Plan Communication Management Manage Communication Control Communication Plan Risk Management
Identify Risks Conduct Qualitative Risk Analyses Conduct Quantitative Risk Analyses
Plan Risk Response 12 Procurement
Management Plan Procurement Management Conduct Procurements Control Procurements
Close Procurements 13 Stakeholders
Management Identity Stakeholders Plan Stakeholders Management
Manage Stakeholders Engagement
Control Stakeholders Engagement Risk
Management Control Risks
11 Scope Management Integration Management Validate Scope Control Scope Time
Management Control Schedule
Cost Management
9 HR Management Plan HR Management
Control Costs 4 5 6 7 Develop Project
Charter Develop Project Management Plan
Direct & Manage Project Work Close Project or Phase 47 Processes 2 24 8 11 2 6 123
Copyright PMI Lahore, Pakistan Chapter 2016
Project Scope Management 5.0
Plan Scope Management 5.1 Collect Requirements 5.2 Define Scope 5.3 Create WBS 5.4 Validate Scope 5.5 Control Scope 5.6
5.0 Project Scope Management
124
Copyright PMI Lahore, Pakistan Chapter 2016
Product Scope Vs. Project Scope
Product scope describes the
characteristics of the
product, service, or result
to be delivered.
Project scope describes the
work required to deliver
the product, service, or result.
Product Project
5.1 Plan Scope Management
Planning Initiating Executing Monitoring & Controlling Closing PMBOK 105
The process of creating a Scope Management
Plan that documents how the scope will be
defined, validated and controlled
Inputs
4
Tools & Techniques2
Outputs
2
5.1 Plan Scope Management
127
Copyright PMI Lahore, Pakistan Chapter 2016
1. Project Management Plan
– Contains all subsidiary plans from other knowledge areas. (16 documents) 2. Project Charter
– Describes high level scope, schedule and budget 3. Enterprise Environmental Factors (EEFs)
• Structure and culture of the company • HR administration and policies • Outside market conditions 4. Organizational Process Assets (OPAs)
• Policies & Procedures
• Historical information & Lessons learnt from other projects
5.1 Collect Requirements
Plan Scope Management
Inputs
PMBOK 108
128
Copyright PMI Lahore, Pakistan Chapter 2016
1. Expert Judgment
– Project manager can use subject matter experts to develop the scope management plan.
2. Meetings
– Meeting attended by the Project Manager may include – Project sponsor
– Selected team members – Selected Stakeholders
Plan Scope Management
Tools and Techniques
PMBOK 109
129
Copyright PMI Lahore, Pakistan Chapter 2016
1. Scope Management Plan
– It provides guidance on how project scope will be defined, developed, monitored, controlled and verified.
– It is a major input for
• Develop Project Management Plan process • Other process of Scope Management
– Components of the scope management plan include:
• Processes for developing scope statement, WBS, acceptance of deliverables, changes requests and their implementation.
Plan Scope Management
Outputs
2. Requirements Management Plan
This is the second management plan from this process.
– It describes how the requirement activities will be planned tracked and reported.
– How requirement will be developed.
– How changes in requirements will be managed
– Traceability structure which will be used for managing requirements
Plan Scope Management
Outputs
131
Copyright PMI Lahore, Pakistan Chapter 2016
Project Scope Management 5.0
Plan Scope Management 5.1 Collect Requirements 5.2 Define Scope 5.3 Create WBS 5.4 Validate Scope 5.5 Control Scope 5.6 132
Copyright PMI Lahore, Pakistan Chapter 2016
Planning
Initiating Executing Monitoring &
Controlling
Closing
Collect Requirements
PMBOK 110
133
Copyright PMI Lahore, Pakistan Chapter 2016
The process of determining, documenting and
managing stakeholders’ needs and requirements
to meet the project objectives.
What are requirements:
• Requirements are conditions and capabilities that are
required to be met by the project with relation to the product,
service or result.
• Some of the requirement that have to be met are related to:
a) Business Requirements b) Stakeholder Requirements c) Functional requirements d) Project Requirements e) Quality Requirements