Production Planning and Control - 2
LIST OF ATTEMPTED QUESTIONS AND ANSWERSMultiple Choice Multiple Answer Question
The commonly used network techniques other than PERT and CPM are as follows
:-Correct Answer
MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ]
Your Answer
MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ]
Multiple Choice Single Answer Question
In an unbalanced assignment, the tasks can be balanced by adding :-Correct Answer
Dummy tasks Your Answer Dummy tasks
Multiple Choice Single Answer Question
One of the causes of inability to meet delivery date originally promised :-Correct Answer
Lack of availability of material in time Your Answer
Lack of availability of material in time Multiple Choice Multiple Answer
Question
The main characteristics of mass and flow production are :-Correct Answer
Continuous flow of material , Low skilled labour , Easy supervision Your Answer
Continuous flow of material , Low skilled labour , Easy supervision Multiple Choice Multiple Answer
Question
In a mass production assembly shop following work measurement techniques are used
:-Correct Answer
Your Answer
Time study , Work sampling , Production study Multiple Choice Single Answer
Question
As the quantity increases, the procurement cost :-Correct Answer Reduces Your Answer Reduces True/False Question
Fluctuation due to changes in season are called cyclical fluctuation. Correct Answer False Your Answer True True/False Question
A type items are always vital under VED analysis. Correct Answer
False
Your Answer False
Select The Blank Question
Random fluctuation is considered for deciding ________. Correct Answer Analytical estimate Your Answer Seasonal fluctuation True/False Question
In assignment matrix, it is a must to determine Jacobean of the determinant.
Correct Answer False
Your Answer False
Select The Blank Question
cost of power over the year for 40000 pieces with 2000 numbers rejection would be Rs ________. Correct Answer 2692 Your Answer 2692
Select The Blank Question
At each ________, work is performed on a product either by adding parts or by completing assembly operations.
Correct Answer Work station Your Answer Work station
Multiple Choice Multiple Answer Question
To operate fixed order quantity system, following parameters are required to be
fixed:-Correct Answer
Standard reorder quantity , Minimum stock , Re-order point Your Answer
Minimum stock , Re-order point , Standard reorder quantity Multiple Choice Single Answer
Question
Why customer is called the king? Correct Answer
Customer's orders gives us work Your Answer
Customer's orders gives us work Select The Blank
Question
A progress card normally contains ________ squares. Correct Answer
Less than 25 Your Answer Less than 25 Select The Blank Question
________ models of OR serve as an ideal aid for determining optimal sequence of jobs.
Correct Answer Sequencing
Your Answer Sequencing
Multiple Choice Single Answer Question
Ordering of raw material is based on :-Correct Answer
Sales forecast Your Answer Sales forecast Select The Blank Question
Heuristics approach gave very good results when Wester and Kilbridge applied it to ________ assembly line.
Correct Answer TV
Your Answer Car
Multiple Choice Single Answer Question
What can be the consequence of inefficient working of department like sales?
Correct Answer
Failure on delivery date to customer Your Answer
Failure on delivery date to customer True/False
Question
In PERT, use of dummy activities is not much essential. Correct Answer
False
Your Answer False
Multiple Choice Multiple Answer Question
Work measurement is responsibility of :-Correct Answer
PPC , Industrial Engineering , Production department Your Answer
PPC , Industrial Engineering , Production department Select The Blank
The batch production requires ________ capital investment as compared to job production. Correct Answer High Your Answer High
Select The Blank Question
Time waste is the earliest of all wastes and yet the________ to correct because it does not litter the floor.
Correct Answer Hazards Your Answer Hazards True/False Question
To solve "n jobs - 2 machines" sequencing problem, it is assumed that each machine can perform only one type of operation and can undertake only one job at a time.
Correct Answer True Your Answer True True/False Question
PERT is suitable in defense projects and R&D where activity times can not be really predicted. Correct Answer True Your Answer True True/False Question
In precedence diagram the length of arrow has very high degree of significance.
Correct Answer False
Your Answer True
Multiple Choice Single Answer Question
emanating from the event is represented by :-Correct Answer
Earliest event time Your Answer
Earliest event time
Multiple Choice Multiple Answer Question
They are type of analytical estimate :-Correct Answer
Moving average , Exponential smothering , Curve fitting Your Answer
Moving average , Exponential smothering , Curve fitting Multiple Choice Single Answer
Question
The production system characterized by complex set of activities that must be performed in a particular order within a given period and within an estimated expenditure is known as
:-Correct Answer Project production Your Answer Project production Match The Following Question
Correct Answer Your Answer
Time taken by each job at each machine Processing time
Processing time
Time between starting of first job and completion of last job Elapsed time
Elapsed time
Number of stages the job has to pass Number of machines
Number of machines
Time during which the machine is standstill Idle time
Idle time
Select The Blank Question
In the assignment model, the measure of effectiveness of each job for each machine can be represented by means of ________.
Correct Answer Matrix
Your Answer Matrix
Multiple Choice Single Answer Question
The ROI of the company can be increased by :-Correct Answer
Increasing profit & decreasing inventory Your Answer
Increasing investment/sales ratio Multiple Choice Multiple Answer Question
The software for CPA would require the following parameters:-Correct Answer
Algorithms , Program code , Database Your Answer
Algorithms , Program code , Database Multiple Choice Multiple Answer
Question
Some of significant characteristics of fixed order quantity system under replenishment systems are as follows
:-Correct Answer
Safety stock is kept to take care of increase in demand during lead time as well as to meet demand when lead time is extended. , Re-order level equals safety stock plus average consumption during lead time , Average inventory equals safety stock plus half of reorder quantity.
Your Answer
Safety stock is kept to take care of increase in demand during lead time as well as to meet demand when lead time is extended. , Re-order level equals safety stock plus average consumption during lead time , Average inventory equals safety stock plus half of reorder quantity.
Multiple Choice Multiple Answer Question
Important considerations in scheduling are :-Correct Answer
Degree of centralization , Relative job priority , Load chart Your Answer
Degree of centralization , Relative job priority , Load chart Multiple Choice Multiple Answer
Question
Methods for recording actual progress of work for shop orders are :-Correct Answer
Your Answer
Progress card , Display board , Network updating Select The Blank
Question
The unit cost of manufacturing is largest in case of ________. Correct Answer
Job production Your Answer Job production Match The Following Question Correct Answer Your Answer HML Analysis Price orientation Price orientation SDE Analysis Procurement difficulties Procurement difficulties ABC analysis Usage value Usage value VED Analysis Criticality Criticality True/False Question
The non-mathematical rationale of the assignment method is one of minimizing opportunity costs.
Correct Answer True Your Answer False True/False Question
Moving average method lags behind the latest trend. Correct Answer True Your Answer True True/False Question
The 'G' group of GOLF analysis involves moderate delivery time and availability of credit usually in the range of 30 to 60 days.
Correct Answer True
Your Answer False
Multiple Choice Multiple Answer Question
Following difficulties are faced by SDE analysis :-Correct Answer
More delivery period , Geographical location of supplier , Reliability of suppliers
Your Answer
More delivery period , Geographical location of supplier , Reliability of suppliers
Multiple Choice Single Answer Question
The work measurement and time study belong to the school of management which was pioneered by
:-Correct Answer Fedric Winslow Taylor Your Answer
Fedric Winslow Taylor
Multiple Choice Single Answer Question
Stock of finished goods are based on :-Correct Answer
Sales forecast Your Answer Sales forecast
Multiple Choice Single Answer Question
The data in respect of spindle nose pertains to :-Correct Answer
Tooling
Your Answer Raw material data
Multiple Choice Multiple Answer Question
In linear programming method of line balancing, there are three types of constraints namely
Cycle time constraint , Step or task constraint , Precedence constraints Your Answer
Cycle time constraint , Step or task constraint , Precedence constraints Select The Blank
Question
Buying for C quantities should be made in ________ quantities . Correct Answer
Large
Your Answer Large
at 11:47 PM 0 comments Links to this post Labels: Production Planning and Control(Set-1)
Production Planning and Control - 1
LIST OF ATTEMPTED QUESTIONS AND ANSWERSMultiple Choice Single Answer Question
The sourcing of vendors in case of 'B' type of items is :-Correct Answer
Medium Your Answer Minimum
Select The Blank Question
In the assignment model, the________ is formed between jobs and machines.
Correct Answer Matrix
Your Answer Matrix
Select The Blank Question
Production Planning and Control department acts as a link between company's sales and ________ department.
Correct Answer Manufacturing Your Answer Manufacturing
Select The Blank Question
________ is used for planning capacity. Correct Answer
Standard Time Your Answer Standard Time Select The Blank Question
Being capable to adjust their production facilities shortly just after change in demand for products and without incurring heavy expenses, greater flexibility in production is provided by ________.
Correct Answer
Job & batch production Your Answer
Continuous production True/False
Question
PERT uses linear programming and probability concepts for planning and controlling activities.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question
Proper Production Planning and Control can reduce cost in :-Correct Answer
Overtime cost Your Answer Overtime cost
Multiple Choice Single Answer Question
Detachable ticket, after filling in required information is :-Correct Answer
Placed in a tray/box Your Answer
Placed in a tray/box Select The Blank Question
company has backlog of orders. Correct Answer
Increases Your Answer Decreases
Multiple Choice Multiple Answer Question
Computerisation of line balancing involve following requirements :-Correct Answer
System software , Application software , User friendly interface Your Answer
System software , Application software , User friendly interface True/False
Question
Curve fitting method of statistical forecasting uses curve line approach. Correct Answer False Your Answer False True/False Question
If set up time for four operations involved is 2 ,1.5, 2 , 2.5 hours respectively, total set up time would be 10 hours.
Correct Answer False
Your Answer False
Match The Following Question
Correct Answer Your Answer
Bought out materials required for production process but do not become part of finished product.
Maintenance, repair, operating [MRO] inventories Maintenance, repair, operating [MRO] inventories Finished goods, ready for sale to customer
Finished goods inventory Finished goods inventory
Idle resource of any kind having economic value Inventory
Inventory
Raw materials, parts, components required to produced finished product Production inventory
Production inventory Select The Blank Question
Rational figure on utilization index can be obtained by carrying out ________ study.
Correct Answer Work- sampling Your Answer Work- sampling
Multiple Choice Single Answer Question
The assignment algorithm was developed by a Hungarian mathematician named
:-Correct Answer D. Konig
Your Answer D. Konig
Multiple Choice Multiple Answer Question
The minimum requirements for application software for line balancing are as follows
:-Correct Answer
1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system.
Your Answer
1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system.
Multiple Choice Multiple Answer Question
A firm has 6 jobs to be processed on three machines A,B and C in the order ABC. The processing time of each job is given in the table below:- Find the idle time on different machines . Job Processing time [ hours ] Machine A Machine B Machine C J1 25 16 20 J2 26 20 19 J3 24 17 18 J4 22 20 21 J5 24 21 17 J6 28 18 13
Correct Answer 74 , 31 , 58 Your Answer 31 , 58 , 60
Multiple Choice Multiple Answer Question
PERT terminology uses words like :-Correct Answer
Network diagram , Events , Slack Your Answer
Network diagram , Events , Slack Multiple Choice Single Answer Question
The most common assembly line is a moving conveyor that passes a series of workstations in a uniform time interval called
:-Correct Answer Cycle time Your Answer Cycle time True/False Question
The make-or-buy decision is not related with profit of the factory. Correct Answer
False
Your Answer True
Select The Blank Question
Generally for ________ flow system, Heuristic method is preferred. Correct Answer
Intermittent Your Answer Intermittent
Multiple Choice Single Answer Question
Document raised by sales department to authorise activities of PPC department for items manufactured to customers order is called :-Correct Answer
Order Acceptance Your Answer Order Acceptance
Multiple Choice Multiple Answer Question
What factors affect the status of PPC department in the company for achieving informal status?
Correct Answer
Manufacturing Process , Work is highly repetitive , Number of workmen is not very large
Your Answer
not very large True/False Question
Increase in inventory carrying cost increases EOQ. Correct Answer False Your Answer False True/False Question
Progressing is only a substitute for poor planning. Correct Answer
False
Your Answer True
Multiple Choice Multiple Answer Question
Detachable Card contain following information :-Correct Answer
Quantity produced , Operation , Date of completion Your Answer
Quantity produced , Operation , Date of completion Multiple Choice Multiple Answer
Question
Weaknesses of PPC department can be studied on following grounds :-Correct Answer
Failures in delivery commitment , Cancellation of orders , Complaints from customers
Your Answer
Failures in delivery commitment , Cancellation of orders , Complaints from customers
Multiple Choice Single Answer Question
Activity R can not start unless activities P & Q are completed . And activity S can not start unless activity Q is over [ I.e. activity P may not be even over ]. Activity R is therefore succedding to activity P & Q while activity S is succeeding to activity
:-Correct Answer Q
Your Answer Q
Multiple Choice Single Answer Question
If the annual usage of a material is 1200 units and the reorder point is at 120 Units, find the lead time.
Correct Answer 4 months
Your Answer 4 months
Multiple Choice Multiple Answer Question
Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time
:-Correct Answer
Tool breakage , Job split up , Change in priorities Your Answer
Tool breakage , Job split up , Change in priorities True/False
Question
Stores issue order for an item is prepared as soon as the route sheet is ready.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question
Time study is useful method of measurement for :-Correct Answer
Short cycle time operations Your Answer
Long cycle time operations Match The Following
Question
Correct Answer Your Answer Index method
Loading and allocation of different jobs on different machines Loading and allocation of different jobs on different machines Critical Path Analysis
Schedule of activities of project Schedule of activities of project Jonsons method
Schedule using priority numbers Critical Ratio Scheduling
Establishing priorities among jobs Establishing priorities among jobs Select The Blank
Question
In check list approach, ________ rating indicates that existing PPC system requires some major improvements in indicated areas. Correct Answer
Fair
Your Answer Fair
Multiple Choice Multiple Answer Question
Because of following reasons there are limitations in forwarding quotation against sales enquiry
:-Correct Answer
The lot is not as per EOQ , Tools / plants required to execute order are not available. , The item is not within the manufacturing range of a company Your Answer
The lot is not as per EOQ , Tools / plants required to execute order are not available. , The item is not within the manufacturing range of a company Multiple Choice Multiple Answer
Question
Following are the factors which influence tool life :-Correct Answer
Type of tool , Material it is required to operate upon , Operators efficiency Your Answer
Type of tool , Material it is required to operate upon , Operators efficiency True/False
Question
C type items would never be vital under VED analysis. Correct Answer
False
Your Answer False
Multiple Choice Multiple Answer Question
The Hungarian method is based on following assumptions :-Correct Answer
Tasks differ in their work contents and facility differ in their capabilities. , Only one task can be assigned to each facility. , As only one task can be
assigned to each facility, the matrix must be of nXn order. Your Answer
Tasks differ in their work contents and facility differ in their capabilities. , Only one task can be assigned to each facility. , As only one task can be assigned to each facility, the matrix must be of nXn order.
Multiple Choice Single Answer Question
The ratio between "time when a product is required" and " time when the product is supplied " is known as
:-Correct Answer Critical ratio Your Answer Critical ratio Select The Blank Question
________ inventories help to balance company's supply with market demand. Correct Answer Finished goods Your Answer Finished goods True/False Question
In order to complete a project on time, each critical activity need not be completed in time.
Correct Answer False
Your Answer False
Multiple Choice Single Answer Question
Production output in night shift is :-Correct Answer
Less than I shift production Your Answer
Less than I shift production Select The Blank
Question
________reflects impact of money tied up in inventory. Correct Answer
Inventory turnover Your Answer
Inventory turnover
Multiple Choice Multiple Answer Question
The line of balance is a device for planning and monitoring progress of :-Correct Answer
Purchase order execution , Project execution , Targeted programs Your Answer
Purchase order execution , Project execution , Targeted programs Select The Blank
Question
Forecasting is function of ________. Correct Answer
Marketing department Your Answer
Chief Executive officer True/False
Question
The Heuristics approach has a base of binary number theory. Correct Answer
False
Your Answer True
Multiple Choice Single Answer Question
What shall be the consequence of acceptance of frequent rush orders by sales department?
Correct Answer Delivery failure Your Answer