• No results found

NUCLEAR SUPPLY CHAIN SYMPOSIUM

N/A
N/A
Protected

Academic year: 2021

Share "NUCLEAR SUPPLY CHAIN SYMPOSIUM"

Copied!
14
0
0

Loading.... (view fulltext now)

Full text

(1)

NUCLEAR SUPPLY CHAIN

SYMPOSIUM

Canadian

Contracting Models

Darryl J. Brown

Gowling Lafleur Henderson LLP

November 10, 2015

Suite 1600 1 First Canadian Place 100 King Street West Toronto, Ontario Canada M5X 1G5 Telephone (416) 862-7525 Facsimile (416) 862-7661 www.gowlings.com

(2)

Canadian Procurement/Construction

Delivery Methods

Various procurement/construction delivery methods exist to

provide alternatives as to how risks and responsibilities are

allocated for a project and how key factors such as time

and price are addressed.

Traditional Delivery Method:

Design-Bid-Build

Stipulated Price

Cost Plus

Unit Price

Contemporary Delivery Methods:

Construction Management (not-at-risk / at-risk)

Design-Build

(3)

Overview of Design-Bid-Build Model

Under this model the owner retains a design team/consultant

such as an architect or engineer to design a project. Once plans

are completed, the owner, usually through a call for bids (or,

possibly sole-sourced negotiations), retains a contractor to

construct the project. The owner, therefore, enters into two

separate contracts: one with the design team/consultant and the

other with the contractor.

Each of the parties may subcontract with various other

consultants, trades and suppliers in order to fulfill their

obligations at each project stage.

(4)

Overview of Design-Bid-Build Model

(cont’d)

Model’s pricing structure may take 3 basic forms:

Stipulated Price

Cost Plus

Unit Price

Cost Plus Model also lends itself to more complex pricing

structures

Guaranteed Maximum Price (Fixed)

Guaranteed Maximum Price with sharing of savings

(5)

Considerations

Design-Bid-Build Model In General:

Structure is good for a risk-averse owner as risks do not flow back to the

owner for construction or design defect issues – they remain with the

contractor and design team, respectively

Owner must await completion of the design before commencing construction

of the project - it cannot be fast tracked

Owner is not fully aware of the price until tender which may delay financing

arrangements, etc.

Design consultant and contractor have the potential to be at odds with each

other should problems arise - both could deny fault and engage in

finger-pointing resulting in delay

(6)

Considerations

Stipulated Price:

Easier for a contractor to provide a fixed price due to the design being

completed before pricing occurs

Should result in fewer changes to the design thereby saving owner

money

Contractor absorbing greater risk, therefore, higher contingency

(7)

Considerations

Cost Plus:

Contractor must keep and disclose full and detailed accounts and records

necessary to document cost

Contractor’s profits are tied to fees paid for all materials and services,

therefore, potentially less incentive to be efficient

Owner does not know the total cost of the construction project at the time of

signing the contract

Unit Price:

Suitable for projects where the required materials can be easily identified but

not the number of such items

Owner does not know the total cost of the construction project at the time of

signing the contract

(8)

Construction Management Method

Similar in framework to traditional construction contract

with the primary difference being that an owner retains a

construction manager (or Owner self-performs) in place of

the general contractor to provide project administration

and technical services such as scheduling, budgeting, and

material selection, but not to do any actual construction

work

No single contractor assumes responsibility for the entire

project

(9)

Considerations: CM Not-At-Risk

 Cost advantages exist in that there is limited risk to the construction

manager whose fees should therefore be less

 Model is suitable for moving

construction along at a fast pace

because procurement/construction can start before design is finalized

 Owner has better control over budget

and schedule

 Costs can be saved given that

contractors enter into contracts directly with the owner with no markup by a middleman

 Construction manager’s experience

may be looked to by the design team and they can work together

 Owner carries the risk of construction regarding scheduling and performance issues, etc. rather than the

construction manager

 Limited incentives for construction manager to aggressively seek cost savings

 Final cost of the design is not known to the owner until everything is in place

 Increased level of contractual

complexity

 Owner may be found to be the

“constructor” given that the owner is entering into several contracts with contractors

(10)

Considerations: CM At-Risk

 Similar to that of a Construction Manager Not-at-Risk model except that the risk of being found

“constructor” now flows to the

construction manager instead of the owner

 Cost savings reduced as construction

(11)

ONE MODEL DOES NOT FIT ALL

Contract Delivery Models and Pricing Structures

are becoming more complex to reflect the

(12)

EXAMPLE: Pricing Options

Hybrid Pricing Options arising to deal with different aspects of EPC contracting

1.

Engineering

Majority of pricing fixed

First of a kind risks or areas with significant unknowns (such as

Inside the Vault) may require Target Price

2.

Procurement

Generally Fixed

3.

Construction

Variations of Fixed and Target Pricing to address allocation of

risks and risk sharing for significant unknowns

(13)

STICKS & CARROTS

(Risk-Sharing)

A.

STICKS

Delay Liquidated Damages for failing to achieve milestones

Escalating Loss of Margin or Entire Fee above Target Price

B.

CARROTS

Bonus if cost savings below Target Price

(14)

CONCLUSION

The best Models allocate risks to the party best able to

manage risk

Goal: achieve a partnership where both parties have an

opportunity to succeed

References

Related documents

If there is no Owner Default under the Construction Contract, the Surety’s obligation to the Owner under this Bond shall arise after the Owner has promptly notified the Contractor

RESOLVED, that the Board of Directors of the Presbyterian Church (U.S.A.), A Corporation (“Corporation”) hereby approves the Grant Policy, attached as

If there is no Owner Default under the Construction Contract, the Surety’s obligation to the Owner under this Bond shall arise after the Owner has promptly notified the Contractor

STRICTLY speaking Panzer-Grenadiers were the armoured infantry element of Panzer (tank) Division or Panzer-Grenadier Divisions and were administered by the Inspectorate of Mobile

14.1 Inasmuch as failure to complete the Work for designated projects (as determined by the Owner) assigned pursuant to this Agreement within the time fixed in accordance

§ 3 If there is no Owner Default under the Construction Contract, the Surety's obligation to the Owner under this Bond shall arise after the Owner has promptly notified the

Upon execution by the Owner of the contract for fulfillment and completion of the Construction Contract, the completing contractor shall furnish to the Owner a performance bond and

isključivo za proizvodnju električne energije. U svjetskoj su proizvodnji električne energije.. hidroelektrane najveći proizvođač među obnovljivim izvorima energije. S oko 20