• No results found

TEST, EVALUATION & ACCEPTANCE BEST PRACTICE. Executive Summary

N/A
N/A
Protected

Academic year: 2021

Share "TEST, EVALUATION & ACCEPTANCE BEST PRACTICE. Executive Summary"

Copied!
36
0
0

Loading.... (view fulltext now)

Full text

(1)

WHITE PAPER:

TEST, EVALUATION & ACCEPTANCE

BEST PRACTICE

BMT’s experience of UOR Capability Delivery

Executive Summary

BMT Defence Services (BMT) has provided support to the UK MoD (primarily DE&S) for the acquisition, and ensuing delivery to theatre, of a number of Land Platform Urgent Operational Requirement (UOR) programmes. We have subsequently identified a number of ‘lessons’ that can be used in future acquisitions to ensure a robust, thorough, yet still agile systems engineering approach to capability delivery. This white paper discusses BMT’s recognised ‘best practice’ relating to the test, evaluation and acceptance process and how our ‘lessons learnt’ from UOR programmes over the past 3 years can be used to deliver front line capability to tight time and cost parameters, yet still achieve the levels of quality and performance required.

(2)

Executive Summary . . . 1 Contents . . . 2 Introduction . . . 3 Aim . . . 3 Definitions . . . 3 Background . . . 3

Requirements and Acceptance Management . . . 8

Requirements Background . . . 8

Requirements and Acceptance Strategy. . . 8

Integrated Test, Evaluation and Acceptance . . . .10

ITEA Principles . . . .10

ITEA Process . . . .12

Plan the Approach . . . .12

Define Verification & Validation Criteria . . . .13

Determine the Evidence Needs (Detailed Trials and Tests Planning) . . . .15

Detail the ITEAP . . . .19

ITEAP Structure . . . .23

Stakeholders and Working Groups. . . .23

Linkage of Requirements Management to Acceptance . . . .25

VVRM . . . .26

ITEAP Schedule . . . .27

Collect Evidence (Execute ITEAP) . . . .27

Factory Acceptance Tests . . . .28

Scenario Base Acceptance . . . .29

Evaluate and Recommend (Evidence Management) . . . .30

Acceptance Declaration . . . .31

Sub-System Contractual Acceptance . . . .31

System Acceptance . . . .32 Capability Acceptance . . . .32 Summary . . . .33 Conclusion . . . .33 Case Studies . . . .34 Project TALISMAN . . . .34

Explosive Line Charge . . . .35

Soldier Short Gap Crossing . . . .35

(3)

“Although much needs improvement in the planning and delivery of longer term requirements, it is notable, and to the DE&S’s great credit, that the equipment acquisition system works best when needs are greatest. The UOR process, which is designed to provide battle-winning equipment at short notice to current operations, appears able to deliver better trade-offs between performance,

cost and time in the interests of ensuring that, by and large, the front line receives the right kit at the right time.”

Bernard Gray - Review of Acquisition for the Secretary of State for Defence, 2009

Aim

This white paper discusses the lessons that BMT Defence Services (BMT) has learnt managing test, evaluation and acceptance, in support of DE&S, to deliver Land Platform Urgent Operational Requirement (UOR) capability to demanding timescales. The aim of this paper is to enable the reader to use this experience in applying test and evaluation ‘best practice’ to any future programme or project.

Definitions

Test - A controlled event designed to measure the performance of an entity in controlled circumstances (typically stimulus / load and environment)1.

Evaluation - The formal analysis of existing information or test results in order to inform an

acceptance decision or the action of determining the overall worth of a solution and how that worth might be increased, on balance, across the properties of effectiveness, cost, time and achievability1. Acceptance - A process, under the control of the Sponsor as the Acceptance Authority, confirming that the user’s needs for military capability have been met by the systems supplied1.

Integrated Test, Evaluation and Acceptance (ITEA) - Confirms that the supplied solution meets the user’s needs. It is also a method of identifying and managing technical and operational risks – and hence time and cost – throughout the programme1.

Background

As the primary intention for all new programmes is to develop and release into service a system or capability that will meet a specified need and be accepted by its intended user, it is necessary to understand why the Testing and Evaluation (T&E) of a developing system is important and how these activities support the systems engineering lifecycle (shown in Figure 1).

three

INTRODUCTION

(4)

four

T&E occurs throughout a number of stages of the lifecycle from initial requirements, leading towards acceptance, into service and sustained through the life of the project (re-activated for upgrade and modification programmes). These stages include:

Development of the concept and the associated requirement sets;

Down-selection of competing systems;

Contract Acceptance, through verification of system requirements;

Validation of user requirements, especially the Key User Requirements (KURs) detailed in the Business Case;

Characterisation and optimisation of interoperability with other systems.

Although this approach has worked well in the past for the more lengthy duration Equipment

Programmes, UOR programmes have become increasingly technically complex in order to deal with a constantly evolving threat or changing operational environment and require a robust, yet agile, T&E process. These activities therefore need careful, hands-on management if the pace of the UOR programme is to be sustained.

(5)

five BMT has previously described a streamlined approach to acquisition in its ‘FAST’ Acquisition White Paper2, summarised in the next 3 paragraphs, which aligns to the MoD recommended guidance for test, evaluation and acceptance due to its iterative nature, improved configuration and continuous cycle of feedback.

The Systems Engineering ‘V’ diagram, pictured in Figure 1, forms the basis of the Concept, Assessment, Demonstration, Manufacture, In-Service, Disposal (CADMID) cycle upon which the Acquisition Operational Framework (AOF) is securely grounded. If the AOF itself is to be streamlined for UOR delivery then it follows that the methodology, or technique, on which it is based should be further analysed.

Figure 2 shows a modified version of the ‘V’ diagram; now termed the ‘O’ diagram. The left hand side of the ‘V’ has been ‘straightened’ to show a more rapid progression through the requirements specification. This occurs through the utilisation and concurrency of consultancy activities to produce an agreed architecture and robust requirements to which industry can Design, Manufacture/Modify, and Test. This is in contrast to the original ‘V’ model in which a ‘waterfall’ approach is taken from the User Requirements, through the System Requirements and then on to the Architecture design in a sequential, and therefore more time-consuming, procedure.

Figure 2: The Systems Engineering ‘O’ Diagram – An adaptation of the ‘V’ Diagram providing a more agile approach

Review

Optioneering

Project start In service

Trials - validation Architecture Requirements Trials - verification Factory Test Unit Test Design Manufacture Analysis Comparison Decision Action St ak eh ol de r co nt rib ut io ns

(6)

six

The continual review process in the design, manufacture and test phases ensures that issues can be identified early and resolved with stakeholder input. Once the system has been delivered by industry, its acceptance is made easier by the presence of robust and testable requirements against which it can be assessed. A highly important factor with this approach is the feedback loop forming the completed ‘O’. This enables feedback on the fielded capability’s performance to be provided to inform the equipment programme and for subsequent planning of modifications to enable uplift from the originally delivered 80% capability.

BMT believes that it is possible to combine MoD guidance with the lessons learnt through BMT’s development of this ‘FAST’ process and their experience of test, evaluation and acceptance activities to determine a ‘best practice’ approach which can be applied to future projects, increasing project success and reducing the costs associated with such activities.

This paper does not cover the requirements scoping elicitation, prioritisation and agreement processes, but focuses on the strategy for requirements management, leading into the strategy needed to manage successful completion of the capability acceptance.

Figure 3 (below) has been included to provide an overview of the documentation set required to successfully follow the recommended acceptance process. The detail behind this diagram is explained throughout the remainder of this paper. It is worth noting however, that the documents displayed in green are supporting documents which are developed throughout other stages of the project.

(7)

seven Key User Requirements User Requirements Document System Requirements Document Requirements and Acceptance Management Plan RAMP (Acceptance Strategy) Master Data and Assumptions List Trials Administration Orders Trials Directive Plans Existing Trials Data Verification and Validation Requirements Matrix ITEA Schedule Stakeholder Responsibility Matrix GFX Plan

Asset & Contract Delivery Schedules Capability Integration Plan TEST Team Master Schedule Business Case Relationship Between ITEAP and CIP Integrated Test, Evaluation and Acceptance Plan Capability Acceptance Report Safety Case First Impressions

Report Test/TrialsReport ExceptionReport Other DLoDReports

(8)

REqUIREmENTS AND ACCEPTANCE

mANAgEmENT

Requirements background

For any Project, the Business Case will state the KURs reflecting the capability, services and performance that the Sponsor expects of the delivered system. As far as is possible, no constraints should be placed on the engineering solution, although constraints relating to systems of systems considerations may be necessary to ensure interoperability with other systems. Approaches to fulfilling the capability using candidate Military Off The Shelf (MOTS) system solutions and Government Furnished Equipment (GFE) components should also be considered.

For more complex programmes, a User Requirements Document (URD) may be developed from the KURs, which can be extremely valuable for developing the requirements for the non-equipment capability (non-EC) Defence Lines of Development (DLoD). Responsibility for non-EC DLoD planning is delegated to DLoD owners, their remit being to plan & manage fulfilment of the particular DLoD requirements. The DLoD owners are expected to report evidence of satisfaction of the non-EC DLoDs as part of the overall capability acceptance case. The System Requirements Document (SRD), derived from the KURs or URD, identifies the engineering constraints and targets that the user has decided to place on the assets and equipment. The System Requirements will be used as the basis for acquisition of the solution, against which the supplied capability will be verified.

Where possible a Prime Contractor will be responsible for supplying the integrated solution to meet the SRD. Sometimes this is not the case and DE&S takes on the role of system integrator with sub-systems procured by DE&S from different suppliers. These sub-systems should be specified against a subset of the SRD; it is important that the Measures of Performance (MoPs) for each sub-system requirement refer to the contribution that the supplier is expected to make rather than the performance of the overall system. This will avoid ambiguity, discussion and delay when it comes to sub-system acceptance. The balance of the overall performance may be due to another sub-system or due to an item of GFE.

Requirements and Acceptance Strategy

Integrated Test, Evaluation and Acceptance (ITEA) is a way of progressively confirming that the Users’ needs have been met by the developed solution and that each of the DLoDs combine effectively to deliver the capability. It also provides a defined method of identifying and managing the technical and operational risks related to the project. However, evidence against a set of acceptance criteria needs to be gathered to determine that this is the case so that approval can be gained from the Sponsor (acting as Acceptance Authority) and Stakeholders from the relevant Capability Integration Working Group (CIWG), responsible for the range of DLoDs, before the system will be accepted into service. For this reason, it is important for each requirement to be explicit, atomic, quantified and testable.

(9)

nine Explicit requirements reduce the possibility that the supplier has misinterpreted what has been asked for and ensures that the recipient is able to identify that what has been delivered meets the identified need. Quantified requirements allow the performance to be established against the identified need and, by being testable, it is possible to reach a consensus among Stakeholders that the requirement has been met rather than being a purely subjective opinion. Each requirement should therefore have at least one testable characteristic with traceability demonstrated between the requirements and the gathered acceptance evidence.

The requirements and acceptance strategy for any project is typically based upon the DE&S AOF recommended systems engineering ‘V’ process model. As the outline of the requirements and acceptance process, shown in Figure 4 below, indicates, the testing, evaluation and acceptance of a system needs to be considered very early on in the project lifecycle and continue throughout its development. In particular, the strategy for acceptance should be defined as early as Project Initiation and captured within the Requirements and Acceptance Management Plan (RAMP)3. The strategy contained within the RAMP defines the process and management of the acceptance activities and outlines the principal goals for the capability acquisition. These goals can then inform the development of the validation criteria in the URD and the verification criteria in the SRD.

Capability Need

Manufacture System

Capability Solution @IOC Deploy @FOC

User Requirements (Operational) Trials & TestsCharacterisation

Indicative Contractual Boundary

System Requirements System Trials & Testing Sub-Systems Trials & Testing Suppliers Design

Validate using Evidence & CIWG agreement

Verify results against Satisfaction Criteria using Evidence & WG decision

Supplier Design Evidence & Certifications Evidence Satisfies Satisfies ITEA Preparation

& Start-up Test & TrialsInitiation Test & TrialsCompletion Sub-System FATs

System Acceptance Capability Acceptance Test & Trials Management

ITEA Timeline

Figure 4: Requirements and Acceptance Process – Linking acceptance activity to requirements definition at the earliest opportunity in a project’s lifecycle

(10)

ten

INTEgRATED TEST, EVALUATION

AND ACCEPTANCE

ITEA Principles

The key principles of ITEA revolve around early engagement of Stakeholders across all DLoDs in order to determine that a full understanding of all evidence collection requirements has been obtained, and that the most effective method of evidence collection can be determined. ITEA also provides an opportunity to determine any dependencies in testing and evaluation activities so that these can be effectively managed throughout the lifecycle. The use of a Combined Test Team (CTT) to collect both developmental and operational evidence may help to ensure that a cost effective and timely delivery of acceptance evidence is achieved.

Whenever possible, a requirement will only be tested once and as early in the programme as possible, with the objective being to minimise the time and cost of live trials, and reduce the dependence on critical resources such as MoD trial facilities which are, at present, in heavy

demand. However, a balance must be struck between the cost of reducing uncertainty and the risks associated with full test coverage. Experience has shown that careful planning can usually mean that the testing of several requirements can be carried out simultaneously and that risk can be reduced by integrating operational evaluation and test activities. Applying a progressive and risk-based approach to evidence collection will not only assist in determining the most important elements of testing and evaluation, and therefore which activities may need additional effort, but also ensures that suitably representative test methods are used throughout development rather than left until critical stages where remedial action may be unfeasible. Regression testing may also be required in some circumstances.

The implementation of an ITEA approach can lead to a number of benefits being realised, including the development of an agreed approach to the collection and evaluation of evidence covering all requirements, all DLoDs and relevant to all Stakeholders, and the ability to determine a clear understanding of the time, cost and risks associated with the test, evaluation and acceptance activities. This approach aims to reduce duplicated effort and make the most efficient use of available test resources by:

Identifying the tests that most effectively measure capability and performance;

Planning the tests to make efficient use of all resources by testing the right aspects at the right time;

Identifying the need to demonstrate the test;

Running the tests, recording all of the relevant data and, where possible, testing once but using the data many times with a focus on optimising the test programme and preventing unnecessary testing through early identification of the evidence required for acceptance;

(11)

eleven The overarching details of the test, evaluation and acceptance process for a project should be contained within a consolidated Integrated Test, Evaluation and Acceptance Plan (ITEAP) as this can be used as a single reference point for all ITEA plans, processes and activities and reduces the need for duplication of information within a number of related documents. Although the ITEAP is primarily a documented plan, it also includes a Verification and Validation Requirements Matrix (VVRM) and an ITEA Schedule as explained in the following sections of this paper, and should contain references to other documentation which may be relevant, such as detailed test plans. This ensures that any relevant required information is always up to date as only one plan needs to be modified throughout system development.

The AOF suggests following a seven stage process to ITEA, shown in Figure 5 below. However, it is worth noting that experience has shown that to get the full benefit of this process, it should be carried out incrementally and not as a series of independent steps. This iterative process ensures that the acceptance methods and activities are constantly reviewed as the project develops and will remain relevant and feasible throughout development, leading to the successful acceptance of the system.

Plan the Approach Define V&V Criteria Determine the Evidence Needs Detail the ITEAP Collect Evidence Evaluate and Recommend Acceptance Declaration

(12)

twelve

ITEA PROCESS

Plan the Approach

As mentioned above, the approach to acceptance, which outlines the capability acquisition goals, should be considered during Project Initiation and detailed within the RAMP. A thorough strategy will ensure that Stakeholder expectations are managed from the outset and confidence is gained in the approach to be taken. Planning the approach in such a way was one of the key factors in BMT winning the contract to provide acceptance support to the TALISMAN Project4.

The acceptance strategy should answer a number of questions relating to the plans for the acceptance activities, primarily:

Who will carry out the process of Acceptance, and what contractual mechanism will be used to enable this?

Has the scope and type of the evidence to be collected been agreed with key Stakeholders, and confirmed with relevant technical experts as sufficient?

When will the testing be completed, and will this be representative of the final product?

Will all products be tested, or will this be limited to a percentage of products or factory tests of component performance?

How will pass/fail criteria be established as part of any test plan, and how will successful testing be planned and scheduled to inform the acceptance process?

The strategy must consider any assumptions made in the project Master Data and Assumptions List (MDAL) and as a minimum, define the following aspects of the project:

The Acceptance Authority, DLoD Owners and Stakeholder roles and responsibilities;

Initial Operating Capability (IOC);

System Acceptance;

The contribution of other Lines of Development;

The relationship between the ITEAP and the Capability Integration Plan (CIP);

Any interdependencies;

Third party generation of evidence (such as suppliers or agencies);

The responsibility for installation and integration testing;

Test policy implications including the use of ranges, simulation and responsibility for test facility validation;

Technical issues such as design certification;

Arrangements for UORs and any associated risks;

Any multinational funding arrangements;

Access and security of acceptance evidence, and

The risk management approach.

(13)

thirteen A key lesson learnt during the support to the TALISMAN project was that whilst it is important to plan the approach to ITEA as thoroughly as possible, it is also necessary to ensure that this approach is flexible should any project changes arise. For example, ideally, acceptance activities should not be planned so tightly that there is a risk of delay to the entire project should one area be delayed. Any flexibility that can be built into the plan will reduce the need for constant rescheduling of activities should delays arise. Where risks such as this become apparent during the planning stages, they must be highlighted and managed accordingly. Consideration should also be given to early testing of some system components as a method of risk reduction although it is recommended that Technology Readiness Level (TRL) Assessments are used to determine the feasibility of such testing.

Define Verification & Validation Criteria

The mechanism for acceptance of the system and its constituent sub-systems will be Verification and Validation (V&V) of the solution against the agreed SRD and URD respectively. Verification determines that the system which has been developed meets the requirements specified within the SRD i.e. that the system was built correctly. Validation determines that the system which has been developed meets the needs of the user as specified in the URD – that the system is the correct solution for the user (that the correct system was built). The tracing between the Requirements sets and their fulfilment through the acceptance process is shown in Figure 6 below.

Validates Satisfies/ Validates Verifies Satisifed By

VVRM

Plan the Approach Operational (Characterisation) Trials System Acceptance Trials & Tests

Supplier Evidence (References) Trials & Test Results Trials & Test Results GFE Information MOTS Sub-System Information Plan the Approach M O P S

(14)

fourteen

In order to gain acceptance from the Stakeholders, the requirements process will have to obtain suitable evidence to prove that the requirements suitably meet the needs. All V&V activity will need to be planned to cover the entirety of the project’s requirement set to ensure that a full acceptance case is made.

This evidence collection will typically be achieved through a series of trials, testing, and inspection of the supplied design solution, with proposed methods for V&V developed in line with the documented acceptance strategy as the User and System Requirements are matured. A number of methods can be used for V&V activities (listed below) and the most appropriate method should be determined based upon the requirement to be tested.

These activities can range from visual inspections, to simulations, to live trials, although it is worth noting that more than one method may be necessary to fully test a requirement. Additionally, in the case of UORs, full trials may not always be possible and in these cases adapted test methods may be required although details of the reasons behind this should be specified within the ITEAP. The International Council on Systems Engineering (INCOSE) Systems Engineering Handbook provides details of the Inspection, Demonstration, Analysis, Test (IDAT) Structure which may be a beneficial reference during system verification.

Standard Verification methods:

Design Review;

Supplier Test;

Supplier Analysis;

Certification;

Independent Test;

Independent Analysis;

Service Trial – TFT/TLT;

Service Trial – OFT;

In-Service Support Evaluation. Standard Validation methods:

Factory Test & Evaluation;

System Integration Test & Evaluation;

Technical Field Trials;

Operational Field Trials;

In-Service Support Evaluation.

(15)

It is possible and recommended that progressive verification is carried out throughout the development of the system and that evidence gathered builds on existing evidence which may have already been gathered and evaluated as this provides the customer with early and increasing confidence of the performance of the system and provides a method for managing expectations. BMT applied this approach for the acceptance activities during the TALISMAN project although this was, in part, forced due to programme delays. In this case, an acceptance review was held around the time of the critical design review to check that the anticipated performance of the system of systems would meet the high level requirements.

Determine the Evidence Needs

(Detailed Trials and Tests Planning)

To determine the level of evidence required for acceptance, it is important to understand the need for the evidence as well as ensuring that the correct evidence is being gathered, and considering the risks and benefits associated with collecting or not collecting it. To ensure that all aspects have been given an appropriate level of detail throughout the collection of evidence, the following steps

as described in the T&E process should be conducted:

Identify the evidence gaps across all requirements, whether equipment related or not;

Identify, agree and endorse the level of evidence required for all requirements;

Identify and review existing evidence, including the consideration of evidence that may not appear to be directly applicable;

Identify remaining evidence gaps;

Risk assessment of the need for evidence;

Identify appropriate method for collecting evidence still required;

Produce the necessary trials schedule;

Conduct the trials;

Evaluate the evidence against the acceptance criteria.

As this process is followed, the VVRM should be populated with the evidence requirements, the evidence as it is gathered and finally the acceptance arguments which will then lead to a fully populated acceptance case.

A number of factors may influence the methods used for evidence collection, including whether there is a need to conduct the activity in a controlled environment. The following are examples of possible influencing factors which should be considered:

Where the capability will be deployed;

Safety and security;

The need and feasibility for testing in a realistic environment;

The use of simulated environments;

The maturity of the system being tested;

(16)

sixteen

The use of destructive or non-destructive testing;

System interfaces and availability;

Availability of and confidence in a suitable test capability;

Legal and regulatory requirements;

Test duration and relationship to the critical path;

Test cost;

Whether ‘probability’ is an issue.

In addition to the type of evidence collection required, the use of certain test facilities is mandated or advised by the MoD, including the Land Systems Reference Centre (LSRC) for land digitisation integration in accordance with JSP 602. The Defence Test and Evaluation Strategy 2008 also mandates that MoD users of T&E are required to use centrally-managed facilities unless a compelling Business Case can be made for an alternative facility. The latest guidance should be obtained from the Trials, Evaluation Services and Targets (TEST) Team during the early stages of planning. The AOF recommends that the TEST Team’s Test and Evaluation Master Catalogue should be used to identify alternative T&E capabilities should these be required.

Ranges and Test and Reference Facilities (T&RF) should be capable of emulating fielded systems and real world conditions and can provide the following benefits:

Cost savings against the expense of proving systems in the field;

Avoidance of interference with operational activities;

Contextual proving of systems before they are fielded;

Safe and secure stressing of a system under test beyond limits experienced in peacetime operations;

Staged release of acquisition capability into service.

Most Land projects will follow current MoD policy of using the British Army Trials Development Units (TDUs) for the ITEA tests and trials although additional manpower requirements over and above that which the TDUs can supply, such as Combat Medics for live firings, need to be considered. Early liaison with the Trials Planning Office (TPO) for Regular Army Assistance to Trials (RAAT) troops is therefore essential. There may also be a requirement for additional Army assets during the testing and trials activities and the management of the availability of these assets should occur as part of the detailed planning for each trial. Any elements of testing which require the use of human beings must now also consider the ethical aspects of the test in question. A statement which determines the ethical aspects of the programme must be included within the ITEAP as mandated by JSP 536 (Ethical Conduct and Scrutiny in MoD Research Involving Human Participants).

In order to ensure their availability and to determine that they can be configured as required, potential trials facilities should be identified and planned as early as possible. In particular, early planning is required for supporting roles, operational trials, calibration and simulation and model validation.

(17)

seventeen ITEA trials & testing activities need to be planned in detail using Trial Directive Plans and Trial

Administration Orders (TAO) which include a detailed description of the planned test stages that will be applied for the project. Working Group (WG) involvement, through planned meetings, will provide advice on the scope of the testing and will enable the trial facilitator (or otherwise agreed agency) to formulate the technical Trials Plan or Directive. Each Trial Directive will contain the detailed technical planning & scheduling for the trial, and will provide strong guidance on the scope of work for the agency(ies) undertaking the testing. Local detailed test plans and schedules are dependent on:

Source and scope of test requirements;

Test supplier and contractual agreement;

Test items and resources (critical if more than one stakeholder group is involved);

Test agency’s facilities;

GFX needs.

This plan will be issued to Stakeholders in advance, in conjunction with a TAO. The TAO deals with the organisational issues and non-technical planning of the test/trial including safety, resources, assets and guidance to the agency on deliverable outputs. As a minimum, it should address the following issues:

Introduction/trials objective;

Safety;

List of test assets, prerequisites and GFE arrangements;

Special conditions;

List of agencies involved in testing and the coordination authority;

Trial location(s);

Special accommodation arrangements;

Trial programme & schedule;

Logistics, transport & vehicle drivers;

Personnel list including contacts for errors, omissions and disruption to programme;

Contractual conditions;

List of reports & other deliverables.

Proposed programmes should be developed in discussion with the Sponsor, DLoD Owners, Prime Contractor and other project Stakeholders with the responsibilities for planning, conducting, evaluating and reporting on T&E being agreed between them. These responsibilities and their agreement must then be captured in the ITEAP, appropriate contractual documents and Internal Business Agreements (IBA).

In most cases, the aim of a trial will be to provide the Project Manager (PM), via the trial sponsor, with formal evidence of testing of the equipment against a sponsor-supplied set of requirements. The requirement list will form the trial agency’s scope of work and will include MoPs or satisfaction criteria for each requirement. The trial agency’s response must address the results of testing against each requirement.

(18)

eighteen

It is the responsibility of the test agency to ensure that any draft Test Directives are agreed in advance of the test/trial and to ensure that the trial technical aims, methods and collection of results are sound, achievable within the trial schedule and conducted in a safe manner. However, the level of effort required for successful trials & testing activities can place a heavy load on project staff for any trials for which the Prime Contractor is not responsible. This is an area where specialist contractor support may prove invaluable such as that provided by BMT for the TALISMAN project.

For the ITEAP master scheduling, testing and trials booking dates must be secured with Stakeholders as far in advance as possible, particularly those agencies who already have busy schedules with MoD UOR projects. In BMT’s experience, it is also important to reschedule activities as soon as possible should programme delays affect the trials schedule as this will ensure that facilities can be used by other programmes if required.

The detailed Test/Trials planning will amplify and expand on the initial master ITEAP planning to provide a tactical level of detail. Figure 7 below illustrates the process.

Figure 7: Test & Trials Planning Equipment PM/

Project Officer Working Group Test / TrialFacilitator

Provide Subject Requirements

Information Collate & Supply

Information Pre-requisites

Organise Assets

& Resources Admin OrderIssue Trial

Agree Scope of Trial

Formulate & Issue Trial Plan (Technical)

Execute Trial Plan & Produce Trial Report Provide Advice on Fulfilment of Requirements Record & Communicate Acceptance Verification

(19)

nineteen

Detail the ITEAP

The ITEAP details the Project Team’s plan for achieving acceptance of the required capability, specifying and executing the defined acceptance strategy against the planned project schedule. This includes assigning responsibilities for test activities, determining any required customer

supplier agreements and monitoring the progress of acceptance throughout the development of the system. It is therefore important that the ITEAP is maintained as a living document which is tailored to the needs of the project throughout its life. The ITEAP will also cover those aspects of T&E that are required to be conducted to inform other processes such as the development of training and definition of safe operating environments.

The AOF suggests that the ITEAP should be initially drafted and then developed in an iterative manner as the project progresses so that early scoping activities can be carried out and a better understanding of the required acceptance activities can be obtained. Experience has shown that applying an iterative process as suggested can produce effective and complete ITEAPs which provide a suitable level of detail to which acceptance activities can be carried out. An eight stage process is recommended, as shown in Figure 8 below, to ensure that all elements of the system are considered and planned appropriately.

THE

EIGHT

STAGE

ITEAP

1

2

3

4

5

8

7

6

Identify Sources of Need for T&E

Scope Outline T&E Requirements Assess Achievability Perform Risk Assessment Consolidate Tests to Form

ITEAP, ITEA Schedule and VVRM Document and Cross-Reference in Project Documentation Develop Information Processes

Optimise the ITEAP and Obtain Stakeholder

Endorsement

(20)

twenty

In developing the ITEAP, it is important to firstly identify the sources of need, considering what is required for not only V&V of the requirements but for also determining what is required for design certification, technology readiness, contract acceptance and to meet safety and environmental needs.

The outline T&E activities can then be scoped for each of the identified sources of need including the development of individual test cases, detailed costs, priorities, responsibilities and dependencies as required. Consideration should be given to the resources required to conduct T&E activities including manpower, facilities, and the use of shared working environments, existing qualification data and Government Furnished Assets (GFX). As the URD and SRD start to evolve, these requirements should be reviewed to ensure their continuing appropriateness and thought given to the impact which activities may have on any related asset or contract delivery schedules.

In order to manage the cost associated with ITEA activities, a balance should be obtained between the costs of reducing uncertainty and the level of risk reduction possible with full test coverage. ITEA management is a complex task which requires a combination of specialist knowledge, experience and judgement and in order to be successful, Stakeholders and SMEs should be engaged early on to ensure that significant issues are not overlooked. These may include the following, for example:

User;

TPO;

Trials Organisations;

The Independent Technical Evaluator (ITE);

Defence Ordnance Safety Group (DOSG);

ISS Network Technical Authority (NTA);

DLoD Owners;

Internal Stakeholders;

Contractors.

Following this scoping activity, it is important to assess the achievability of the T&E activities. This assessment must include the assessment of the estimated cost against budget, schedule to critical path milestones and the demand for resources against their availability. Any issues should be highlighted as specified within the project risk management documentation.

Although the Sponsor typically owns the ITEAP, it is common for it to be managed within the project team by the Requirements Manager or an Acceptance Manager. The Requirements Manager manages and processes inputs and evidence from the relevant DLoD owners to ensure the capability can be achieved and escalates issues to the Sponsor through the Programme Board for resolution if required. To relieve some of the workload of the Project Manager and Requirements Manager, ITEA Management is another area where specialist contractor support may be of great benefit. BMT have experience in carrying out this role for a number of projects, including for each of the projects discussed in the Case Studies section of this paper.

(21)

twenty one Additionally, a risk and opportunity process should be defined in the ITEAP to provide Stakeholders with a means of raising new risks and opportunities and a risk assessment carried out, including risks which arise due to assumptions made. The following should be considered as a minimum:

Non-availability of test articles and facility on the day of test;

Failure of (integration) tests;

Consequent collapse of project management plan.

Possible mitigation actions should be identified which may be implemented if required. It is therefore recommended that:

The uncertainty of cost and schedule estimates are quantified;

Best practise is used, across MoD and Industry, to build the ITEA schedule;

The implications of schedule uncertainty on resource availability are considered;

The use of operational SMEs is maximised at the design stages;

SMEs are involved and in the early stages of ITEA, and that;

There is sufficient use of incremental verification to ensure there are no surprises at completion of manufacture.

Where Government Furnished Assets (GFA) are involved it is important that the financial

implications are understood by both the supplier and MoD as dependence on GFA is a risk that needs to be managed.

Once these initial stages have been carried out, it is possible to consolidate the T&E activities and document them within the ITEAP, ITEA schedule and VVRM. Details of the content of each of these elements can be found below. It is important to maintain links between the tests which are to be completed and the requirements which they will satisfy to ensure traceability throughout. This traceability will be important as the V&V activities progress and evidence is gathered of the systems compliance with requirements. BMT’s experience in this area has, on occasion, identified unnecessary testing which had been included simply because the test agency had always done it. By removing these additional tests, the workload and cost of test activities can be reduced, without affecting the overall integrity or capability of the equipment being tested.

A number of steps can be taken to ensure the robustness of the ITEAP, including:

Refinement of the dependencies and sequencing to resolve bottlenecks including updates to the project master schedule as required;

Identification of which body will be required to evaluate evidence, and when;

Development of the plan to include all sources of test and contributing organisations;

Explicit definition of accountabilities and liabilities;

Checking whether the ITEAP protects any relevant Intellectual Property Rights (IPR) in test results and whether there will be any problems with accounting, liability and insurance where assets are ‘loaned’ across organisation boundaries;

(22)

twenty two

To prevent duplication of effort and ensure that the most up to date information is available, the ITEAP should document and cross-reference the Stakeholder Responsibility Matrix (SRM), GFX Plan and Asset and Contract Delivery Schedules as appropriate. It is however recommended that when referring to another document, an overview of the content being discussed is given in the referring document.

It is important to develop formal processes and procedures regarding the management of test and evaluation activities which cross organisational boundaries including the collation and evaluation of V&V evidence, the management of disputes, test facilities and GFX, and integration and interoperability testing. These processes must include the incorporation of the non-EC DLoDs into validation testing and might cover areas such as:

The verification of individual DLoDs;

The collation and management of evidence;

The evaluation of evidence, and the conduct of acceptance decision-making;

The management of disputes, provisos, and remedial action;

The management of test articles;

The management of test facilities and availability problems;

The management of GFX and availability problems;

Installation and test;

Integration and interoperability testing;

The Test, Evaluation and Acceptance of UORs.

Finally, the ITEAP can be optimised and stakeholder endorsement obtained. This should include regulatory Stakeholders such as:

Quality Assurance;

Air and Sea worthiness if appropriate;

Safety;

Environment;

Security.

Any conclusions drawn in the achievability and risk assessment stages should be reflected in the ITEAP. This can then be baselined and published, along with the ITEA Schedule, and maintained in line with project configuration control processes. The SRM, Asset and Contract Delivery Schedules and other dependent plans should also remain aligned with the ITEAP and ITEA Schedule. A copy of each project’s ITEAP needs to be logged with the TEST Team who manage the UK Test and Evaluation capability portfolio and hold responsibility for managing the future T&E capability requirements on behalf of Cap JTES.

(23)

twenty three

ITEAP STRUCTURE

Although the above section details the processes which are recommended for developing an ITEAP, it is important to structure the document, as with all project documents, in a way which promotes readability. It is suggested that the structure determined by the AOF is used where possible to maintain consistency between projects. This structure is as shown in Figure 9 below with additional detail on selected areas provided in the following sections:

Stakeholders and Working Groups

A CIWG will provide the overall assessment of the capability being procured across all the DLoDs to the relevant Capability Lead. BMT has attended a number of CIWGs in support of Manoeuvre Support Team (MST) and Protected Mobility Team (PMT). Usually chaired by a full Colonel with full representation by Stakeholders, a CIWG is an authoritative, dynamic entity with considerable influence over the destiny of a capability.

Strategic Context & ITEA Objectives Military Capability Context DLODs and Capability Integration Project ITEA Schedule & Milestones ITEA Stakeholders & Organisation Test and Evaluation Strategy Risks, Assumptions & LFE Stakeholder Responsibility Matrix DLODs and Project Milestones VVRM or VVR Management Plan ITEAP T&E Process Project

Interdependences AnnexesITEA

Aim & Objectives T&E Schedule Project Strategy ITEA Schedule System Description Trials Programme Project Plans Main ITEA Risks Requirements Management Evaluation of Evidence Project Processes ITEA Assumptions Project Documentation Evidence Management ITEA Resources Verification Methodologies Contractual Elements Combined Testing Resources Contractual Requirements Test & Evaluation Acceptance GFX

Stakeholders AcceptanceStrategy OpportunitiesITEA Risks & Responsibilities AcceptanceProcess AssumptionsITEA

ITEA

Organisation Verification AcceptanceMilestones LFE & Validation Acceptance Organisation DLOD T&E Acceptance Criteria

(24)

twenty four

Stakeholders assigned as DLoD Owners will provide DLoD maturity readiness evidence to the CIWG. The DE&S Project and Requirements Managers (RM) will also contribute evidence, their principle viewpoint being the satisfaction of requirements within the Equipment and Logistic DLoDs, as defined in the SRD and the Integrated Logistical Support Statement of Work (ILS SOW)5. Specialist WGs/Panels may be formed to deal with specialist Equipment Capability and any other DLoD acceptance assessment issues, and will typically be engaged throughout the test and acceptance phase. Specialist WGs may include some or all of the following:

CIWG;

ILS WG;

Safety and Environment WG (Safety Panel);

Electromagnetic Environmental Effects (E3) Working Group. Members may include Defence E3 Authority (DE3A), Dstl, DOSG and 3rd Party trials managers

(e.g. Electromagnetic Compatibility (EMC) test establishments). Having chaired the E3WG for a number of projects, BMT has found it to be an invaluable forum for trials planning as well as assessment of evidence.

Specific System Requirements may be allocated to a WG when specialist advice is required for verification. It will then be the responsibility of the WG to assess evidence from trials and other sources to determine if each requirement MoP has been fulfilled. This delegation is a very effective way of avoiding bottlenecks in the acceptance process and is a more effective utilisation of

Stakeholders’ valuable time.

The Terms of Reference for WG members will typically include:

To provide specialist requirement verification advice to the Project within the remit supplied by the WG Chair. All safety issues arising are considered to be within the remit;

To recommend any amendments to requirement Verification/Validation Criteria,

MoPs and requirement priorities;

To provide technical trial planning as input into the ITEAP;

To assess and recommend acceptance or rejection of evidence gathered to demonstrate the acceptance of requirements.

Other key Stakeholders who may need to be consulted include:

The TPO as the point of contact for the allocation of trials tasks to the Land TDUs, and for manpower allocation through RAAT. BMT has regular contact with the team who runs the office, and has experience of completing the TPO Form 1 (Trial Proposal and Tasking Proforma). BMT has worked with 6 of the 7 TDUs over the last 3 years and has found that they are an essential part of the trials and acceptance process. As well as

5 There is often duplication between the ILS SOW and the SRD. In BMT’s view the ILS section of the SRD should be restricted

to equipment design issues that affect the support solution such as supportability, maintainability, reliability etc rather than ILS processes and deliverables that support the project management of procuring the support solution.

(25)

twenty five running specific trials to gather acceptance evidence, they can offer invaluable user input to the design process;

The TEST team who publish the T&E Catalogue which has been compiled with the co-operation of teams in the Defence community, including the MoD, Industry and academia, and lists the wide range of evaluation capabilities available to the UK;

The Test and Evaluation Coordination Cell as part of the TEST team, who compile a Master List of T&E Activities which may be consulted by projects considering the availability of trials facilities;

The Arms and Services Directors (ASDs) who are responsible for providing policy, direction and professional advice to their respective Arm or Service and to sustain the delivery of military capability from the Army both now and in the future. One ASD will be appointed as the lead for a new capability, but others may well be involved for specialist areas. BMT has worked successfully with a range of post holders within EinC(A), DRAC and Dinf.;

The DE&S Operational Vehicles Office (OVO) who determine priorities for vehicle programmes and will mediate when there may be a programming conflict for trials facilities between different project.

Linkage of Requirements Management to Acceptance

As mentioned previously, traceability between requirements and acceptance evidence needs to be maintained throughout system development. BMT uses the IBM Rational DOORS® requirements database version 9.2 with the KEYPAQ add-on as the principal tool for all requirements and acceptance management. The DOORS®/KEYPAQ system allows for electronic links to be created between information to provide traceability and can be used to import and export the requirements set in Microsoft Office document formats so that this method can be used for projects with little or no access to the DOORS® software.

The following requirement attributes are used in the SRD to provide sufficient information for linkage to acceptance:

Measure of Performance: Text and numerical data specifying the required effectiveness or performance envelope of each requirement. The lower ‘Threshold’ figure indicates the level of performance below which the requirement ceases to provide an acceptable level of benefit. The upper ‘Objective’ figure indicates the level above which there is no justification, financial or otherwise, for further improvements in performance. There is no need to assign both upper and lower targets to every requirement;

Verification Criteria: These attributes list the primary criteria against which it will be demonstrated that the requirement has been met, and the primary methodology to be used to demonstrate achievement of the requirement;

Verification Authority: This attribute shows who is responsible for the final decision on whether the requirement criteria are validated/verified against the evidence supplied from acceptance activities. Where specialist advice may be required, for example in

(26)

interpreting evidence, a specialist WG/Panel may be nominated. Although this attribute is not mandated by the AOF, it has proved to be very useful in BMT’s experience, especially throughout the TALISMAN project.

VVRM

Test activity, like experimentation and analysis, generates volumes of data and meta-data that must be transformed into information and evaluated to create knowledge and inform acceptance decisions. That data information and knowledge must be consolidated, distributed, used and archived. The VVRM provides a method of tracing the requirements through to the relevant tests and trials which are to be conducted in order to determine whether the system meets the stakeholder needs and should be accepted. There should be references to:

User and System Requirements;

Evidence and information, including tests and results;

Acceptance criteria and recommendations;

Responsibilities;

Progress and milestones.

The VVRM will usually be managed by the Authority, although it is accepted that the Prime Contractor will typically be heavily involved in its completion with respect to the contracted requirements. To ensure completeness, it is important to ensure that the VVRM covers the V&V of any non-contracted requirements as well as the validation of the URD.

Typically this will be developed in DOORS® or Microsoft Excel®, but the key aspects are that the information should be displayed in a table, as this shows the progression of each requirement through the development of the system in an easy to view manner, and that traceability can be demonstrated and maintained between the requirements and the associated information. Traceability management can prove extremely complex and any methods which can be utilised to reduce this are highly recommended. Reference to TRLs and System Readiness Levels (SRLs) may be useful to demonstrate progression of the system.

The headings required within the VVRM can vary depending on the project, although it is possible to combine information related to test procedures and their results with the V&V information to minimise duplication of effort. A possible VVRM layout is shown in Table 1 below:

twenty six

UR

ID RequirementUser SRID RequirementSystem ProcedureTest ExpectedOutcome ResultsTest Responsibility References

(27)

twenty seven

ITEA SCHEDULE

The ITEA Schedule is part of a Project’s Master Planning Schedule and shows the expected dates and durations of key project and acceptance activities and milestones, including when resources are required. As with the ITEAP, this schedule shows the pan-DLoD activities throughout the lifecycle and will be a living document as, especially during the initial stages of the project, activities are likely to change as the understanding of what is required develops and the possibility for a number of activities to occur concurrently may become apparent. At Initial Gate (IG) the schedule is likely to include a number of aspirations identifying key T&E milestones and the possible resources required rather than specific dates or events. At Main Gate (MG) these dates will be more precise providing a schedule which contractors and DLoD owners can contract/plan against. By this stage, all assets required throughout the life of the programme should have been identified and costed within the ITEAP.

The key acceptance stages for a typical Land project are outlined below and should be identified within the ITEA Schedule:

Sub-Systems Factory Acceptance Testing;

Suppliers Contract Acceptance;

System Acceptance;

Characterisation (Operational) Trials;

Logistics & other non-EC DLoDs Acceptance;

Capability Acceptance.

The TEST Team maintain a Master Schedule covering the usage of all UK T&E capabilities (covering a period of 20 years) and a catalogue of all UK facilities (MoD and Civilian) which should be

consulted when determining the ITEA schedule, as understanding the availability of assets required to conduct activities should enable a more realistic schedule for the acceptance of the project capability into service to be developed.

It is recommended that the ITEA Schedule is produced and managed within Microsoft Project with a baseline being created to determine between initial planned activity and the actual dates and durations of the activities being carried out.

Collect Evidence (Execute ITEAP)

Evidence collection activities occur for all requirements across all DLoDs. Although many of these activities may just require confirmation that a specific activity has taken place and been signed off by the appropriate organisation, Equipment DLoD evidence collection activities, such as tests and trials, tend to be more complex and typically require some sort of Demonstration, Analysis, Test or Inspection.

(28)

Once the ITEAP has been developed, the plan can be executed with trials facilities being booked, tests carried out, evidence collected and results and evidence collated within the VVRM. Tests should be carried out at a number of relevant test points, including design reviews and development milestones, and the progress of DLoDs should be managed and recorded within the ITEAP as the acceptance process progresses.

BMT has organised the MoD and independent trials elements of various projects using MoD facilities as recommended by the Subject Matter Expert (SME) Stakeholders, with support from industry test facilities such as MIRA where necessary. When production programmes slip, a lot of effort is required to reschedule trials to meet the delayed programme. It is worth considering contracting this support to the Prime Contractor in an attempt to make them bear the consequences of delivery delays. Following execution of the trials, the agency(ies) test reports will be issued as soon as possible to the PM, whereupon, if necessary, the WG will be consulted regarding their interpretation of the results and whether the requirements have been fulfilled. Below are a number of lessons which have been learnt during the execution of ITEA activities.

Factory Acceptance Tests

Thorough Factory (or Production) Acceptance Tests (FATs) of every unit will support the supplier’s Quality Assurance process prior to delivery to the customer. For a newly developed system, the test documentation to support the FAT will itself need significant development effort. Lessons learnt about FATs include:

Production schedules will inevitably be under pressure, but sufficient time needs to be allowed for setting to work and other preparations for acceptance, otherwise these will end up being done as part of testing and cause a lot of disruption. Preparations for acceptance can be included as a check-list in the FAT document;

Software functionality testing can be very time-consuming, if every function is to be tested. This only needs to be done when a new release of software needs to be tested, rather than on every production unit. However; testing a subset of the platform’s software functionality can be a useful method of testing that interconnecting cables have been correctly installed;

Representing the customer, BMT has sat alongside the supplier during early FATs to develop confidence in the supplier’s test processes. BMT provided a number of observations on the FAT documentation which the supplier acted on. Once that confidence was established it was possible to limit oversight to inspection of the completed FAT documents with occasional ‘dip-tests’;

It will normally be possible for the customer to sign off a significant number of system requirements during a FAT, including software functionality and visual inspection of installations. BMT has regularly represented the customer, calling on the RM or the TDUs for specialist input where necessary;

(29)

twenty nine

The MoD Quality Assurance Representative (QAR) is a key stakeholder in the acceptance process, and it is essential to engage with them when developing the FAT process and documentation.

However exhaustive the FAT process and Quality Inspections, DSDA 932 inspections may still pick up some deficiencies; the production schedule should ideally contain contingency for rectification and re-inspection.

Scenario Based Acceptance

It is always worth considering the value of a systems view and looking at capability evaluation based on realistic scenarios. This means testing the overall system (or system of systems) and capabilities as well as atomic requirement testing at lower equipment or subsystem levels. The scenarios may involve some level of simulation and emulation.

This system level testing may reveal previously unknown interactions between supposedly independent functions, which would not be revealed by testing the atomic system requirements. BMT helped to gather a great deal of TALISMAN acceptance evidence during Exercise Comanche Charge run by EinC(A) and Royal Engineers Trials and Development Unit (RETDU) in Jordan in Autumn 2009. Although a unit level training exercise for the TALISMAN squadron that was about to deploy the capability to theatre, the acceptance activities covered most of the DLoDs and included:

Acceptance testing on a number of vehicles prior to handover to the squadron due to lack of time in UK prior to shipping;

Sign-off of about half the functional requirements by RETDU, in representative light levels, dust and heat. One component of the TALISMAN capability, the High Mobility Engineering Excavator (HMEE), performed exceptionally well, transforming previously negative impressions formed during trials in the UK in unrepresentative conditions;

Feedback on maintainability by the Royal Electrical and Mechanical Engineers (REME) unit in support;

Interoperability testing that was not possible in UK revealing a significant problem. BMT was tasked to organise an investigation back in the UK, co-ordinating a number of SMEs and test facilities; this identified quick fixes that could be implemented in time for the theatre deployment;

Assessment of the effectiveness of concepts and doctrine embodied in the TTPs used by the squadron;

Assessment of the TALISMAN organisation and manning;

Assessment of the individual and unit level training developed for TALISMAN;

DOSG testing and clearance for smoke-dischargers.

(30)

thirty

Evaluate and Recommend (Evidence Management)

The management of evidence throughout the acceptance process is another iterative process which should be applied and reviewed throughout the development of the system. The acceptance evidence should be built up within the VVRM and results from tests and trials assessed by

appropriate Stakeholders and SMEs, with compliance statements recorded as appropriate. As mentioned previously, the progress of DLoDs should be maintained within the ITEAP and ITEA Schedule with any issues highlighted as they arise, including the need for further evidence collection. A number of trials reports may be beneficial to aid evidence management including:

First Impressions Report (FIR);

Test / Trial Report;

Exception Report;

Other DLoD Reports.

Following the assessment of these results, a period of evidence evaluation needs to be carried out. This needs to be scheduled into the ITEA schedule early on in the project as there is often a need for several different agencies/Stakeholders to review the same evidence. Sufficient time must be allocated for this to happen and for the production of the appropriate reports.

Where there is a non-compliance, the report must clearly identify the gap between the achieved performance and the performance required, the impact of the non-compliance on system performance, and any remedial action required. Agreement should be sought from Stakeholders and alternative options discussed where agreement is not possible. These options may include:

Re-design;

Quality investigation;

Modification;

Trade off;

Re-trial or re-plan.

(31)

thirty one System failures, component failures, operability issues, maintainability issues, reliability issues and safety concerns are all examples of incidents that may be identified during acceptance activities. It is important they are captured as early as possible, sentenced appropriately and action taken. BMT has supported full incident sentencing using codes in accordance with Def Stan 00-42, and also has developed a simpler process that is more appropriate to the timescales of a UOR. For more information on this process, please contact BMT using the contact details at the end of this paper. BMT has often found that the user or tester will identify potential design improvements that are outside the scope of the endorsed requirements. These should still be logged as incidents but may be sentenced as ‘Capability Improvements’ that can be addressed if funds allow, or in a future capability increment.

The pace of a UOR programme means that trials and testing may reveal some endorsed requirements that cannot be met. Some form of concession or requirement trade will need to be sought at the appropriate level, supported by an impact statement and proposed way ahead.

Acceptance Declaration

At each of the key milestones throughout the project, a recommendation should be made to the Acceptance Authority. These milestones shall include:

Contract Acceptance;

Systems Acceptance;

In-Service Date (ISD);

Initial Operating Capability (IOC);

Full Operating Capability (FOC);

Any agreed Equipment Delivery Dates (EDDs).

Sub-System Contractual Acceptance

Acceptance for sub-systems will be achieved when compliance has been demonstrated by the suppliers through providing performance evidence against the subset of System Requirements, using a VVRM, and depends upon the completion of all sub-system integration test and

trials activities.

The VVRM will be generated by the Project Manager from the System Requirements set and supplied to the supplier in either DOORS® or spreadsheet format. Sub-system suppliers will provide the requirements compliancy, performance and references to evidence for each sub-system requirement listed with the completed VVRM to the PM.

(32)

thirty two

System Acceptance

Final System Acceptance for the System is achieved when compliance has been demonstrated, with evidence, against all the individual requirements of the SRD.

The DOORS® database will have been populated with all the information necessary to ascertain the status of each system requirement, and will be used to generate reports listing the test and trials achieved with summary results.

The PM or RM should retain a pack of acceptance evidence as an electronic folder. This can be managed by BMT on their behalf if required, and will contain electronic copies of reports and other evidence documents that are referred to within the DOORS® requirements set as requirements satisfaction evidence.

Capability Acceptance

The FOC Acceptance milestone is the final milestone and marks the culmination of the ITEA activities.

The capability acceptance comprises of the final analysis, reporting and presentation of the acceptance case to the Capability lead by the RM. This presentation can be made when:

Any System Acceptance and Operational (characterisation) re-testing is completed;

Capability and safety issues and risks have been reviewed and mitigated where possible;

A full set of requirements satisfaction evidence has been collected and entered into the DOORS® database and is available for review;

The Safety Case has been issued;

Development of the non-EC DLoDs (Training and Logistics) is sufficiently matured to support the IOC.

The PM will need to supply the RM with sufficient information input for the final Capability Acceptance report; the inputs are expected to comprise of:

Status of the satisfaction of all Key User (including non–EC DLoDs) and System Requirements;

Any Concessions raised against supplier-delivered sub-systems (equipment);

Any delivered equipment issues, in plain English, regarding safety and capability for linkage into any CIP. This completes the feedback loop described in BMT’s ‘FAST’ Acquisition White Paper.

(33)

thirty three

SUmmARY

BMT has provided trials, evaluation and acceptance support to a number of Land UOR projects in recent years. This paper combines the lessons learnt during these support activities with MoD guidance to provide a number of recommendations on how best to proceed on future projects. Using the information given within this paper, it is possible to achieve a robust and comprehensive ITEAP, ITEA Schedule and VVRM, ensuring that all aspects of a system that need to be tested or evaluated are considered with processes and evidence managed accordingly. The BMT ‘lessons learnt’ highlight some of the key issues surrounding ITEA and suggest methods for overcoming related problems during future projects.

Conclusion

Whilst these lessons have been learnt in the execution of UOR programmes, they can be applied to any project. It is certainly worth considering contracting out the detailed management of trials, evaluation and acceptance, allowing the MoD PM and RM to concentrate on and direct the high level programme issues.

References

Related documents

Findings from this study advocated for the effect of peer- mediated picture exchange communication system intervention in improving vocabulary knowledge in children

Historians are finding more and more routes to public-engagement, and, given the p ublic fascination with stories of ruined lives, biographical research and liquid

To determine the prevalence of undiagnosed diabetes and impaired glycaemic state (IGS) and compare the WHO 1998 and IEC criteria for diagnosis of T2DM in patients admitted to

That paper shows that by measuring shocks to this technology as the sole source of permanent shocks to the relative price of investment goods, investment- specific technology

Hence the values of the mean ratio of hourly photo synthetically- Active Radiation (PAR) to the hourly global (broadband) solar radiation(R s ) predicted by the second k t model

The three substances in the body externally are the head, hands, and feet, and internally are the three elixir fields of upper, middle, and lower, and in the boxing arts, they are

Two seminars address this knowledge need: “What the Capital Project Manager Needs to Know about Soil, Foundations, Concrete, Welding, and Piping”, and “What the Capital Project

To be presented at the annual American Association for Adult and Continuing Education Conference, Louisville, KY.. Writing for