• No results found

Meeting Date 04/05/11

N/A
N/A
Protected

Academic year: 2021

Share "Meeting Date 04/05/11"

Copied!
29
0
0

Loading.... (view fulltext now)

Full text

(1)

City of Largo Agenda Item 18

{

{

{

{

{

In January, the City opened the new Largo Community Center at 400 Alternate Keene Road in Largo.  As an aspect   of the approved capital project, upon opening the new facility, the Facilities Management Division would then begin  the process of demolishing the previous structure. The Office of Management & Budget conducted a bid process for the demolition of the Old Community Center   Building on 4th Street NW in Largo's Downtown.  Fifteen (15) Bids were received.  After reviewing the submitted bids,  staff is recommending award to Honc Destruction, the lowest bidder.   If approved, staff will immediately begin the  process of directing the vendor to demolish the structure. This project is expected to be completed within 45 days of notice to proceed. Upon completion the site will be graded  level and hydroseeded with grass seed, creating a passive park setting. Sidewalks along the northern boundary of the   site will be left in place for pedestrian access. As requested by the City Commission at the March 1, 2011 Commission Meeting, staff has returned this item for   consideration   with   additional   information   and   an   analysis   of   the   benefits   of   demolition   of   this   structure.     This  information is attached to this memo.

Presenter: Glenn Harwood, Facilities Manager PW ­ Public Works TITLE: Department: $40,000.00 AWARD OF BID NO. 11­B­350, DEMOLITION OF COMMUNITY CENTER, TO HONC DESTRUCTION IN THE AMOUNT OF $37,444 Budgeted  Amount: Budget 

Page No(s).: Available Amount:

City Attorney  Reviewed: Consistent   With: Advisory Board  Recommendation: Not Applicable Potential  Motion/  Direction  Requested: I MOVE TO APPROVE/DISAPPROVE AWARD OF BID NO. 11­B­350, DEMOLITION OF COMMUNITY CENTER,  TO HONC DESTRUCTION IN THE AMOUNT OF $37,444.

Staff Contact: Glenn Harwood, Facilities Manager 727­586­7418 [email protected] Attachments: Bid Tabulation, Executive Summary Yes No N/A For Against N/A

04/05/11

Meeting Date

DTIF Funding  Source(s): Budget  Amendment  Required: Source: Yes No Yes No N/A $40,000.00 Expenditure Amount: Sufficient  Funds  Available: Yes No N/A 184 $37,444.00 Additional Budgetary 

(2)
(3)

Former Community Center Executive Summary The FY 2011 Budget includes $40,000 for planned demolition of the former Community Center on 4th Street  following completion of the new Community Center on Alternate Keene Road.   At the City Commission  Meeting of March 1, 2011, the City Commission postponed action on the award of demolition contract for the  former Community Center building.  The City Commission requested staff consider the reuse of the building  as a new IT Data Center, housing computer servers and telecommunications equipment for the City.  The   City Commission also requested input from the City's Historical Preservation Advisory Committee (HPAC)   and the Historical Society as to whether  the building  should  be preserved due to its  possible historic   significance.  

Staff   has   obtained   information   from   the   Public   Works,   Information   Technology   (IT),   and   Community  Development   Departments   related   to  the   City   Commission's   request,   and   the   HPAC   has   convened   to  discuss this issue.  Based on the information obtained, it is not recommended that the City pursue use of  this building as an IT Data Center.  Locating an IT Data Center at this site does not best meet the needs of   the IT Department.  Based on the size and current structural rating of the building, substantial modifications  would be required that make the cost of retrofitting this building equal to or greater than new construction   east of Alternate 19/CSX railroad tracks, in closer proximity to other major City facilities.  Additionally, reuse  of the building (in whole or in part) will disrupt the parcel assembly that has taken place over the past   decade for the purposes of downtown redevelopment in accordance with the West Bay Drive–Community  Redevelopment District Plan.  The Chamber of Commerce has submitted correspondence supporting the  demolition   of   the   former   Community   Center,   and   the   HPAC   has   stated   that   the   structure   has   been   substantially modified to where the building itself does not have historical significance in accordance with   historical preservation criteria.   It is staff's recommendation to proceed with the demolition of the former   Community Center building and subsequently market the property for redevelopment as will be discussed at   the upcoming City Commission Work Session on June 14, 2011. Public Works In March 2005, Facilities Management contracted with McCarthy and Associates to perform a preliminary  structural evaluation of the building.  At the time of the evaluation, the former Community Center consisted   of the original building and a subsequent addition that was built to replace part of the facility that was   destroyed by a fire. The addition/renovation was completed in 1990. The structural analysis was performed  on both the multi­purpose room addition and the renovated one story building. The findings of the report   from the structural evaluation are summarized below, and a copy of the report is attached: Original building (west end, renovated 1990) • One story masonry structure with a flat roof.  • Roof is constructed with steel beams, bar joists and metal deck. • Original drawings were not available limiting ability to calculate design capacity of the structure. Building addition (east end)  • There does not appear to be any vertical reinforcement of the masonry load bearing walls.

• The   roof   structure   consists   of   pre­engineered   wood   trusses,   plywood   sheeting,   and   metal   tile  shingles.  • Wood trusses are secured to a wood top plate with a light gauge metal hurricane clip of minimal   capacity. • Based on this review, the addition does not appear to meet wind load criteria required by the current   (2005) building code. • Note: Building codes and wind load criteria have been revised since this study was completed. The current building is approximately 18,000 square feet in size. Facilities Management estimates the costs   to harden the structure to current building codes and 150+ mph wind loads (required for a data center) to be   $2 million. This figure is based on cost estimates developed to harden the Police Department building,   which is approximately the same size building footprint (15,000 sf). 

(4)

Other issues to take into consideration: • The bid for demolition was opened on February 10th and is valid for 90 days; extension beyond 90   days would require a request from the City for the contractor to hold pricing for additional time. • No building maintenance, utility expenses or custodial budget was included for this facility for FY  2011, nor anticipated for FY 2012 and beyond.  • All utilities to the building have been disconnected and would require several thousand dollars to re­ establish service. • The building is currently unconditioned (no air conditioning) which will cause it to deteriorate more  rapidly due to heat and humidity intrusion. • Several items have been removed from the building for re­use at other facilities prior to demolition,   including the automatic transfer switch and diesel fuel for the generator, automatic door openers,   drinking fountains, etc. • The environmental report generated as part of the demolition identified approximately 18,000 sf of   mastic (floor tiles and mirror adhesive) that contain asbestos. Any renovation to the building would  include abatement costs to remove the asbestos prior to reuse. Information Technology Evaluation of the former Community Center as a potential data center resulted from development of basic  minimum requirements and recommendations by City staff, without the use of consultants that specialize in  this capacity. Communication vendors were contacted for budgetary estimates of moving their service to the   former Community Center. The cost of moving the physical equipment was not obtained, as the actual   process of moving was not evaluated. The initial relocation would only include the City Hall computer room,  City Hall telecommunications room, and the Infrastructure Division of IT (not the entire IT Department). This   evaluation is from a technology perspective only; issues of building condition, economic development, and  historical significance were handled by other departments.  Reason for Relocation: The City needs to relocate its main computer room and telecommunications equipment  from the City Hall  building to a secure building able to withstand a Category 5 storm event, creating a new data center, in order  to preserve technology and communications during a disaster. The estimated floor space needed for the  relocation is 2,000 to 3,000 square feet.  Current Network Environment: The City Hall building serves as the primary computer, telecommunications and switching hub, from which  all data and communications pass through. The Largo Public Library and Environmental Services both have   secondary end­point computers room, not on the City network.   The Library computer room serves the   Library   Patron   Network,   and   the   Environmental   Services   computer   room   serves   the   Wastewater  Reclamation Facility (WRF) monitoring control system. The City possesses a stand­alone switching hub  located in Largo Central Park, referred to as the "Hut".   This small building, located between Seminole   Boulevard and the large tunnel of the Largo Central Park Railroad, is deemed the weakest link in the entire  City technology network due to its physical location, the building structure, and its unprotected proximity to   Seminole Boulevard. All other buildings on the City network are considered end­points. The new Community  Center (currently an end­point) was designed and built to be used as a backup computer room in case the  City Hall building became unusable (providing the computer equipment was usable post disaster). With the backup computer room in the new Community Center, plans were being drafted to connect (via   fiber optics) the new Community Center to other City emergency operations buildings to create a redundant   network loop for disaster planning. This would eliminate the need for the City Hall building in order to   establish connections to other City emergency operations buildings should the new Community Center   backup computer room be activated. At this time, should the new Community Center be activated as the   City's computer room due to City Hall being unusable, delivery of computer services to other City buildings  may  not be  possible,  as  all  network  connectivity  currently  requires  connection  to City  Hall.  Telephone  services   to   emergency   operations   buildings   would   be   limited   to   single   business   lines   installed   in   the  emergency operations buildings, should City Hall become unusable. 

(5)

Opportunity Considerations:

With the relocation of the City's computer room and telecommunications equipment to a new data center,  consideration should be given to strengthening the City network, minimizing stand­alone hub points, and  long­term development of a redundant fiber network loop for continuity of technology and communications in  the   event   of   a   disaster.   These   considerations   would   result   in   long­term   financial   savings   through   the  reduction of physical equipment and building maintenance. The following items should be considered in  determining the location of the site for a new data center. • The physical location should be “network centralized” (i.e., located in the middle of the majority of  computer and telecommunications usage) in order to minimize fiber runs between sites. • The physical location should be within an area of “network zero latency” in order to minimize the use  of remote client computing software. This is a bandwidth issue, in where a zero latency area is   considered non­interruptable. • The physical location should be above the 100 year flood plain. • The building should be one story, eliminating the cost associated with second floor weight load  requirements and special elevators. A loading dock should be provided.  • The physical location should have easy access to multiple vendor's communications infrastructure in  order to minimize build out cost to the new data center. • The physical location should be capable of providing access to multiple power grids, and preferably  a hospital grid (which are the first to be turned on after a storm event).   • The building should be easily expandable to allow for technology growth.  Consideration could be  provided for inclusion of other local government data centers. • The physical location should allow for the removal of the stand­alone switching hub (“Hut”) in order   to reduce the number of “hops” (times data must travel through a switch or router) in the network,   equipment requirements, and building maintenance.  Centrally locating a new facility in relation to  other existing facilities will subsequently reduce capital equipment replacement and operating costs. • The   physical   location   should   allow   for   long   term   permanent   occupancy   in   order   to   minimize 

disruptions to City business and aggregate cost over a long time period.

The following non­location related items that should be considered in conjunction with the computer room  and telecommunications equipment relocation to a new data center are:

• All new fiber optic runs should be buried to ensure maximum survivability.

• Activate the new Community Center as a switching hub, providing three active switching hubs  connected   by   two   fiber   legs   (Community   Center,   new   IT   Server   Building,   and   Public   Works  Administration). Only one future fiber run would then be required to complete a redundant fiber loop.   With appropriate equipment, the redundant fiber loop could become a self­healing network, whereby   if one switching hub were to fail, city­wide communications would not be disrupted.

• Create   telecommunications   redundant   service   by   placing   one   telecommunications   switching  processor at the new Community Center and the other in the new data center. This would provide   two different feeds/routes from the vendor for telecommunication services. Former Community Center Evaluation The following addresses the above recommendations in reference to utilizing the former Community Center  as the City's new data center. Location network centralized Does not provide optimum distance for fiber runs between  the   various   City   sites.   Current   estimates   for   fiber  connectivity to the network are $435,000 to $450,000.   Location within network zero latency Is within tolerance for zero network latency.

Above the 100 year flood plain Meets this requirement.

One story with loading dock One story requirement met, however would need loading  dock   and   concern   of   floor   to   ceiling   height   due   to   the  necessity for a raised floor for the computer room.

(6)

Access to multiple vendor infrastructure Access to communication vendors services currently being  evaluated.

• Bright   House   data   circuits,   $6000   to   relocate  service

• Verizon voice circuits, still waiting on a response • Verizon data circuits, still waiting on a response Capable of multiple power grids Access to redundant power grids not determined at this 

time (determined by Progress Energy).

Expandable Refurbishing   the   entire   building   would   allow   for   this  capability,   but   add   recurring   cost   for   unused   portion   of  building.

Allow for removal of “Hut” Instead of eliminating the Hut, the network would have an  increased   reliance   on   the   Hut,   subsequently   requiring  additional capacity, equipment and building maintenance. Allow for long­term occupancy This would require preserving the current land foot print 

and impact future economic development in downtown. Install buried fiber optics to new building Can be achieved, however cost to install fiber to this site 

has a premium of about 20% due to obtaining permits to  utilize   (cross   underneath)   railroad   right­of­way   and  increased distances to other City locations. 

Activate   new   Community   Center   as   a 

switching hub Could be done, but not feasible at this time due to cost. Create   telecommunication   redundancy   by 

installing two new switches Could   be   done,   but   may   be   near   maximum telecommunications   tolerances   in   order   to   achieve  optimum performance.

Community Development

Historical Preservation Advisory Committee (HPAC)

The   HPAC   discussed   the   former   Community   Center   at   their   retreat   of   March   10,   2011   (see   attached   minutes). Three of the five HPAC members were in attendance at the meeting, and two members of the   Largo Historical Society (LHS) participated in the Community Center discussion.

It  was  conveyed  to  the  HPAC   by  staff  that  the  City  Commission   requested   they  discuss   the  possible  historical significance of the former Community Center located at 65 4th Street NW. The committee agreed  to use the following criteria, provided by staff, to guide their evaluation of the historical significance of the   building. • The structure is the site of a significant local, state or national event; or • The structure associated in a significant way with the life or activities of a person(s) or institution(s)   of importance in local, state, or national history; or • The structure embodies the distinctive characteristics of an architectural style, historical period,  method of construction or is the work of a master builder, designer or architect whose individual   work has influenced the development of the nation, state of Florida, Pinellas County or Largo; or • The structure is  associated with distinctive elements of the cultural,  social, political,  economic, 

scientific, religious, prehistoric, or architectural history that have contributed to the pattern of history   in the community, the county, west­central Florida, the state or nation; or  • The site has yielded or is likely to yield information important to the pre­history or history of the  nation, the State of Florida, Pinellas County or Largo; or • The structure is listed or has been determined eligible for listing in the National Register of Historic   Places.  In addition to the evaluation criteria, the HPAC was also provided with a brief background report on the  building, based on research into City records. This report noted that the original building on the site was built  

(7)

in the 1930s through the Works Progress Administration by the Civilian Conservation Corps. A construction  project completed in the 1970s expanded the footprint of the original building. An electrical fire in 1988  destroyed most of the original structure, and a new building (the multipurpose room portion) was built on the   footprint of the original structure.  The HPAC members and the LHS members agreed that the building itself is not historically significant since  it was primarily reconstructed in the late 1980s (a few people noted that the stage inside the building could   be a part of the original structure). However, they did note that the site of the building does have cultural and  social   significance,   since   it   has   been   a   hub   of   community   activity   for   the   past   70   years.   Several   in   attendance related that they had personal memories associated with the location. The group also raised  concerns about demolishing another building in the traditional downtown area and losing a community   space.   They   therefore   recommended   that   future   redevelopment   should   reflect   the   cultural   and   social  significance of the site and draw people to the downtown. In summary, the HPAC consensus was that the Community Center currently is not a historically significant   structure. Although members felt that the structure is not historically significant, their recommendation is that  the City embrace cultural uses in the downtown, including an appropriate re­use in the redevelopment area   to provide a social and cultural outlet that brings people downtown. For a more detailed record of the  discussion, meeting minutes have been attached. Economic Development Over the past ten or more years, the City of Largo has purchased sites in and around the 4th Street  Community Center. Many of the sites were obtained in order to provide large tracts of land for future   redevelopment in the traditional downtown area. From previous public­private partnerships (Hampton Inn  and West Bay Village), staff has learned that larger, single­owner parcel sites are better opportunities for a   developer to consider in redeveloping in an urban area. This is the case in Largo as well as other cities in  Pinellas County that are redeveloping their traditional downtowns. The recent update of the West Bay Drive Community Redevelopment Plan envisions higher densities and  whole block redevelopment that provides an active urban environment in the District. The assembly of  individual parcels into large parcels (and full blocks when possible) assists in meeting the Plan's objectives.  The Community Center site comprises just under one­half of a city block, and the building is part of a larger  area of assembly that is bordered by a full city block to the west, 3/4ths of a city block to the north, and more   than one­half of the block to the east. In all, the City owns approximately four (4) acres of land on four  contiguous blocks. The goal for redevelopment of the downtown is also shared by a community partner in business growth, the  Largo Mid­Pinellas Chamber of Commerce. In a letter to Mayor Gerard (attached), the Chamber's Board of   Directors states its support for the demolition of the Community Center in order to “provide a shovel­ready   opportunity” for a developer, since the facility is an integral part of the City's land assembly activities. City   staff concurs with this assessment and feels that cleared land is the most marketable way to redevelop the   area. The intersection of 4th Street and West Bay Drive is a desirable location for developers because it is a   signalized intersection. The signalization provides better access for larger projects and attracts a higher   quality tenant to the location. In addition to the signalized intersection, this area along West Bay Drive has   some of the highest traffic counts for a secondary roadway in Pinellas County. The traffic count figures and   the signalized intersection lend to the marketability of the area that includes the old Community Center  building.

The   economic   conditions   that   started   in   2008   have   slowed   market   interest   in   redevelopment   of   the  downtown   area.   Retail   development,   business   expansions   and   new   home   construction   have   slowed  significantly, and in some cases have almost come to a stop. West Bay Village has been affected both in   housing resale and the vacancy rates in the commercial properties. Real estate conditions are improving,  however, with a focus on urban redevelopment over suburban development where the infrastructure is in 

(8)

place and the area demographics are known and not subjective.

Community Development staff have been promoting the city­owned parcels to developers and end users at  the various events that they have attended over the past two years. Developers and relocation experts are  now more active in site selection than in the previous two years. Interest in City­owned properties downtown   is beginning to increase, and staff continues to promote the parcels as redevelopment opportunities for a   public­private   partnership.     Staff   will   be   discussing   the   proposed   redevelopment   plans   for   City­owned  properties at the June 14, 2011 City Commission Work Session.

Attachments:

Correspondence – McCarthy & Associates, Inc., March 25, 2005

Meeting Minutes – Historical Preservation Advisory Committee, March 10, 2011 Correspondence – Largo Mid­Pinellas Chamber of Commerce, March 8, 2011

(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)

Former Community Center Executive Summary The FY 2011 Budget includes $40,000 for planned demolition of the former Community Center on 4th Street  following completion of the new Community Center on Alternate Keene Road.   At the City Commission  Meeting of March 1, 2011, the City Commission postponed action on the award of demolition contract for the  former Community Center building.  The City Commission requested staff consider the reuse of the building  as a new IT Data Center, housing computer servers and telecommunications equipment for the City.  The   City Commission also requested input from the City's Historical Preservation Advisory Committee (HPAC)  and the Historical  Society  as to whether the building should be preserved due to its possible  historic   significance.  

Staff   has   obtained   information   from   the   Public   Works,   Information   Technology   (IT),   and   Community  Development   Departments   related   to   the   City   Commission's   request,   and   the   HPAC   has   convened   to  discuss this issue.  Based on the information obtained, it is not recommended that the City pursue use of  this building as an IT Data Center.  Locating an IT Data Center at this site does not best meet the needs of   the IT Department.  Based on the size and current structural rating of the building, substantial modifications  would be required that make the cost of retrofitting this building equal to or greater than new construction   east of Alternate 19/CSX railroad tracks, in closer proximity to other major City facilities.  Additionally, reuse  of the building (in whole or in part) will disrupt the parcel assembly that has taken place over the past   decade for the purposes of downtown redevelopment in accordance with the West Bay Drive–Community  Redevelopment District Plan.  The Chamber of Commerce has submitted correspondence supporting the  demolition   of   the   former   Community   Center,   and   the   HPAC   has   stated   that   the   structure   has   been   substantially modified to where the building itself does not have historical significance in accordance with   historical preservation criteria.   It is staff's recommendation to proceed with the demolition of the former   Community Center building and subsequently market the property for redevelopment as will be discussed at  the upcoming City Commission Work Session on June 14, 2011. Public Works In March 2005, Facilities Management contracted with McCarthy and Associates to perform a preliminary  structural evaluation of the building.  At the time of the evaluation, the former Community Center consisted   of the original building and a subsequent addition that was built to replace part of the facility that was   destroyed by a fire. The addition/renovation was completed in 1990. The structural analysis was performed  on both the multi­purpose room addition and the renovated one story building. The findings of the report   from the structural evaluation are summarized below, and a copy of the report is attached: Original building (west end, renovated 1990) • One story masonry structure with a flat roof.  • Roof is constructed with steel beams, bar joists and metal deck. • Original drawings were not available limiting ability to calculate design capacity of the structure. Building addition (east end)  • There does not appear to be any vertical reinforcement of the masonry load bearing walls.

• The   roof   structure   consists   of   pre­engineered   wood   trusses,   plywood   sheeting,   and   metal   tile  shingles.  • Wood trusses are secured to a wood top plate with a light gauge metal hurricane clip of minimal   capacity. • Based on this review, the addition does not appear to meet wind load criteria required by the current  (2005) building code. • Note: Building codes and wind load criteria have been revised since this study was completed. The current building is approximately 18,000 square feet in size. Facilities Management estimates the costs   to harden the structure to current building codes and 150+ mph wind loads (required for a data center) to be   $2 million. This figure is based on cost estimates developed to harden the Police Department building,   which is approximately the same size building footprint (15,000 sf). 

(18)

Other issues to take into consideration: • The bid for demolition was opened on February 10th and is valid for 90 days; extension beyond 90   days would require a request from the City for the contractor to hold pricing for additional time. • No building maintenance, utility expenses or custodial budget was included for this facility for FY  2011, nor anticipated for FY 2012 and beyond.  • All utilities to the building have been disconnected and would require several thousand dollars to re­ establish service. • The building is currently unconditioned (no air conditioning) which will cause it to deteriorate more  rapidly due to heat and humidity intrusion. • Several items have been removed from the building for re­use at other facilities prior to demolition,   including the automatic transfer switch and diesel fuel for the generator, automatic door openers,   drinking fountains, etc. • The environmental report generated as part of the demolition identified approximately 18,000 sf of   mastic (floor tiles and mirror adhesive) that contain asbestos. Any renovation to the building would  include abatement costs to remove the asbestos prior to reuse. Information Technology Evaluation of the former Community Center as a potential data center resulted from development of basic  minimum requirements and recommendations by City staff, without the use of consultants that specialize in  this capacity. Communication vendors were contacted for budgetary estimates of moving their service to the  former Community Center. The cost of moving the physical equipment was not obtained, as the actual   process of moving was not evaluated. The initial relocation would only include the City Hall computer room,  City Hall telecommunications room, and the Infrastructure Division of IT (not the entire IT Department). This   evaluation is from a technology perspective only; issues of building condition, economic development, and  historical significance were handled by other departments.  Reason for Relocation: The City needs to relocate its main computer room and telecommunications equipment  from the City Hall   building to a secure building able to withstand a Category 5 storm event, creating a new data center, in order  to preserve technology and communications during a disaster. The estimated floor space needed for the  relocation is 2,000 to 3,000 square feet.  Current Network Environment: The City Hall building serves as the primary computer, telecommunications and switching hub, from which  all data and communications pass through. The Largo Public Library and Environmental Services both have   secondary end­point computers room, not on the City network.   The Library computer room serves the   Library   Patron   Network,   and   the   Environmental   Services   computer   room   serves   the   Wastewater  Reclamation Facility (WRF) monitoring control system. The City possesses a stand­alone switching hub  located in Largo Central Park, referred to as the "Hut".   This small building, located between Seminole   Boulevard and the large tunnel of the Largo Central Park Railroad, is deemed the weakest link in the entire  City technology network due to its physical location, the building structure, and its unprotected proximity to   Seminole Boulevard. All other buildings on the City network are considered end­points. The new Community  Center (currently an end­point) was designed and built to be used as a backup computer room in case the  City Hall building became unusable (providing the computer equipment was usable post disaster). With the backup computer room in the new Community Center, plans were being drafted to connect (via   fiber optics) the new Community Center to other City emergency operations buildings to create a redundant   network loop for disaster planning. This would eliminate the need for the City Hall building in order to   establish connections to other City emergency operations buildings should the new Community Center   backup computer room be activated. At this time, should the new Community Center be activated as the   City's computer room due to City Hall being unusable, delivery of computer services to other City buildings  may  not  be  possible,  as  all  network  connectivity  currently  requires  connection   to  City  Hall.  Telephone  services   to   emergency   operations   buildings   would   be   limited   to   single   business   lines   installed   in   the  emergency operations buildings, should City Hall become unusable. 

(19)

Opportunity Considerations:

With the relocation of the City's computer room and telecommunications equipment to a new data center,  consideration should be given to strengthening the City network, minimizing stand­alone hub points, and  long­term development of a redundant fiber network loop for continuity of technology and communications in  the   event   of   a   disaster.   These   considerations   would   result   in   long­term   financial   savings   through   the  reduction of physical equipment and building maintenance. The following items should be considered in  determining the location of the site for a new data center. • The physical location should be “network centralized” (i.e., located in the middle of the majority of  computer and telecommunications usage) in order to minimize fiber runs between sites. • The physical location should be within an area of “network zero latency” in order to minimize the use  of remote client computing software. This is a bandwidth issue, in where a zero latency area is  considered non­interruptable. • The physical location should be above the 100 year flood plain. • The building should be one story, eliminating the cost associated with second floor weight load  requirements and special elevators. A loading dock should be provided.  • The physical location should have easy access to multiple vendor's communications infrastructure in  order to minimize build out cost to the new data center. • The physical location should be capable of providing access to multiple power grids, and preferably  a hospital grid (which are the first to be turned on after a storm event).   • The building should be easily expandable to allow for technology growth.  Consideration could be  provided for inclusion of other local government data centers. • The physical location should allow for the removal of the stand­alone switching hub (“Hut”) in order   to reduce the number of “hops” (times data must travel through a switch or router) in the network,   equipment requirements, and building maintenance.  Centrally locating a new facility in relation to  other existing facilities will subsequently reduce capital equipment replacement and operating costs.

• The   physical   location   should   allow   for   long   term   permanent   occupancy   in   order   to   minimize  disruptions to City business and aggregate cost over a long time period.

The following non­location related items that should be considered in conjunction with the computer room  and telecommunications equipment relocation to a new data center are:

• All new fiber optic runs should be buried to ensure maximum survivability.

• Activate the new Community Center as a switching hub, providing three active switching hubs 

connected   by   two   fiber   legs   (Community   Center,   new   IT   Server   Building,   and   Public   Works  Administration). Only one future fiber run would then be required to complete a redundant fiber loop.   With appropriate equipment, the redundant fiber loop could become a self­healing network, whereby  if one switching hub were to fail, city­wide communications would not be disrupted.

• Create   telecommunications   redundant   service   by   placing   one   telecommunications   switching  processor at the new Community Center and the other in the new data center. This would provide   two different feeds/routes from the vendor for telecommunication services. Former Community Center Evaluation The following addresses the above recommendations in reference to utilizing the former Community Center  as the City's new data center. Location network centralized Does not provide optimum distance for fiber runs between  the   various   City   sites.   Current   estimates   for   fiber  connectivity to the network are $435,000 to $450,000.   Location within network zero latency Is within tolerance for zero network latency.

Above the 100 year flood plain Meets this requirement.

One story with loading dock One story requirement met, however would need loading  dock   and   concern   of   floor   to   ceiling   height   due   to   the  necessity for a raised floor for the computer room.

(20)

Access to multiple vendor infrastructure Access to communication vendors services currently being  evaluated.

• Bright   House   data   circuits,   $6000   to   relocate 

service

• Verizon voice circuits, still waiting on a response

• Verizon data circuits, still waiting on a response Capable of multiple power grids Access to redundant power grids not determined at this 

time (determined by Progress Energy).

Expandable Refurbishing   the   entire   building   would   allow   for   this  capability,   but   add   recurring   cost   for   unused   portion   of  building.

Allow for removal of “Hut” Instead of eliminating the Hut, the network would have an  increased   reliance   on   the   Hut,   subsequently   requiring  additional capacity, equipment and building maintenance. Allow for long­term occupancy This would require preserving the current land foot print 

and impact future economic development in downtown. Install buried fiber optics to new building Can be achieved, however cost to install fiber to this site 

has a premium of about 20% due to obtaining permits to  utilize   (cross   underneath)   railroad   right­of­way   and  increased distances to other City locations. 

Activate   new   Community   Center   as   a 

switching hub Could be done, but not feasible at this time due to cost. Create   telecommunication   redundancy   by 

installing two new switches Could   be   done,   but   may   be   near   maximum telecommunications   tolerances   in   order   to   achieve  optimum performance.

Community Development

Historical Preservation Advisory Committee (HPAC)

The   HPAC   discussed   the   former   Community   Center   at   their   retreat   of   March   10,   2011   (see   attached   minutes). Three of the five HPAC members were in attendance at the meeting, and two members of the   Largo Historical Society (LHS) participated in the Community Center discussion.

It  was   conveyed  to the  HPAC  by  staff  that  the  City   Commission  requested  they  discuss  the  possible  historical significance of the former Community Center located at 65 4th Street NW. The committee agreed  to use the following criteria, provided by staff, to guide their evaluation of the historical significance of the   building. • The structure is the site of a significant local, state or national event; or • The structure associated in a significant way with the life or activities of a person(s) or institution(s)   of importance in local, state, or national history; or • The structure embodies the distinctive characteristics of an architectural style, historical period,  method of construction or is the work of a master builder, designer or architect whose individual   work has influenced the development of the nation, state of Florida, Pinellas County or Largo; or

• The  structure is associated with  distinctive elements  of the cultural, social,  political, economic, 

scientific, religious, prehistoric, or architectural history that have contributed to the pattern of history  in the community, the county, west­central Florida, the state or nation; or  • The site has yielded or is likely to yield information important to the pre­history or history of the  nation, the State of Florida, Pinellas County or Largo; or • The structure is listed or has been determined eligible for listing in the National Register of Historic   Places.  In addition to the evaluation criteria, the HPAC was also provided with a brief background report on the  building, based on research into City records. This report noted that the original building on the site was built  

(21)

in the 1930s through the Works Progress Administration by the Civilian Conservation Corps. A construction  project completed in the 1970s expanded the footprint of the original building. An electrical fire in 1988  destroyed most of the original structure, and a new building (the multipurpose room portion) was built on the   footprint of the original structure.  The HPAC members and the LHS members agreed that the building itself is not historically significant since  it was primarily reconstructed in the late 1980s (a few people noted that the stage inside the building could   be a part of the original structure). However, they did note that the site of the building does have cultural and  social   significance,   since   it   has   been   a   hub   of   community   activity   for   the   past   70   years.   Several   in  attendance related that they had personal memories associated with the location. The group also raised  concerns about demolishing another building in the traditional downtown area and losing a community   space.   They   therefore   recommended   that   future   redevelopment   should   reflect   the   cultural   and   social  significance of the site and draw people to the downtown. In summary, the HPAC consensus was that the Community Center currently is not a historically significant   structure. Although members felt that the structure is not historically significant, their recommendation is that  the City embrace cultural uses in the downtown, including an appropriate re­use in the redevelopment area   to provide a social and cultural outlet that brings people downtown. For a more detailed record of the  discussion, meeting minutes have been attached. Economic Development Over the past ten or more years, the City of Largo has purchased sites in and around the 4th Street  Community Center. Many of the sites were obtained in order to provide large tracts of land for future   redevelopment in the traditional downtown area. From previous public­private partnerships (Hampton Inn  and West Bay Village), staff has learned that larger, single­owner parcel sites are better opportunities for a   developer to consider in redeveloping in an urban area. This is the case in Largo as well as other cities in  Pinellas County that are redeveloping their traditional downtowns. The recent update of the West Bay Drive Community Redevelopment Plan envisions higher densities and  whole block redevelopment that provides an active urban environment in the District. The assembly of  individual parcels into large parcels (and full blocks when possible) assists in meeting the Plan's objectives.  The Community Center site comprises just under one­half of a city block, and the building is part of a larger  area of assembly that is bordered by a full city block to the west, 3/4ths of a city block to the north, and more   than one­half of the block to the east. In all, the City owns approximately four (4) acres of land on four  contiguous blocks. The goal for redevelopment of the downtown is also shared by a community partner in business growth, the  Largo Mid­Pinellas Chamber of Commerce. In a letter to Mayor Gerard (attached), the Chamber's Board of   Directors states its support for the demolition of the Community Center in order to “provide a shovel­ready  opportunity” for a developer, since the facility is an integral part of the City's land assembly activities. City   staff concurs with this assessment and feels that cleared land is the most marketable way to redevelop the   area. The intersection of 4th Street and West Bay Drive is a desirable location for developers because it is a   signalized intersection. The signalization provides better access for larger projects and attracts a higher  quality tenant to the location. In addition to the signalized intersection, this area along West Bay Drive has   some of the highest traffic counts for a secondary roadway in Pinellas County. The traffic count figures and   the signalized intersection lend to the marketability of the area that includes the old Community Center  building.

The   economic   conditions   that   started   in   2008   have   slowed   market   interest   in   redevelopment   of   the  downtown   area.   Retail   development,   business   expansions   and   new   home   construction   have   slowed  significantly, and in some cases have almost come to a stop. West Bay Village has been affected both in   housing resale and the vacancy rates in the commercial properties. Real estate conditions are improving,  however, with a focus on urban redevelopment over suburban development where the infrastructure is in 

(22)

place and the area demographics are known and not subjective.

Community Development staff have been promoting the city­owned parcels to developers and end users at  the various events that they have attended over the past two years. Developers and relocation experts are  now more active in site selection than in the previous two years. Interest in City­owned properties downtown  is beginning to increase, and staff continues to promote the parcels as redevelopment opportunities for a   public­private   partnership.     Staff   will   be   discussing   the   proposed   redevelopment   plans   for   City­owned  properties at the June 14, 2011 City Commission Work Session.

Attachments:

Correspondence – McCarthy & Associates, Inc., March 25, 2005

Meeting Minutes – Historical Preservation Advisory Committee, March 10, 2011 Correspondence – Largo Mid­Pinellas Chamber of Commerce, March 8, 2011

(23)
(24)
(25)
(26)
(27)
(28)
(29)

References

Related documents

04/11/21 General Monthly Meeting/Board Meeting 05/02/21 General Monthly Meeting/Board Meeting 06/13/21 General Monthly Meeting/Board Meeting 07/11/21 General Monthly

Parasitology Information SPECIMEN DATA Specimens Collected: 3 Date Collected: 05/10/2021 Date Received: 05/11/2021 Date Reported: 05/12/2021 Methodology: Microscopy

Solving the resulting linear program for Example 4.1 gave an optimal value of 873 248, so strictly larger than the (true) optimum (838 493) and strictly smaller than the optimal

Changes in service use before and following an inpatient rehabilitation stay were examined using quantitative outcome measures that included: (1) the number of admissions to

[r]

The empirical evidence supports the cointegration hypothesis of Portuguese rates and the “puzzle” well known in the literature of the EH: although forecasts of short-term rates

Specifically, we hypothesized a mediation model in which: parental solicitation drives to youth disclosure; this would strengthen family communication, which in turn would

Eklundh 2016; Kioupkiolis 2018): for some, the likes of Occupy and the Indignados pointed to a non-representative logic of ‘horizontal assemblies’ (Hardt and Negri 2012; Sitrin