Cross-border Economic
Cooperation
András Rákóczi Managing president
KIÚT Regional Development Association
STRATEGIC POSITION
IN THE NEW EUROPE
STRATÉGIAI PONTOK AZ ÚJ EURÓPÁBAN:
IMPORTANT BORDER CROSSING POINTS IN THE EUROPEAN UNION
PÁRATLAN ADOTTSÁGOK - STRATÉGIAI ELHELYEZKEDÉS
OUTSTANDING ADVANTAGES - STRATEGIC POSITION ELHELYEZKE-DÉS: EGYIK LEGFONTOSABB KELET-NYUGATI KÖZLEKEDÉSI FOLYOSÓ MENTÉN (V. sz. Transz-Európai Folyosó) LOCATED ON A MAJOR TRANSPORT CORRIDOR (No.5 Pan-European corridor
ZÁHONY ENSURES
EUROPEAN
C
ONDITIONS IN THE
NEIGHBOURHOOD OF
THE EASTERN
MARKETS
Railway on the border of HU-SK-UA
Vehicular heavy traffic in Záhony
(trucks/year) 0 20000 40000 60000 80000 100000 120000 140000 1998199 9 200 0 200 1 200 2 2003200420052006200720082009 belépő kilépőRailway heavy traffic in Záhony
The volume of the railway transit in Záhony
0 1000 2000 3000 4000 5000 6000 ezer tonna Bejövő Kimenő
Trimodális logisztika
150 thousand trucks/ year
Logistic center
„KIÚT” REGIONAL DEVELOPMENT ASSOCIATION
Why was the KIÚT Regional Development
Association organized?
•
1990 – year of changes, Comecon broke
•
EU orientation in the economic connection.
•
The railway transit between Hungary-Ukraine
fell back
1990 – 15 million tons, 7000 person
2000 – 6 million tons, 2000 person
•
We are searching for expedient from this
„KIÚT” REGIONAL DEVELOPMENT ASSOCIATION
The Association was organized on 10th
of February 2000:
•
15 economic entity (
Co.’s & Ltd’s
)
•
3 Sub-regional association (31 local
government)
•
21 individual
Aims:
developing of vehicular, regional
development, logistic, economic,
A fejlesztési terület The development Area
MODERN, INTEGRATED LOGISTIC SERVICES BY THE PRIVATE COMPANIES
rail transport
rail-rail and rail-road transhipment storage customs warehouse packaging ROLA terminal Distribution centres Row material processing TRANSHIPMENT OF BULK GOODS LOADING BY CRANE LOADING BY SMALL EQUIPMENT HANDLING LIQUID CARGO CHANGING OF AXLES RAKTÁROZÁS WAREHOUSING SERVICES
The competitive Záhony
Geographical aptitude
Záhony and its area includes 94 km2
Functioning structure (wide gauge railway 150 km,
european gauge railway 300 km)
Qualified human resources Competitive transport fees Low lighterage
Customs
Other services (banks, insurance companies,
service stations)
FEJLETT ÜZLETI INFRASTRUKTÚRA ADVANCED BUSINESS INFRASTRUCTURE LOGISZTIKAI KÖZPONT LOGISTIC CENTRE IPARI PARK INDUSTRIAL PARK TERÜLET-FEJLESZTÉSI TÁRSASÁGOK REGIONAL DEVELOPMENT COMPANIES BANKI INFRASTRUKTÚRA BANKING INFRASTRUCTURE SZÁLLÍTMÁNYOZÓ CÉGEK TRANSPORTATION COMPANIES VÁMÜGYNÖK-SÉGEK CUSTOMS AGENT ACTIVITY
Configuration Plan
1. Establishment of an intermodal public industrial and logistical area
It is necessary to establish a 160ha industrial and logistical park in the area of Fényeslitke – Komoró in favor of the realization of the specific investor intentions
(24 MILLION EURO)
Goals of the project:
• Construction of wide-gauge and standard
European-gauge railway tracks until the border of the site
• Drinking water and municipal sewage network • Establishment of facilities to remove surface
water
• Establishment of telecommunications network • Construction of electricity and gas network
Industrial site
Actual stage of the project:
• The proprietary rights of the
RFH co. ltd. is registered
• The public procurement
procedure of the construction of municipal water supply
facilities, internal transport infrastructure and electricity is closed
Execution deadline: 29th August 2010
• The selection of the rail
infrastructure building contractor is in progress
Fullfilment deadline: 31st May 2010
2. a. Rail-tracks to be renewed
Renewing of 43 km wide gauge railway 30 million euro
2. b. Renewal of traffic way - 27 km 85 million EUR
Záhony and its Area flagship project
3. Supporting the small and medium enterprises operating
in the area
The elements of the project
Amount of state support: 3,1 billion Ft, the enterpreteneurs give 2 billion Ft own resources hereby 38 project were executed.
Záhony and its Area flagship
project
4. Development of secondary and high-level education helping
industrial-logistics and economic life, according to the needs of the measurable economic activities
(2 million Euro)
The elements of the project
Záhony and its Area flagship project
5. Complex international marketing, economic and
traffic-diplomatic programme (3 million EUR)
The elements of the project
Economic geography Worksla-Steel: Transport
Transporting steel block to Zahony By railway via Csop
By ship via Juzhnyi port forward to Duna-Tisza (Tisza is not shipped yet)
Южный
Чоп Комсомольск
Загонь
Poltava Ore processing Factory Worksla-Steel steel processing Factory Загонь Чоп Дунай Загонь
The sales markets of the products of the
companies
Eastern-southern-European countries,
Ukraine, Turkey, Greece and other states are the markets
of the products of the Worksla-Steel
Hungary
Using technological chain means
advantage in the car, machine and ship fabricated factory at
the Middle-east and the South-European
companies.
Загонь
Transportation ways and length of time
Szállítási útvonalak és id
ő
tartamok
Záhony
Further development plans
Establishing logistic center between Záhony and
Tiszabezdéd (private investment)
Variable gauge between Hungary-Ukraine
Creating joint industrial park on the
Hungarian-Ukrainian border
Development of transport links in the Baltic and
Black Sea regions
38 38
C
D
Effect of the study’s examination to clearway
of Záhony and its area
M34
M34 M34
M340 M340
The joint Hungarian-Slovakian-Ukrainian
Three border bridge variation is not Soluble economically (yellow line)
The „C” variation got into the development plans
Köszönöm megtisztel
ő
figyelmüket!
KIÚT Regional Development