Offshore Pile Testing Campaign Wikinger
Pile driving analysis, static and dynamic load tests in 40m water depth
Jan Fischer, Fichtner Water & Wind GmbH, Hamburg, Germany Rob van Dorp, Allnamics BV, Den Haag, The Netherlands
Wikinger OWF
Developer
Iberdrola Renewables Deutschland GmbH The Windfarm
Turbine: 70 Adwen AD 5-135 (5 MW, Rotor-, 135 m) Project Capacity: 350MW
Foundation: Jackets
Water depth: 36 m to 42 m Pile testing campaign
Execution: Bilfinger Marine & Offshore Systems GmbH Date: 2014/2015
Installation
Company: Boskalis and Volker Stevin Start: spring 2016
Slide 2 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Location
Slide 3 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Pile testing campaign
Slide 4 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
General
Only very little information exists about the skin friction and toe
resistance behavior of typical Baltic Sea soils as glacial till and chalk.
Why
Gain soil data information for
driveability studies and for bearing capacity calculations
How
Extensive offshore pile testing campaign including pile driving analysis (PDA), dynamic load tests (DLT) and pull out static load tests (SLT-T)
Source: ECSMGE 2015, Barbosa et al.
Special Task:
Testing underwater, in depths of approx. 40 m
Fichtner / Allnamics
Slide 5 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Drivability predictions / hammer selection
Producing the deep sea operation sensors, cables etc. (for PDA and DLT)
Development of method statements for the different investigation phases
Pile driving analysis / dynamic load tests (at altogether six piles)
Signal matching (using AllWave-DLT)
Back calculation (simulation) of the pile driving using the results from the pile driving protocols and the dynamic load tests
Execution of the static tension pull out test (SLT-T) in terms of correct application of the different load steps
Interpretation of the static tension pull out test
Restrike dynamic load tests including signal matching
Interpretation of the soil setup on the basis of the results from the different phases
etc.
Phase I
Installation of nine piles at three different locations, including pile driving analysis (PDA) and dynamic load testing (DLT)
Slide 6 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Location Water depth [m MSL]
Diameter [m]
Pile length
[m]
Penetration depth at the end
of driving [m BSF]
WK-a 40.0 1.37 21.8 16.8
WK-b 38.2 1.37 35.7 30.7
WK-c 36.6 1.37 36.0 31.0 MV Lone: DP2 Vessel by SAL
Test piles:
Phase I - Equipment
Slide 7 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Triplex Template (Pile guiding frame)
Pile Hammer
(MENCK MHU 800S)
Phase I - Video
Slide 8 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Instrumentation
Slide 9 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
• Two equipped test piles per location (for SLT and DLT)
• Two separate sets per pile
• Each set consisting of two strain transducers and two
acceleration transducers
• Each 'pair' (strain and acceleration) placed
diametrically opposed on the pile shaft
• Special deep sea sensors and cables
Data recorder (PDR) Instrumentation and testing
Phase II: Execution of one static tension pull out test (SLT-T) and one dynamic re-strike test (DLT) per test location.
More than ten weeks after pile installation as part of Phase I
Phase II - Equipment
Slide 10 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Reference frame (SLT-T) Displacement measurement
Loading beam (SLT-T) Force application
Hammer (DLT)
Phase II - Video
Slide 11 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
page 12
Slide 12 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Locking Tool Loading Beam and Reference Frame
Phase II – SLT-T
page 13
Slide 13 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
Phase II – SLT-T
Phase II – Results
Slide 14 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
0.0 0.2 0.4 0.6 0.8 1.0 1.2
0 0.2 0.4 0.6 0.8 1 1.2
normalized displacement [-]
normalized Force [-]
Statische Probebelastung
Load-Displacement
Static tension pull out test (SLT-T)
0.0 0.2 0.4 0.6 0.8 1.0 1.2
0.0 0.2 0.4 0.6 0.8 1.0 1.2
normalized force [-]
normalized time [-]
Allnamics strain gauges (mean value) Load cells (cumulative value)
-0.4 -0.2 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4
0 10 20 30 40 50 60
normalized force [-]
time [ms]
DLT restrike
Strain transducer 1 Strain transducer 2
Acceleration trancducer 1 (v*Z) Accerleration trancducer 2 (v*Z)
Restrike dynamic load test
Summary
Slide 15 Offshore Pile Testing Campaign Wikinger l Jan Fischer & Rob van Dorp l Geotechniekdag 2015
• The entire offshore testing campaign can be considered a huge success, especially since tests of this nature had not been performed before
• During the execution of the work in Phase I and Phase II, all tests could be carried out with high accuracy and high quality data
• The obtained test results led to a detailed understanding of the skin friction and toe resistance values for large diameter offshore pipe piles in typical Baltic Sea soils, i.e. glacial till and chalk
What is next
• On the basis of the obtained test results, the installation of the wind turbine piles was predicted by us
• The results were used e.g. for pile driving fatigue calculations, as an important value for the pile design
Thank you for your attention
Fichtner Water & Wind GmbH Hammerbrookstrasse 47b D-20097 Hamburg
Tel. +49 40 300673 – 0
[email protected] www.fww.fichtner.de
Allnamics BV Waterpas 98 NL-2495 Den Haag Tel. +31 (0)882556264 [email protected] www.allnamics.eu
FICHTNER
WATER & WIND
FICHTNER
WATER & WIND