IPPs are Cost-Effective
Presentation to Joint Review Panel
of Site C EIS
December 10, 2013
(Summary of Written Submission on Nov. 25, 2013)
Philip K. Barton – Lawyer, Entrepreneur and Engineer.
Representing several IPP clients developing renewable projects in BC
Acted in past for developers, lenders and contractors in $500+ million of IPPs 22 MW ($65 million) Jamie Creek started in my basement: COD expect Q1 2014
Boughton Law – 50 lawyers in Vancouver
Focus on finance, mergers & acquisitions and litigation.
Steve Davis – IPP Consultant, Engineer, MBA
Past President of Independent Power Producers association of B.C. and developer of several IPP projects in B.C.
Presenters:
EIS overlooks Alternatives
Alternatives are more cost effective
Steve Davis & Associates Consulting Ltd.
3
IPPs have identified over 1,000 potential renewable projects in BC: 600 run-of-river projects;
400 wind projects;
40 biomass projects, and 16 geothermal projects.
BC Hydro’s 2013 Integrated Resource Plan (IRP) lists many projects with Unit Energy Cost (UEC) lower than Site C.
With limited time and resources, we have assembled a New Portfolio of projects which is more cost effective.
The IPP sector can quickly assemble and propose other new portfolios with lower costs and very small environmental impacts.
BC Hydro assessed 3 main portfolios:
Steve Davis & Associates Consulting Ltd.
Based on these specific portfolios, BC Hydro asserts that
Site C is the most cost-effective for BC’s future electricity
11 Site C EIS Technical Memo “Alternatives to the Project” (June 4, 2013)
BC Hydro
Clean
Generation
Block
51000 MW of
Pumped Storage
+
11 wind,
1 MSW,
1 ROR, and
1 Biomass
BC Hydro
Clean +
Thermal
Generation
Portfolio
500 MW of
Pumped Storage,
588 MW of SCGT
6MW:
PROJECT:
SOURCE:
488 MW
Revelstoke #6 (Upgrade)
Table 3-24 of IRP
220 MW
GMS #1-5 (Upgrade)
Table 3-24 of IRP
320 MW
Geothermal Projects in
Lower Mainland TR
Table 3-15 of IRP
33 MW
Municipal Solid Waste
Clean Generation Block
80 MW
Wood Biomass
Clean Generation Block
1141 MW
New Portfolio #1 with Capacity ~ 1,100 MW
Steve Davis & Associates Consulting Ltd.
7
All data is strictly from BC Hydro’s Documents (IRP & Technical Memo).
Steve Davis & Associates Consulting Ltd.
8
New Portfolio #1 delivers 5,109 GWh of energy
All data is strictly from BC Hydro’s Documents (IRP & Technical Memo).
Furthermore, we assert:
Steve Davis & Associates Consulting Ltd.
9
Site C AUEC = $110
$F2013/MWh
+$5
Sunk Costs
+$11
10% Cost Overrun
Revised Site C AUEC
= $126
$F2013/MWh
BC Hydro does not make these adjustments in its comparison of alternatives
Site C vs New Portfolio #1:
Steve Davis & Associates Consulting Ltd.
10
Adjusted Site C AUEC
AUEC Portfolio #1
(Rev+GMS+Geothermal)
$126 per MWh
>
$122/MWh
(All data from BC Hydro)
MW:
PROJECT:
SOURCE:
488 MW
Revelstoke #6 (Upgrade)
Table 3-24 of IRP
220 MW
GMS #1-5 (Upgrade)
Table 3-24 of IRP
294 MW
Simple Cycle Gas Turbine
(SCGT)
50% of SCGT from BC
Hydro Clean+Thermal
33 MW
Municipal Solid Waste
Clean Generation Block
80 MW
Wood Biomass
Clean Generation Block
1115 MW
New Portfolio #2 with SCGT Peaking Gas
delivers 1,115 MW
Steve Davis & Associates Consulting Ltd.
11
All data is strictly from BC Hydro’s Documents (IRP & Technical Memo).
New Porfolio #2 delivers 5,112 GWh of Energy
Steve Davis & Associates Consulting Ltd.
12
All data is strictly from BC Hydro’s Documents (IRP &
Technical Memo)
AUEC
=
$138/
MWh
Site C vs New Portfolio #2:
Steve Davis & Associates Consulting Ltd.
13
Revised Site C AUEC
Portfolio #2 AUEC
(Rev+GMS+SCGT)
$126 per MWh
or
$138/MWh
(All data from BC Hydro)
Still cost effective? Barely…
1. Data: New Portfolio is assembled from BC Hydro’s IRP.
2. Prices: Bid prices for IPPs will be lower than the UECs by BC Hydro.
3. Asset Lives: Actual for renewable IPPs are longer than the figures BC Hydro uses in their UEC calculations.
4. Cost Adjustments: BC Hydro imposes adjustments on IPPs that are too high or unnecessary: soft costs, freshet, time of delivery, etc.
5. WACC: BC Hydro imposes lower Weighted Average Cost of Capital
6. First Nations: FN oppose Site C; FN support many IPP projects across BC.
7. Construction Risks and Over-runs: FN opposition and construction boom will cause great risk to BC Hydro ratepayers (and BC taxpayers with public debt).
8. New Portfolio: Private sector is ready, willing and able to accept all development risk, financing risk, construction risk and operational risk.
9. Economic Development: Many IPP projects across BC vs. single mega-project.
10.Non-Firm Energy: IPPs average supply is $68/MWh (BCH 2012 Annual Rpt).
Additional Points:
Steve Davis & Associates Consulting Ltd.
IPP Cost Reductions vs Site C:
•
Deduct Income Tax payments to government
•
Deduct value of equity given to First Nations in IBAs
•
More efficient EPA contracts with comparable penalties
•
Consider non-firm energy as well as firm energy
Site C Cost Adders vs IPPs:
•
Remove Cost of Capital support from Province
•
Include Cost of equity during construction
•
Match Water License Terms (Max 40 years)
Total of Additional Adjustments = $20 - $40/MWh
(Net Reduction of IPP costs vs Site C costs)
Additional Cost Adjustments
(not yet quantified)
•
IPPs are Cost Effective
• Our Portfolio #1 has an AUEC that is 3% less than Site C.
• Renewable portfolios can deliver energy and capacity
• Our pricing analysis used BC Hydro data
• And included several conservative assumptions
•
Many new alternative portfolios can be created from the
1,000+ IPP projects identified – likely cheaper
•
Site C is not the most cost effective
•
Significant adverse environmental impacts are not justified
Conclusion:
Steve Davis & Associates Consulting Ltd.
APPENDIX
New Portfolios offer New Balance
Steve Davis & Associates Consulting Ltd.
18
Bill Bennett, Minister of Energy and Mines stated:
“Governments make decisions on balance,
and the balance in this case leads us to think this is the
best available source of a large amount of electricity,
and that justifies the environmental impact.”
Vancouver Sun – December 7, 2013