Risk Category
Risk Category
((P
Ph
ha
as
se
e
w
wiis
se
e))
C
CO
OS
ST
T//E
E..H
Hr
r
1
1 Tec
Techni
hnical
cal Ris
Risks
ks
Requirements
Requirements
Specifications
Specifications
Technology
Technology
Complexity
Complexity
Interfaces
Interfaces
Performance
Performance
Quality
Quality
Safety
Safety
Security
Security
2
2 Ex
Exter
ternal
nal Ris
Risks
ks
Contractors
Contractors
Sub-contractors
Sub-contractors
Suppliers
Suppliers
Regulatory
Regulatory
Market
Market
Customer
Customer
Weather
Weather
3
3 Org
Organi
anizat
zation
ional Risk
al Risks
s
Project dependencies
Project dependencies
Resources
Resources
Funding
Funding
Prioritization
Prioritization
Org. Breakdown Str
Org. Breakdown Str
Resp. Assigned Matrix
Resp. Assigned Matrix
4
4 Pro
Proj M
j Mgm
gmt R
t Risk
isks
s
Estimating
Estimating
Planning
Planning
Controlling
Controlling
Resource Utilization
Resource Utilization
Communication
Communication
Information
Information
Health/Safety
Health/Safety
RISK REGISTER
RISK REGISTER
Project Name:
Project Name:
Description of Risks
Description of Risks
Identified Risks/Triggers
Identified Risks/Triggers
Impact (+
Impact (+
Environment
Environment
5
5 Com
Comme
merci
rcial
al Ris
Risks
ks
Contractual
Contractual
Financial
Financial
Regulatory
Regulatory
Consents
Consents
Reputation
Reputation
P
Prro
ojje
ec
ct
t P
Ph
ha
as
se
e
D
DE
EL
LIIV
VE
ER
RA
AB
BL
LE
ES
S
C
CE
EO
O
Major deliverable/WP
Major deliverable/WP delivera
deliverables
bles
Responsibility Assignment Matrix - RAM
Responsibility Assignment Matrix - RAM
NAME OF THE PROJECT
C
Co
on
nttrro
oll
Q
Qu
ua
alliitta
attiiv
ve
e A
An
na
ally
ys
siis
s
T
TIIM
ME
E
Q
QU
UA
AL
LIIT
TY
Y
S
SC
CO
OP
PE
E
II//E
E
V
VH
H//H
H//M
M//L
L//V
VL
L
Risk
Risk
Owner
Owner
Project Manager:
Project Manager:
ve
Project Manager
A
B
C
D
E
P
Sr.Mgmt
% P
Consequence
Risk
%P x I
Thresholds
Time period (hr/dy)
Cost/Res hrs
Ph-1 I/c
Ph-2 I/c
Ph-3 I/c
Ph-4 I/c
Function Hd-1
F
ERMORMING ORGANIZATION
Priority/
Resource Buffer
Ranking
EV VAC-1 VAC-2 VAC-3 CPI SPI
CEO
Sr.
Proj
Function Hd-2
Function Hd-3
mgmt
mgr
List of potential
Common Risk
Responses
Causes
Positive Risk Strategies
Avoid/Transfer/Mitigate/Accept
Date of Review:
Phase
Team Members
Incharges
tion Heads
Negative Risk Strategies
Avoid/Share/EnhanceAcceptSTATUS REPORT &
ACTION PLAN
ncy Plans
Performing Organization
Team Members
Fallback (backup) Plan
Workaround Plan
WP-D
DAY
A
B
C
Total
%C
EV
AC
Rate
M.Hr.
M.Hr. M.Hr. M.Hr.
A.MHr.
Rs.
1
8
8
75%
6
8
2
8
8
3
8
10
18
4
8
10
6
24
5
8
10
6
24
6
10
6
16
7
10
6
16
8
6
6
9
6
6
10
6
6
BAC=
Planned
%P
6.1%
SV= EV-PV
-2
CV= EV-AC
-2
Completed
%C
4.5%
SPI= EV/PV
0.75
CPI= EV/AC
0.75
SV% SV/PV -25%
CV% CV/EV -33%
VAC-1
BAC-EACVAC-2
BAC-EACPHASE -A:
BACph PVph
WP
BAC
%P
PV
%C
EV
AMHr
A
500
80%
400
60%
300
375
500
400
B
600
75%
450
50%
300
325
1100
850
C
450
50%
225
45%
202.5
250
1550
1075
D
132
6.1%
8
4.5%
6
8
1682
1083
E
400
2082
F
350
2432
G
300
BAC=
2732
Actuals
Activities
Cum
Planned
%Pph 39.6%
SV= EV-PV -274.5
CV= EV-AC -149.5
Completed%Cph 29.6% SPI= EV/PV
75%
CPI= EV/AC
84%
SV% SV/EV -25%
CV% CV/EV -18%
VAC-1
BAC-EACVAC-2
BAC-EACPROJECT -A:
BACp
PHASE
PV
%Pph
PVp
%Cph
EV
AMHr
A
2732 39.6% 1083 29.6%
809
958
2732
B
3550
6282
C
2880
9162
D
3850
13012
Planned
%P
8.3%
SV= EV-PV -274.5
CV= EV-AC -149.5
Completed%C
6.2%
SPI= EV/PV 0.747
CPI= EV/AC 0.844
SV% SV/PV -25%
CV% CV/EV -18%
VAC-1
BAC-EACVAC-2
BAC-EACCalculating Risk in Project Network based on PERT calculation
ACTIVITY redecesso Optimistic ost Likel Pessimisticime Estimat Variance Std Dev
Start (o+4m+p)/6 A Start 10 22 22 20 4 2 B Start 20 20 20 20 0 0 C Start 4 10 16 10 4 2 D a 2 14 32 15 25 5 E b,c 8 8 20 10 4 2
F b,c 8 14 20 14 4 2 G b,c 4 4 4 4 0 0 H c 2 12 16 11 5.4 2.33 I g,h 6 16 38 18 28.4 5.33 J d,e 2 8 14 8 4 2 Finish j,i,f
43
33
5.745Assume Project Manager has commited 50 days to the customer, what are the chances of meeting the de
We need to calculate the value of 'Z' Z = (D-u)/Std Deviation D = Desired Project Com u = The critical time of th Z= 1.22 Std Deviation of the critic Z = The number of Std D
Refer Table A below, The probability Z of 1.22 (column 1.2 and .02) occurs .8888 or say 89%
We can also calculate backwards:
What deadline is consistent with a 95% probability of on-time completion?
Here the 'Z' value associated with 0.95 is 1.645 We know thatu is 43 days and Std Deviation is 5.745
D = u + Std Dev ( correspondence value of Z) 52.45
What are the chances that the non-critical Path c-h-I will make the project late?
Now D = 43, so we have Z= (43-39)/6.155 = 0.65
Now Z = .65 is associated with 0.74 of being on time, or 1-.74 = 0.26 chances of delaying the project
Duration Variance Std Dev
Project Duration =
39 37.9 6.155 Z= 0.65
Assuming that these two paths (a-b-j and c-h-I) are independent. What is the probability that both paths The probability is 0.50 x 0.74 = 0.37
TABLE - A: Cummulative (Single Tail) Probabilities of the Normal Probability Distributio
Z
0.00
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.0 0.5000 0.5040 0.5080 0.5120 0.5160 0.5199 0.5239 0.5279 0.1 0.5398 0.5438 0.5478 0.5517 0.5557 0.5596 0.5636 0.5675 0.2 0.5793 0.5832 0.5871 0.5910 0.5948 0.5987 0.6026 0.6064 0.3 0.6179 0.6217 0.6255 0.6293 0.6331 0.6368 0.6406 0.6443 0.4 0.6554 0.6591 0.6628 0.6664 0.6700 0.6737 0.6772 0.6808 0.5 0.6915 0.6950 0.6985 0.7019 0.7054 0.7088 0.7123 0.7157 0.6 0.7257 0.7291 0.7324 0.7357 0.7389 0.7422 0.7454 0.7486 0.7 0.7580 0.7611 0.7642 0.7673 0.7704 0.7734 0.7764 0.7794 0.8 0.7881 0.7910 0.7939 0.7967 0.7995 0.8023 0.8051 0.8078 0.9 0.8159 0.8186 0.8212 0.8238 0.8264 0.8289 0.8315 0.8340 1.0 0.8413 0.8438 0.8461 0.8485 0.8508 0.8531 0.8554 0.8577 1.1 0.8643 0.8665 0.8686 0.8708 0.8729 0.8749 0.8770 0.8790 1.2 0.8849 0.8869 0.8888 0.8907 0.8925 0.8944 0.8962 0.8980 1.3 0.9032 0.9049 0.9066 0.9082 0.9099 0.9115 0.9131 0.9147 1.4 0.9192 0.9207 0.9222 0.9236 0.9251 0.9265 0.9279 0.9292 1.5 0.9332 0.9345 0.9357 0.9370 0.9382 0.9394 0.9406 0.9418 1.6 0.9452 0.9463 0.9474 0.9484 0.9495 0.9505 0.9515 0.9525 1.7 0.9554 0.9564 0.9573 0.9582 0.9591 0.9599 0.9608 0.9616 1.8 0.9641 0.9649 0.9656 0.9664 0.9671 0.9678 0.9686 0.9693 1.9 0.9713 0.9719 0.9726 0.9732 0.9738 0.9744 0.9750 0.9756 2.0 0.9772 0.9778 0.9783 0.9788 0.9793 0.9798 0.9803 0.9808 2.1 0.9821 0.9826 0.9830 0.9834 0.9838 0.9842 0.9846 0.9850 2.2 0.9861 0.9864 0.9868 0.9871 0.9875 0.9878 0.9881 0.98842.3 0.9893 0.9896 0.9898 0.9901 0.9904 0.9906 0.9909 0.9911 2.4 0.9918 0.9920 0.9932 0.9925 0.9927 0.9929 0.9931 0.9932 2.5 0.9938 0.9940 0.9941 0.9943 0.9945 0.9946 0.9948 0.9949 2.6 0.9953 0.9955 0.9956 0.9957 0.9959 0.9960 0.9961 0.9962 2.7 0.9965 0.9966 0.9967 0.9968 0.9969 0.9970 0.9971 0.9972 2.8 0.9974 0.9975 0.9976 0.9977 0.9977 0.9978 0.9979 0.9979 2.9 0.9981 0.9982 0.9982 0.9983 0.9984 0.9984 0.9985 0.9985 3.0 0.9987 0.9987 0.9987 0.9988 0.9988 0.9989 0.9989 0.9989 3.1 0.9990 0.9991 0.9991 0.9991 0.9992 0.9992 0.9992 0.9992 3.2 0.9993 0.9993 0.9994 0.9994 0.9994 0.9994 0.9994 0.9995 3.3 0.9995 0.9995 0.9995 0.9996 0.9996 0.9996 0.9996 0.9996 3.4 0.9997 0.9997 0.9997 0.9997 0.9997 0.9997 0.9997 0.9997
Projects
6
6
6
6
6
6
6
6
A
B
C
D
E
F
G
H
Total Hrs.
Experience Verification - Reporting M
BACKUP DOCUMENT BEFORE FILLING EXPERI
(6 years if graduate; and 8 years if non-graduate from the date you
A
B
C
D
E
F
G
List major deliverables for each project work that you personally under
How to prepare for PMP certification:
Assumption: Study @
week #
1
Definitions - PMBOK
2
Understanding Input-Output relationship : refer to PM
3
Mug-up Input-Output relationship : refer to PMCC Han
4
Understand Generic Management & Project Initiation
5
Understand Project Scope mgmt
6
Understand Project Time & Cost mgmt
7
Understand Project Quality, HR and Communication
8
Understand Project Risk mgmt & perform PMKQ pract
GO FOR PMP CERTIFICATION
Controlling
Closing
Proj Total hrs:
Initiation
Planning
Execution
PV
EV
AC
M.Hr.
M.Hr.
M.Hr.
8
6
8
16
34
58
82
98
114
120
126
132
ETC=
BAC-EV
126
To complete balace work
EAC-1 AC+ETC
134
To complete total work
EAC-2 BAC/CPI
176
To complete total work
-2
-44
EVph
ACph
300
375
600
700
802.5
950
808.5
958
Cummulative
mulative
ETC=
BAC-EV
1924
To complete balace work
EAC-1 AC+ETC 2882
To complete total work
EAC-2 BAC/CPI 3237
To complete total work
-149.5
-505.18
PVp
EVp
ACp
1083
808.5
958
ETC=
BAC-EV 12204
To complete balace work
EAC-1 AC+ETC
958
To complete total work
EAC-2 BAC/CPI 15418
To complete total work
12054
-2406.1
ad lines?
pletion Date = 50 days e project = 43 days al path = 5.745
ill be complated on time.
n
0.08
0.09
0.5319 0.5359 0.5714 0.5753 0.6103 0.6141 0.6480 0.6517 0.6844 0.6879 0.7190 0.7224 0.7517 0.7549 0.7823 0.7582 0.8106 0.8133 0.8365 0.8389 0.8599 0.8621 0.8810 0.8880 0.8997 0.9015 0.9162 0.9177 0.9306 0.9319 0.9429 0.9441 0.9535 0.9545 0.9625 0.9633 0.9699 0.9706 0.9761 0.9767 0.9812 0.9817 0.9854 0.9857 0.9887 0.98900.9913 0.9916 0.9934 0.9936 0.9951 0.9952 0.9963 0.9964 0.9973 0.9974 0.9980 0.9981 0.9986 0.9986 0.9990 0.9990 0.9993 0.9993 0.9995 0.9995 0.9996 0.9997 0.9997 0.9998 @1200 hr/y
Total
6
6
6
6
7200 hrs
5040
30% effective Utilization
4680
35% effective Utilization
Total
4500
37.5% effective Utilization
nths
ENCE VERIFICATION FORM
H
hrs
ook:
effort hrs per day only
C Handouts
outs
APPLY FOR PMP CERTIFICATION
gmt
1 IT PROJECT
2 BUSINESS OPPORTUNITY
3 INITIATE BUSINESS OPPORTUNITY 4 Start Project
5 Create Opportunity/Problem Statement 6 Develop Initial Project Team
7 GATHER SUPPORTING DATA
8 Gather High Level Business Requirements 9 Conduct Management/Business Survey
10 Analyze Survey Findings and Business Functions 11 Develop High Level Scope, Objectives, and Constraints 12 ANALYZE CURRENT SYSTEM
13 Assess Current System Capacity/Functionality 14 Assess Current System Cost/Benefit
15 ASSESS ALTERNATIVES
16 Define General Systems Requirements 17 Define Potential Build vs. Buy Alternatives 18 Evaluate Technical Implications of Alternatives 19 Estimate Cost/Benefit/Risk of Alternatives
20 Compare Potential Solutions with Project Objectives 21 PRESENT ALTERNATIVES
22 Review Findings on Alternatives with Project Sponsor 23 Obtain Sponsor Approval
24 Determine Project Priority 25 DEVELOP PROJECT PLAN
26 Finalize Project Definition/Scope Statement
27 Determine Project Staffing Needs - User and Technical 28 Develop Project Plan/Schedule
29 FUNCTIONAL REQUIREMENTS AND LOGICAL DESIGN 30 DESIGN FUNCTIONAL SYSTEM
31 Conduct JAD to Define and Document Detailed Functional Requirements 32 Develop Conceptual Design
33 Document Business Process Flows 34 Define Logical I/O Format
35 Define Processing Requirements 36 Define Logical Data Structures 37 Develop Screen Dialogs
38 Develop Overall System Flow 39 Identify Acceptance Testing Criteria
40 Hold Design Walkthru with User and Technical Analyst(s) 41 PREPARE USERS DOCUMENTS
42 Determine User Operations/Data Entry Procedures 43 Determine User Training & Education Requirements 44 Identify Security Requirements
45 Prototype Business Process
SAMPLE PROJECT FOR DEVELOPING PROJECT PLAN
For a typical IT Project, the deliverables upto level-2 has been given below. You are required to eloborate further 2 levels of deliverables upto "Work Packages". You are then required to list down the activities for each Work Package.
Inter-Link Work Packages
46 REVIEW LOGICAL DESIGN
47 Prepare Presentation for Project Sponsor 48 Obtain Sponsor Approval of Logical Design
49 INTERNAL REQUIREMENTS AND PHYSICAL DESIGN 50 DEVELOP DETAILED SPECIFICATIONS
51 Outline Programs, Files, Jobs, Tables 52 Identify Data Elements
53 Define/Document Program Specifications 54 Define/Document Job Specifications 55 Define/Document File Specifications 56 Define/Document Table Specifications
57 Define/Document Detailed Screen Layout and Report Specifications 58 Define/Document Security Specifications
59 Hold Specification Walkthru with Technical Analyst(s) 60 FINALIZE TECHNICAL REQUIREMENTS
61 Define System Control Considerations 62 Define System Backup/Recovery Needs 63 Determine Data Retention Requirements 64 Review Memory Requirements
65 Review Peripheral Equipment 66 Review Workstation Requirements 67 Review Disk Space Requirements 68 Review CPU Requirements
69 Determine Technical Training Requirements 70 REVIEW PHYSICAL DESIGN
71 Prepare/Conduct Management Review of Physical Design 72 Obtain Sponsor Approval of Physical Design
73 CODING AND TESTING
74 ESTABLISH PROGRAM TEST STRATEGY 75 Review Physical Testing Environment 76 Schedule and Prioritize Test Shifts 77 Establish Test File Sources
78 Establish Test Sequence
79 Determine Software Testing Requirements 80 Determine Operations Requirements 81 Test Strategy Complete
82 CODE AND UNIT TEST PROGRAMS 83 Code and Unit Test Required Program #1 84 Code and Unit Test Required Program #2 85 Code and Unit Test Required Program #3 86 Code and Unit Test Required Program #4 87 Code and Unit Test Required Program #5 88 Code and Unit Test Required Program # n 89 OUTLINE TEST SPECIFICATIONS
90 Develop System Test Plan 91 Develop Stress Test Plan 92 Develop Acceptance Test Plan 93 Develop Parallel Test Plan 94 SYSTEM TEST
96 Perform Stress Testing
97 Review Results with User and Operations 98 Complete System Test
99 ACCEPTANCE TEST
100 Finalize Acceptance Test Criteria 101 Review Acceptance Test Plan 102 Perform Acceptance Test 103 Complete Acceptance Test 104 PARALLEL TEST
105 Review Parallel Test Plan 106 Perform Parallel Test 107 Complete Parallel Test 108 IMPLEMENTATION
109 PLAN AND COMMIT COMPUTER SERVICES 110 Prepare Site in User Location(s)
111 Order Computer Supplies 112 Review Test Controls 113 Review Site Operation
114 Review Personnel Requirements 115 Establish System Security
116 SYSTEM DOCUMENTATION
117 Complete Operations Documentation 118 Complete Program Documentation 119 Complete User Guide
120 PREPARE ORGANIZATION & FINALIZE USER PROCS 121 Finalize User Documentation
122 Finalize Data Input Procedures 123 Finalize Data Output Documents 124 Review Manual User Procedures 125 Review Business Recovery Plans 126 Perform Hardware Testing
127 COMPLETE USER EDUCATION AND TRAINING 128 Train Trainers
129 Train Installation Team 130 Train User Personnel
131 INVENTORY SOFTWARE/REVISE DOCUMENTATION 132 Prepare Software Libraries
133 Build Documentation Library
134 DEVELOP SYSTEM CONVERSION REQUIREMENTS 135 Develop Conversion Plan/Schedule
136 Design Conversion Programs/Procedures 137 Hold Conversion Strategy Walkthru
138 Execute Mock Conversions 139 Execute Data Conversion 140 Data Conversion Complete 141 CUTOVER
142 Set Up Environment 143 Install Data Bases
144 Move from Test to Production 145 Monitor and Certify the System 146 OBTAIN SPONSOR SIGN-OFF
147 Secure Sponsor Sign-off on System 148 Secure Sponsor Sign-off on User Guides 149 INITIATE NEW SYSTEM OPERATION 150 Transfer Operational Responsibility to User 151 Establish Change Control Procedures
152 Transfer System Responsibility to Technical Maintenance Function 153 System Implementation Complete
154 CLOSE DOWN OLD SYSTEM
155 Establish Programs Retention Period 156 Archive System Documentation 157 Archive Master Data Files
158 Re-Allocate Computer Resources 159 Archive Programs
160 CONDUCT EVALUATION
161 Develop/Distribute Customer Questionnaire 162 Evaluate Customer Responses
163 Hold Lessons Learned Meeting 164 End Project
165 PROJECT ADMINISTRATION 166 Project Administration
167 Project Planning and Control 168 Project Meetings
169 Staff Administration - Non-Project Related 170 Staff Activities
171 Staff Meetings
172 Production Support and Maintenance
WBS ID WBS DESCRIPTION 1 Power & Utilities Simulation Model - PWUS 1.1 REQUIREMENTS PHASE
1.1.1 Discover User NEEDS
1.1.1.1 Prepare Preliminary User Needs / Requirements
1.1.1.1.1 Establish Project Objectives & Management Concerns 1.1.1.1.2 Get functional requirements
1.1.1.1.3 Get information on external interface 1.1.1.1.4 Get operating environment requirements 1.1.1.1.5 Get performance requirements
1.1.1.1.6 Get standard requirements 1.1.1.1.7 Get special user requirements 1.1.1.1.8 Prepare Prototype
1.1.1.1.9 Evaluate Prototype
1.1.1.1.10 Conduct feed back session
1.1.1.1.11 Document User Needs and Preliminary Requirements 1.1.1.2 Technically Analyze Requirements
1.1.1.2.1 Develop process model 1.1.1.2.2 Develop logical data 1.1.1.2.3 Verify Requirements 1.1.1.2.4 Set up data dictionary
1.1.2 Prepare Preliminary Project Planning 1.1.2.1 Develop Preliminary Project Plan 1.1.2.1.1 Prepare Preliminary Scope statement
1.1.2.1.2 Prepare WBS upto level-1 of project life cycle 1.1.2.1.3 Prepare Milestone Chart
1.1.2.1.4 Prepare RAM, Comm Plan, Sch., Scope, Cost & Risk Mgmt Plan 1.1.2.1.5 Prepare change control system
1.1.2.1.6 Prepare Resource estimation and project schedule 1.1.2.1.7 Prepare Preliminary Project Plan
1.1.2.2 Prepare High-level project Cost and Schedule Budget 1.1.2.2.1 Estimate high-level project cost and prepare budget 1.1.2.2.2 Prepare high-level Milestone Schedule of project life cycle 1.1.2.2.3 Document project constraints and assumptions
1.1.2.3 Obtain Preliminary Project Plan Approval 1.1.3 Finalize Project Requirements
1.1.3.1 SRS finalization 1.1.3.1.1 Prepare SRS
1.1.3.1.2 Obtain Approval of S RS 1.1.3.2 Test Case Preparation 1.1.3.2.1 Prepare Test case
1.1.3.2.2 Obtain Approval of Test case 1.1.3.3 Obtain Customer Approval 1.2 DESIGN PHASE
1.2.1 Standards & Checklists Preparation 1.2.1.1 Top Down Design Standards & Checklists
1.2.1.1.1 Top Down Design Standards & Checklists Preparation 1.2.1.1.2 Top Down Design Standards & Checklists Review 1.2.1.1.3 Top Down Design Standards & Checklists Fixation 1.2.1.1.4 Top Down Design Standards & Checklists Verification 1.2.1.1.5 Top Down Design Standards & Checklists SQA Review
1.2.1.1.5 Top Down Design Standards & Checklists Baseline and Release 1.2.1.2 Coding Standards & Checklists
1.2.1.2.1 Coding Standards & Checklists Preparation 1.2.1.2.2 Coding Standards & Checklists Review 1.2.1.2.3 Coding Standards & Checklists Fixation 1.2.1.2.4 Coding Standards & Checklists Verification 1.2.1.2.5 Coding Standards & Checklists SQA Review
1.2.1.2.6 Coding Standards & Checklists Baseline and Release 1.2.1.3 Math Modeling Standards & Checklists
1.2.1.3.1 Math Modeling Standards & Checklists Preparation 1.2.1.3.2 Math Modeling Standards & Checklists Review 1.2.1.3.3 Math Modeling Standards & Checklists Fixation 1.2.1.3.4 Math Modeling Standards & Checklists Verification 1.2.1.3.5 Math Modeling Standards & Checklists SQA Review
1.2.1.3.6 Math Modeling Standards & Checklists Baseline and Release 1.2.1.4 Graphics Standard & Checklists
1.2.1.4.1 Graphics Standards & Checklists Preparation 1.2.1.4.2 Graphics Standards & Checklists Review 1.2.1.4.3 Graphics Standards & Checklists Fixation 1.2.1.4.4 Graphics Standards & Checklists Verification 1.2.1.4.5 Graphics Standards & Checklists SQA Review
1.2.2 Top Down Design 1.2.2.1 TDD Preparation 1.2.2.2 TDD Review 1.2.2.3 TDD Fixation 1.2.2.4 TDD Verification 1.2.2.5 SQA Review
1.2.2.6 TDD Baseline and Release 1.2.3 Math Modeling 1.2.3.1 MMN Preparation 1.2.3.2 MMN Review 1.2.3.3 MMN Fixation 1.2.3.4 MMN Verification 1.2.3.5 SQA Review
1.2.3.6 MMN Baseline and Release 1.3 DEVELOPMENT PHASE 1.3.1 Coding
1.3.1.1 Utility Boiler Coding 1.3.1.1.1 Coding
1.3.1.1.2 Code Review
1.3.1.1.3 Code review Fixation 1.3.1.1.4 Code Review Verification 1.3.1.1.5 SQA Review
1.3.1.1.6 Code Baseline and Release 1.3.1.2 Pressure Flow Network Coding 1.3.1.2.1 Coding
1.3.1.2.2 Code Review
1.3.1.2.3 Code review Fixation 1.3.1.2.4 Code Review Verification 1.3.1.2.5 SQA Review
1.3.1.2.6 Code Baseline and Release 1.3.1.3 Wet Gas Compressor Coding 1.3.1.3.1 Coding
1.3.1.3.2 Code Review
1.3.1.3.3 Code review Fixation 1.3.1.3.4 Code Review Verification 1.3.1.3.5 SQA Review
1.3.1.3.6 Code Baseline and Release 1.3.1.4 Turbine Coding
1.3.1.4.1 Coding 1.3.1.4.2 Code Review
1.3.1.4.3 Code review Fixation 1.3.1.4.4 Code Review Verification 1.3.1.4.5 SQA Review
1.3.1.4.6 Code Baseline and Release 1.3.1.5 Surface Condenser Coding 1.3.1.5.1 Coding
1.3.1.5.2 Code Review
1.3.1.5.3 Code review Fixation 1.3.1.5.4 Code Review Verification 1.3.1.5.5 SQA Review
1.3.1.5.6 Code Baseline and Release 1.3.2 Configuration
1.3.2.1 Instructor Station Confugration
1.3.2.1.1 Instructor Station Configuration Preparation 1.3.2.1.2 Instructor Station Configuration Review 1.3.2.1.3 Instructor Station Configuration Fixation 1.3.2.1.4 Instructor Station Configuration Verification
1.3.2.1.5 Instructor Station Configuration Baseline and Release 1.3.2.2 Operator Station Configuration
1.3.2.2.1 Operator Station Configuration Preparaton 1.3.2.2.2 Operator Station Configuration Review 1.3.2.2.3 Operator Station Configuration Fixation 1.3.2.2.4 Operator Station Configuration Verification
1.3.2.2.5 Operator Station Configuration Baseline and release 1.3.2.3 Graphics Development
1.3.2.3.1 Graphics Preparation 1.3.2.3.2 Graphics Review 1.3.2.3.3 Graphics Fixation 1.3.2.3.4 Graphics V erification
1.3.2.3.5 Graphics Baseline and Release 1.3.3 Unit Testing
1.3.3.1 Utility Boiler Unit Testing 1.3.3.1.1 Testing
1.3.3.1.2 Bug Fixing 1.3.3.1.3 Verification
1.3.3.2 Pressure Flow Network Unit Testing 1.3.3.2.1 Testing
1.3.3.2.2 Bug Fixing 1.3.3.2.3 Verification
1.3.3.3 Wet Gas Compressor Unit Testing 1.3.3.3.1 Testing
1.3.3.3.2 Bug Fixing 1.3.3.3.3 Verification
1.3.3.4 Turbine Unit Testing 1.3.3.4.1 Testing
1.3.3.4.2 Bug Fixing 1.3.3.4.3 Verification
1.3.3.5 Surface Condenser Unit Testing 1.3.3.5.1 Testing
1.3.3.5.2 Bug Fixing 1.3.3.5.3 Verification
1.3.4 User Manual Preparation 1.3.4.1 Preparation of User Manual 1.3.4.1.1 Review User manual 1.3.4.1.2 Fixation User manual 1.3.4.1.3 Verification user manual 1.3.4.1.4 SQA Review
1.3.4.1.5 Conversion of User Manual to Online Help 1.3.4.1.6 Review of Online Help
1.3.5 Integrating Testing
1.3.5.1 Integrated Dynamic Testing 1.3.5.1.1 Testing
1.3.5.1.2 Bug Fixing 1.3.5.1.3 Verification
1.3.6 Acceptance / Domain Testing 1.3.6.1 Acceptance / Domain Testing 1.3.6.1.1 Testing
1.3.6.1.2 Bug Fixing 1.3.6.1.3 Verification
1.4 PROJECT MANAGEMENT 1.4.1 Project EV Progress Meetings 1.4.1.1 Project & Risk Review Meetings 1.4.1.1.1 Project Kick-off meeting 1.4.1.1.2 Project Review Meeting #1 1.4.1.1.3 Project Review Meeting #2 1.4.1.1.4 Project Review Meeting #3 1.4.1.1.5 Project Review Meeting #4 1.4.1.1.6 Project Review Meeting #5 1.4.1.1.7 Project Review Meeting #6 1.4.1.1.8 Project Review Meeting #7 1.4.1.2 Milestone Meetings
1.4.1.2.1 Completion of Presales and Planning 1.4.1.2.2 Completion of Requirement PUSW SRS 1.4.1.2.3 Release of PUWS
1.4.1.2.4 Completion of Acceptance (PUWS) 1.4.2 Training
1.4.2.1 Domain Training 1.4.2.2 Domain Training
1.4.3 Project Metrics Report
1.4.3.1 December Project Meterics Report 1.4.3.2 January Project Meterics Report 1.4.3.3 February Project Meterics Report 1.4.3.4 March Project Meterics Report 1.4.4 Release Audit
1.4.4.1 Release to Acceptance 1.4.4.2 Product Release