Project Manager: Mark Treiber Last Updated: May 9, 2014
O365 – Email & Calendar Implementation
Page 2 of 27
1
C
ONTENTS
2 Approval & Revision History ... 3
3 Introduction & Purpose ... 4
4 Executive Summary ... 5
5 Project Scope & Requirements ... 7
6 Team Structure – Integration ... 9
7 Project Approach ... 12 8 Project Timeline ... 13 9 Issue Management ... 15 10 Scope Management ... 17 11 Cost Management ... 20 12 Communication Management ... 22 13 Quality Management ... 25 14 Risk Management ... 26
Page 3 of 27
2
A
PPROVAL
&
R
EVISION
H
ISTORY
EXECUTIVE COMMITTEE INITIAL / SIGNATURE DATE
John Krogman JK 5/9/2014
Bruce Maas BM 5/9/2014
Rick Konopacki RK 5/9/2014
REVISION COMMENTS DATE
Draft To be review by Executive Committee 3/26/2014
Draft – version 2 Updated Team Structure from Risk Assessment Review
4/7/2014 Version 1.0 Updated Risk, Communications, Project
Timeline
4/23/2014 Operating Version Updated Cost, Quality, Team Structure 5/5/2014 Operation Version – for
approval
Page 4 of 27
3
I
NTRODUCTION
&
P
URPOSE
This project management plan formally recognizes the existence of the O365 Email & Calendar Project Implementation at University of Wisconsin. The goal is to document what the project is, what the project will deliver, and how the project will be managed. This document will reference where all relevant project artifacts are located along the process to approve deliverables in relation to scope, cost, schedule, quality, communication, risk, and issues.
Page 5 of 27
4
E
XECUTIVE
S
UMMARY
4.1
B
USINESSC
ASES
UMMARY(F
ROMAE
I
NITIATIVEB
USINESSC
ASE6/6/2012)
The objective of this project is to build out the email and calendaring consolidation proposed as an opportunity within Phase I of Administrative Excellence. This will include incorporating salient portions of the work completed within the campus project launched in May of 2010.
Team members will identify a single email and calendaring platform for the UW-Madison community (including faculty, staff, and students) that meets the broad needs of the University. The team will identify the system, quantify the investment required and efficiencies anticipated, and determine service levels and policies that would govern the administration and use of the new system.
4.2
B
USINESSC
ASEN
EED(FROM
AE
INITIATIVE
BUSINESS
CASE
6/6/2012)
Email is one of the most widely used communication services on campus. In March, the AE email & calendaring team conducted a campus-wide use case survey, which indicated that a majority of employees spend two hours or more per day on work-related email. Electronic calendars are also widely used, with two-thirds of employees using a UW-hosted calendar and the remaining third using either external calendars such as Google or Yahoo, or paper calendars.
WiscMail and WiscCal, the current email and calendar systems implemented and supported by the Division of Information Technology (DoIT), have not been adopted campus-wide, with many schools and colleges choosing instead to implement and support their own local email and calendaring services. While the team identified 20 systems across campus as a result of this project, the total number is estimated to be between 35 and 50 systems. These disparate systems result in increased costs due to duplication of hardware, software licensing, infrastructure, and end user support. The total operating costs of redundant systems across campus are estimated to be approximately $1.6 million.
The annual financial impact on productivity from scheduling meetings across disparate systems is an estimated $6.1 million in hours of lost labor.
A unified system for email and calendaring will reduce infrastructure costs on the IT side and will enable the recovery of a significant amount lost productivity on the end user side. This would create a significant opportunity for schools, colleges, and DoIT to redirect labor to other activities which are more beneficial to the teaching, learning, and research missions of the University. Over a five year period, the cumulative potential cost savings are estimated to be $11 million in operating costs plus workforce efficiency gains of approximately $30.5 million.
Page 6 of 27
These savings will be achievable only if all of campus adopts the recommended solution. There currently is no formal policy for the use of email and calendaring systems.
4.3
R
EFERENCED
OCUMENTATION• Business Case –
https://sharepoint.aims.wisc.edu:8181/sites/AEemail/Phase%20II%20Team%20Work%20Products/Forms/AllItems.as px
Page 7 of 27
5
P
ROJECT
S
COPE
&
R
EQUIREMENTS
5.1
O
BJECTIVE(
FROMP
ROJECTC
HARTERA
PPROVED ON8/24/2012)
Team objectives are to plan and execute the implementation of a campus-wide UW-Madison email and calendaring solution (Microsoft Office 365), as recommended by the Phase II Administrative Excellence (AE) work team, vetted by the Advisory Committee and approved by the Steering Committee.
5.2
G
OALS(F
ROMP
ROJECTC
HARTERA
PPROVED ON8/24/2012)
The primary goal of the team is to successfully convert UW-Madison campus users from their current email and calendaring platform to the MS Office 365 email and calendaring product, including technical implementation, transition of data, user training, development and communication of support
resources, and hand off to the DoIT support organization:
Rollout Group #1 – early adopters (Date: TBD)
80% majority of campus users (Date: TBD)
100% of users identified for conversion (Date: TBD)
5.3
S
COPE(F
ROMP
ROJECTC
HARTERA
PPROVED ON8/24/2012)
In Scope:
• Implementation of Microsoft Office 365 Exchange Online Out of scope:
• Implementation of software in the MS Office 365 suite unrelated to email & calendaring is considered out of scope, though significant work may be performed concurrently.
Microsoft Office 365 SharePoint Online
Microsoft Office 365 Lync Online for Enterprises
Microsoft Office 365 Office Professional Plus
• Though the development of a campus-wide active directory is critical to the success of the Email and Calendaring Implementation Team, a separate companion project team is charged with creating the directory.
Related projects & initiatives:
• Directory Services/Authentication (Campus-wide Active Directory) • AE Enterprise IT Decision-Making: Future State
Page 8 of 27
5.4
R
EFERENCED
OCUMENTATION:
• Project Charter -
Page 9 of 27
6
T
EAM
S
TRUCTURE
–
I
NTEGRATION
6.1
T
EAMS
TRUCTURER
OLES:
` COO John Krogman Project Management Mark Treiber Communication
DoIT: Brian Rust UW-Comm: Greg Bump Service Delivery: Matt Goins Technical Team: Jenny Rado
Office 365 Email & Calendaring Project Team – Functional Structure
Team Leader: Patrick Brennan
Technical Architect: Jesse Thompson Technical Team
Provisioning & Acct Management: Jesse Thompson
Transition Interoperability: Collin Cudd
Documentation and Support: Mark Jenkins
Mail Flow/ASAV: Steve Kohlbeck
Technical Communications: Jenny Rado
WM/WC Data Migration: David Karnowski
Training Development/Delivery: Ara Mesdjian
5/1/2014
Service Delivery Lead: Scott Gletty-Syoen
Service Delivery Planning Teams: Organizational Readiness: Matt Goins
Technology Lead : Shawn Cannon
Training Coordinator: Nicole Olthafer Tool and Process Development: Ben Rissman
Migration Coordination: Dan Michalski, Justin Marita
Help Desk Coordination: Marc Tunes
Organizational Support Coordination: RaDs On-Site Services Coordination: Christina Gomez
Business Analyst: Bulut Nesim
Team Management & Business Process Owners Chris Holsman Tamara Walker Brandon Bernier
Executive Advisory Group: Email & Calendaring
CIO: Bruce Maas DoIT: John Krogman SMPH: Rick Konopacki
Liaison:
Tamara Walker Architectural Advisory Team
Jesse Thompson Joe Streeter Ryan Larscheidt Jon Miner
Steve DeVoti Madison Technology Advisory
Group (MTAG) Bobby Burrow
Leadership Representative (Dean/Director) Migration Partner
Administrative Contact Transition Sponsor Transition Advocate Organization Managers/Supervisors Calendar Power Users End Users / Employees
Steering Committee
Organizational Groups
Service Delivery Team
Training Advisory Committtee
Campus Advisory Kelly Bauman/Lisa Diaz – AIMS Tim Czerwonka – Comp Sci Don McDermott – Med School Jeff Ballard – Engineering
6.1.1 Steering Committee / COO (Project Sponsors)
Provided final decision to approve the implementation of the MS Office 365 email & calendaring solution; maintains all final decision-making authority; will continue to support implementation through participation in change management / communication activities as appropriate.
6.1.2 Project Manager
Page 10 of 27
6.1.3 Executive Advisory Group
Oversee the progress of the Implementation Team; manage, administer, and fund the work of the team; ultimately responsible for the overall success of the project
6.1.4 Communication Team
Develop and distribute the media as approved by the implementation team
6.1.5 Organizational Groups
Leadership Representative – The dean or director of an organization.
Migration Partner – Technical point of contact. In cooperation with the Transition Advocate,
completes and monitors the technical requirements of the transition through the Organizational Readiness Website.
Administrative Contact – Administrative point of contact. Communicates with the Office 365
Team and their organization’s leadership.
Transition Sponsor – Leadership representative who participates actively and visibly.
Communicates directly with managers and employees to build a coalition of transition sponsorship within their organization. Also communicates leadership decisions to their organization.
Transition Advocate – Keeps organization leadership up to date on transition issues, support
options, and the activities of their organization’s implementation staff. In cooperation with the Migration Partner, the Transition Advocate monitors, edits, and maintains their organization’s transition plan on the Organizational Readiness Website. Keeps Transition Sponsor updated for progress reporting.
Organization Managers / Supervisors – Communicates and engages staff in the transition process.
Calendar Power Users – Members of an organization with advanced technical and practical
knowledge of the calendaring system. May also have special access privileges.
End Users / Employees – Complete all end-user tasks to prepare for the transition.
6.1.6 Training Advisory Committee
Assist Service Delivery & Technical Team on decisions that will support the Organizational Groups in technology adoption and training
6.1.7 Campus Advisory
Assist Service Delivery & Technical Team on decisions that will support the Organizational Groups adopt the new system
6.1.8 Office 365 Technical Team - Team Lead: Pat Brennan
• Install and configure infrastructure and applications necessary to support the delivery and management of Office 365 services
Page 11 of 27
6.1.9 Office 365 Service Delivery - Team Lead: Scott Getty-Syoen
• Collaborative team of project and local staff to work within the business unit.
• Tactical team to execute migrations to Office 365; including pre-work and data migration execution
6.1.10 Architecture Advisory Team
• Advisory team that reviews architecture and design considerations for the email and calendaring solution, including the implementation process and tools.
• Integrates with
• Liaison between Project Team and Madison Technical Advisory Group (MTAG)
6.1.11 Madison Technical Advisory Group (MTAG)
Advisory group that receives periodic progress updates from the team, and provides feedback
6.1.12 Business Process Owners
Support the team through the allocation of resources, removal of roadblocks, participation in change management and communication activities, and ensuring the project benefits are sustained through policy and process leadership
Page 12 of 27
7
P
ROJECT
A
PPROACH
7.1
M
AJORD
ELIVERABLES(F
ROMP
ROJECTC
HARTERA
PPROVED8/24/2012)
7.1.1 Pre-Work
Project Structure – update with Project Management Plan (revised 3/31/2014)
Project Leadership – See Team Structure (revised 3/302014)
Team Membership – See Team Structure (revised 3/30/2014)
Project Charter – 8/24/2012
Project Management Infrastructure – updated with Project Management Plan (revised 5/2/2014)
7.1.2 Contracting
Professional Services – revised 3/10/2014
Licensing Agreements - TBD
7.1.3 Analysis/Project Planning
O365 Solutions Architectural Workshop (SAW)
Migration Due Diligence Sessions (MDD)
7.1.4 Design & Technical Planning
Final Design – to be review with Microsoft Engagement
7.1.5 MS Office O365 Installation & Configuration
Pilot Users – users tested and operating in O365 environment
7.1.6 Campus Conversions
Rollout Group #1 – Early Adopters
80% Majority of Campus Users
100% of Users Identified for Conversion
Page 13 of 27
8
P
ROJECT
T
IMELINE
8.1
K
EYM
ILESTONES BYO
RGANIZATIONALG
ROUPSAll Organizational Groups will be scheduled with a Go-Live (ETA) date which will determine the actual Kickoff Date and proceed to determine the Key Milestone dates to completion the migration for that Organizational Group.
Go-Live
(ETA) #/weeks Migr Coor date Kickoff date Tr Prep date
############# ############# #############
############# ############# #############
############# ############# #############
############# ############# #############
8.1.1 Pre-Transition – Census Completion
Census Follow-up
Transition Kickoff
Transition Preparedness Meeting
8.1.2 Transition Implementation
All Staff Kickoff Meeting
Check-In #1
Check-In #2
Check-In #3
Training Period
Go Live Confirmation Meeting
8.1.3 Office 365 Go-Live
Go-Live Day
Page 14 of 27
8.2
M
ASTERP
ROJECTP
LAN8.2.1 Implementation Schedule Tracking
Office 365 Organization Schedule Planning
o Data from Census and other data will be collected to create a Master Schedule that contains all Organizational Groups
o Schedule will be posted on the O365 Transition Site: http://www.365transition.wisc.edu
8.2.2 Variance Tracking & Reporting
Baseline Report
o After a preliminary Implementation Schedule is proposed, the following metrics will be calculated and base lined:
10% users migrated - Completion Date 20% users migrated - Completion Date 30% users migrated- Completion Date 40% users migrated- Completion Date 50% users migrated- Completion Date 60% users migrated- Completion Date 70% users migrated- Completion Date 80% users migrated- Completion Date
Page 15 of 27
9
I
SSUE
M
ANAGEMENT
9.1
I
SSUEM
ANAGEMENT9.1.1 Issue Management Responsibilities
The importance of identifying, monitoring and communicating issues is critical in the overall efforts of project management. A clear process by which issues are managed and escalated, supported by an effective scope management plan, are critical. All project team members and others affiliated with the project are responsible for identifying issues as early as possible and for notifying the project manager.
9.1.2 Issues Tracking
All issues will be documented by the teams. They will be entered into issue tracking systems and assigned to owners to manage and report progress by the Service Delivery & Technical Team Leads.
9.1.3 Master Issue Log
Project Management will maintain a Master Issue Log for tracking issues that will impact Schedule, Cost, or Quality. These will be reviewed with Leadership & Executive Advisory.
9.1.4 Issue Escalation
The Service Delivery & Technical Team Leads will be responsible for escalating issues. Criteria for Escalation:
ISSUE TYPE CRITERIA
Schedule Delay of more than 1 week
Cost Increase of > 10% of planned
Quality Quality Metric outside of control limits
Risk All Risks with High Impact
Communication TBD by Communication Plan
Resource / Team Member / Stakeholder
Any potential issue or risk that could result in schedule, cost, or quality variance
Issue Log
Page 16 of 27
9.2
I
SSUEM
ANAGEMENTF
LOWO365 Email & Calendar Implementation Project
Issue Management
O365 Email & Calendar Project Project Manager: Mark J. Treiber Last Updated:3/26/2014 Service Delivery
Team Technical Team
JIRA Service Delivery Issue Log Tech Team Issue Log Issue Escalation? Project Management Executive Advisory Group Architecture Advisory
Master Issue Log
Master Risk Log
Review with Leadership
Communication Plan
9.3
R
EFERENCED
OCUMENTATION:
Page 17 of 27
10
S
COPE
M
ANAGEMENT
10.1
S
COPEM
ANAGEMENTP
ROCESSScope Management includes the processes required to ensure that the work plan includes all the work agreed upon, and only the work agreed upon for a successful project completion. It is primarily concerned with defining and controlling what is or is not included in the project.
This section describes how project scope will be managed and how scope changes will be integrated into the project. It also includes a clear description of how scope changes will be identified, classified and tracked.
Scope changes originate in one of three ways. An issue (See section 9 - Issue Management) becomes a scope issue, someone requests a change, or a decision is needed to allow progression on the project. All scope change requests will follow the following process:
1. Change Request or Decision Needed is requested by team member
2. Project Manager reviews the Change Request or Decision Needed and logs the request 3. Project Manager reviews with Leadership to validate
4. Project Manager puts request into Decision Document or Change Document a. Including the impacts to Time, Cost, and Quality
5. Project Manager reviews request with Executive Advisory Group
6. Executive Advisory Group (acting as the Change will review Decision or Change and make one of three decisions:
a. Approved – Change/Decision can move forward
b. Reject – Change/Decision is not justified based on its impact
c. Deferred – Change/Decision will need to be approved by Steering Committee 7. Approved Change/Decision Updates
a. Updates Project Timeline b. Updates to Cost Management c. Updates to Quality Management
Page 18 of 27
10.2
P
ROCESSF
LOW
O365 Email & Calendar Implementation Project
Change Management/Decision Process
O365 Email & Calendar Project Project Manager: Mark J. Treiber Last Updated:3/26/2014 Service Delivery
Team Technical Team
Scope Change or Decision? Project Management Executive Advisory Group Architecture Advisory Decision/Change Log Review with Leadership Decision Document/ Change Request Approve/Reject Steering Committee (if necessary)
Page 19 of 27
10.3
D
ECISION/
C
HANGEL
OGProject Management will maintain a Master Decision/Change Log for tracking all items will impact Schedule, Cost, or Quality. These will be reviewed with Leadership & Executive Advisory.
10.4
R
EFERENCED
OCUMENTATION:
Master Issue/Decision Log: Maintained in the O365 Project Management Repository Decision / Change Log
Page 20 of 27
11
C
OST
M
ANAGEMENT
11.1
C
OSTM
ANAGEMENTP
LAN11.1.1 Anticipated Solution Cost (From Business Case)
TYPE
UPFRONT/ONE-TIME
REOCCURRING NOTES
Labor $543,750 $1,241,250 Assumes administrators in distributed units
will continue to spend 15% of their time managing email & calendaring
Infrastructure - $122,000 Includes routing, admin. Console
Licensing - $303,020 Per mailbox fees are based on defined plans
and may fluctuate based on user needs
Communication - $9,000 -
Training $120,000 - -
TOTAL COSTS $636,750 $1,675,270 -
11.1.2 Proposed Tracking of Costs
11.1.2.1 Cost Management – Main
Project Management will maintain a Master Cost Management Plan for maintaining the Projected vs. Actual Costs & Benefits for the project. These will be reviewed with Leadership & Executive Advisory on a monthly basis.
Cost Management Plan - Main
Projected Year 1 Year 2 Year 3 Year 4 Year 5 Total
Up-Front Costs 663,750 - - - - 663,750 Recurring Costs 1,675,270 1,675,270 1,675,270 1,675,270 1,675,270 8,376,350 One-Time Savings - - - -Recurring Savings - - -
-Net Savings/(Costs) - - -
-Actual FY2014 FY2015 FY2016 FY2017 FY2018 Total
Up-Front Costs - - - -Recurring Costs - - - -One-Time Savings - - - -Recurring Savings - - -
-Page 21 of 27
11.1.2.2 Cost Management – Costs
11.1.2.3 Cost Management – Benefits
11.2
REFERENCE
DOCUMENTATION:
• Master Cost Management Plan: Maintained in the O365 Project Management Repository Cost Management Plan - Costs
Projected Up-Front / One-Time Recurring (annually)
Labor 543,750 1,241,250 Infrastructure - 122,000 Licensing - 303,020 Communication - 9,000 Training 120,000 Total Costs 663,750 1,675,270
Actual Up-Front / One-Time FY2014 FY2015 FY2016 FY2017 FY2018 Total
Labor - - - - - - -Infrastructure - - - - - - -Licensing - - - - - - -Communication - - - - - - -Training - - - - - - -Total Costs - - - - - -
-Cost Management Plan - Benefits
Projected Recurring (annually)
Operating Costs -Calendar Efficiency
-Total Benefits
-Actual FY2014 FY2015 FY2016 FY2017 FY2018 Total
Total Converted Users - - - -
-Operating Costs - - - - - -Calendar Efficiency - - - - -
-Page 22 of 27
12
C
OMMUNICATION
M
ANAGEMENT
12.1
I
NTERNALC
OMMUNICATIONS12.1.1 Meetings
TYPE PURPOSE ATTENDEES TIME OUTPUT
Service Delivery Keep entire team updated
on progress
Core Service Delivery Team
Wednesday 3:00pm Agenda
Weekly Reports Service Delivery Leadership Review direction, risks, &
issues
Team Leader & Management
Monday 11:30am Updates to
Risks/Issues
Technical Team Keep entire team updated
on progress
Core Technical Team
Tuesday 9:00am Agenda
Weekly Reports Technical Team Leadership Review direction, risks&
issues
Team Leader & Management
Monday 3:30pm Updates to
Risks/Issues
Service/Technical Integration Determine proper
crossovers
Team Leaders & Management
Wednesday 11:00am Updates to
Risks/Issues
Communication Review & approve
communication
Communication Team
Thursday 9:00am Communication
Plan
Executive Committee High Level Update
Review Risks Executive Committee Thursday 1:00pm Agenda Executive Level Status
Quality Meetings Develop Quality Control
Metrics
Quality Team As Needed Updates to
Quality Plan
Architecture Meetings Review & Approve
Architecture
Architect Team As Needed Decision
Information
Steering Committee Major Project Decisions Project Leadership As Needed Decision
Information
12.1.2 Meeting Documentation
All documentation will be maintained on one of the preferred technologies. All team members need to keep documentation in one of the following repositories.
TYPE MAIN REPOSITORY
Collaboration Google Docs
Box Folders
Shared Team Documentation Box Folders
SharePoint Site
Overall Project Team Documentation SharePoint Site
Page 23 of 27
• Service Delivery Index -
https://docs.google.com/a/wisc.edu/spreadsheet/ccc?key=0Ak8h_p9WqlxOdEt1cTBnVXVtQUd4eUphVm5iMTZ0bmc &usp=sharing#gid=0
12.1.3 Meeting Ground Rules
Team Ground Rules
-https://sharepoint.aims.wisc.edu:8181/sites/AEemail/Shared%20Documents/Forms/AllItems.aspx
12.2
E
XTERNALC
OMMUNICATIONS12.2.1 Communication Toolkit
The Service Delivery team will work with Migration Partners from each Organizational Group to assist in providing consistent communication to the end-users (via email templates, etc) - links to the communication will be found - https://data.office365.wisc.edu
Page 24 of 27
12.2.2 Email and Calendar Transition
The main site for the transition - https://www.365transition.wisc.edu/ will be used to keep campus informed on implementation.
o “Students, Faculty & Staff – information for end-users on migration o “Migration” Section – information for Migration Partners
o “Project Information” Section – information about news, project management, and archived communications
Page 25 of 27
13
Q
UALITY
M
ANAGEMENT
13.1
Q
UALITYM
ANAGEMENTP
LAN13.1.1 Quality Control
13.1.1.1 Quality Control Team
Mark Treiber John Krogman Kevin Cherek Tamara Walker Pat Brennan Brandon Bernier
13.1.1.2 Quality Control Tracking
Project Management will maintain a Master Quality Control for tracking all quality metrics for the project. These will be proposed by the Quality Control Team and managed and tracked
throughout the implementation.
13.2
REFERENCE
DOCUMENTATION:
• Master Quality Control Plan: Maintained in the O365 Project Management Repository
Quality Control
Critical To Quality Time Period Group Sig Char #
Significant Characteristic Description Measurement Method Control Limits Stability (Y or N) Control Plan A-1 Y A A-2 Y A-3 Y B-1 Y B B-2 Y B-3 Y
Page 26 of 27
14
R
ISK
M
ANAGEMENT
14.1
R
ISKM
ANAGEMENTP
ROCESSO365 Email & Calendar Implementation Project
Risk Management Process
O365 Email & Calendar Project Project Manager: Mark J. Treiber Last Updated:3/26/2014 Project
Management
Executive Advisory Group Master Issue Log
Master Risk Log
Service Delivery/ Tech Team Leadership Review Mitigation Plans Master Project Plan
Page 27 of 27
14.1.1 Master Risk Register
Project Management will maintain a Master Risk Register for tracking all risks for the project issues that will impact Schedule, Cost, or Quality. These will be reviewed with Leadership & Executive Advisory.
14.1.1.1 Risk Register - All risks that could have impact on the project
14.1.1.2 Preventative Actions – Response to a documented risk to prevent or reduce the risk from happening
14.1.1.3 Contingency Actions – Planned response to a documented risk after the risk has occurred
14.2
REFERENCE
DOCUMENTATION:
• Master Risk Register: Maintained in the O365 Project Management Repository Risk Register
Risk # Status Category Date Raised Raised By Description of Risk Description of Impact Likelihood Impact Priority
Summary Description Rating
Preventative Actions
Risk # Description of Risk PA# Status Preventative Actions Action Owner Action Date
Summary Preventative Actions