2020 Tallahassee-Leon County Multimodal Project Summary
Quarters 3 & 4 • July - December 2020
2021 Tallahassee-Leon County
Multimodal Project Summary
Quarters 3 & 4 • July - December 2020
This Biannual Update on Multimodal Transportation Projects details
the information for bicycle and pedestrian projects within Leon County
that are currently under design, under construction, or that have been
completed within the calendar year. Projects are organized by their
implementing agency. There are currently fi ve agencies funding and
constructing transportation improvements in Leon County, including the
City of Tallahassee, Leon County, Blueprint, Capital Region Transportation
Planning Agency, and the Florida Department of Transportation.
For more information on the Biannual Update or any of the projects
contained within this report, please contact the Tallahassee-Leon County
Planning Department at (850) 891-6400.
Multimodal Projects Update
•
City of Tallahassee
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) ImprovementProgram Anticipated Start Date Notes Planning Study, PD&E, Pre-Engineering as of Dec 31, 2020
Market District, Maclay Commerce Drive and Maclay Blvd
Maclay Blvd - Maclay Commerce to just short of Village, Maclay Commerce Financial Plaza to Martin Hurst
Sidewalk/
Multiuse path Both Capital improvements 2019 In PD&E , full design in 2020 South Macomb Street Gaines St. to St. Francis St. Sidewalk TBD Capital Improvements TBD Not currently a funded project
for construction Under Design as of Dec 31, 2020
Blountstown Street Sidewalk Tennessee St. to Tharpe St. Sidewalk West TA Grant/Capital
Improvements 2021 Design Complete, construction in 2021 Gadsden Street Sidewalk
Phase I Magnolia Dr. to Perkins St. Sidewalk TBD Capital improvements 2021 Design underway, construction to commence 2021 Gadsden Street Sidewalk
Phase II Palmer Ave to Harrison St Sidewalk TBD Capital improvements 2021 Design underway, construction to commence 2021 Jakes and Patterson Street S. Bronough St. to Adams St. Sidewalk Capital Improvements 2021 Design underway, construction
to commence 2021 Lorene Street Driveway to Pensacola Street
(about 250’) Sidewalk West Capital improvements 2020 Construction to commence July 2020 Paul Russell Road Monday St. to Apalachee Pkwy. Sidewalk West Capital Improvements -
Prioritized Sidewalks TBD Project not currently funded for construction Railroad Avenue FAMU Way to Gaines St. Sidewalk
/Multiuse path West Capital Improvements 2019 Currently in design, Scheduled to start construction FY2021 Richview Road Apalachee Pkwy. to Springforest Rd. Sidewalk
& Bike Lanes Both Capital Improvements 2019 Construction to begin in 2020 Saxon Street Campbell St. to Floral St. Sidewalk CRA funded 2021 Start construction late 2020 Texas Street Polk Dr. to Putnam Dr. Sidewalk West Capital improvements 2020 Construction to begin 2Q 2020 Tram Road Trail Capital Circle SE to Four Oaks Blvd. Trail/sidewalk North Capital improvements 2021 Currently in design, construction
expected to start late 2020 Walden Road Adiron Way to Tapestry Senior Living Sidewalk South Capital improvements 2020 Currently in design, expected
to go to construction late 2020 Yaeger Street S. Meridian St. to Oak Terrance Apts. Sidewalk North Capital Improvements 2018 Project not currently funded
for construction Zillah Street PASS Tram Rd. to Paul Russell Rd. Sidewalk
Multimodal Projects Update
•
City of Tallahassee
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) ImprovementProgram Anticipated Start Date Notes Under Construction as of Dec 31, 2020
Alachua Avenue Magnolia Dr. to Short St. Sidewalk South Capital Improvements 2018 Bond Linear Park St Marks Trail to
Speed Spence Stevens Park Multi-use path CRA funded 2020
Branch Street Tharpe St. to W. 10th Ave. Sidewalk East Capital Improvements 2018 Construction underway, (Substantially Complete) FAMU Way Extension
Segment 3 Gamble Rd. to Lake Bradford Rd. Bike/Ped Improvements Both Capital Improvements 2018 Iamonia Street Roberts Ave. to Levy Ave. Sidewalk West Capital Improvements 2018 Polk Drive x Sidewalk South Capital Improvements -
Prioritized Sidewalks 2018 Phase I completed, Phase II construction to begin 05/2020 Putnam Drive S. Monroe St. to Country Club Dr. Sidewalk Monroe - Meridian,
North;
Monroe - Country Club Drive, South
Capital Improvements -
Prioritized Sidewalks 2018 Sidewalk construction substantially complete Rankin Avenue Roberts Ave. to Roswell Dr. Sidewalk East Capital Improvements 2018
Weems Road Extension Mahan Dr. to Automotive Way Multi-use path West/South Capital Improvements 2018 Construction to be complete July 2020
Weems Road Improvement
Phase II CSX to Mahan Dr. Multi-use path East Capital Improvements 2018 Construction scheduled to be complete October 2020 Completed as of Dec 31, 2020
City Hall - Perimeter
ADA Rehabilitation Perimeter of City Hall Sidewalk Both Capital Improvements -FAMU Way Extension
Segment 2 Pinellas St. to Gamble Rd. Bike/Ped Improvements Both Capital Improvements -Glenview Drive Meridian Rd. to Thomasville Rd. Sidewalk South Capital Improvements -Mitchell Avenue Ann Dr. to Betton Rd. Sidewalk West Capital Improvements -
Prioritized Sidewalks -Oakland Avenue S. Monroe St. to S. Meridian St. Sidewalk North/South Capital Improvements -
Prioritized Sidewalks -Palmetto Street S. MLK Jr. Blvd. to S. Adams St. Sidewalk North Capital Improvements -
Prioritized Sidewalks -Volusia Street NW Corner of Volusia St.
-Multimodal Projects Update
•
Leon County
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Anticipated Const. Start Date Estimated Project Cost Funded Amount Funding Source Notes Under Design as of Dec 31, 2020
Blountstown Highway Williams Landing Rd. to
Fort Braden School Sidewalk North SRTS 2022 $890,789 SRTS Grant or Leo County Involves construction of boardwalk and crosswalk installation Blountstown Highway Merry Robin Rd. to
Sir Richard Rd. Sidewalk South SRTS 2022 $605,000 SRTS Grant or Leo County Designed concurrently with Williams Landing Rd. project Chaires Cross Road Green Oak Dr. to
Capitola Rd. Sidewalk South/West Capital Projects N/A $500,000 Leon County The sidewalk has been completed from Green Oak Drive to the eastern entrance of the Chaires Elemen-tary School. The remaining section from the School entrance to CSX Railroad is under design.
Crowder Road @ US 27
(N Monroe Street) East Side Monroe St. along Crowder Rd. Turn Lane Addition, Sidewalk
S/W
North Side Capital Projects 2020/2021 Leon County Turn lane addition, 6 foot sidewalk on north side from US 27 to CVS Entrance At 100% Design- In R/W Acquisition
Gadsden Street
Sidewalk 6th Ave. to 8th Ave. Sidewalk East Community Sidewalk Enhancement 2021 $799,750 Leon County Under Design (60%) Gearhart Road CSX Railroad to
Capital Circle Sidewalk South & West 11/2020 $1,355,220 Construction commencement in November 2020 Maclay Road Meridian Rd. to
City Limits Sidewalk North Community SidewalkEnhancement 2024 $2,271,609 Leon County This project also considers additional 260 feet stretch of sidewalk addition along the east side of Meridian Road, extending from the intersection of Maclay Road and Meridian Road to the Maclay School entrance.
Magnolia Drive
Multi-Use Trail S. Monroe St. to Pontiac Dr. Multi-UseTrail South Capital Projects 2021 3.7 Million BP2000, COT, Leon County 8’ w/ 4’ Buffer foot Trail, Roadway Reconstruction, Waster and Sewer upgrade Phase I, Reconstruction of built 10’ Trail to 7’ Trail w? 3’ Buffer.
Underground Electric, Telecommunication and TV Magnolia Drive
Multi-Use Trail Pontiac Dr. to Diamond St. Multi-Use Trail South & East Capital Projects 2022 3.7 Million BP2000, COT, Leon County 8’ w/ 4’ Buffer foot Trail, Roadway Reconstruction, Waster and Sewer upgrade Old St. Augustine Rd.
& Blair Stone Rd. Intersection
Old St. Augustine Rd. & Blair Stone Rd. Intersection
Intersection Improvement to add turn lane
TBD Capital Projects 2021 Leon County Sidewalks will be added. Plans currently at 90%. Currently working on Utility Coordination& R/W Acquisition
Old St. Augustine Road Lafayette St. to Paul Russell Rd (excluding intersection)
Sidewalk North
& South Community Sidewalk Enhancement TBD Leon County Lafayette St. to Blair Stone Road - SW on South Side. Blair Stone Road to Paul Russell SW on North Side. Currently at 60% Design, may require considerable easement acquisition
Tharpe Street Capital Circle NW to
Ocala Rd. Bike/Ped Improvements Both Capital Projects N/A Unfunded Blueprint Construction is unfunded Timberlane Road Martin Hurst Rd. to
Market St. Sidewalk Improvement & Crosswalk
Multimodal Projects Update
•
Leon County
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Anticipated Const. Start Date Estimated Project Cost Funded Amount Funding Source Notes Tram Road Gaile Ave. to
Crossing Rocks Rd. Multi-Use Trail South SRTS 2021 $1,450,496 Leon County 10 foot concrete trail. 4 feet of the 10 foot wide trail will be constructed with porous concrete to mitigate stormwater
Tram Road Crossing Rocks Rd. to
Capital Circle SE Multi-UsTrail South Community SidewalkEnhancement TBD $2,076,575 LeoCounty 10 foot multi-use trail Woodville Highway Natural Bridge Rd. to
Hickory Ln Sidewalk East SRTS 2021 $135,860 Pursuing SRTS Grant 6 foot sidewalk east side of Woodville Hwy. Under Construction as of Dec 31, 2020
Bannerman Road Thomasville Rd. to
Meridian Rd. Widening & Bike/Ped Improvements
Both Capital Projects N/A $999,037 Bannerman Shopping Center Developer & Sales Tax Extension
The fi rst section (800 - 900 feet west of Quail Commons) has been completed. Remainder of Bannerman improvements will be funded by new sale tax which goes into effect 2020.
Completed as of Dec 31, 2020
Beech Ridge Trail Kinhega Drive to
Lawton Chiles Lane Sidewalk North SRTS - $524,000 LeonCounty 5’ to 6’ concrete sidewalk Chadwick Way Bull Headley Rd. to
Deer Lake Rd. Sidewalk North SRTS - $418,735 LeonCounty Crowder Road &
Indian Mounds Road CVS Entrance to Indian Mounds Rd. Sidewalk TBD Community Sidewalk Enhancement - $1,491,257 Leon County Indian Mound Road added to this project (Construction Complete) Innovation Park
Central Pond Trail Multi-Use Trail N/A JPA - Innovation Park Killearn Lakes
Greenway Trail Copperfi eld Circle and Deer Lake Rd. Multi-Use Trail N/A SRTS 2020 $13,706 Completed in 2020 Lonnie Rd. Torchmark Rd. to
Dempsey Mayo Rd. Sidewalk West & South - $886,245 Leon County Natural Bridge Road Woodville Highway to
Taff Rd. Sidewalk North - $350,975 Leon County Old Bainbridge Rd 7th Ave. to
Volusia Street Sidewalk West - $59,421 Leon County Perkins Road Point View Dr. to
Roweling Oaks Ct. Sidewalk and Crossing Improvements
- $7,027 Leon County
Multimodal Projects Update
•
Bluprint Intergovernmental Agency
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Antic.Start FundedAmount FundingSource NotesPlanning Study, PD&E, Pre-Engineering as of Dec 31, 2020 Airport Gateway Phase I Road improvements,
multi-modal faculties, road creation, intersection improvements, community enhancements
TBD Blueprint
2020 2020 $68,232,193 Local Sales Tax Planning and pre-engineering in procurement; Phase 1 design expected to be complet-ed by end of 2023. Capital Cascades
Trail - Segment 4 From CCT Seg. 3 Central Drainage Ditch to South of Orange Ave
Multi-Use Trail TBD Blueprint
2000 2020 $20,000,000 Local Sales Tax Blueprint has developed the procurement documents for the professional services in consultation with the City and County stormwater teams. Advertising for planning and design services for the project will occur this summer with construction expected to begin in 2022.
Northeast Gateway:
Welaunee Blvd. Phase 1 New road creation, greenway development, intersection improvements
TBD Blueprint
2020 2020 $58,811,606 Local Sales Tax Tentative project schedule includes completion of the PD&E study in fall 2020 with fi nal design and permitting completion in 2022 and construction completed by 2025 Thomasville
Road Trail Bradford Roadto Live Oak Plantation
Multi Use Trail TBD CRTPA/ Blueprint 2020 2020 CRTPA - $125,000; Annual Funding for Greenways $790,000 CRTPA/FDOT/
Local Sales Tax CRTPA is currently conducting a feasibility study; Thomasville Road Greenway Trail has been prioritized by the IA Board for Implementation
University
Greenway N/A Multi Use Trail TBD Blueprint 2020 2021 Estimated Cost - $2,345,669 Local Sales Tax University Greenway is one of 5 GWMP projects advance by the IA Board, and is mov-ing forward, concurrently, with the Airport Gateway Project Under Design as of Dec 31, 2020
Capital Cascades
Trail - Segment 3D Cleveland St. to Central Drainage Ditch
Multi Use Trail, Stormwater
Facilities; Amenities N/A Blueprint 2000 2020 Total Segment 3 Funding $67,776,617
Local Sales Tax Construction is being Permitted for Section 3DB Capital Cascades
Trail - Van Buren St. S. Adams Street to Under the Over Sidewalk Blueprint 2000 2020 $1,100,000 Local Sales Tax One of the amenities of CCT Seg. 3. Provides beautifi cation, sidewalk, and parking. Currently procuring construction Capital Circle SW Crawfordville Rd.
to Orange Ave. Roadway widening, Multi Use Trail Greenway, Debbie Lightsey Nature Park
North/
East Blueprint 2000/FDOT 2019 Over $105 Mil-lion to FY 2024 FDOT, Local Sales Tax Dol-lars
Design contract awarded for Debbie Lightsey Nature Park and Greenway; Construction expected to begin in 2021
Capital Circle SW
Golden Aster Trail Capital Circle and Lake Bradford to Lake Hiawatha
Trail improvements &
bike lane addition North Blueprint 2020 2019 Annual Funding for Greenways $750,000
Local Sales Tax Design expected to be completed January 2021, construction to follow Capital Circle SW
Lake Munson Spur Connector
Lake Henrietta
to Lake Munson Improved Trail N of CCSW Blueprint 2020 2019 Annual Funding for Greenways $750,000
Local Sales Tax Design expected to be completed January 2021, construction to follow Lake Jackson
Greenway Lake Jackson Indian Mounds to Lake Ella
Multi-Use Trail TBD Blueprint
2020 2020 Annual Funding for Greenways $790,000
Local Sales Tax The Lake Jackson Greenway has been prioritized by the IA Board. The Project is cur-rently under design, which is expected to end in Q4 2021. Construction estimated to begin in Q1 2022.
Magnolia Drive
Multi-Use Trail Phase I Retrofi t: S. Meridian St. to Pontiac Dr.
Multi-Use Trail South\
East Blueprint 2000 2019 Total Proj-ect Funding $12,990,162
Local Sales Tax Redesign and incorporationof underground utilities is underway; Right-of-way acquisi-tion is underway and construcacquisi-tion is anticipated to begin in 2021; design at 100%
Multimodal Projects Update
•
Bluprint Intergovernmental Agency
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Antic.Start FundedAmount FundingSource NotesMagnolia Drive
Multi-Use Trail Phase II: Pontiac Dr. to Diamond St.
Multi-Use Trail South\
East Blueprint 2000 2019 Total Proj-ect Funding $12,990,162
Local Sales Tax Redesign and incorporation of underground utilities is underway; Right-of-way acquisi-tion is underway and construcacquisi-tion is anticipated to begin in 2021; design at 100% Magnolia Drive
Multi-Use Trail Phase 3 Diamond St. to Apalachee Pkwy
Multi-Use Trail TBD Blueprint
2000 2019 Total Proj-ect Funding $12,990,162
Local Sales Tax Redesign and incorporation of underground utilities is underway; Right-of-way acquisi-tion is underway and construcacquisi-tion is anticipated to begin in 2021; design at 90% Magnolia Drive
Multi-Use Trail Phase 4 S. Meridian St. to S. Monroe St.
Multi-Use Trail TBD Blueprint
2000 2019 Total Proj-ect Funding $12,990,162
Local Sales Tax Redesign and incorporation of underground utilities is underway; Right-of-way acquisi-tion is underway and construcacquisi-tion is anticipated to begin in 2021; design at 100% NE Corridor
Connector: Bannerman Rd.
Quail Commons
Drive to Meridian Roadway widening; multi use trail TBD Blueprint 2020 2019 $3,300,000 in FY 2020 Local Sales Tax IA Board accepted feasibility study at September 2020 IA Board meeting, which showed need to widen Bannerman Road to four lanes from Quail Commons Drive to Preservation Road and need for operational improvements from Preservation Road to Meridian Road. Design and right of way acquisition are planned for completion in 2023, at which time project will be advertised for construction pending IA Board approval for bond issuance in FY 2022 to support right of way acquisition and construction services.
Orange Meridian
Placemaking E. Drainage Ditch and S. Meridian St. to S. Monroe St.
TBD/Multi Use Trail N/A Blueprint
2020 2019 TBD Local Sales Tax Design contract was awarded and expected to continue through 2020. Southwood
Greenway Capital Circle SE and SE Park Multi Use Trail Blueprint 2020 2020 Leveraging Opportunity w/ COT; estimated cost $360,000
Local Sales Tax June 27, 2019 meeting, the IA Board authorized Blueprint to enter into costsharing agreement with the City of Tallahassee for completion of a portion of the Southwood Trail Greenway between Capital Circle Southeast and the future City Southeast Park. Design and permitting currently underway and coordinated Attachment 6 Page 1 of 3 through the City of Tallahassee.
Completed as of Dec 31, 2020 Capital Cascades
Trail - Segment 3B MLK Jr. Blvd. to S. Adams St. Stormwater Pond/Conveyance and Bike/Ped Improvements Both Blueprint 2000 - $8,000,000 Local Sales Tax Grand Opening Held 10-15-15 Capital Cascades
Connector Bridge South Adams St. to Gadsden St. Pedestrian Bridge & Multi-Use Trail N/A Blueprint 2000 - $5,300,000 FDOT, Local Sales Tax, CRTPA Grand Opening 16 Capital Cascades
Trail - Segment 3B Cleveland St. to MLK Jr. Blvd. Stormwater Pond/Conveyance and Bike/Ped Improvements North & South Blueprint 2000 - $9,000,000 Local Sales Tax Project complete other than permit closeout and as-builts Capital Cascades
Trail - Segment 3C Pinellas St. toGamble St. Multi-Use Trail N/A Blueprint 2000 - Local Sales Tax Grand Opening August 2018 Capital Circle
NWSW - W1 Crawfordville Rd. to Orange Ave. PD&E N/A Blueprint 2000 - $4.5M* Local Sales Tax PD&E Accepted by FHWA January 2016 Magnolia Drive
Multi-Use Trail Phase 6 S. Monroe St. to S. Adams St.
Multi Use Trail N&S Blueprint
2000 - $800,000 Local Sales Tax N2 - Capital
Circle NW/SW North of Orange Ave. to US 90 Highway Widening, Bike/Ped Improvements & Wetland Mitigation
Both Blueprint
Multimodal Projects Update
•
Capital Region Transportation Planning Agency
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Anticipated Start Date FundingSource Notes Planning Study, PD&E, Pre-Engineering as of Dec 31, 2020Orange Avenue Monroe Street to Capital Circle, SW Potential Widening N/A 2019 FDOT Design funded in FY 23
Pensacola Street Appleyard Drive to Capital Circle, SW Potential Widening N/A 2020 FDOT Seeking Project Development and Environment Study funding
Thomasville Road Live Oak Plantation Road to Betton
Road Shared Use Path N/A 2019 CRTPA Feasibility study complete Oct. 2020; Public engagement phase ongoing US 90 (Mahan Drive) Pedrick Rd to Monticello Bike Trail Shared Use Path N/A 2019 CRTPA Feasibility study anticipated to be complete in
September 2020. Under Construction as of Dec 31, 2020
Crawfordville Highway Leon County Line to SR 267 Widen to 4 lanes FDOT Work
Program 2021 FDOT Crawfordville Highway SR 267 to East Ivan Road Widen to 4 lanes FDOT Work
Program 2024 FDOT Complete as of Dec 31, 2020
Apalachee Parkway Magnolia Drive Intersection Addition of Crosswalk East Intersection
Improvement- N/A Construction complete 2019 North Monroe Street Tharpe St. to Seventh Ave. Medians/ Pedestrian
Im-provements N/A RMP - FDOT/Federal Construction complete March 2017 Ochlockonee Bay Trail Sopchoppy to Mashes Sands Park
(Wakulla County) Bicycle Improvements N/A RMP - Bicycle trail connecting Sopchoppy to Mashes Sands Park, following CR 372, Surf Road Sixth Avenue Monroe St. to Gadsden St. Design/Construction for
Multimodal Projects Update
•
Florida Department of Transportaion
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Anticipated Start Date Notes Planning Study, PD&E, Pre-Engineering as of Dec 31, 2020
North Monroe Street Lakeshore Dr. to John Knox Rd. Sidewalk - Surface Trans-portation Block Grant
2021 #445053-1; Preliminary Engineering funded 2021 Roberts Elementary School
Safe Routes N/A Sidewalk - SRTS 2023 #4456131; Preliminary Engineering funded 2023 South Monroe Street Harrison St. to FAMU Way Sidewalk - - TBD #445052-1
Under Design as of Dec 31, 2020
Blountstown Street Tennessee St. to Tharpe St. Sidewalk N/A Capital Projects 2021 #446633-1; Construction start date anticipated 2021 Capital Circle NWSW - W1 Crawfordville Rd. to Springhill Rd. Addition of lanes
and reconstruc-tion (will include sidewalks and sidepath)
N/A Capital Projects TBD #415782-9; Construction funded in FY 21
Capital Circle NWSW - W1 Springhill Rd. to Springhill Rd. Addition of lanes and reconstruc-tion (will include sidewalks and sidepath)
N/A Capital Projects TBD #219749-2; Right-of-way funded in FY 20; Construction funded in FY 25
County Road 375
(Smith Creek Road) South of Fire Dept. to SR 20 Blountstown Hwy. Bike Lane/Side-walk Both FHWA Grant 2021 #442060-1; Construction start date anticipated 2021 County Road 375
(Smith Creek Road) NF-320 to South of Fire Dept. Bike Lane/Side-walk Both Capital Projects 2021 #442060-2; Construction start date anticipated 2021 North Monroe Street Clara Kee Blvd. to Harriett Dr. Sidewalk East SRTS TBD #440383-1
Completed as of Dec 31, 2020
6th Avenue Monroe St. to Gadsden St. & South to Beard St. Sidewalks Both Capital Projects -7th Avenue Colonial Dr. to Gadsden St. Sidewalks North Capital Projects -Apalachee Parkway Monroe St. to Frontage Roads Sidewalks and
Safety Improve-ments
Both Resurfacing -
Maintenance - Sidewalk safety improvements near FDOT at Lafayette on ramp to Apalachee Pkwy. 430784-1 Title in Work Pro-gram: SR 20 From SR 61- E of SR 261.
E. Lafayette Street
Service Road CSX RR Tunnel to Seminole Dr. Bike Path/Trail South N/A
-Glenview Drive N. Meridian Rd. to Thomasville Rd. Sidewalk South Capital Projects - #436991-1; Completed 2019 Magnolia Drive S. Meridian Rd. to Pontiac Dr. Sidewalk South Capital Projects
-Multimodal Projects Update
•
Florida Department of Transportaion
•
July - December 31, 2020
Roadway Segment Project Type Road Side (If Applicable) Improvement Program Anticipated Start Date Notes North Monroe Street Seventh Avenue to Tharpe Street Right of Way
Acquisition for Pedestrian Im-provements and Raised Medians
N/A Capital Projects
-Old Bainbridge Road US 27 to Gadsden County Line Add Paved
Shoul-der Both Safety Project - #436621-1; Completed 2020 Orange Avenue Lake Bradford to Monroe Street Resurfacing Both Resurfacing -
Maintenance -Orange Avenue Capital Circle SE to Lake Bradford Road Sidewalks North Capital Projects -Orchard Pond Greenway Road Old Bainbridge Road to Meridian Road New Road
Con-struction N/A State Infrastruc-ture Bank/Tolls/ Private Funds
-SR 10 (US 90) SR 10 (US 90) east of CR 59 to Jefferson County