262 Page: Thursday, October 2 2014
2001 GO Bonds-Campus Development
2001 LTGO's 2001 LTGO's Expenditures By Program $4,972,900 $5,143,600 $1,758,100 $6,086,125 $0 $6,086,125 $4,972,900 $5,143,600 $1,758,100 $6,086,125 $0 $6,086,125 Total:Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $4,972,900 $5,143,600 $1,758,100 $6,086,125 $0 $6,086,125 $4,972,900 $5,143,600 $1,758,100 $6,086,125 $0 $6,086,125 Total: $4,972,900 $5,143,600 $1,758,100 $6,086,125 $0 $6,086,125
Debt Service and Interest
$4,972,900 $5,143,600 $1,758,100 $6,086,125 $0 $6,086,125
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 20132001 LTGO's
In 2001, the County issued LTGO's to finance the construction of a Public Service Center. The PSC consolidated offices into one location and created space in the Courthouse to be primarily a law and justice center for courts.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
263 Page: Thursday, October 2 2014
2003 $11.835 GO and Refunding Bonds
2003 $11.835 GO and Refunding Bonds2003 $11.835 GO and Refunding Bonds Expenditures By Program $1,591,277 $972,665 $482,874 $737,720 $0 $737,720 $1,591,277 $972,665 $482,874 $737,720 $0 $737,720 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $1,591,277 $972,665 $482,874 $737,720 $0 $737,720 $1,591,277 $972,665 $482,874 $737,720 $0 $737,720 Total: $1,591,277 $972,665 $482,874 $737,720 $0 $737,720
Debt Service and Interest
$1,591,277 $972,665 $482,874 $737,720 $0 $737,720
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
2003 $11.835 GO and Refunding Bonds
2003 $11.835 GO and Refunding Bonds2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support County-Wide
Purpose: Scope:
264 Page: Thursday, October 2 2014
2004- GO Bond-Fairgrounds Debt Svc
2004- GO Bond-Fairgrounds Debt Svc 2004- GO Bond-Fairgrounds Debt Svc Expenditures By Program $2,193,385 $2,354,081 $1,168,666 $2,379,760 $0 $2,379,760 $2,193,385 $2,354,081 $1,168,666 $2,379,760 $0 $2,379,760 Total:Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $2,193,385 $2,354,081 $1,168,666 $2,379,760 $0 $2,379,760 $2,193,385 $2,354,081 $1,168,666 $2,379,760 $0 $2,379,760 Total: $2,193,385 $2,354,081 $1,168,666 $2,379,760 $0 $2,379,760
Debt Service and Interest
$2,193,385 $2,354,081 $1,168,666 $2,379,760 $0 $2,379,760
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 20132004- GO Bond-Fairgrounds Debt Svc
2004- GO Bond-Fairgrounds Debt Svc 2011-2012 2013-2014 2013 2015-2016Operational Planning Categories
Purpose: Scope:
265 Page: Thursday, October 2 2014
2005 $5.7M - GO Bonds
2005 $5.7M - GO Bonds 2005 $5.7M - GO Bonds Expenditures By Program $698,396 $698,196 $346,698 $701,431 $0 $701,431 $698,396 $698,196 $346,698 $701,431 $0 $701,431 Total:Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $698,396 $698,196 $346,698 $701,431 $0 $701,431 $698,396 $698,196 $346,698 $701,431 $0 $701,431 Total: $698,396 $698,196 $346,698 $701,431 $0 $701,431
Debt Service and Interest
$698,396 $698,196 $346,698 $701,431 $0 $701,431
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 20132005 $5.7M - GO Bonds
2011-2012 2013-2014 2013 2015-2016Operational Planning Categories
Purpose: Scope:
266 Page: Thursday, October 2 2014
2013 Claim Settlement
2013 Claim Settlement Loan of $10.5 million
2013 Claim Settlement Expenditures By Program $0 $0 $0 $3,059,310 $0 $3,059,310 $0 $0 $0 $3,059,310 $0 $3,059,310 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $0 $0 $0 $3,059,310 $0 $3,059,310 $0 $0 $0 $3,059,310 $0 $3,059,310 Total: $0 $0 $0 $3,059,310 $0 $3,059,310
Debt Service and Interest
$0 $0 $0 $3,059,310 $0 $3,059,310
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 20132013 Claim Settlement
2011-2012 2013-2014 2013 2015-2016Operational Planning Categories
Purpose: Scope:
267 Page: Thursday, October 2 2014
CAD/800 MHz System Replacement Fund
This fund set up for 2001/2002 accounts for the equipment replacement for CAD/E911 and 800 Mhz radio capital needs
Equipment Replacement Expenditures By Program $3,440,235 $2,102,186 $1,118,857 $1,616,700 $0 $1,616,700 $3,440,235 $2,102,186 $1,118,857 $1,616,700 $0 $1,616,700 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Capital Expenditures Expenditures By Object Category $1,955,570 $1,484,665 $485,486 $1,616,700 $247,557 $871,300 $0 $1,616,700 $0 $0 $0 $1,616,700 $3,440,235 $2,102,186 $1,118,857 $1,616,700 $0 $1,616,700 Total: $3,440,235 $2,102,186 $1,118,857 $1,616,700 $0 $1,616,700 Transfers Capital Expenditures $1,955,570 $1,484,665 $485,486 $1,616,700 $247,557 $871,300 $0 $1,616,700 $0 $0 $0 $1,616,700 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013Equipment Replacement
Equipment Replacement 2011-2012 2013-2014 2013 2015-2016Operational Planning Categories
Essential Regional (County-wide)
Purpose: Scope:
268 Page: Thursday, October 2 2014
CATS Debt Service
CATS Debt ServiceCATS Debt Service Expenditures By Program
$1,293,800 $1,290,750 $645,000 $0 $0 $0
$1,293,800 $1,290,750 $645,000 $0 $0 $0
Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $1,293,800 $1,290,750 $645,000 $0 $0 $0 $1,293,800 $1,290,750 $645,000 $0 $0 $0 Total: $1,293,800 $1,290,750 $645,000 $0 $0 $0
Debt Service and Interest
$1,293,800 $1,290,750 $645,000 $0 $0 $0
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
CATS Debt Service
CATS Debt Service2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Purpose: Scope:
269 Page: Thursday, October 2 2014
Community Health Center
Community Health Center Expenditures By Program
$15,544,814 $4,795,752 $2,388,593 $4,491,436 $0 $4,491,436
$15,544,814 $4,795,752 $2,388,593 $4,491,436 $0 $4,491,436
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers
Debt Service and Interest Expenditures By Object Category $4,572,282 $10,972,532 $4,795,752 $0 $2,388,593 $0 $4,491,436 $0 $0 $0 $4,491,436 $0 $15,544,814 $4,795,752 $2,388,593 $4,491,436 $0 $4,491,436 Total: $15,544,814 $4,795,752 $2,388,593 $4,491,436 $0 $4,491,436 Transfers Debt Service and Interest $4,572,282 $10,972,532 $4,795,752 $0 $2,388,593 $0 $4,491,436 $0 $0 $0 $4,491,436 $0 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Community Health Center
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Essential County-Wide
Purpose: Scope:
270 Page: Thursday, October 2 2014
Community Health Debt Service
Community Health Debt ServiceCommunity Health Debt Service Expenditures By Program $2,938,716 $2,673,598 $1,321,674 $2,702,068 $0 $2,702,068 $2,938,716 $2,673,598 $1,321,674 $2,702,068 $0 $2,702,068 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $2,938,716 $2,673,598 $1,321,674 $2,702,068 $0 $2,702,068 $2,938,716 $2,673,598 $1,321,674 $2,702,068 $0 $2,702,068 Total: $2,938,716 $2,673,598 $1,321,674 $2,702,068 $0 $2,702,068
Debt Service and Interest
$2,938,716 $2,673,598 $1,321,674 $2,702,068 $0 $2,702,068
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Community Health Debt Service
Community Health Debt Service2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Purpose: Scope:
271 Page: Thursday, October 2 2014
Con. Futures Debt Service
Con. Futures Debt ServiceCon. Futures Debt Service Expenditures By Program
$591,725 $591,726 $295,863 $1,542,976 $0 $1,542,976
$591,725 $591,726 $295,863 $1,542,976 $0 $1,542,976
Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $591,725 $591,726 $295,863 $1,542,976 $0 $1,542,976 $591,725 $591,726 $295,863 $1,542,976 $0 $1,542,976 Total: $591,725 $591,726 $295,863 $1,542,976 $0 $1,542,976
Debt Service and Interest
$591,725 $591,726 $295,863 $1,542,976 $0 $1,542,976
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Con. Futures Debt Service
Con. Futures Debt Service2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Purpose: Scope:
272 Page: Thursday, October 2 2014
Conservation Futures
This fund reflects the budget for the Conservation Futures levy, a special property tax earmarked for the acquisition of open space. The tax rate is $.0625/thousand. The tax revenues for this fund are dedicated to the debt service for the LTGO bond issued in 1994 for the acquisition of nineteen (19) properties. Conservation Futures Expenditures By Program $12,496,269 $7,130,403 $1,925,946 $7,749,230 $0 $7,749,230 $12,496,269 $7,130,403 $1,925,946 $7,749,230 $0 $7,749,230 Total:
Actual Budget Actual Baseline Adjustment Total Required
Salaries, Regular Benefits Supplies Temporary Services Professional Services Other Services Transfers
Debt Service and Interest Capital Expenditures Expenditures By Object Category $41 $8 $15,589 $472 $477,961 $0 $4,047,878 $6,793,060 $1,161,260 $0 $0 $0 $0 $867,678 $8,900 $3,453,825 $0 $2,800,000 $0 $0 $0 $129 $219,067 $74,082 $1,632,668 $0 $0 $0 $6,154 $0 $0 $250,000 $0 $5,243,076 $0 $2,250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,154 $0 $0 $250,000 $0 $5,243,076 $0 $2,250,000 $12,496,269 $7,130,403 $1,925,946 $7,749,230 $0 $7,749,230 Total: $12,496,269 $7,130,403 $1,925,946 $7,749,230 $0 $7,749,230 Salaries, Regular Benefits Supplies Temporary Services Professional Services Other Services Transfers Debt Service and Interest Capital Expenditures $41 $8 $15,589 $472 $477,961 $0 $4,047,878 $6,793,060 $1,161,260 $0 $0 $0 $0 $867,678 $8,900 $3,453,825 $0 $2,800,000 $0 $0 $0 $129 $219,067 $74,082 $1,632,668 $0 $0 $0 $6,154 $0 $0 $250,000 $0 $5,243,076 $0 $2,250,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,154 $0 $0 $250,000 $0 $5,243,076 $0 $2,250,000 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013Conservation Futures
This budget accounts for the Conservation Futures levy, a special property tax earmarked for the acquisition of open space. The tax rate is $.0625/thousand.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
273 Page: Thursday, October 2 2014
Economic Development REET II
The BOCC created a fund to account for part of the REET II that was extended in 2002 to promote economic development through capital improvements related to roads, parks, water, and sewer systems and other improvements that mitigate the impacts of residential, industrial, and commercial growth.
Economic Development Expenditures By Program $7,694,184 $8,500,702 $6,906,324 $6,568,400 $600,000 $7,168,400 $7,694,184 $8,500,702 $6,906,324 $6,568,400 $600,000 $7,168,400 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers
Debt Service and Interest Capital Expenditures Expenditures By Object Category $4,629,529 $2,873,114 $191,541 $8,380,702 $0 $120,000 $6,906,324 $0 $0 $6,568,400 $0 $0 $600,000 $0 $0 $7,168,400 $0 $0 $7,694,184 $8,500,702 $6,906,324 $6,568,400 $600,000 $7,168,400 Total:
Department Summary
2011-2012 2013-2014 2013 2015-2016274 Page: Thursday, October 2 2014
Economic Development REET II
$7,694,184 $8,500,702 $6,906,324 $6,568,400 $600,000 $7,168,400
$600,000 Transfers
Debt Service and Interest Capital Expenditures $4,629,529 $2,873,114 $191,541 $8,380,702 $0 $120,000 $6,906,324 $0 $0 $6,568,400 $0 $0 $600,000 $0 $0 $7,168,400 $0 $0 Total:
REET Capital Repair for Parks 3086-482-01
This decision package requests continued funding and use of the REET Capital Repair program in the amount of $600,000 for Regional Parks. The requested funding also pays for limited internal and departmental staff time to manage capital repairs. This program has been in existence for over ten years and is essential for keeping the Regional Parks infrastructure safe and operational.
Captain William Clark
- Bank Stabilization around concrete canoes $10,000 Daybreak
-Repave boat ramp parking lot and restripe $80,000 -Repair pot holes in west parking lot $ 7,000 Frenchman's Bar
-Remove pole barn at south end $8,000 Lewisville
-Repave road to Island section $37,000 -Replace picnic table pads (10) $12,000 -Resurface concrete at bath house $27,000 -Re-roof Central, Dogwood, Filbert, Hemlock &
Juniper shelters $75,000 -Re-gravel A parking lot $10,000 -Repair & rebuild cracked stove & fire places at
C, K & A shelters $65,000 Lucia Falls
-Assess viewing deck for any safety concerns $ 1,000 -Demolish deck behind old restaurant $15,000 Minkler
- Repaint rental $15,000 Moulton Falls
- Paint high bridge $ 8,000 Vancouver Lake Park
-Install ADA path to beach $60,000 -Repair cracked restroom wall Ph2 $35,000 Various
-Signage $35,000
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$600,000 Program By Object Category 0.00 $0 0.00 $0 3083-000-597086-Transfer Out to 3086 Program Summary 2011-2012 2013-2014 2013
Economic Development
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Discretionary Local
Purpose: Scope:
275 Page: Thursday, October 2 2014
Facilities Energy Savings
Facilities Energy Savings - Capital Lease Expenditures By Program $261,965 $919,965 $430,529 $1,029,825 $0 $1,029,825 $261,965 $919,965 $430,529 $1,029,825 $0 $1,029,825 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $261,965 $919,965 $430,529 $1,029,825 $0 $1,029,825 $261,965 $919,965 $430,529 $1,029,825 $0 $1,029,825 Total: $261,965 $919,965 $430,529 $1,029,825 $0 $1,029,825
Debt Service and Interest
$261,965 $919,965 $430,529 $1,029,825 $0 $1,029,825
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Facilities Energy Savings - Capital Lease
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Purpose: Scope:
276 Page: Thursday, October 2 2014
General Obligation - 1993 $5.01M
Fairground Park Acq. & Fund 1991 BAN Expenditures By Program $172,124 $88,655 $88,655 $0 $0 $0 $172,124 $88,655 $88,655 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $172,124 $88,655 $88,655 $0 $0 $0 $172,124 $88,655 $88,655 $0 $0 $0 Total: $172,124 $88,655 $88,655 $0 $0 $0
Debt Service and Interest
$172,124 $88,655 $88,655 $0 $0 $0
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Fairground Park Acq. & Fund 1991 BAN
This program reflects principal and interest on general obligation bond debt incurred for acquisitions of property adjacent to the fairgrounds.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
277 Page: Thursday, October 2 2014
General Obligation - 1998
General Obligation - 1998 Expenditures By Program $4,090,132 $4,111,500 $2,054,750 $3,913,500 $0 $3,913,500 $4,090,132 $4,111,500 $2,054,750 $3,913,500 $0 $3,913,500 Total:Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $4,090,132 $4,111,500 $2,054,750 $3,913,500 $0 $3,913,500 $4,090,132 $4,111,500 $2,054,750 $3,913,500 $0 $3,913,500 Total: $4,090,132 $4,111,500 $2,054,750 $3,913,500 $0 $3,913,500
Debt Service and Interest
$4,090,132 $4,111,500 $2,054,750 $3,913,500 $0 $3,913,500
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013General Obligation - 1998
Pay debt service requirements on Jail Work Center and Juvenile Detention expansion.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
278 Page: Thursday, October 2 2014
General Obligation - 1999
1999 General Obligation Bonds for new Jail Work Center, Remittance Processor, Tri-Mountain Golf Equipment, and general equipment.
General Obligation - 1999 Expenditures By Program $863,325 $845,900 $1,204,400 $848,000 $0 $848,000 $863,325 $845,900 $1,204,400 $848,000 $0 $848,000 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $863,325 $845,900 $1,204,400 $848,000 $0 $848,000 $863,325 $845,900 $1,204,400 $848,000 $0 $848,000 Total: $863,325 $845,900 $1,204,400 $848,000 $0 $848,000
Debt Service and Interest
$863,325 $845,900 $1,204,400 $848,000 $0 $848,000
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013General Obligation - 1999
To meet debt service payments on new Jail Work Center, Remittance Processor, Tri-Mountain equipment, and general capital.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Essential Regional (County-wide)
Purpose: Scope:
279 Page: Thursday, October 2 2014
General Obligation - 1999 $3M GO Bonds
LTGO's for the joint Fire/Sheriff Fairgrounds FacilityFire/Sheriff Fairgrounds Facility Expenditures By Program $477,846 $482,710 $242,355 $483,210 $0 $483,210 $477,846 $482,710 $242,355 $483,210 $0 $483,210 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $477,846 $482,710 $242,355 $483,210 $0 $483,210 $477,846 $482,710 $242,355 $483,210 $0 $483,210 Total: $477,846 $482,710 $242,355 $483,210 $0 $483,210
Debt Service and Interest
$477,846 $482,710 $242,355 $483,210 $0 $483,210
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Fire/Sheriff Fairgrounds Facility
To meet general LTGO on the Fire/Sheriff Fairgrounds Facility.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Essential Regional (County-wide)
Purpose: Scope:
280 Page: Thursday, October 2 2014
General Obligation 1996
This department was set up to track the debt service payments for the LTGO issued in 1996.
General Obligation 1996 Expenditures By Program $803,478 $808,576 $410,348 $405,600 $0 $405,600 $803,478 $808,576 $410,348 $405,600 $0 $405,600 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $803,478 $808,576 $410,348 $405,600 $0 $405,600 $803,478 $808,576 $410,348 $405,600 $0 $405,600 Total: $803,478 $808,576 $410,348 $405,600 $0 $405,600
Debt Service and Interest
$803,478 $808,576 $410,348 $405,600 $0 $405,600
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013General Obligation 1996
This department has only one program. See department description.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
281 Page: Thursday, October 2 2014
General Obligation 1996 800 MHz
This department was set up to track the debt service payments for the LTGO issued in 1996 for the 800 MHz communications system.
General Obligation 1996 800 MHz Expenditures By Program $489,458 $485,486 $247,557 $477,450 $0 $477,450 $489,458 $485,486 $247,557 $477,450 $0 $477,450 Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $489,458 $485,486 $247,557 $477,450 $0 $477,450 $489,458 $485,486 $247,557 $477,450 $0 $477,450 Total: $489,458 $485,486 $247,557 $477,450 $0 $477,450
Debt Service and Interest
$489,458 $485,486 $247,557 $477,450 $0 $477,450
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013General Obligation 1996 800 MHz
This department has only one program. See department description.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
282 Page: Thursday, October 2 2014
General Obligation Bonds-PWTF
Design & Engineering Expenditures By Program
$170,548 $219,126 $97,650 $194,428 $0 $194,428
$170,548 $219,126 $97,650 $194,428 $0 $194,428
Total:
Actual Budget Actual Baseline Adjustment Total Required
Debt Service and Interest Expenditures By Object Category $170,548 $219,126 $97,650 $194,428 $0 $194,428 $170,548 $219,126 $97,650 $194,428 $0 $194,428 Total: $170,548 $219,126 $97,650 $194,428 $0 $194,428
Debt Service and Interest
$170,548 $219,126 $97,650 $194,428 $0 $194,428
Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Design & Engineering
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
283 Page: Thursday, October 2 2014
Information Reserve - Data Processing
The Information Technology Reserve Fund funds replacement of major software applications as identified in the Information Technology Strategic Plan.
Server Replacement Plan Expenditures By Program
$2,110,352 $4,070,446 $434,627 $2,857,289 $9,415,942 $12,273,231 $2,110,352 $4,070,446 $434,627 $2,857,289 $9,415,942 $12,273,231 Total:
Actual Budget Actual Baseline Adjustment Total Required
Salaries, Regular Benefits Allowances Overtime/Comp Time Supplies Temporary Services Professional Services Travel and Training Other Services Transfers Capital Expenditures Expenditures By Object Category $49,443 $5,698 $6 $342 $43,332 $2,780 $795,281 $72,801 $53,596 $776,552 $310,521 $8,600 $0 $0 $0 $45,773 $0 $1,195,433 $0 $150,000 $599,498 $2,071,142 $88,624 $18,529 $24 $0 $3,859 $0 $314,762 $8,829 $0 $0 $0 $179,112 $49,148 $0 $0 $0 $0 $477,000 $0 $152,029 $0 $2,000,000 $49,000 $0 $0 $0 $0 $0 $450,000 $20,000 $148,142 $0 $8,748,800 $228,112 $49,148 $0 $0 $0 $0 $927,000 $20,000 $300,171 $0 $10,748,800 $2,110,352 $4,070,446 $434,627 $2,857,289 $9,415,942 $12,273,231 Total:
Department Summary
2011-2012 2013-2014 2013 2015-2016284 Page: Thursday, October 2 2014
Information Reserve - Data Processing
$2,110,352 $4,070,446 $434,627 $2,857,289 $9,415,942 $12,273,231 Salaries, Regular Benefits Allowances Overtime/Comp Time Supplies Temporary Services Professional Services Travel and Training Other Services Transfers Capital Expenditures $49,443 $5,698 $6 $342 $43,332 $2,780 $795,281 $72,801 $53,596 $776,552 $310,521 $8,600 $0 $0 $0 $45,773 $0 $1,195,433 $0 $150,000 $599,498 $2,071,142 $88,624 $18,529 $24 $0 $3,859 $0 $314,762 $8,829 $0 $0 $0 $179,112 $49,148 $0 $0 $0 $0 $477,000 $0 $152,029 $0 $2,000,000 $49,000 $0 $0 $0 $0 $0 $450,000 $20,000 $148,142 $0 $8,748,800 $228,112 $49,148 $0 $0 $0 $0 $927,000 $20,000 $300,171 $0 $10,748,800 Total: Bi Discover Replacement
Enterprise Content Mgt System
JMS Carryover Funds
REGJIN carryover funds
Tidemark Replacement Carryover
3194-390-03
3194-390-01
3194-390-06
3194-390-05
3194-390-04 In June 2014 Oracle, our Financial Management System (FMS) vendor, scheduled de-support of Oracle Business Intelligence Discoverer (BI Discoverer), our FMS reporting software package add-on. BI Discoverer enables end users in various departments to create reports that can be easily run by other FMS users. Because of the de-support of BI Discoverer and other pressing reporting needs, such as for HR and benefits, this Decision Package requests funding to acquire an end user reporting solution that will replace BI Discoverer and enhance reporting functionality without requiring substantial effort on the part of the Application Services Department.
Financial Services and Application Services have been gathering requirements for a reporting solution to replace BI Discoverer. Various vendors have been identified and are being evaluated to determine how well they meet those requirements. It is estimated that selection of vendor finalists for trial will be completed by 2014 year end.
The reporting solution will cost approximately $180,000.00. This cost will cover the installation of the new software, licensing, and supported maintenance for one year. Subsequent maintenance fees will be approximately 25% of non-discounted licensing costs annually. Current Discoverer maintenance of $5,000 will be eliminated annually.
This request is for a one-time charge in the 2015-2016 biennium with ongoing annual maintenance beginning in 2015 of $30,000 per biennium.
Enterprise Content Management System Implementation Package. Supplemental funding is requested to replace the County-Wide Oracle Imaging System which will be unsupported by Oracle in December 2015. This is an addition to funding request of $318,032 that was approved in the last biennium. None of the originally approved funding has been spent to date and will be used along with the net new revenue to implement a new system. The cost of the system will be $934,000 with $192,000 for software, $20,000 for IS hardware, $49,000 contingency, $20,000 for training, $77,000 for the first two years of maintenance, and $576,000 for professional services which includes labor, travel, consulting, development and conversion.
This package is to request to carry funds over from the 2013-14 biennium to the 2015-16 biennium to complete the ongoing Jail Management System(JMS) Project.
This package is to request to carry funds over from the 2013-14 biennium to the 2015-16 biennium to complete the ongoing REGJIN Project.
Actual Budget Actual Baseline Adjustment Recommended
$180,000 $616,000 $2,430,958 $1,533,569 $4,584,273 Program By Object Category 0.00 0.00 0.00 0.00 0.00 $0 $0 $0 $0 $0 3194-390-594180-Capital-General Gov.
3194-390-518868-County S/W & H/W Maintenance
3194-390-594190-Capital-Gen Government
3194-390-594190-Capital-Gen Government
Program Summary
2011-2012 2013-2014 2013
Server Replacement Plan
Maintain and upgrade existing servers and purchase new servers when needed.
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Essential Regional (County-wide)
Purpose: Scope:
285 Page: Thursday, October 2 2014
Information Reserve - Data Processing
$9,415,942 Tidemark Replacement Carryover
Two Factor Authentication
3194-390-04
3194-390-02 This decision package is a request to carry funds over from the 2013-14 biennium to the 2015-16 biennium to complete the ongoing Tidemark Replacement Project.
In October 2013, the FBI implemented additional security measures upon organizations requiring access into their systems. Among these new measures will be the use of two factor authenication for all users attempting access into the FBI systems. Two-Factor Authentication typically requires the end user to use something they know, example a password, and something they have, example a token fob, in order to gain access to the system.
Budget Adjustment Total:
$71,142
0.00 $0
0.00 $0
3194-390-518875-CCIS Application Support and Programming
3194-390-594121-Capital Outlay-Sheriff
286 Page: Thursday, October 2 2014
Orchards Road Benefit Area - TIF
This fund is a reserve fund for Transportation Impact Fees collected in the Orchards Road Benefit Area.
Orchards Road Benefit Area Expenditures By
Program
$0 $83,000 $0 $242,200 $0 $242,200
$0 $83,000 $0 $242,200 $0 $242,200
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $83,000 $0 $242,200 $0 $242,200 $0 $83,000 $0 $242,200 $0 $242,200 Total: $0 $83,000 $0 $242,200 $0 $242,200 Transfers $0 $83,000 $0 $242,200 $0 $242,200 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Orchards Road Benefit Area
This program reflects transfer from the Orchards Road Benefit Reserve Fund.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
287 Page: Thursday, October 2 2014
PIF Development #1
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #1 Expenditures By Program $0 $0 $8,564 $6,700 $0 $6,700 $0 $0 $8,564 $6,700 $0 $6,700 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $8,564 $6,700 $0 $6,700 $0 $0 $8,564 $6,700 $0 $6,700 Total: $0 $0 $8,564 $6,700 $0 $6,700 Transfers $0 $0 $8,564 $6,700 $0 $6,700 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #1
This program reflects transfers to the City of Vancouver from PIF District No 2.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
288 Page: Thursday, October 2 2014
PIF Development #10
Exists solely to receipt and transfer money to the City of Vancouver.
PIF -- Development #10 Expenditures By Program $20,859 $40,000 $37,011 $0 $0 $0 $20,859 $40,000 $37,011 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Capital Expenditures Expenditures By Object Category $2,859 $18,000 $40,000 $0 $37,011 $0 $0 $0 $0 $0 $0 $0 $20,859 $40,000 $37,011 $0 $0 $0 Total: $20,859 $40,000 $37,011 $0 $0 $0 Transfers Capital Expenditures $2,859 $18,000 $40,000 $0 $37,011 $0 $0 $0 $0 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #10
This program reflects transfers to the City of Vancouver from PIF District No. 10.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
289 Page: Thursday, October 2 2014
PIF Development #4
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #4 Expenditures By Program $440 $0 $0 $0 $0 $0 $440 $0 $0 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $440 $0 $0 $0 $0 $0 $440 $0 $0 $0 $0 $0 Total: $440 $0 $0 $0 $0 $0 Transfers $440 $0 $0 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #4
This program reflects transfers to the City of Vancouver from PIF District No. 4.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
290 Page: Thursday, October 2 2014
PIF Development #5
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #5 Expenditures By Program $52,433 $60,000 $51,843 $0 $0 $0 $52,433 $60,000 $51,843 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $52,433 $60,000 $51,843 $0 $0 $0 $52,433 $60,000 $51,843 $0 $0 $0 Total: $52,433 $60,000 $51,843 $0 $0 $0 Transfers $52,433 $60,000 $51,843 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #5
This program reflects transfers to the City of Vancouver from PIF District No. 5.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
291 Page: Thursday, October 2 2014
PIF Development #6
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #6 Expenditures By Program $27,319 $140,000 $50,293 $0 $5,000 $5,000 $27,319 $140,000 $50,293 $0 $5,000 $5,000 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $27,319 $140,000 $50,293 $0 $5,000 $5,000 $27,319 $140,000 $50,293 $0 $5,000 $5,000 Total: $27,319 $140,000 $50,293 $0 $5,000 $5,000 $5,000 Professional Services Transfers $0 $27,319 $0 $140,000 $0 $50,293 $0 $0 $0 $5,000 $0 $5,000 Total:
Parks Administration Increase 0001-488-01
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 Program By Object Category 0.00 $0 0.00 $0 3176-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #6
This program reflects transfers to the City of Vancouver from PIF District No. 6.
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
292 Page: Thursday, October 2 2014
PIF Development #7
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #7 Expenditures By Program $68,202 $80,000 $108,321 $0 $40,000 $40,000 $68,202 $80,000 $108,321 $0 $40,000 $40,000 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $68,202 $80,000 $108,321 $0 $40,000 $40,000 $68,202 $80,000 $108,321 $0 $40,000 $40,000 Total: $68,202 $80,000 $108,321 $0 $40,000 $40,000 $40,000 Professional Services Transfers $0 $68,202 $0 $80,000 $0 $108,321 $0 $0 $0 $40,000 $0 $40,000 Total:
Parks Administration Increase
Tower Crest Park Construction
0001-488-01
3055-488-04 The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Approve funding and process to design Tower Crest Neighborhood Park as part of the Greater Clark Parks District.
PIF District 7 development funds will be utilized to complete this work.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 $35,000 Program By Object Category 0.00 $0 0.00 0.00 $0 $0 3177-488-597001-Transfer Out To 0001 3177-488-597055-Transfer Out To 3055
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #7
This program reflects transfers to the City of Vancouver from PIF District No. 7.
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
293 Page: Thursday, October 2 2014
PIF Development #8
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #8 Expenditures By Program $6,725 $40,000 $36,227 $0 $0 $0 $6,725 $40,000 $36,227 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Capital Expenditures Expenditures By Object Category $5,796 $929 $40,000 $0 $36,227 $0 $0 $0 $0 $0 $0 $0 $6,725 $40,000 $36,227 $0 $0 $0 Total: $6,725 $40,000 $36,227 $0 $0 $0 Transfers Capital Expenditures $5,796 $929 $40,000 $0 $36,227 $0 $0 $0 $0 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #8
This program reflects transfers to the City of Vancouver from PIF District No. 8.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
294 Page: Thursday, October 2 2014
PIF Development #9
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
PIF -- Development #9 Expenditures By Program $365 $70,000 $100,000 $0 $105,000 $105,000 $365 $70,000 $100,000 $0 $105,000 $105,000 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $365 $70,000 $100,000 $0 $105,000 $105,000 $365 $70,000 $100,000 $0 $105,000 $105,000 Total: $365 $70,000 $100,000 $0 $105,000 $105,000 $105,000 Professional Services Transfers $0 $365 $0 $70,000 $0 $100,000 $0 $0 $0 $105,000 $0 $105,000 Total:
Parks Administration Increase
Sorenson Park Construction
0001-488-01
3055-488-03 The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Approve funding and process to design Sorenson Neighborhood Park as part of the Greater Clark Parks District.
PIF District 9 development funds will be utilized to complete this work.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 $100,000 Program By Object Category 0.00 $0 0.00 0.00 $0 $0 3179-488-597001-Transfer Out To 0001 3179-488-597055-Transfer Out To 3055
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF -- Development #9
This program reflects transfers to the City of Vancouver from PIF District No. 9.
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
295 Page: Thursday, October 2 2014
PIF District 10 - Acquis& Develop. combined
PIF Acq & Dev #10 Expenditures By Program
$0 $0 $0 $165,672 $0 $165,672
$0 $0 $0 $165,672 $0 $165,672
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $0 $165,672 $0 $165,672 $0 $0 $0 $165,672 $0 $165,672 Total: $0 $0 $0 $165,672 $0 $165,672 Transfers $0 $0 $0 $165,672 $0 $165,672 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
PIF Acq & Dev #10
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
296 Page: Thursday, October 2 2014
PIF District 5 - Acquis& Develop. combined
PIF Acq & Dev #5 Expenditures By Program
$0 $0 $0 $272,853 $40,000 $312,853
$0 $0 $0 $272,853 $40,000 $312,853
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $0 $272,853 $40,000 $312,853 $0 $0 $0 $272,853 $40,000 $312,853 Total: $0 $0 $0 $272,853 $40,000 $312,853 $40,000 Professional Services Transfers $0 $0 $0 $0 $0 $0 $0 $272,853 $0 $40,000 $0 $312,853 Total:
Otto Brown Park Construction
Parks Administration Increase
3055-488-02
0001-488-01 Approve funding and process to design Otto Brown Neighborhood Park as part of the Greater Clark Parks District.
PIF District 5 development funds will be utilized to complete this work.
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$35,000 $5,000 Program By Object Category 0.00 $0 0.00 0.00 $0 $0 3275-488-597055-Transfer Out To 3055 3275-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF Acq & Dev #5
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
297 Page: Thursday, October 2 2014
PIF District 6 - Acquis& Develop. combined
PIF Acq & Dev #6 Expenditures By Program
$0 $0 $0 $0 $5,000 $5,000
$0 $0 $0 $0 $5,000 $5,000
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $0 $0 $5,000 $5,000 $0 $0 $0 $0 $5,000 $5,000 Total: $0 $0 $0 $0 $5,000 $5,000 $5,000 Professional Services Transfers $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000 $0 $5,000 Total:
Parks Administration Increase 0001-488-01
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 Program By Object Category 0.00 $0 0.00 $0 3276-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF Acq & Dev #6
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
298 Page: Thursday, October 2 2014
PIF District 7 - Acquis& Develop. combined
PIF Acq & Dev #7 Expenditures By Program
$0 $0 $0 $0 $5,000 $5,000
$0 $0 $0 $0 $5,000 $5,000
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $0 $0 $5,000 $5,000 $0 $0 $0 $0 $5,000 $5,000 Total: $0 $0 $0 $0 $5,000 $5,000 $5,000 Professional Services Transfers $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000 $0 $5,000 Total:
Parks Administration Increase 0001-488-01
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 Program By Object Category 0.00 $0 0.00 $0 3277-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF Acq & Dev #7
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
299 Page: Thursday, October 2 2014
PIF District 8 - Acquis& Develop. combined
PIF Acq & Dev #8 Expenditures By Program
$0 $0 $0 $216,000 $0 $216,000
$0 $0 $0 $216,000 $0 $216,000
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $0 $216,000 $0 $216,000 $0 $0 $0 $216,000 $0 $216,000 Total: $0 $0 $0 $216,000 $0 $216,000 Transfers $0 $0 $0 $216,000 $0 $216,000 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
PIF Acq & Dev #8
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
300 Page: Thursday, October 2 2014
PIF District 9 - Acquis& Develop. combined
PIF Acq & Dev #9 Expenditures By Program
$0 $0 $0 $0 $5,000 $5,000
$0 $0 $0 $0 $5,000 $5,000
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $0 $0 $0 $0 $5,000 $5,000 $0 $0 $0 $0 $5,000 $5,000 Total: $0 $0 $0 $0 $5,000 $5,000 $5,000 Professional Services Transfers $0 $0 $0 $0 $0 $0 $0 $0 $0 $5,000 $0 $5,000 Total:
Parks Administration Increase 0001-488-01
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 Program By Object Category 0.00 $0 0.00 $0 3279-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013PIF Acq & Dev #9
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
301 Page: Thursday, October 2 2014
Park Impact Fees--District 1
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
Park Impact Fees--District 1 Expenditures By
Program
$0 $0 $29,810 $35,000 $5,000 $40,000
$0 $0 $29,810 $35,000 $5,000 $40,000
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Capital Expenditures Expenditures By Object Category $0 $0 $0 $0 $29,810 $0 $0 $35,000 $5,000 $0 $5,000 $35,000 $0 $0 $29,810 $35,000 $5,000 $40,000 Total: $0 $0 $29,810 $35,000 $5,000 $40,000 $5,000 Professional Services Transfers Capital Expenditures $0 $0 $0 $0 $0 $0 $0 $29,810 $0 $0 $0 $35,000 $0 $5,000 $0 $0 $5,000 $35,000 Total:
Parks Administration Increase 0001-488-01
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 Program By Object Category 0.00 $0 0.00 $0 3071-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013Park Impact Fees--District 1
This program reflects PIF expenditures in park service district No. 1. Dollars are transferred from the impact fee fund to the Capital Acquisition Fund for expenditure on eligible projects.
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
302 Page: Thursday, October 2 2014
Park Impact Fees--District 10
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
Park Impact Fees--District 10 Expenditures By Program $19,006 $90,000 $90,000 $1,933,000 $5,000 $1,938,000 $19,006 $90,000 $90,000 $1,933,000 $5,000 $1,938,000 Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Capital Expenditures Expenditures By Object Category -$11,996 $31,002 $90,000 $0 $90,000 $0 $0 $1,933,000 $5,000 $0 $5,000 $1,933,000 $19,006 $90,000 $90,000 $1,933,000 $5,000 $1,938,000 Total: $19,006 $90,000 $90,000 $1,933,000 $5,000 $1,938,000 $5,000 Professional Services Transfers Capital Expenditures $0 -$11,996 $31,002 $0 $90,000 $0 $0 $90,000 $0 $0 $0 $1,933,000 $0 $5,000 $0 $0 $5,000 $1,933,000 Total:
Parks Administration Increase 0001-488-01
The newly formed Parks Division requests additional funding to pay for internal contracted services from different departments and divisions within Clark County. This request also seeks funding to support additional seasonal temporary staff and needed supplies to support the functions of the division. No full time staffing is being requested at this time. The 2015 & 16 biennium period will be utilized to analyze the long term administrative staffing needs for the Parks Division.
Revenues for this request are from PIF Acquisition and Development funds as well as the GCPD Fund and the General Fund.
Budget Adjustment Total:
Actual Budget Actual Baseline Adjustment Recommended
$5,000 Program By Object Category 0.00 $0 0.00 $0 3080-488-597001-Transfer Out To 0001
Department Summary
Program Summary 2011-2012 2013-2014 2013Park Impact Fees--District 10
This program reflects PIF expenditures in park service district No. 10. Dollars are transferred from the impact fee fund to the Capital Acquisition Fund for expenditure on eligible projects.
2011-2012 2013-2014 2013 2015-2016
Budget Adjustments FTE Expenditure Revenue
Operational Planning Categories
Support Internal
Purpose: Scope:
303 Page: Thursday, October 2 2014
Park Impact Fees--District 4
The information presented here is for prior period expenditures.
Park Impact Fees--District 4 Expenditures By
Program
$1,302 $0 $258 $0 $0 $0
$1,302 $0 $258 $0 $0 $0
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Expenditures By Object Category $1,302 $0 $258 $0 $0 $0 $1,302 $0 $258 $0 $0 $0 Total: $1,302 $0 $258 $0 $0 $0 Transfers $1,302 $0 $258 $0 $0 $0 Total:
Actual Budget Actual Baseline Adjustment Recommended
Program By Object Category
Department Summary
Program Summary
2011-2012 2013-2014 2013
Park Impact Fees--District 4
This program reflects PIF expenditures in park service district No. 4. Dollars are transferred from the impact fee fund to the Capital Acquisition Fund for expenditure on eligible projects.
2011-2012 2013-2014 2013 2015-2016
Operational Planning Categories
Support Internal
Purpose: Scope:
304 Page: Thursday, October 2 2014
Park Impact Fees--District 5
This budget reflects the transfer of impact fee funds to other County funds to reimburse for acquisition and development of capital facilities to serve new growth.
Park Impact Fees--District 5 Expenditures By
Program
$163,366 $160,000 $160,144 $1,983,000 $5,000 $1,988,000
$163,366 $160,000 $160,144 $1,983,000 $5,000 $1,988,000
Total:
Actual Budget Actual Baseline Adjustment Total Required
Transfers Capital Expenditures Expenditures By Object Category $163,366 $0 $160,000 $0 $160,144 $0 $0 $1,983,000 $5,00