• No results found

Developing Critical Path Method Scheduling (CPM)

N/A
N/A
Protected

Academic year: 2021

Share "Developing Critical Path Method Scheduling (CPM)"

Copied!
39
0
0

Loading.... (view fulltext now)

Full text

(1)

Developing Critical Path Method 

Scheduling (CPM)

(2)

Pretest

Pretest

1 An activity which is on critical path has a 1. An activity which is on critical path has a 

planned duration of 5 days.  What is the  total float for the activity?

total float for the activity? a. 0 b 1 b. 1 c. 2 d 3 d. 3

(3)

Pretest

Pretest

2 Which is not a widely recognized type of 2. Which is not a widely recognized type of  scheduling method? a CPM a. CPM b. Linear c Vertical c. Vertical d. Bar

(4)

Pretest

Pretest

3 Which of the following is directly affected by 3. Which of the following is directly affected by  project scheduling? a Time a. Time b. Cost c Work Flow c. Work Flow d. Man Power All f th b e. All of the above

(5)

Pretest

Pretest

4 Of the three (3) main scheduling methods 4. Of the three (3) main scheduling methods,  which one uses relationships between  activities? activities? a) Linear b) CPM b) CPM c) Bar

(6)

Pretest

Pretest

5 Which scheduling method is the most 5. Which scheduling method is the most  commonly practiced? a) Bar a) Bar b) Vertical c) Linear c) Linear d) CPM

(7)

Pretest

Pretest

6 Total Float is the amount of time an activity 6. Total Float is the amount of time an activity 

can be delayed without delaying completion  date of the project

date of the project.

a) True b) False b) False

(8)

Pretest

Pretest

7. The Work Breakdown Structure (WBS) should be 7. The Work Breakdown Structure (WBS) should be 

used for identifying the activities and for  organizing the schedule.

a) True b) False

(9)

Pretest

Pretest

8. Which of the following should be used in 8. Which of the following should be used in  determining activity durations? a) Historical Data) b) Manuals c) Experience c) Experience d) Field recommendations e) All of the above

(10)

Pretest

Pretest

10 Who should do project scheduling? 10. Who should do project scheduling? a) Project Manager b) Owner b) Owner c) Superintendent d) All f th b d) All of the above

(11)

Pretest

Pretest

9. There is always more than one correct logic for 9. There is always more than one correct logic for 

completion of a project. a) True)

(12)

Purpose and Background for 

h d l

Construction Schedules

Determine reasonable and accurate contract  time for constructionContract time is the maximum time allowed in the  contract for completion of all work contained in the contract for completion of all work contained in the  contract documents. h d l h fProject Scheduling is the process of:Identifying the activities necessary to complete the  project projectAssigning realistic durations to each activityEstablishing start and finish dates for each activity

(13)

What Does a Schedule Do?

What Does a Schedule Do?

Helps the owners in planning during theHelps the owners in planning during the  development of the projectPublic NotificationsPublic NotificationsRoad ClosuresConstruction sequencing, phasing &  milestonesAlternate bid schedules

(14)

Effects of Insufficient Contract Time

Effects of Insufficient Contract Time

Bid prices may be higherUnusual number of time overrunsContractor ClaimsMissed milestones

(15)

Effects of Excessive Contract Time

Effects of Excessive Contract Time

Cost inefficiencies by the contractorCost inefficiencies by the contractor

Public may be inconvenienced unnecessarilyTravel on unsafe roadways for and extended

Travel on unsafe roadways for and extended  period of time

* If the time set is such that all work on a  If the time set is such that all work on a  project may be stopped for an extended 

period and the contractor can still complete period and the contractor can still complete  the project on schedule – time allowed was  excessive

(16)

Schedule Guidelines

Schedule Guidelines

When should you create your first schedule?When should you create your first schedule?

Schematic Drawings ‐30% Design Development 50%

Design Development – 50%

Submittal Drawings – 90%

(17)

Determining Contract Time –

d

Production Rate

What is Production Rate?What is Production Rate?

The quantity produced or constructed over a  specific time period.

specific time period.

Why is this important?

Helps determine appropriate completion time

Helps determine appropriate completion time.

Production rates may vary considerably 

d di j i l i d

depending on project size, location and  setting.

(18)

Determining Contract Time –

d

Production Rate

Establishing Production RatesEstablishing Production Rates

Divide the total quantity of an item by the  number of days/hours used to complete the  item.

Base production rates upon a 5‐day work week/  8hr crew days/ our per piece of equipment

8hr crew days/ our per piece of equipment

Historic data DOT data

DOT data

RSMeans

Cost Data books

(19)

Hot Asphalt Concrete Pavement 

d

Production Rate:

HACP Paving (max) – 1 980 tons/day HACP Paving (max)  1,980 tons/day HACP Paving (min) – 1,320 tons/day Starting Rate = (1980 + 1320)/2 = 1,650  tons/day (8 hour day) Projects Specifics:j pCold Temps

(20)

Other Factors Affecting Contract 

Times

Effects of Traffic

Curing Times / waiting periods between paving courses

Curing Times / waiting periods between paving coursesSetup/mobilization/special equipmentSeasonal LimitationsConflicting OperationsConflicting OperationsSubmittal review TimesFabrication TimesLead timesLead timesLong – lead ItemsHolidays N b f C / SiNumber of Crews/crew SizeEnvironmentalTemporary construction S ilSoils

(21)

Steps for Creating CPM Schedules

Steps for Creating CPM Schedules

Define the Work DayDefine the Work Day

Define the Project Calendar & Task Calendar d if G d S h i i iIdentify, Group and Sequence the ActivitiesSet activity DurationsLink ActivitiesDocumentationDocumentationUpdate

(22)

Defining the Work Day

Defining the Work Day

Work hours establish the daily work times.

(23)

Defining the Project Calendar

Defining the Project Calendar

Defines project’s work and non‐work daysDefines project s work and non work days

Saturdays, Sundays, Holidays

Other Contractual non work days

Other Contractual non‐work days

Local Events

Task Calendars define work that can only be  performed at a specific time and date.

(24)

Activities

Activities

A key factor in any realistic schedule is to include the y y right activities.Consider each project as unique. B k j t i t i di id l ti itiBreak project scope into individual activitiesWork Breakdown Structure (WBS) should be used for  identifying the activities and for organizing the scheduleThe number of activities depends upon the complexity of  the projectOnce Activities are identified and grouped, determine  the general sequencing of the activities.

(25)

Typical Activity Inclusions & 

l

Exclusions

StakingStakingOnly show staking tasks that are necessary to start  the project (e.g., clearing limits and slope stakes).  p j ( g g p )Clearing & GrubbingShow only work needed to begin major activitiesy g jErosion Control

In‐place items before major grading operationsIn place items before major grading operations

Earthwork

Break out rock excavation as a separate activityBreak out rock excavation as a separate activity

(26)

Typical Activity Inclusions & 

l

Exclusions

Pavement Structure ItemsCombine associated items as one work activitySeparate major structure items such as; base course  and asphalt and asphaltBridge ActivitiesShow by phase of construction – foundation, y p , substructure, superstructureSub Excavation C bi i t ti itCombine into one activityDrainage

(27)

Typical Activity Inclusions & 

l

Exclusions

Turf EstablishmentTurf Establishment

Show as one item

Signage & StripingSignage & Striping

Combine all permanent traffic control signing  and striping into one activity

and striping into one activity.

Guardrail

(28)

Activity Durations

Activity Durations

• Setting durations is a critical step to creating aSetting durations is a critical step to creating a  reasonable schedule.

• Factors effecting time should be taken into • Factors effecting time should be taken into  consideration. Adj i i d i b d d i • Adjust activity durations based on production  rates. • Try and limit the duration for any activity to 20  days.

(29)

Link Activities

Link Activities

Determine activity relationshipsy p

Late Finish (LF): The latest time an activity can be finished.

Late Start (LS): The latest time an activity can be started 

without delaying completion of the project LS LF D without delaying completion of the project. LS = LF – DTotal Float: The amount of time an activity can be delayed  without delaying completion date of the project. TF = LF – EF + LS – ESFree Float: The amount of time an activity can be delayed  without delaying early start time of the following activityy g y g y – Critical Path: A series of connected activities with each  activity having zero float (free, and total) time.

(30)

Link Activities

Link Activities

The order in which activities will be performed is p called logicHow one activity relates to another activity is called  logical relation logical relationFinish to StartFinish to FinishStart to StartDefining proper logic requires understanding of the  project projectThere is always more than one correct logic for  completion of a project.

(31)

Documentation

Documentation

Document any assumptions:Document any assumptions:

Production rates Equipment TypesEquipment TypesQuantities CCrewsFollow the logic

(32)

Update

Update

A Schedule is only a tool!

(33)

Check List

Check List

Reviews/Submittals/Are there critical submittals? What Time is needed?Are there critical testing periods & how long? A th iti l i ti & h l ?Are there critical review times & how long?What are the assigned calendars for submittals &  review times?What are the logical connections between review  activities and contractor’s actual work?

Procurement activitiesProcurement activities

Time for reviewing false‐work plans, shop drawings,  post‐tensioning plans, mix designs, etc.

(34)

Check List

Check List

PermitsPermits

Are permits required?

Time to obtain necessary permits?

(35)

Check List

Check List

Specific Activity Requirementsp y qAdditional time for obtaining specialty items or  materials with long‐lead requirements (i.e. Traffic  Signal Equipment) Signal Equipment)Curing time and waiting periods between successive  paving courses or between concrete operations

Embankment settlement periods or embankmentEmbankment settlement periods or embankment 

surcharges.

Coordination with Utilities

False‐work & Shoring activitiesPunch‐list and cleanup activities

(36)

Check List

Check List

Material/Product Testing and DelaysMaterial/Product Testing and Delays

Government/Owner furnished material Trial shafts or piles

Trial shafts or piles

Sample walls

Ti f f b i ti f t t l t l d th

Time of fabrication of structural steel and other  specialty items

Staining painting or other samples needing

Staining, painting or other samples needing  approvals

(37)

Check List

Check List

Construction Limitations and RequirementsHaul characteristicsType of earthwork (sliver cuts, benching)Work area restrictionsEquipment congestionq p gAllowable bad weather daysMaterial availability

Labor shortages and resource loadingLabor shortages and resource loading

Traffic Volumes

Traffic staging events (closures, detours)

Critical interface activities (utilities, RR)Critical interface activities (utilities, RR)

Restrictions for nighttime and weekend operations

Conflicting operations of adjacent projects, both public and  private

p

(38)

Check List

Check List

Project Commitmentsoject Co t e tsEnvironmental CommitmentsWinter seasonClearing, grubbing, grading restrictionsNoise restrictionSWPPPSeasonal limitations for certain activitiesProject Calendar Requirements W k W kWork WeekHolidaysOther non‐working times

(39)

Check List

Check List

Does the final schedule include/show:/ – Critical Path? – NTP date and completion date f k ll l d – Entire scope of work, all activities in plans and specs? – Construction Staging and mobilization?

– Realistic duration of individual activities?Realistic duration of individual activities?

– Maximum 20‐day duration for any one activity?

– Activities have at least one predecessor and 1 successor? – No negative lag for activities/

– Project Duration, Interim Milestones, Black‐out dates,  contract work days?

References

Related documents