• No results found

What Went Wrong Right? Recognizing Risk Impacts on Cost and Schedule. Scope Development

N/A
N/A
Protected

Academic year: 2021

Share "What Went Wrong Right? Recognizing Risk Impacts on Cost and Schedule. Scope Development"

Copied!
35
0
0

Loading.... (view fulltext now)

Full text

(1)

1

Scope Development

What Went

Wrong

Right?

Recognizing Risk Impacts

on Cost and Schedule

(2)
(3)
(4)

Course Outline

Session 1: Overview of the Risk Management

Process

Session 2: Determining Cost & Schedule Impacts

from Risks

Session 3: Calculating Contingency Using Range

Estimating

(5)

5

Scope Development

Session One

(6)
(7)

PMI – Professional Development Days

Risk is . . .

an EVENT that

may or may

(8)

Quantifying Risk

• Very Unlikely (VU)

• Unlikely (U)

• Possible (P)

• Likely (L)

• Very Likely (VL)

(9)

PMI – Professional Development Days

Quantifying Risk

Negligible

Marginal

Significant

Critical

Crisis

ASSESS CONSEQUENCES

(10)

Risk Level Matrix

SEVERITY Negligible Marginal Significant Critical Crisis

PROBABILITY

Very Likely Moderate High High High High

Likely Moderate Moderate High High High

Possible Low Moderate Moderate High High

Unlikely Low Low Moderate Moderate High

(11)

PMI – Professional Development Days

Cookbook or Chaos

Do we all have a different risk

perception or tolerance?

(12)

Project Risk Assessment Scenario

Consider the following: The concrete on the project is on the critical path. You are currently 5 days behind

schedule with an unhappy client. There is a slab placement scheduled for tomorrow. The chance of showers is 50%. Would you place the slab? If not, at what % would you place?

Now, the placement is a wall. Would you place the concrete?

(13)

13

Scope Development

Session Two

(14)

Impact of Risks on Cost & Schedule

Eliminate / Avoid

Mitigate / Reduce

Transfer

Sharing

Insurance

(15)

PMI – Professional Development Days

Risk Avoidance

Eliminate the potential cause(s) of the Risk:

Avoid risk by not bidding the project

Perform the activity/task a different way

(16)

Risk Reduction

Reduce Probability

- replace used equipment with new - change method of construction - perform a sensitivity analysis - conduct preventative maintenance - benchmark Reduce Consequences - obtain spares

- review schedule for resequencing, paralleling activities, or a different approach

- work overtime

(17)

PMI – Professional Development Days

Risk Transfer

Includes transferring risk to entities that are more

capable of controlling it

Subcontract specialty work

Subcontract work to more productive subs

Negotiate contract terms at formation of contract (bid

(18)

Risk Sharing

Share risk with the owner

Partnering

Different contract types share/reduce risk

- Cost Reimbursable (More risk on owner)

- Unit Price (Quantity to Owner, Productivity to Contractor) - Cost Plus Incentive

(19)

PMI – Professional Development Days

Insurance

Some risks are best

handled through insurance which is actually risk

transfer

Workers Comp

Builder’s Risk

General Liability

(20)

Accept & Manage Risk

Accepted risk must be managed

Management practices include:

- Contingency planning

- Proper staffing (Experienced teams & leaders) - Strong Programs

- Strong Project Controls - Training

(21)

PMI – Professional Development Days

Risk Impact Determination

Impact of handling strategies

- cost

- schedule

(22)

Residual Risk

RESIDUAL RISK

The risk that remains after handling strategies have been implemented.

• there is no residual risk if risk is avoided, transferred, or insured

• the residual risk is the same as the original risk if accepted

• the residual risk Probability and/or Consequences should be reduced if actions were effective and appropriate

(23)

PMI – Professional Development Days

Risk Impact Determination

WHAT IS

(24)

Contingency Definition

CONTINGENCY: A specific allocation of resources

added to the estimate or schedule for unknowns due to an evaluation of the possibility, probability, risk and

consequences for overrunning the base estimate.

Contingency components

• Schedule uncertainty: related to inherent variability in the schedule

• Estimate uncertainty: related to inherent variability in the estimate • Residual risk: related to “risk events” not fully mitigated in the risk

(25)

PMI – Professional Development Days

Risk Impact Determination

HOW DO YOU

CALCULATE A

RISK-BASED

CONTINGENCY?

(26)

Contingency Determination

Range Estimating

- One of many probabilistic approaches to cost estimating and/or scheduling

- Determines probabilities associated with cost overruns and/or schedule delays

- Mathematically determines contingency - Based on Monte Carlo simulation

(27)

PMI – Professional Development Days

Work Group Example

(28)

Instructions...

For each of the following questions (to be provided) please provide a 90% range response (i.e., a range in which you are 90% certain that the true value lies within).

• The goal is NOT to test your knowledge of

useless trivia, but to practice estimating under uncertainty.

(29)

PMI – Professional Development Days

Analysis of Responses

• There were 10 questions

• Each were asked to be 90% confident

• Therefore, if perfectly calibrated, the average

number of correct responses should be 9

• The actual number of average correct

responses was …

(30)

Calibration Issues

• of 415 tests given, there was an average of

6.54 misses (3.46 correct responses)

• Why? Imperfect calibration. Overconfidence

is the most prevalent bias associated with estimating under uncertainty.

(31)

31

Scope Development

Session Three

(32)

Risk & Opportunity Management:

A CONTINUOUS process throughout lifecycle

Bid or No Bid Submit Proposal Prospect Selection Prospect Phase Proposal Phase Execution Phase Knowledge Management

Bidding Negotiating Executing Closing

Award R&O Identification Qualitative Assessment Handling & Response Impact Determination Monitoring & Management R&O Reporting R&O Plan

(33)

PMI – Professional Development Days

CLOSING THOUGHTS

Managing project risk is not a discrete one time event

Must be kept active throughout the project life-cycle,

(34)

Identify and Reduce Risk

* No animals were harmed in the making of this graphic

And to think I could have used the culvert!!

(35)

35

References

Related documents