Generator relay protection setting
Generator relay protection setting
calculation instruction
calculation instruction
Instruction: This setting calculation instruction is only
Instruction: This setting calculation instruction is only forfor reference,reference,
protection device running setting is confirmed by user.
protection device running setting is confirmed by user.
XJ Electricity Co., Ltd
XJ Electricity Co., Ltd
2010.11
2010.11
Catalog
1. Generator Differential Protection 87G ...3
2. Overall Differential 87ALL ...4
3. Generator Inter-turn Fault 95G ...6
4.Generator Inadvertent Energize protection Stator Earth Fault Protection of startup condition 99V ... ... ... 7
5. Generator Over-voltage 59G ...7
6. Reverse Power Protection 32G ; Low Forward Power Protection 37G ...8
7. Generator Stator Overload 49G ...9
8. Generator Negative-Sequence Over-current 46G ...10
9. Generator Pole Slipping 78G ... 11
10. Generator loss of excitation protection 40G ...13
11. Generator Under & Over Frequency 81G ...14
12. Generator Over Fluxing 24G ...15
13. Generator Under-voltage 27G ...16
14. Stator Earth Fault 100% 64G1 ...16
15. Stator Earth Fault 100% 64G2 ...17
16. Stator Earth Fault 95% 64G3 ...17
17. Field Winding Earth Fault( 64F ...18
18. Generator 95% Voltage Check 59GB ...18
19. Back Up Impedance 21G ...18
1. Generator Differential Protection 87G
1.1 Basic parameter
CT ratio nTA 8000/5
rated primary current I gn1 7060A
rated secondary current I gn2 n A
I I TA gn gn 4.41 1600 7060 1 2
=
=
=
1.2 Setting calculation1 Min operation current op.0
Setting by the max unbalanced current under the condition of avoid the normal generator rated load.
2 2
2 0
. rel 2 0.03 gn 1.5 2 0.03 gn 0.09 gn
op K I I I
I
=
×
×
=
×
×
=
Suggest to select I op.0
=
0.2I gn22 Min brake current I res.0
2 0
. gn res I
I
=
3 Ratio brake coefficientS
External three-phase short-circuit the maximum short-circuit current:
69 . 32 1600 8 . 13 3 08 . 0 100000 8 . 13 3 , , ) 3 ( max .
=
×
×
×
=
×
×
×
=
TA d b n X S I k A I I k res 32.69 ) 3 ( max .=
.max=
The max unbalanced current of differential protection when the generator is outer short circuit
A I K K K I k cc er ap unb 2 0.1 0.5 32.69 3.27 ) 3 ( max .
=
×
×
×
.max=
×
×
×
=
Therein ap is the non-periodic branch coefficient select 1.5 2.0 cc is the
same type coefficient of transformer select 0.5 er is the error coefficient of
transformer ratio select 0.1
Put the condition of the differential protection won’t error operate under the max
outer short circuit current the secondary current value I op.max of correspondent max
A 9 . 4 27 . 3 5 . 1 I K
Iop.max
=
rel unb.max=
×
=
Therein rel is the reliable coefficient, select 1.3 1.5.
The ratio brake coefficient S is 12 . 0 53 . 3 69 . 32 324 . 1 9 . 4 I I I I S 0 . res (3) max 0 . op max . op
=
−
−
=
−
−
=
Suggest to select S=0.3 4 Sensitivity checkSensitivity check principle : Generator terminal side of two-phase metallic short-circuit occurs when generator is parallel off:
A n X S I TA d b k 28.3 1600 8 . 13 3 08 . 0 100000 866 . 0 8 . 13 3 866 . 0 , , min .
=
×
×
×
=
×
×
×
×
=
A I I res k 14.15 2 min .=
=
A I I S II op
=
op.0+
( res−
res.0)=
1.324+
0.3×
(14.15−
3.53)=
4.512 27 . 6 51 . 4 3 . 28 min .
=
=
>
=
op k sen I I K5 Output model : Trip All CBs
2. Overall Differential 87ALL
2. 1 Basic parameter
Name M.T. HV Side Generator terminal A.T. HV Side
Rated Voltage kV 230 13.8 13.8
Rated Current A 452.4 7539.6 7539.6
CT ratio 1000/1 8000/5 8000/5
Second side Current A 0.45 4.71 4.71
2.2 Setting Calculation
1 Min operation current I op.0
Setting by the max unbalanced current under the condition of avoid the normal main transformer rated load.
b b I I 0.24 ) 05 . 0 05 . 0 06 . 0 ( 5 . 1 I ) m U f ( K Iop.0
=
rel i(n)+
∆
+
∆
b=
×
+
+
=
Suggest to select Iop.0
=
0.5 I bbTherein
b
secondary side.
rel
K
is the reliable coefficient K rel
=
1.3~ 1.5 )n ( i
f
is the transformer ratio error of the current transformer under rated current.
U
∆ is the error caused due to the regulation of transformer tapping (relative to the
percent of the rated voltage).
m
∆ is the error caused due to the incomplete matching of transformer ratios of TA and
TAA, ∆m takes 0.05 in general.
2 Min brake current I res.0
Suggest to select I res.0
=
I b3 Ratio brake coefficient S
The calculation of three-phase main transformer high-voltage busbar metallic short-circuit occurs current when generator is parallel off:
A n S X X I TA b T d k 1.674 1000 230 3 100000 07 . 0 08 . 0 1 230 3 1 ,, ) 3 ( max .
=
×
×
×
+
=
×
×
×
+
=
External three-phase short-circuit the maximum short-circuit current: (3) max . i aper st max . unb (K K f U m)I I
=
+
∆
+
∆
k A 4185 . 0 674 . 1 ) 05 . 0 05 . 0 1 . 0 5 . 1 1 (×
×
+
+
×
=
=
stK is the same type coefficient of TA K st =1.0
aper
K
is non-periodic coefficient of TA K aper =1.5~2.0 5P or 10P type TA
or K aper
=
1.0 TP type TASetting of ratio braking coefficient S
31 . 0 36 . 0 674 . 1 225 . 0 4185 . 0 5 . 1 I -I I -I K S res.0 res.max op.0 unb.max rel
=
−
−
×
=
=
Suggest to select: S=
0.4 4 Sensitivity checkSensitivity check principle : Main transformer high-voltage side of two-phase metallic short-circuit occurs when generator is parallel off:
A n X X S I TA T d b k 1.45 1000 230 3 ) 07 . 0 08 . 0 ( 100000 866 . 0 230 3 ) ( 866 . 0 , , min .
+
×
×
×
=
×
=
×
×
×
+
×
=
A I
I res.min
=
k .min=
1.45A I
I S I
I op
=
op.0+
( res−
res.0)=
0.225+
0.4×
(1.45−
0.36)=
0.6615 . 1 19 . 2 661 . 0 45 . 1 min .
=
=
>
=
op k sen I I K5 Setting of second harmonic braking coefficient
Suggest to select: 15%
6 Difference current quick brake
Select: I op
=
5I b7 Difference current quick brake sensitivity check
Sensitivity check principle : Main transformer low-voltage side of two-phase metallic short-circuit occurs:
A n X X X S I TA T S d b k 5.08 1000 230 3 ) 07 . 0 022 . 0 //( 08 . 0 100000 866 . 0 230 3 ) //( 866 . 0 , ,
+
×
×
×
=
×
=
×
×
×
+
×
=
2 . 1 26 . 2 25 . 2 08 . 5=
>
=
=
op k sen I I K8 Output model: Trip all CBs
3. Generator Inter-turn Fault 95G
3.1 Basic parameter
Rated secondary current I gn2 A n I I TA gn gn 4.41 1600 7060 1 2
=
=
=
PT ratio nTV 3 1 . 0 3 1 . 0 3 8 . 13 3.2 Setting Calculation 1 Zero-sequence VoltageSetting by the max unbalanced zero-sequence voltage under the condition of avoid the normal generator rated load.
V U op
=
22)Fault branch negative-sequence direction elements
A I gn i
=
3% 2=
3%×
4.41=
0.13 ε V U gn u=
1% 2=
1%×
110/ 3=
0.63 εVA U I n n P gn gn TA TV gn p 0.1% 3 0.1% 3 4.41 100 0.76 % 1 . 0 2 2
×
=
×
×
×
=
×
×
=
×
=
ε 3) Time delay t=
0.1s4 Output model: Trip All CBs
4.Generator Inadvertent Energize protection Stator Earth Fault Protection of
startup condition 99V
4.1 Basic parameter
Rated secondary current I gn2 4.41A
Rated secondary voltage U gn2 110V
4.2 Setting calculation
1 Low impedance element setting
( )
Ω
=
×
×
×
=
×
=
38.4 41 . 4 3 . 0 3 110 8 . 0 3 . 0 3 8 . 0 2 2 gn gn set I U Z( )
Ω
=
×
=
=
0.85 set 0.85 38.4 32.6 set Z R2 Over current element setting
( )
A II op
=
0.3 gn2=
0.3×
4.41=
1.323 Stator Earth Fault Protection of startup condition operation voltage
V U op
=
10Time delay t
=
2s4 Output model
Generator Inadvertent Energize protection: Trip 220kV CB & excitation CB Stator Earth Fault Protection of startup condition: Trip excitation CBs
5. Generator Over-voltage 59G
5.1 Basic parameter
Rated secondary voltage U gn2 110V
5.2 Setting Calculation 1 Operation voltage
I: U op
=
1.05U gn2=
1.05×
110=
115.5VII: U op
=
1.1U gn2=
1.1×
110=
121V2 Time delay Select
I: t
=
30sII: t
=
10sIII: t
=
0.5s3 Output model: Trip all CBs
6. Reverse Power Protection 32G ; Low Forward Power Protection 37G
6.1 Basic parameter
Generator rated power Pn 135WM
Generator rated secondary power Pn2 672.6W
6.2 Setting Calculation 1 Min operation power
W K rel
op
=
+
)=
0.5×
(3%+
1−
98.6%)×
672.6=
14.8Suggest to select op
=
10WTherein K rel is the reliable coefficient select 0.5~0.8
is the min loss when steam turbine is in reverse power operation generally
select 2 ~4 of the rated power
is the min loss when steam turbine is in reverse power operation generally select
η Pgn is the rated capacity of generator.
2 Time delay
Reverse Power Protection 32G t 1
=
5s(32G) ) 32 ( 60 2 s G t=
Low Forward Power Protection 37G
3 Output model
Reverse Power Protection 32G :
Time delay t 1: Alarm
Time delay t 2: Trip All CBs Low Forward Power Protection 37G : Trip All CBs
) 37 (
1s G
7. Generator Stator Overload 49G
7.1 Basic parameter
Rated secondary current I gn2 4.41 A
allowed heat time constant of stator winding K
37.5
7.2 Setting calculation 1 Time specified overload
Stator winding time specified over-load can be set by the condition of the long term allowed loading current can reliable return.
A
I
K
K
gn r rel op4
.
41
5
.
14
9
.
0
05
.
1
2=
×
=
×
=
Therein K rel is the reliable coefficient select 1.05 r
K is the return coefficient select0.9
Time specified overload time delay: t
=
9s2 Reverse time specified overload
Reverse time specified over-current can be set by the over-load ability allowed by stator winding it should be determined by the over-load ability allowed by the stator winding of the motor manufacturer. The relation of allowed duration time is :
) 1 ( I K t 2 *
−
+
α=
Therein K is the allowed heat time constant of stator winding it should be based on the parameter provided by the motor manufacturer
* is the per-unit value based on stator rated current
α is the heat radiation constant and related to the stator winding temperature
rising and temperature margin generally select 0.01~0.02.
3 Reverse time specified startup current
Reverse time specified startup current op.min should be set by the condition of
matched with time specified over-load protection
A
K
C opop.min
=
0=
1
.
05
×
5
.
14
=
5
.
4
Therein op is the set value of time specified startup current K C 0 is the matching
coefficient select 1.05
Reverse time specified delay lower limit: t min
=
120sReverse time specified delay upper limit current op.max can be set by the condition of three phase metal short circuit at generator side
A
X
I
d gn op32
.
7
135
.
0
41
.
4
" 2 max .=
=
=
(
)
s I K t op 7 . 0 01 . 0 1 41 . 4 1 . 55 5 . 37 ) 1 ( 2 2 max* . max=
+
−
⎟
⎠
⎞
⎜
⎝
⎛
=
+
−
=
α 4 Output modelTime specified overload: Alarm
Reverse time specified overload: Programming Trip
8. Generator Negative-Sequence Over-current 46G
8.1 Basic parameter
Rated secondary current I gn2 4.41 A
The per-unit value of generator long term allowed
negative-sequence current I 2∞
. . 08 .
0 PU
time constant of withstanding negative-sequence current
ability of rotor surface A
10
8.2 Setting calculation 1 Time specified overload
The negative-sequence time specified over-load should be set on the condition of
under the generator long term allowed negative-sequence current 2∞ can reliable
return
A
K
I
K
r gn rel op0
.
39
95
.
0
41
.
4
08
.
0
05
.
1
2 2=
×
×
=
=
∞Therein K rel is the reliable coefficient select 1.05 K is the return coefficientr
select0.85 0.95
∞
2 is the per-unit value of generator long term allowed negative-sequence current
Time specified overload time delay: t
=
5s2 Reverse time specified overload
The reverse time specified negative-sequence over-load was confirmed by the allowed negative-sequence over-current ability of the generator rotor surface. The relation mode between the generator short time withstanding negative-sequence over-current multiple and allowed duration time is
2 2 2 * 2
−
∞=
I
I
A
t
Therein is the per-unit value of generator negative-sequence current
∞
2
I is the per-unit value of generator long term allowed negative-sequence
current
A is the time constant of withstanding negative-sequence current ability of rotor
surface
Reverse time specified startup current
The reverse time specified startup current op.min generally be set by the
operation current in correspondent with delay1000s set value of reverse time
specified delay lower limit
A
I
A
I
gn op0
.
08
0
.
56
1000
10
41
.
4
1000
2 2 2 2 min .=
+
∞=
×
+
=
Reverse time specified delay upper limit current op.max should be set by the condition of main transformer HV side two phase metal short circuit
A
X
X
X
I
t G d gn op8
.
38
125
.
0
2
141
.
0
135
.
0
41
.
4
2
2 " 2 max .=
+
+
=
+
+
×
=
s I I A t2
.
76
08
.
0
41
.
4
38
.
8
10
2 2 2 2 2 * 2 min=
−
⎟
⎠
⎞
⎜
⎝
⎛
=
−
=
∞ 3 Output modelTime specified overload: Alarm
Reverse time specified overload: Programming Trip
9. Generator Pole Slipping 78G
9.1 Basic parameter
Generator neutral CT ratio 8000/5=1600 Generator terminal CT ratio 13.8/0.11=125.4 9.2 Setting calculation
1 Reduced generator transformer system reactance etc. to the named unit (ohm)value with the generator side voltage is 13.8kV.
Generator
=
( )
Ω
×
×
=
0.267 7060 3 13800 237 . 0 ' d X Main transformer=
×
=
×
=
0.132( )
Ω
180 8 . 13 125 . 0 2 2 n gn k t S U X X System(
÷
)
=
( )
Ω
=
0.031 8 . 13 220 8 . 7 2 s Xst
X setting of system relation impedance
( )
Ω
=
+
=
+
=
t s 0.132 0.031 0.163 st X X X2 Reduce X d ' X t & X st to the secondary side value of generator side TV TA.
) ( 4 . 3 4 . 125 1600 267 . 0 ' 2 '
=
×
=
×
=
Ω
TV TA d d n n X X ) ( 68 . 1 4 . 125 1600 132 . 0 2=
×
=
×
=
Ω
TV TA t t n n X X ) ( 08 . 2 4 . 125 1600 163 . 0 2=
×
=
×
=
Ω
TV TA st st n n X X3 Setting lens principal axis obliquity
Select system impedance angle :
0
85
=
Ψ
z4 Setting of operation power angle set
) ( 71 . 0 8 . 0 7060 15 . 1 3 13800 9 . 0 15 . 1 3 9 . 0 min . 1
×
=
Ω
×
×
×
=
×
=
COS ϕ I U R n n 0 0 0 0 min . 180 2 68.5 43 267 . 0 163 . 0 71 . 0 54 . 1 2 180 54 . 1 2 180=
−
×
=
+
×
−
=
′
+
−
°
=
arctg X X R arctg d st L setSuggest to select δ set
=
12005 Tripping blocking current setting
This protection use generator neutral CT, CT ratio is 8000/5 Main transformer high side circuit breaker rated breaking current is 40kA
=
×
×
=
8 . 13 230 1600 40000 5 . 0 set I 208ASuggest to select I set
=
180 A6 Slipper times setting
Outer zone Slipper times setting:N =4
Inner zone, Slipper times setting:N =1 #1Generator 2 #2 Generator 3 #3 Generator 4 #4 Generator
7 Reactance line position Z C
) ( 377 . 1 53 . 1 9 . 0 9 . 0 2
=
×
=
Ω
=
t C X Z 8 Startup current) ( 3 . 5 41 . 4 2 . 1 2 . 1 I 2 A I st
=
n=
×
=
9 Time delay Outer zone :0.5s Inner zone :0.1s 10 Output modelOuter zone :Alarm Inner zone :Trip all CBs
10. Generator loss of excitation protection 40G
10.1 Basic parameter
Generator neutral CT ratio 8000/5=1600 Generator terminal CT ratio 13.8/0.11=125.4 10.2 Setting calculation
Reduced generator transformer system reactance etc. to the named unit (ohm)value with the generator side voltage is 13.8kV.
Generator
=
( )
Ω
×
×
=
2.33 7060 3 13800 065 . 2 d X( )
Ω
=
×
×
=
0.267 7060 3 13800 237 . 0 ' d X Main transformer=
×
=
×
=
0.132( )
Ω
180 8 . 13 125 . 0 2 2 n gn k t S U X X System(
÷
)
=
( )
Ω
=
0.031 8 . 13 220 8 . 7 2 s X stX setting of system relation impedance
( )
Ω
=
+
=
+
=
t s 0.132 0.031 0.163 st X X XAs X d
=
X q Salient pole power equal 0W 1 Set of static and stable boundary impedance) ( 7 . 29 4 . 125 1600 33 . 2 1
=
×
=
×
=
Ω
TV TA d B n n X Z ) ( 1 . 2 4 . 125 1600 163 . 0 1=
×
=
×
=
Ω
TV TA st A n n X Z2 Set of stable asynchronous impedance
) ( 7 . 29 4 . 125 1600 33 . 2 2
=
×
=
×
=
Ω
TV TA d B n n X Z) ( 7 . 1 4 . 125 1600 267 . 0 5 . 0 5 . 0 ' 2
=
×
=
×
×
=
Ω
TV TA d A n n X Z3 Set of generator terminal low voltage
) ( 88 110 8 . 0 8 . 0 U 2 V U st
=
n=
×
=
4 Time delay Select t1=1.5S t2=1.5S t3=3S 5 Output modelloss of excitation zone 1: Alarm loss of excitation zone 2: Trip all CBs loss of excitation zone 3: exit
11. Generator Under & Over Frequency 81G
11.1 Basic parameter
Generator under & over frequency capability tables provided by the equipment manufacturing factor:
Allow run-time Allow run-time
Frequency Hz accumulated time (min) Each time(s) Frequency Hz accumulated time (min) Each time(s) 5 . 51 0 . 51
<
F≤
30 30 47.5<
F≤
48 60 60 51 5 . 50<
F≤
180 180 5 . 47 47<
F≤
10 20 5 . 50 5 . 48<
F≤
Run Continuously 47 5 . 46<
F≤
2 5 5 . 48 48<
F≤
300 300 11.2 Setting calculation 1 Under frequency zone Iunder-frequency zone I frequency setting f 1.set
=
48.5Hzunder-frequency zone I accumulated time
∑
t 1.set=
18000sunder-frequency zone I time delay t 1.set
=
300s2 Under frequency zone II
under-frequency zone II frequency setting f 2.set
=
48Hzunder-frequency zone II time delay t 2.set
=
60s3 Under frequency zone III
under-frequency zone III frequency setting f 3.set
=
47.5Hzunder-frequency zone III accumulated time
∑
t 3.set=
600sunder-frequency zone III time delay t 3.set
=
20s4 Under frequency zone IV
under-frequency zone IV frequency setting f 4.set
=
47Hzunder-frequency zone IV time delay t 4.set
=
20s5 Over-frequency
over-frequency setting f set
=
51Hzover-frequency time delay t set
=
30s6 Generator terminal low voltage setting U set
=
0.8U n=
88V7 Output model: Programming Trip
12. Generator Over Fluxing 24G
12.1 Basic parameter
Generator over excitation capability tables provided by the equipment
manufacturing factor: Stator voltage/Frequency 1.25 1.19 1.15 1.12 1.10 1.09 1.08 1.07 1.05 Time(sec) 5 7.5 10 15 20 30 45 60 ∞ 12.2 Setting calculation
1 Time specified over fluxing
Over fluxing times: N 0
=
1.06, time delay: t 0=
5sSelect rated voltage as reference voltage 110V 2 Reverse time specified over fluxing
Over fluxing times: N 1
=
1.07 time delay:t 1=
60sOver fluxing times: N 2
=
1.08 time delay:t 2=
45sOver fluxing times: N 3
=
1.09 time delay:t 3=
30sOver fluxing times: N 5
=
1.12 time delay:t 5=
15sOver fluxing times: N 6
=
1.15 time delay:t 6=
10sOver fluxing times: N 7
=
1.19 time delay:t 7=
7.5sOver fluxing times: N 8
=
1.25 time delay:t 8=
5s3 Output model: Trip all CBs
13. Generator Under-voltage 27G
13.1 Basic parameter
Generator terminal PT ratio
3 11 . 0 3 11 . 0 3 8 . 13 13.2 Setting calculation V U U set
=
0.6 n=
66 Time delay: 0.5s 13.3 Output model: Alarm14. Stator Earth Fault 100% 64G1
14.1 Basic parameter
Neutral earthing transformer ratio 13.8/0.3kV
Neutral earthing transformer secondary resistance ( Rn) 1.3
Ω
Neutral earthing transformer primary resistance ( R N ) 2750.8
Ω
Neutral earthing transformer secondary CT ratio(nTA0) 100/1
Generator 3 relative capacitance (3C 0) 1.392µ F
Generator capacitive reactance ( X C 0) 6860
Ω
14.2 Setting calculation 1) earthing resistance
The setting of earthing resistance low set value should be set by the principle of one point earthing in the distance within 20% of generator neutral, the earthing fault
point current 3I0 safe earthing current Is(1A). Means
S C N g gn I jX R R U I
≤
−
+
×
=
) //( 3 3 3 3 2 . 0 3 0 0S C N set g gn I jX R R U
=
−
+
×
) //( 3 3 3 3 2 . 0 0 . 1 ) 6860 //( 8 . 2750 3 3 3 13800 3 2 . 0 .=
−
×
+
×
×
j RgsetΩ
=
k Rg.set 5.2 Suggest to selectEarthing resistance high value: Rhg.set
=
10kΩ
Earthing resistance low value: Rlg.set
=
5kΩ
Time delay:
high value time delay:3s low value time delay:0.5s
A n K R U I TA I n n set 0.5 100 1 . 1 3 . 1 300 2 . 0 0 2 . 50
×
×
=
×
=
×
×
×
=
αTherein α can generally be selected as 20
I
K is the reliable coefficient generally select 1.1.
2) Output model
high value : Alarm low value : Trip all CBs
15. Stator Earth Fault 100% 64G2
15.1Basic parameter
Generator terminal PT ratio
3 1 . 0 3 1 . 0 3 8 . 13
Generator neutral PT ratio 0.1 3
8 . 13
15.2 Setting calculation
Setting value by the protection device according to measured data Time delay : 5s
15.3 Output model: Alarm
16. Stator Earth Fault 95% 64G3
16.1 Setting calculation
The fundamental wave zero-sequence voltage has two sections protection including high value and low set value.
unbalance fundamental wave zero-sequence voltage of neutral single phase voltage transformer when normal operation or three phase voltage transformer open triangle winding at generator side. The setting value applied in the project should avoid the max zero-sequence unbalance voltage that transmitted to the generator side when system HV side and plant transformer LV side earthing short circuit.
The setting of high set value zero-sequence voltage is 20 30V.
Suggest to select:U op. H
=
20V high value U op.l=
10V low value According to the measured maximum value of zero sequence voltage imbalance adjustmentTime delay:
High value: 0.1s Low value: 0.3s 16.2 Output model
High value: Trip all CBs Low value: Trip all CBs
17. Field Winding Earth Fault( 64F
Non-electrical time delay is setting by the owner
18. Generator 95% Voltage Check 59GB
18.1 Basic parameter
rated secondary voltage U gn2 110V
18.2 Setting Calculation 1 Operation voltage
V U
U op
=
0.95 gn2=
0.95×
110=
1042 output model: Alarm
19. Back Up Impedance 21G
Based on actual engineering experience, this protection is valueless ,we suggest don’t use it. 19.1 Basic parameter
Generator neutral CT ratio 8000/5=1600 Generator terminal CT ratio 13.8/0.11=125.4 19.2 Setting calculation
1 Reduced generator transformer to the named unit (ohm)value with the generator side voltage is 13.8kV. Generator
=
( )
Ω
×
×
=
0.25 7060 3 13800 221 . 0 ' d X Main transformer=
×
=
×
=
0.132( )
Ω
180 8 . 13 125 . 0 2 2 n gn k t S U X X) ( 19 . 3 4 . 125 1600 25 . 0 ' 2 '
=
×
=
×
=
Ω
TV TA d d n n X X ) ( 68 . 1 4 . 125 1600 132 . 0 2=
×
=
×
=
Ω
TV TA t t n n X X 3 Rset 1=
X d '2×
1.2=
3.83(Ω
) ) ( 01 . 2 2 . 1 2 2=
t×
=
Ω
set X R 20. TV Fuse-failure 160G 21.1 Basic Parameterrated secondary current I gn2 4.41 A
21.2 Setting Calculation