• No results found

Fire Protection Piping Installation and Testing-Feb. 12, 2014

N/A
N/A
Protected

Academic year: 2021

Share "Fire Protection Piping Installation and Testing-Feb. 12, 2014"

Copied!
104
0
0

Loading.... (view fulltext now)

Full text

(1)

Page 1 of 104 Prepared By (Contractor/Sub-Con) Reviewed By (QA/QC Manager) Reviewed By (Safety Manager) Approved By (Project Manager)

Name: Eng. Samir Maamari Eng. Oussama Abbas Eng. Koffi Christope Signature:

Date:

Method Statement

For

Fire Protection Piping Installation And Testing

(Package 421)

Submitted By:

Advance Vision Co.

(2)

Page 2 of 104

List of Contents

Section

Title

Page

1.0 SCOPE OF WORKS 06 2.0 PURPOSE 06 3.0 ACRONYMS 06 4.0 CLASSES OF FIRE 07 5.0 CLASSIFICATION OF OCCUPANCY 07 6.0 AREA OF APPLICATION 08-09 7.0 RESPONSIBILITIES

7.1 The Construction Manager 9

7.2 The Site Engineer 9-10

7.3 The QA/QC Engineer / Inspector 10

7.4 The Safety Engineer / Safety Officer 10

7.4 The Foremen 10-11

8.0 TECHNICAL SUBMISSIONS

8.1 Shop Drawing 11

8.2 Material Submittals for Fire Fighting System & Accessories 12-13 9.0 CONFORMANCE CRITERIA

9.1 The Contract Specification for Fire Fighting 13 9.2 Fire Protection Codes and Standards 13-14

9.3 Approved Shop Drawings 14

10.0 HEALTH AND SAFETY 14-15

(3)

Page 3 of 104

List of Contents

Section

Title

Page

11.0 GENERAL PROCEDURES

11.1 Material delivery, handling & storage 16

11.2 Tools and Equipment 17-18

11.3 Pre-Installation Procedures 18

11.3.1 Painting Procedure 19

11.3.2 Grooving Procedure 19

11.3.2.1 Setting Grooving Machine 20-24 11.3.2.2 Pipe Grooving Procedure 24-29 11.3.2.3 Pipes Threading Procedure 29-31 11.4 Installation Procedures

11.4.1 Sleeves 31-34

11.4.2 Fire Sealant 34

11.4.3 Groove Coupling Installation 35-36

11.4.4 Lubrication of Gasket 36

11.4.5 Tightening Nuts of Grooved Coupling 36-38 11.4.6 Mechanical Tee - Installation 39-41 11.4.7 Installation Hanger & Support 41-42 11.4.8 Installation Beam Clamp Hanger & Support 42 11.4.9 Installation Flexible Coupling as per NFPA 13 - Chapter 9 42-43

11.4.10 Pipe Identification, Tagging and Labeling 44 11.4.10.1 Pipe Identification Installation 44 11.4.10.2 Valve - Tag Installation 44-45 11.4.10.3 Warning - Tag Installation 45-46 11.4.10.4 Metal Label for Equipment Installation 46

11.4.11 Automatic Wet Sprinkler System 47-48 11.4.11.1 Intallation Wet Sprinkler System 48-51 11.4.11.2 Hydrostatic Pressure Leak Test 51-53 11.4.11.3 Flushing Procedure 53-54

(4)

Page 4 of 104

List of Contents

Section

Title

Page

11.4.12 Automatic Clean Agent Fire Suppression System (FM200) 55-56 11.4.12.1 Installation Automatic Clean Agent Fire

SuppressionSystem(FM200) 56-57

11.4.12.2 Maximum Horizontal Spacing of FM200 57-58 11.4.12.3 Pipe Size Change of FM200 58 11.4.12.4 FM200 Cylinder Installation 59-60 11.4.12.5 Nozzle Installation 61 11.4.12.6 Conduits and Cable Installation 61 11.4.12.7 FM200 Panel Installation 62 11.4.12.8 Pneumatic Test Procedures 62-63 11.4.12.9 Integration of FM200 System 63-70 11.4.12.10 Inteface of FM200 System 71-72 11.4.13 IG 55 Inert Gas Fire Suppression System 72

11.4.13.1 IG-55 Physical Properties 72-73 11.4.13.2 IG 55 Primary Components 73 11.4.13.3 Installation of IG 55 Inert Gas Fire Suppression System 73-74

11.4.13.4 Racking Assembly 75

11.4.13.5 Cylinder Assembly 75-77 11.4.13.6 Pressure Gauge w/ Low Pressure Switch 77-78 11.4.13.7 Manifold Assembly 79

11.4.13.8 Valve Assembly 79

11.4.13.9 Discharge Hose Kit 80 11.4.13.10 Pneumatic Leak Test 81-82

11.4.13.11 Interface 82-83

11.4.14 Foam Fire Suppression System 84-85 11.4.14.1 Installation of Foam System 85-87 11.4.14.2 Installation of Rational Flow Controllers 87 11.4.14.3 Bladder Tank Installation 87-88 11.4.14.4 Foam Suppression Panel Installation 88 11.4.14.5 Hydrostatic Testing 88-90

11.4.14.6 Flushing 91

(5)

Page 5 of 104

List of Contents

Section

Title

Page

11.4.15 Automatic Pre-action Sprinkler System 92-93

11.4.15.1 Interface 94

11.4.16 Installation Deluge System 95

11.4.16.1 Interface 96-97

11.4.17 Standpipe & Hose Systems 97-98 11.4.17.1 Wall Mounted – Fire Hose Cabinet 98-100 11.4.17.2 Reccessed Mounted – Fire Hose Cabinet 100-102 11.4.18 FDC ( Siamese Connection ) 102-103 11.4.19 Portable Fire Extinguisher 103-104

11.4.20 References 104

11.4.21 Attachment 104

11.4.21.1 Approved Material Submittal

11.4.21.2 421-A000-SH-F-04-ZZ0001 Fire Protection Pipe Support Detail

11.4.21.3 421-F136-SH-F-04-020001-001001-00 Fire Protection Detail Second Floor

11.4.21.4 421-RFI-M-00246 Rev.00 - Disinfection of Pipes for Wet

Pipe Sprinkler System

(6)

Page 6 of 104

1.0 SCOPE OF WORKS

The scope of This Method Statement is to define all the sequence and work for installation and testing of Fire Fighting System, as per our scope of work, at KAIA

PROJECT – Jeddah, K.S.A. and to ensure that all works / activities are in full

compliance with specifications, drawings and standards .

2.0 PURPOSE

The purpose of this Method Statement is to describe the quality control procedure to be followed during installation of Fire Fighting System works activities.

3.0 ACRONYMS

S.N. ACRONYMS Meaning

1 NFPA National Fire Protection Association 2 QA/QC Quality Assurance/Quality Control 3 WPSS Wet Pipe Sprinkler System

4 KAIA King abdulaziz International Airport 5 K.S.A. Kingdom of Saudi Arabia

6 BMS Building Management System 7 PPE Personal Protective Equipment 8 MEP Mechanical, Electrical and Plumbing 9 HSE Health and Safety Engineer

10 SBG Saudi Binladin Group 11 CRS CM’s Reply to Submittals 12 DCS Document Submittal

13 DN Nominal Diameter

14 NPS Nominal Pipe Size

15 SH Shop Drawing

16 F Fire Protection

17 DAR Dar – al – handasah

18 ITP Inspection and Testing Plan 19 AFFF Aqueous Film – Forming Foam

20 ID Inside Diameter

21 ASME American Society of Mechanical Engineer 22 FDC Fire Department Connection

23 AWWA American Water Works Association

(7)

Page 7 of 104

4.0 CLASSES OF FIRES

A generally accepted method of classification separates combustible materials into five types:

Class A Fires

Ordinary combustible materials such as wood, cloth, paper, rubber, and many plastis (typical for wet-based sprinkler systems

Class B Fires

Flammable liquids, combustible liquids, petroleum greases, tars, oil, oil-based paints, solvents, lacquers, alcohols, and flammable gases

Class C Fires Fires that involve energized electrical equipment

Class D Fires Combustible metals such as magnesium, titanium, zirconium, sodium, lithium, and potassium

Class K Fires Fires in cooking appliances that involve cooking oils and fats

5.0 CLASSIFICATION OF OCCUPANCY

The criteria for occupancy classification is defined in NFPA 13: The categories are broken in five areas based on building use type:

Light Hazard: Low quantity of combustibles with low heat release (e.g.,

churches, hospitals, museums)

Ordinary Hazard 1: Moderate quantity of combustibles with moderate

heat release and 8-foot stockpiles (e.g., mechanical rooms, restaurant kitchens, laundry facilities)

Ordinary Hazard 2: Moderate quantity of combustibles with moderate

heat release and 12-foot stockpiles (e.g., stages, library large stack rooms, repair garages)

Extra Hazard 1: High quantity of combustibles with high heat release and

no flammable or combustible liquids (e.g., aircraft hangers, saw mills)

Extra Hazard 2:High quantity of combustibles with high heat release and

flammable and combustible liquids (e.g., plastics processing, flammable liquids spraying)

(8)

Page 8 of 104

6.0 AREA OF APPLICATION

The building is provided with the following System:

S.N. Building/Zone(421) WPSS FM200 IG-55 DELUGE FOAM

FIRE HOSE CABINET Pre- Action 1 Flans Glazing  2 Zone A-Terminal Processor   3 Zone B-West Domestic Pier  

4 Zone C-East Doestic Pier

 

5 Zone D-Central Pier  

6 Zone E-International Hub   7 Zone F-West International Pier   8 Zone G-East International Pier   9 Zone H-Garden   10 F155-APM Maintenance Station  11 J150-MR & FFS    12 J600-Crisis Management Centre   13 G100-ATC Tower    14 G200-West Supporting Tower    15 G300-Meteorological Observation Building  

16 F160-First & Business Class Car Park With Link   17 F170-CIP/VIP Car Park   18 B110-Transmitter Site  19 B124 Radio Site   20 B160-Temporary GSE Maintenance Facility

(9)

Page 9 of 104

7.0 RESPONSIBILITIES

7.1 The Construction Manager

 To ensure that all preparation and application works are carried out according to the contract specifications, shop drawings and manufacturer data sheet.

 To ensure that the progressing of work is carried out according to the planned program and as per approved Method Statement.  To ensure that the manpower, equipments and materials required to

execute the work are available.

 To ensure that the related quality procedures are practiced and implemented.

7.2 The Site Engineer

 Coordinate all the site activities required for the installation of the fire fighting system, whether external or internal, according to the project specification, manufacturer data sheet and approved shop drawings.

 To provide all necessary information and distribute responsibilities to his team.

S.N. Building/Zone(421) WPSS FM200 IG-55 DELUGE FOAM

FIRE HOSE CABINET Pre- Action 21 B360-Saudi Airlines “MCC” 22 H110 Data Center   23 H120 Data Center  

(10)

Page 10 of 104

 To monitor the progress of work in relation with work program and to report to the construction manager.

 To ensure that the foreman is fully aware of the work sequence and related testing before proceeding with installation.

 To coordinate with safety officer and to ensure that the works are carried out in safe practicing method.

7.3 The QA/QC Engineer / Inspector

 To ensure full compliance of the work with the related approved method statement.

 Ensure that the materials being delivered and used are in accordance with the project specification and approved material submittal.

 To maintain comprehensive inspection and test records for the purpose of reference and documentation.

7.4 T h e Safety Engineer/ Safety Officer

 Ensure that the work is perform under the safety measures.  Ensure that all staff are wearing safety PPE.

Ensure that good housekeeping are implemented at work site.  To maintain continuous inspections of the site activities, advise and

train the involved personnel on daily basis to prevent accidents, personnel injury or property damage.

7.5 The Foreman

Shall explain the Method Statement for his Subordinates.

 To ensure the work is carried out properly and according to instruction received from site engineer.

 To ensure the adequate resources of machinery, labor and materials are available.

(11)

Page 11 of 104

 To control the disposal of waste materials according to the instruction of site engineer.

 Coordinate fully with the safety officer in order to maintain safe working condition and proper housekeeping of the site.

8.0 TECHNICAL SUBMISSIONS(will be submitted in a separate submittal) 8.1 Shop Drawings

Shop Drawings shall be submitted to the consultant for approval. These Drawings should contain the following details:

 Lay – out of Fire Fighting Pipes.

Type, size of pipe and fittings accessories.  Connection details, details of accessories…etc.  Hydraulic Calculation for each building.

Coordination drawing with MEP.

 Seismic analysis, expansion and movement joint’s locations and types, etc.

(12)

Page 12 of 104

8.2 Material submittals for fire fighting system and accessories:

S.N. Submittal Description Reference Number Status

1.0 Paint for Fire Fighting Pipes 421-422-MTS-F-00772-00 CODE 2 2.0 Paint for Fire Fighting 421-422-MTS-F-00624-02 CODE 2 3.0 Seamless Black Steel Pipes for Fire

Wet Systems 421-422-MTS-F-00266-01 CODE 2

4.0 Seamless Black Steel Pipes for Fire

Wet Systems 421-422-MTS-F-00267-01 CODE 2

5.0 Seamless G.I. / Carbon Steel Pipes –

Fire Protection 421-422-MTS-F-00539-00 CODE 2

6.0 Seamless Fire Pipes 421-422-MTS-F-00552-00 CODE 2 7.0 G.I. pipes for Sleeves Application 421-MTS-M-00107-01 CODE 1 8.0 Hanger & supports For Fire Fighting

Applications 421-422-MTS-F-00548-00 CODE 2

9.0 Hanger & supports For Fire Fighting

Applications 421-422-MTS-F-00523-00 CODE 2

10.0 Hanger & supports For Fire Fighting

Applications 421-422-MTS-F-01109-01 CODE 2

11.0 Hanger & Supports for Fire Fighting

Application 421-422-MTS-F-00454-00 CODE 2

12.0 Malleable Threaded Fittings for Fire

Fighting 421-422-MTS-F-00428-00 CODE 2

13.0 Malleable Iron Threaded Fittings 421-422-MTS-F-01221-00 CODE 2 14.0 Threaded Fittings 421-422-MTS-F-01226-00 CODE 2 15.0 Grooved Coupling & Fittings for Fire

Fighting System 421-422-MTS-F-00317-00 CODE 2

16.0 Grooved Coupling & Fittings 421-MTS-M-00049-00 CODE 2 17.0 Fire Alarm Control Cable for FM200

and Foam 421-422-MTS-F-01421-00 CODE 2

18.0 Wrought Forged Steel Flanges – Fire

Fighting 421-422-MTS-F-00609-00 CODE 2

19.0 Fire Protection Valves and Devices 421-422-MTS-M-00186-01 CODE 2

20.0 Mueller Valves FF 421-MTS-F-01371-00 CODE 2

21.0 Fire Fighting Valves 421-422-MTS-M-249-00 CODE 2 22.0 Zone Control Valve Assembly 421-422-MTS-F-00575-00 CODE 2 23.0 Water Pressure Reducing Valves

(13)

Page 13 of 104

S.N. Submittal Description Reference Number Status

24.0 Pressure Reducing Valves – Fire

Fighting Application 421-422-MTS-F-00514-00 CODE 2

25.0 Sprinklers 421-MTS-F-00437-01 CODE 2

26.0 Pressure Gauge for Use in Fire

Fighting System 421-422-MTS-F-00391-00 CODE 2

27.0 Sprinklers 421-422-MTS-F-00457-01 CODE 2

28.0 Sprinklers 421-422-MTS-F-00549-00 CODE 2

29.0 Sprinklers 421-422-MTS-F-00478-00 CODE 2

30.0 Zone Control - Valves 421-422-MTS-F-00487-00 CODE 2 31.0 Foam-Water System for B120 Radio

Sire – All VHF/UHF Station Buildings 421-MTS-F-00460-04 CODE 2 32.0 Fire Hose Reel Cabinets 421-422-MTS-F-00744-01 CODE 3 33.0 IG-55 Fire Suppression System 421-MTS-F-01400-00 CODE 3

9.0 CONFORMANCE CRITERIA

9.1 The Contract Specifications for Fire Fighting System

Div. 21, Section 211313 – Wet-pipe Sprinkler System.

Div. 21, Section 211100 – Facility Fire-Suppression Water-Service Piping.

Div. 21, Section 212200 – Clean-Agent Fire-Extinguishing System. Div. 21, Section 211339 – Foam-Water System.

Div. 21, Section 211316 – Dry-Pipe Sprinkler System. Div. 21, Section 211200 – Fire Suppression Standpipes.

Div. 21, Section 210553 – Identification for Fire-Suppression Piping & equipment.

9.2 Fire Protection Codes & Standards

NFPA 10 – Standard for Portable Fire Extinguishers.

(14)

Page 14 of 104

NFPA 13 – Standard for the Installation of Sprinkler Systems. NFPA 14 – Standard for the Installation of Standpipe & Hose Systems.

NFPA 15 – Standard for Water Spray Fixed Systems for Fire Protection.

NFPA 16 – Foam-Water Sprinkler & Foam-Water Spray System. NFPA 24 – Standard for the Installation of Private Fire Service

Mains & Their Oppurtenances.

NFPA 2001 – Standard on Clean Agent Fire Extinguishing Systems. NFPA 72 – Guide on alternative Approaches to Life Safety.

9.3 Approved Shop Drawings

10.0 HEALTH AND SAFETY

Advance Vision Co. will ensure safety of personnel as per

Project standards.

 All personnel involved will use necessary PPE as required such as safety helmet, glasses, coverall, shoes, gloves, ear plugs etc.

 The workers will made aware of the safety requirements related to this activity through daily toolbox and safety talk.

 All required work permits will be acquired and kept available at respective work Site hanged clearly in plastic folders.

 Spark arrestor and warning lights will be installed on all mobile equipment.

(15)

Page 15 of 104

 Every effort shall be made to assure that employees can accomplish their assigned scope of work safely.

 The ability to determine the storage areas, access, potential and existing hazard on the will identified the facilities for welfare, first aid and sanitation, the work permit procedures and

requirements and the basic precautions on dealing with fire hazard and damage to property at the planning stage.

 Ensure the proper sequence of construction operations, outline potential hazards at each stage and indicate the precautionary measures to be adopted on site by the area foreman / site supervisor. Carry out checking over work methods and precautions against supervision prior the commencement of work.

 Carry out provision of the warning sign and isolation requirements on site.

 Site HSE manager will be response to the site safety issues and as a key manager to this project.

Advance Vision Co. and sub-subcontractors

Fully comply with approved SBG safety plan (421-422-DCS-

PLN-G-00027-04).

 Risk Assessment Matrix (RAM) is attached.

10.1 Environmental Requirements:

 The building should ideally been closed and weather-tight.

 The building should be in a reasonable condition with regard to cleanliness, temperature and humidity.

 The building should be in a reasonable condition with regard to cleanliness, temperature and humidity.

 Clear access for vehicles should be available to facilitate unloading of materials in a safe manner.

(16)

Page 16 of 104

 Clear gangways and access to lifts and staircases should be available.

 Difficulty of access can lead to damage of materials that in turn may reflect in the quality of the finished work.

 Scrap Material are carefully and safely disposed off.

11.0 GENERAL PROCEDURES

11.1 Material delivery, handling & storage

 Check the reference of delivered material against approved submittal.

 Check the material against the purchase order.

 Deliver pipes and tubes with factory end cap. Maintain the end cap thru shipping, storage and handling to prevent damage to the pipe end to prevent deposit of dirt, debris and moisture inside it.  Check Portable fire extinguisher for any damage in the body, the

availability of the hose and proper pressure by looking at the sight glass.

 Keep the extinguisher in the original pack and store it in a dry and shaded location.

 Chemicals such as paints, primer and thinner, check their expiration date before receiving.

 Chemicals must be stored in well ventilated location and away from direct sunlight.

(17)

Page 17 of 104

11.2 Tools and Equipment

Measuring Tape – for measurements.

Spanner Set – use in installing fire hose cabinet.

Leve Bar

Adjustable Pipe Wrench – to tighten the connected threaded

pipes.

Speed Metal Cutting Machine – to cut exact sizes of pipes.;

Pipe Threading Machine – to thread end pipes.

Hole Drilling Machine for Pipes – use to make hole prior to

install mechanical tee fittings.  Roll Grooving Machine – to make groove at end pipes.

Hammer – use to punch anchor or bolt prior to install pipe

Support.

Drill Machine – to drill slab soffit prior to install anchor bolt or expansion bolt.

Paint Spray Machine – use in painting the pipe.

Pipe Vise Table – use to hold the pipe or threaded rod when

cutting.

Scaffolding and ladder – use to overhead installation of pipes.

Pipe Stand – use to level the pipe during threading & grooving.

Hack and Saw – use to cut full threaded rod prior to install pipe

support.  Chalk Line

(18)

Page 18 of 104

Air Compressor – use in air leak testing.

Drum / Empty Container – use to stock water and to drain water

during hydostatic leak testing.  End Caps – use to plug all end pipes opening prior for leak

testing.

Caution Tape / Barricade – for safety measure during installation & leak testing.

Water – use as medium in hydrostatic leak testing.

Garden Hose – use to drain water during flushing.

Calibrated Pressure Gauge – use as measuring device in leak testing.

11.3 Pre- Installation Procedure

 All the materials received at site shall be inspected and stored upon receipt as per the manufacture’s recommendations.

 Make sure that allrelative approved drawings are available at site for the execution at site.

 It is very important for the fire suppression system that the drawings are coordinated with other systems to avoid conflict while erecting.

 Proceed with installation only after unsatisfactory conditions have been corrected.

(19)

Page 19 of 104

11.3.1 Painting Procedure

o Refer to the approved Method Statement for Sand Blasting and Painting activities for Fire Fighting and Chilled Water Pipes. (Reference: 421-422-DCS-MST-M-01965-00).

o All damaged painted pipes during installation should be repaint manually using paint brush.

11.3.2 Grooving Procedure

o Use the Roll grooving equipment to groove the pipe. Check pipe end, it must be smooth and free from indentation, projection and roll marks in the area from pipe end to groove. Removed oil, grease and dirt.

o Measurement taken across grooved ends must not exceed the maximum allowable diameter.

o Align groove ends of matting components, before inserting the gasket apply lubricant to gasket and housing interior. o Insert one bolt into the housing and thread the nut loosely on

to the bolt until the nut be flush with bolt end to allow for swing over feature. Make sure housing key engage the groove properly on both pipes.

o Insert washer below the nut, remaining bolt and thread the nut finger tight onto bolt. Nuts must be tightened evenly by alternating sides according to torque.

o Coupling installation shall be complete when visual metal-to-metal contact is reached and the required torque is achieved.

(20)

Page 20 of 104

11.3.2.1 Setting Grooving Machine

(reference from Victaulic Operating and Maintenance Manual TM-VE270/271 VSD)

1. Make sure the proper roll set is installed on the tool for

the pipe size and material to be grooved. Rolls are marked with the pipe size, part number and the color coded according to the pipe material.

2. Loosen the wing nuts and move the adjustable guards

to the full up position. Tighten the wing nuts.

3. Set the groove diameter stop to the pipe size and

schedule / thickness to be grooved by backing off the depth adjuster lock and aligning the depth adjuster with the proper.

(21)

Page 21 of 104

4. If the tool is equipped with the optional pipe stabilizer:

Retract the pipe stabilizer, if necessary, to insert the pipe onto the lower roll by loosening the locking handle and retracting the stabilizer roler with the handwheel.

5. Insert a length of pipe that is the correct size and

schedule over the lower roll. Make sure the pipe end contacts the lower-roll backstop flange. The pipe must rest directly on top of the roll and must not be skewed to one side or the other.

6. Close the valve on the hydraulic hand pump by

(22)

Page 22 of 104

7. Pump the handle of the hydraulic hand pump to bring

the upper roll down into firm contact with pipe.

8. Loosen the wing nuts and adjust each guard to

conform to and tightly pinch the pad against the pipe. Tighten the wing nuts to secure each guard in position. Remove the guard setting pad.

(23)

Page 23 of 104

9. Loosen the wing nuts and adjust each guard to

conform to and lightly pinch the pad against the pipe. Tighten the wing nuts to secure each guard in position. Remove the guard setting pad.

10. Remove the guard setting pad. Store the pad on the

hook provided under the hydraulic hand pump support.

(24)

Page 24 of 104

11. Open the valve on the hydraulic hand pump by turning

it counterclockwise to allow the upper roll and arm to move the full up position.

11.3.2.2 Pipes Grooving Procedure

(reference from Victaulic Operating and Maintenance Manual TM-VE270/271 VSD) 1. Before grooving the pipe, make sure the setting of

groove machine is being followed properly. Connect the tool to an internally-grounded electrical source. When roll grooving pipe that exceeds the maximum length, a roller type pipe stand must be used. The roller stand must be capable of handling the weight of the pipe, while allowing the pipe to rotate freely

2. Place the Pipe Stand at a distance slightly beyond

half the pipe length from the tool. Refer to the drawing.

(25)

Page 25 of 104

3. Position the pipe stand approximately 0-1/2 a degree

to the left for the tracking angle. Refer to the drawing.

Note: when pipe flare is excessive, right-to-left Trucking must be kept to a minimum. It may be necessary to use less than ½ a degree for the tracking angle.

4. If the tool is properly set up in a level position, but

the back end of the pipe is higher than the end being grooved, the pipe may not track, in addition, excessive flare may occur on the pipe end. Refer to the “Tool Setup” section and the drawings above for tool setup and pipe positioning requirements.

5. Before grooving, make sure all instructions in the

previous sections of this manual have been followed.

(26)

Page 26 of 104

6. Connect the tool to an internally-grounded electrical

source.

7. Depress the safety foot switch momentarily to

ensure the tool is operational. The lower roll should be rotating clockwise when viewed from the front of the tool.

Remove foot from the switch.

8. Open the valve on the hydraulic hand pump turning

it counterclockwise to allow the upper roll and arm to move to the full up position.

(27)

Page 27 of 104

9. Insert a length of pipe that is the correct size and

thickness onto the lower roll. Make sure the pipe contacts the lower-roll backstop flange completely.

Remove hands from the pipe.

10. Close the valve on the hydraulic hand pump

by turning it clockwise.

11. The operator should be positioned on the safety

foot switch/hydraulic hand pump side of the tool,as shown above. Pump the handle of the hydraulic hand pump to bring the upper roll down into firm contract with the pipe.

12. Depress and hold down the safety foot switch. The

pipe will begin to rotate clockwise when viewed from the front of the tool. As the pipe rotates, begin forming

the groove by pumping the handle of the hydraulic hand pump slowly.

(28)

Page 28 of 104

 Do not pump the handle of the hydraulic hand pump too fast. The rate should be sufficient to groove the pipe and maintain audible, moderate-to-heavy load on the motor/drive.

13. Continue the grooving process until the depth

adjuster lock comes into contact with the top of the tool body. Continue pipe rotation for several

revolutions to ensure groove completion.

14. Release the safety foot switch, and withdraw foot

from the switch.

(29)

Page 29 of 104

15. Open the valve on the hydraulic hand pump by

turning It counterclockwise to release the pipe. Remove the Pipe from the tool.

16. If no more roll grooving will be performed for a

while,disconnect the tool from the electrical source.  The groove diameter must be within specification for the diameter and wall thickness of pipe. The groove diameter should be checked and adjusted, as necessary, to ensure grooves remain within specification.

11.3.2.3 Pipes Threading Procedure

1. A die head will be attached to cut the thread. 2. Machine now have the ability to threads pipes.

3. A heavy duty pipe threader can also cut your pipe into

workable sections.

4. The pipe threading machine will be used to thread the

end section of your pipe.

5. Inspect the pipe threader before beginning and

replace dies or any parts that show signs of wear.

6. Mount your pipe firmly in the pipe vise by placing

it in the vise and then tightening until it is held tightly.

(30)

Page 30 of 104

7. Cut the end of the pipe cleanly and squarely by using a

pipe cutter. The pipe cutter will have a thin cutter wheel, which will slice through pipe as you guide it in the space. Be sure to wear goggles and protective gear.

8. Ream the cut end of the pipe to remove any burrs from

the cut using a reamer, which is a cylinder – shaped rotary cutting tool that you run smoothly across the freshly cut edges of the pipe to remove rough edges.

9. Select your die head according to the size and type of

pipe you are threading and the thread from your require.

10. Place the die head over the pipe on the threader. 11. Press steadily on the front of the die head, while

simultaneously pushing the handle down to start threader. Before placing too much pressure on the handle, check to be sure that the ratchet pawl is engaged.

12. Use weight as leverage to apply pressure on the handle,

while holding it firmly. Be sure to maintain proper footing and balance for maximum control. Never use a tool or mechanism to hold the handle in place in order to free your hands, this can be dangerous and could result in injury.

13. Apply threading oil generously while threading.

Using on oil too thin as a substitute for threading oil can result in sub-standard threading.

14. Cease threading when the end of the threading die

is flat against the end of the pipe. When the die is even with the pipe, that means the correct threading size has been reached. If you continue pushing after this point, you will damage the thread.

(31)

Page 31 of 104

15. Reverse the ratchet mechanism and turn the die head in

the opposite direction. Be care full to maintain control of the threader as the dies are removed. Threads can be damaged when the die head is being removed if you don’t maintain control and move the piece smoothly.

16. Stand the pipe on end and gently tap it to remove

any particles that may be lodges within.

17. Clean the pipe with cloth, removing any oil. Be careful,

the threads will be very sharp.

18. Seal the threading with a pipe thread compound when

attaching the pipe to the connector.

19. Clean the pipe threader machine thoroughly after use so

the oils and metal pieces do not damage the machine, which could cause sub-standard threading during your next project.

11.4 Installation Procedure 11.4.1 Sleeves

o Size of Sleeves against pipe diameter shall be installed as per the approved shop drawing.

o Establish the exact location and/or elevation of the pipes to be provided with pipe sleeve, referring on the approved shop drawings.

o Install following pipe sleeves as per its application: passing through penetration in floors, partition, roofs and walls.

(32)

Page 32 of 104

Area of Application Material Specification Pipe Size

Fire Protection Piping Sleeves.

Exterior & Interior Concrete walls

above grade

Galvanized Steel Pipe Sleeve

As per approved

materials All Pipe Size

Concrete slabs above grade

Galvanized Steel Pipe Sleeve

As per approved

materials All Pipe Size

Interior partitions Galvanized Steel Pipe Sleeve

As per approved

materials All Pipe Size

o Approved G.I. sleeves as per material submittal shall be used wherever it through penetration in floors, partitions, roofs and walls.

o Site engineer shall ensure that outside diameter of sleeve is greater than the pipe diameter and it should be sized to accommodate the outside diameter of the insulation.

o Wherever the pipe work passes through a fire rated structure the gap in between the sleeve and the pipe shall be caulked with approved fire stop compound capable of achieving fire separation compatible with the structure through which it passes.

o Cut sleeves to length for mounting flush with both surfaces. Extend sleeves installed in floors of mechanical equipment areas or other wet areas 2 inches (50mm) above finished floor level. Using grout, seal the space outside of sleeves in slabs and walls without sleeve-seal system.

o Install sleeves for pipes passing through interior partitions. Cut sleeves to length for mounting flush with both surfaces. o For pipe sleeves at reinforced concrete section should be

closed at both ends. Install the pipe sleeve and secure by providing cross-brace using reinforcing bars. This shall prevent the sleeve from moving during concrete pouring. The pipe sleeve should be installed well before the completion of re-bars and form works installation.

o After the installation of sleeves, it shall be covered with polythelene sheet.

(33)

Page 33 of 104

o Site engineer shall ensure that the G.I. sleeve is tightly tied with reinforced steel rod.

o After the installation is carried out, Inspection shall be raised for engineers witness and approval of Consultant.

Pipe Floor Penetration

(34)

Page 34 of 104

Pipe Wall Penetration

11.4.2 Fire Sealant (will be submitted in a separate submittal)

o After the removal of the concrete forms and installation of the pipeline, the annular space between the sleeve and the pipe shall be filled with caulking material (oakum) leaving enough space at both ends of the sleeve for sealing and then apply approved fire sealant.

o Note: the above mentioned details above the installation of fire rated sealant does not mean that it will under Advance Vision Scope, that the scope will be as per contract.

(35)

Page 35 of 104

11.4.3 Groove Coupling Joint Installation 1. Inspect pipe ends for smoothness.

2. Apply lubricant to gasket and housing interior.

3. Slip on gasket to pipe end.

(36)

Page 36 of 104

5. Install coupling housing.

6. Tighten nuts and bolts.

11.4.4 Lubrication of Gasket (ref. Victaulic field installation handbook)

(37)

Page 37 of 104

11.4.5 Tightening Nuts of Grooved Coupling (ref. Victaulic field installation handbook)

o Tighten Nuts: tighten the nuts evenly by alternating sides until metal-to-metal contact occurs at the angle bolt pads. Make sure the housings’s keys completely engage the grooves and the offsets are equal at the bolt pads. To ensure a rigid joint, equal and positive offsets are preferred. Note: It is important to tighten the nuts evenly to prevent gasket pinching. An impact wrench or standard socket wrench or standard socket wrench can be used to bring the bolt pads into metal-to-metal contact. Refer to the “impact wrench usage Guidelines” section in this manual.

o Visually inspect the bolt pads at each joint to ensure metal-to-metal contact is achieved.

o “Negative” bolt pad offsets can occur when the nuts are not tightened evenly, which produces over-tightening of one side and under-tightening of the other side. In addition, “negative” offsets can occur if both nuts are under-tightened.

(38)
(39)

Page 39 of 104

11.4.6 Mechanical Tee – Installation Procedure (ref. Victaulic field installation handbook)

(40)

Page 40 of 104

3a. Make sure the locating collar engages the outer hole properly. Check this engagement by rocking the upper

outlet housing in the hole.

4. Install Remaaining Bolt / Nut: Insert the remaining bolt. Thread a nut onto the bolt finger-tight. Note: Make sure the

oval neck of each bolt seats properly in the bolt hole.

5. Tighten Nuts: Make sure the locating collar is still positioned properly in the outlet hole. Tighten the nuts

evenly by alternating sides until the upper (outlet) housing contracts the pipe completely.

(41)

Page 41 of 104

o If a branch connection is made to the upper housing before the Mechanical T is installed on the pipe. Make sure the branch connection is 90⁰ to the pipe run before completing the tightening sequences of the Mechanical T assembly. o When the Mechanical T is used as a transistion piece

between two runs, it must be assembled unto the runs before the branch connection is made.

o Victaulic female threaded products are designed to accommodate standard ANSI make pipe threads only. Use of male threaded products with special features, such as probes, dry pendent sprinkler heads, etc., should be verified as suitable for use with this Victaulic product. Failure to verify suitability in advance may result in assembly problems or leakage.

Branch Connection

11.4.7 Installation of Hangers & Support

o Refer to the approved shop drawing details for support

(reference: 421-A000-SH-F-04-ZZ0001).

o Layout the support using string blue chalk line to maintain the straightness and correctness in spacing of the supports.

(42)

Page 42 of 104

o Install pipe hanger and supports as per approved issued for construction detailed drawings.

o Hanger and support material should be according to the approved material submittal and passed the QA/QC Engineer inspection.

o Spacing of support and installation detailed as per approved shop drawing shall be implemented.

11.4.8 Installation of Beam Clamp Hanger & Support

o Refer to the approved shop drawing details for support

(reference: 421-F136-SH-F-04-020001).

o Layout the support using string blue chalk line to maintain the straightness and correctness in spacing of the supports. o Install pipe hanger and supports as per approved issued for

construction detailed drawings.

o Hanger and support material should be according to the approved material submittal and passed the QA/QC Engineer inspection.

o Spacing of support and installation detailed as per approved shop drawing shall be implemented.

11.4.9 Installation of Flexible Coupling as per NFPA 13 – Chapter 9

o 9.3.2.1 – listed flexible pipe coupling joining grooved end pipe shall be provided as flexure joints to allow individual sections of piping 2 ½ inches (65mm) or larger to move differentially with the individual sections of the building to which is attached.

o 9.3.2.2 – Coupling shall be arranged to coincide with structural separations with a building.

(43)

Page 43 of 104

o 9.3.2.3 – Systems having more flexible couplings than required by this section shall be provided with additional sway bracing as required.

o 9.3.2.3.1 – Within 24 inches (610mm) of the top and bottom of all risers, unless the following provisions are met: (a) In risers less than 3 feet (0.9m) in length, flexible couplings are permitted to be omitted. (b) In risers 3 feet to 7 feet (0.9m

to 2.1m) in length, one flexible coupling is adequate.

o Within 12 inches (305mm) above and within 24inches

(610mm) below the floor in multistory buildings.

o On both sides of concrete or masonry walls within 1 foot

(305mm) of the wall suface, unless clearance is provided.

o Within 24 inches (610mm) of the top of the drops exceeding

15 feet (4.6m) in length to the portions of systems supplying

more than one sprinkler, regardless of pipe size.

o Within 24 inches (610mm) above and 24 inches (610mm) below any intermediate points of support for a riser or other vertical pipe.

o 9.3.2.3.2 – when the flexible coupling below the floor is above the tie-in main to the main supplying that floor, a flexible coupling shall be provided in accordance with one of the (1) on the horizontal portion within 24 inches (610mm) of the tie-in (2) on the vertical portion of the tie-in where the tie-in incorporates a riser.

o 9.3.2.4 – flexible coupling for drops to hose lines, rack sprinklers, mezzanine and free-standing structures shall be installed regardless of the pipe sizes (1) within 24 inches

(610mm) of the top of the drop. (2) within 24 inches (610mm) above the uppermost drop support attachment,

where drop supports are provided to the structure, rack, or mezzanine. (3) within 24 inches (610mm) above the bottom of the drop where no additional drop support is provided.

(44)

Page 44 of 104

11.4.10 Pipe Identification, Tagging and Labeling

o Clean the piping and equipment surfaces of substances that could impair bond of identification devices, including dirt, oil, grease, release agents, and incompatible primers, paints, and encapsulants.

11.4.10.1 Pipe Identification Installation

After the pipe layout hydrostatically tested and finally painted, install pipe identification for every 3 meters apart and every change in direction.

 Background Color – Red.  Letter Color – White.

 Lettering Size – at least 1-1/2 inches (38mm) high.  Flow – Direction Arrows – integral with piping-system service lettering to accommodate both directions or as separate unit on each pipe label to indicate flow direction.

 Pre –Tensioned Pipe Labels – pre-coiled, semi-rigid formed to cover full circumference of pipe and to attach to pipe without fasteners or adhesive.

11.4.10.2 Valve - Tag Installation

Are mainly used for identification & safety. Therefore, clear & visible information that they withstand

exposure to harsh environments & retain important data. Valves tags that will not rust or corrode and are also made to last in a wide range of temperatures. Stamped or engraved with ¼ inch (6.4mm) letters for

piping-system abbreviation and 1/2 inch (13mm) numbers.

(45)

Page 45 of 104

 Tag Material; Brass – 0.032 inch (0.8mm) thick, with predrilled holes for attachment hardware.

 Valve-Tag Color – Red.  Letter Color – White.

 Valve Schedule – for each piping system on 8-1/2-by-

11-inch (A4) bond paper. Tabulate valve number,

piping system, system abbreviation (as shown on valve tag), location of valve (room or space), normal-operating position (open, closed, or

modulating), and variations for identification. Mark valves for emergency shutoff and similar special uses.

11.4.10.3 Warning - Tag Installation

 Material & thickness – multilayer, multicolor, plastic labels or mechanical graving, 1/16 inch (1.6mm) thick, predrilled holes for attachment hardware.  Letter Color – Black.

 Background Color – Yellow.

 Minimum Label Size – length and width vary for required label content, but not less than 2-1/2 by ¾

inch (64 by 19mm).

 Minimum Letter Size – ¼ inch (6.4mm) for name of units if viewing distance is less than 24inches

(600mm), ½ inch (13mm) for viewing distances up

to 72 inches (1830 mm), and approximately larger lettering for greater viewing distances. Include secondary lettering two-thirds to three-fourths

the size of principal lettering.

 Fastener – stainless-steel rivets or self-tapping srews.  Adhesive – contact-type permanent adhesive,

(46)

Page 46 of 104

 Label Content – include caution and warning

information, plus emergency notification instructions.

11.4.10.4 Metal Label for Equipment Installation

 Material & thickness – Brass 0.032 inch (0.8 mm) thick, with predrilled holes for attachment hardware.  Letter Color – White.

 Background Color – Red.

 Minimum Label Size – length and width vary for required label content, but not less than 2-1/2 by ¾

inch (64 by 19mm).

 Minimum Letter Size – ¼ inch (6.4 mm) for name of units if viewing distance is less than 24 inches (600 mm) for viewing distances up to 72 inches (1830

mm), and proportionately larger lettering for greater

viewing distances. Include secondary lettering two- thirds to three-fourths the size of principal lettering.  Fasteners – stainless-steel rivets or self-tapping

screws.

 Adhesive – contact-type permanent adhesive, compatible with label and with substrate.

 Label Content – include equipment’s drawing designation or unique equipment number, drawing numbers where equipment is indicated (plans, details, and schedule), and the specification section number and title where equipment is specified.

(47)

Page 47 of 104

11.4.11 Automatic Wet Sprinkler System

o Sprinkler Systems – Fully automated sprinkler system shall be provided to all buildings in accordance to NFPA

Requirement.

o The minimum pressure available at each sprinkler shall be designed in such a way that the required design density is achieved or the required flow at each sprinkler is achieved based on the application of the area whichever is higher. But in any case the minimum pressure requirement stated in NFPA 13 & recommendation of the sprinkler manufacturer are met.

o Each sprinkler system shall be connected with an alarm check valve & isolation valve. Each alarm check valve shall not serve a portion of floor exceeding 4831 sq.m. In any case if the floor area exceeds 4831 sq.m. additional alarm check valve with riser shall be provided. Non return valves shall be installed in the breeching inlet piping to avoid back flow of water from the system. Each sprinkler riser shall be

connected with a breeching inlet. Breeching inlet piping shall be connected to the downstream of the alarm check valve. o The sprinkler system shall be zoned and each zone shall be

provided with an isolation valve supervised electrically, flow switch (connected to the fire alarm system) test and drain valve, pressure gauge, etc. to comply with NFPA 13. The outlet of the drain valve shall be connected to the nearest floor drain.

o Automatic air release valves shall be installed at the elevated level of each riser with an isolation valve and end cap.

o All the isolation valves shall be provided with a supervisory switch which shall be electrically supervised in the main fire alarm panel. There shall be an individual address for each isolation valve.

(48)

Page 48 of 104

o Control and Alarms Requirements – shall be connected to the fire alarm system, BMS monitoring provided as defined in the BMS design report. Pressure reducing valves or other restricting devices shall be used to control the maximum pressure & maximum flow for each water outlet point

o Pressure Gauges – shall be installed in each system riser. Pressure gauge should installed above and below each alarm check valve where such devices are present.

o Water Flow Detecting Devices – the alarm apparatus for a wet pipe system shall consist of a listed waterflow detecting alarm device with the necessary attachments required to give an alarm.

o Relief Valves – a gridded wet pipe system shall be provided with a relief valve not less than ¼ in. (6.4mm).

o Fire Water supply to all buildings shall be connected to the external fire fighting distribution site wide utility network. The supply pipe shall be sized hydraulically to meet building fire fighting flow requirements.

11.4.11.1 Installation Wet Sprinkler System

1. Keep the materials in good storage conditions and

implement proper handling.

2. Prior to commencement of any work, areas and access will be inspected to conformthat areas are ready to start the work.

3. Carefully unload required lengths and sizes of pipes to the

work area. Identify type and location of pipes to be installed.

4. Fire protection water piping installation inside building

(Seamless Black steel piping)

(49)

Page 49 of 104

b) Determine the position of the pipe supports hanging points and mark out on theconcrete surface.

c) By means of string and chalk lines the actual pipe layout

will be identified, so as to allow for the installation of pipe supports, anchors and guides.

d) Mark pipe support locations, drill and install anchor bolt

onto slab soffit. ensure the anchor is totally inside concrete.

e) Supports will be fixed in place to suit the elevation of piping. Threaded rods shall be straight, firmly fixed to the

fastener and extend perpendicular.The Pipe support

shall be horizontal and firmly fixed to the threaded rod.

f) Pipes are then lifted to the required location & level manually or by use of Chain pulley. Position & tighten the pipe supports to firmly hold the pipe.

g) The pipe will be checked for initial level and position and, if necessary, adjusted on the pipe support, carefully aligned prior to final connection.

h) Assemble the pipes using threaded fittings I grooved couplings / flange fittings as per approved submittal.

i) Threaded Pipes & Fittings: - Apply a thin layer of paste applied & a few strands of jute yarn are wound over the threaded ends of pipes. Insert the threaded pipe ends into the screwed fitting & tighten the pipe firmly using an appropriate pipe spanner & finally pipe system is checked for proper alignment & re-leveled, if required.

j) Grooved Pipes & Fittings: -A thin film of lubricant is

applied to the Neoprene rings of the grooved fittings & the grooved pipe is inserted into the fitting. The bolts on the fitting are then tightened to firmly joint the pipe & finally pipe system is checked for proper alignment & re-leveled, if required.

(50)

Page 50 of 104

k) Remove scale, slag, dirt, and debris from inside and

outside of pipes, tubes, and fittings before assembly.

l) Install hanger rod and split ring support or common

bracket support to required position and level. Comply with requirements for hanger materials in NFPA 13 Installation of Sprinkler System.Hanger rod sizes will be in accordance with the requirements of the specification.

m) Supports will be arranged as near as possible to pipe

joints and any change in direction.

n) Risers shall be supported by pipe clamps or by hangers located on the horizontal connections within 24 inches of the centerline of the riser. Distance between supports for risers shall not exceed 25 ft (7.6 m).

o) During the installation, the open ends of pipes will be

protected by plug or plastic caps, which will only be removed when the adjoining sections will be installed.

p) Pipes and Fittings up to 50 mm dia. shall be threaded type and 65 mm dia. andabove shall be groove type connection as per specification and approved material submittal.

q) Pipes crossing construction expansion joints, mechanical

type expansion joints to be installed in the system. ( or group of flexible couplers achieving the required expansion)

r) Install sleeves for piping penetrations of walls and floors.

s) It shall be ensured that all complete installation look neat

and tidy , and there is adequate support spacing between pipes as possible.

t) Install labeling and pipe markers on piping according to

(51)

Page 51 of 104

6. Install sprinkler control valves, test assemblies, and drain

risers adjacent to standpipes when sprinkler piping is connected to standpipes.

7. Install automatic (ball drip) drain valve at each check valve

for department connection, to drain piping between fire-department connection and check valve. Install drain piping to and spill over floor drain or to outside building. Install alarm devices in piping systems.

8. Install shutoff valve, backflow preventer, pressure gage,

drain, and other accessories indicated at connection to water-service piping.

9. Grooved Coupling Connection for all valve size connection.

11.4.11.2 Hydrostatic Pressure Leak Test

 The installation to be tested shall be inspected for compliance with the drawings and specifications. Significant variations shall be investigated and

corrected, if required, before proceeding with the tests.

a) Before testing ensure that all temporary connections have been made and that only personnel needed for the

pressure test are present.

b) All items for test have to be provided on site before the test i.e. pressure gauges, instruments, water etc.

c) Before taking up pressure testing, each valve in the pipe

system will be checked by closing and opening to observe if it is workingefficiently (any valve found not working satisfactorily is replaced). Keep open all the in-line valves.

d) Isolate any parts of the system that their pressure rating is less than the testing pressure such as relief valves, automatic air vents and all devices that might be damaged by the test pressure.

e) No pressure shall be applied against the closed gate of gate valves. All valves shall be in the open position but completely back seated during testing. End valves shall be capped installed by blind flange.

(52)

Page 52 of 104

f) No testing shall be carried out against or through the pressure reducing valves. The setting of the pressure reducing valves shall not be changed for testing purposes.

g) Plug all the open ends of pipes, keeping only two points

open, one at the highest end & ·the other at the lowest end of the pipe section to be checked.

h) Install a gate valve at the highest open end of the pipeline

and keep it fully open to act as "air purge point to relieve the trapped air from the pipeline.

i) A "Tee" connection Is installed at the lower end of the

pipe. A water pressure gauge with a gate valve & a hydraulic pressure pump are attached to one end of this Tee connection & a gate valve at the other free end of the Tee connection to act as a "Filling Point".

j) Verify pressure gauges for calibration certificates. Check proper filling and pressurization sequence of piping system to be tested.

k) Fill pipe slowly with water through the filling point. Do not use power-driven pumpunless approved.

l) Fill absorbent pipes with water and Allow to stand 24

hours at working pressure.

m) Once all the air in the pipe system is purged through the

"purge point" and only water starts flowing out indicating

that the pipeline is free from trapped air, shut the air relief

gate valve at the topend of the pipeline. Once the

pipeline is filled with water shut the gate valve at the filling

point too.

n) All piping and attached appurtenances subjected to

system working pressure shall maintain that pressure without loss for 24 hours. Test pressure shall not exceed maximum pressure for any valve, or other component in system under test.

o) Now start applying water pressure through hydraulic

pressure pump, till the pipeline attains a test pressure of

1.5 times the working pressure for 2 hours.

p) Walk along the pipe line route & Inspect for any leakage. If any leakage is found, drain off the water from the system by opening the filllng point at the lowest end of the system .Rectify the leak by tightening the joint or replacing of defective pipe I fitting as the case may be.

(53)

Page 53 of 104

q) The test pressure shall be read from a gauge located at

the low elevation point of the system or portion being tested.

r) Once the test has been satisfactorily completed the test

pressure shall be released slowly so as not to produce shocks and sudden contractions that might damage the piping.

s) Prepare reports for tests and for corrective action

required.

t) Note:Notify Consultant at least 24 hours before Testing

must be made. Perform test specified as with the presence of Consultant.

11.4.11.3 Flushing Procedure

 After approval of installation of pipes and fittings, flushing shall be done for sprinkler system with clean water to remove dust and debris that might have been present during construction works.

 All obstructions, debris and superfluous matters, shall be removed from the pipeline. All piping shall be flushed out before commissioning.

 Items of equipment which would be sensitive to damage during hydro flushing shall be removed, blocked off or isolated.

 Hydrostatic or water flush: use clean, fresh water.  Install test drain valve to the drain points.

 Provide empty drum or container.  Provide water supply.

 Provide flow measurement in flushing water supply line to be used as basis for verification of flow velocities in piping system.

 Test drain valve shall be flushed in fully open position at drain points.

 The drain points should be tapp or near the floor drain. If ever there is no floor drain near the drain point, we can used empty drum or container to stored flush water. Observe proper disposition of flush water.  All piping systems shall be flushed using high

(54)

Page 54 of 104

 Flushing has to be done by filling the system from one and leaving the bottom valve open at the opposite end with pressurized clean potable water with required flow maintaining 10 ft/sec water velocity to carry out all debris/dirt/slag along with it.

 The flushing operation shall be continued until

satisfactory cleaning is ensured then close all bottom ends.

 Note: Disinfections process in fire fighting is not NFPA requirement, the disinfections chemical material will cause rusting and reactions with steel pipes. Refer to RFI Submission Reference: 421-A000-M-AV-01712

Rev.00. And if ever required by consultant the

disinfections will be prepared by specialist and will be separately submitted.

11.4.11.4 Interface

 The wet pipe system employs automatic (fusible link, glass bulb, or closed type) sprinklers attached to piping containing water pressure at all times. When fire

occurs, individual sprinklers are actuated by the heat, and water flows immediately.

S.N. ⁰F ⁰C ⁰F ⁰C Temperature Classification Color Code Glass Bulb 1 100 38 135-170 57-77 Ordinary Uncolored/ Black Orange / Red

2 150 66 175-225 79-107 Intermediate White Yellow /

Green

3 225 107 250-300 121-149 High Blue Blue

4 300 149 325-375 163-191 Extra High Red Purple

5 375 191 400-475 204-246 Very High Green Black

6 475 246 500-575 260-302 Ultra High Orange Black

7 625 329 650 343 Ultra High Orange Black

Alarm Check Valve – the wet pipe system is

controlled by an alarm check valve. When a sprinkler activates, the flow of water raises the alarm valve clapper from its seat, thereby lifting the pilot valve disc from the nozzle. These permits water to enter the alarm line. A water motor gong is actuated by the flow. An optional pressure switch may be attached on the alarm line to provide an electric signal. The electric can be send to the building’s main fire alarm control panel.

(55)

Page 55 of 104

 Where the water supply has constant pressure, the alarm valve is used without the retard chamber. In cases where a local alarm is adequate, water is admitted directly to water motor-driven gong. If no water motor gong is required.

11.4.12 Automatic Clean Agent Fire Suppression System (FM200)

o FM200 gaseous fire suppression is provided for the electrical ITC equipment rooms to comply with the requirements of NFPA 2001.

o The discharge duration of the gas will be within 10 seconds. Design concentration for FM200 will be 7.19 %.

o A fire detection, actuation & alarm system will be provided for each individual gas suppression system. A minimum of 2 Nos. detectors with a combination of ionization & optical type smoke detectors will be provided with actuation for gas release and be achieved by cross zoning of the detectors (double knock). Detector allocation is based on a maximum of 23 sq/m per detector. Heat detectors are provided in the battery room with cross zoning.

References

Related documents

SFPR Delaware State Fire Prevention Regulations NFPA 11 - Standard for Foam Extinguishing Systems.. NFPA 12 - Standard on Carbon Dioxide Extinguishing Systems NFPA 12A -

Duct detectors required by the provisions of IMC and NFPA shall be connected to the building fire alarm control panel system, where provided, in accordance with the.. requirements

from fire sprinkler systems where water treatment is not added shall be prevented by the installation of not less than an Approved Double Check Valve Assembly, and such a device

set of specialised injuries which are peculiar to your patient 

In the design of shallow foundation or traffic surface, foundation or traffic surface, design engineers need to know design engineers need to know the bearing capacity of soil

As far as the letter by the first respondent to the applicant’s attorneys which was annexed to applicant’s replying affidavit, its contents stating that it

1 Connect pressure gauge 99 362 to the test connection on the return fuel manifold and open the test connection. 2 Crank the engine using the

To compare the effectiveness of eradication methods between pulled, sprayed (spring and fall spraying combined) and invaded control plots, we used generalized linear mixed