U
U
U
UA
A
A
AT No.1 & No.2
T No.1 & No.2
T No.1 & No.2
T No.1 & No.2 Protection Relay Setting &
Protection Relay Setting &
Protection Relay Setting & Test
Protection Relay Setting &
Test
Test
Testing
ing
ing
ing
Contents
1. Setting of UAT #1 Protection Relay - - - P. 3 – P13
2. UAT #1 Protection Relay Test Record Sheet - - - P.14 – P.21
3. Setting of UAT #2 Protection Relay - - - P. 22 – P.32
4. UAT #2 Protection Relay Test Record Sheet - - - P. 33 – P.40
Setting of UAT-1 Protection Relay Type RET670
F87T - Unit Aux. Transformer Differential Protection
1. Terminal identification
Station Name : KERAMASAN
Bay Name: UAT-1
Relay Name RET 670
Relay serial No
Frequency 50 Hz
Aux voltage 110 VDC
2. General Data
Transformer: GSUT-1, two winding
Rated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kV
W1 rated current - Ir1 315 A W2 rated current - Ir2 550 A
Connection Dyn11 (resistive grounding at Y winding)
p.u. Impedance 0.08 at Base 6 CT ratio W1 (11kV) 750 / 1 A CT ratio W2 (6.3kV) 1250 / 1 A VT ratio W1 11 / 0.11 kV VT ratio W2/W3 6.3 / 0.11 kV
Short circuit data :
Three-phase short circuit current at 6.3kV busbar 9300 A Phase to Ground short circuit current at 6.3kV busbar 11 A Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 A measured at 6.3kV side
Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 A measured at 11kV side
3. Setting Considerations
Protection Scheme- Transformer 2 winding differential protection (87T) is applied as main
protection to mostly protect the transformer from internal phase to phase fault. Very small earth fault current due to resistive grounding makes REF protection will not be effective and sensitive enough to protect the transformer from internal earth fault. Therefore, sensitive earth fault protection relay shall then be provided in the backup protection relay.
Differential current setting (Idmin)
The usual practice for transformer protection is to set the bias characteristic to a value of at least twice the value of the expected spill current under
through faults conditions. Spill current may arise from several conditions such as : - transformer phase shift and ratio error
- current transformer ratio error - different CTs characteristic
Idmin of 0.3 x Ibase is normally recommended to be applied. Zero-sequence current substraction
A differential protection may operate unwanted due to external earth faults in cases where the zero sequence current can flow only on one side of the power transformer but not on the other side. This is the situation when the zero sequence current can not be properly transformed to the other side of the power transformer having a combined Y and D connection group. In such case, the zero sequence substraction function shall be set ON for Y winding and OFF for D winding.
4. Setting of analogue input
Configure analogue inputs for TRM1 (-X401) : Set analogue current channels
AI1 AI2 AI3 AI4 AI5
Ctprim = 750 750 750 1250 1250
Ctsec = 1 A 1 A 1 A 1 A 1 A
CTStarPoint = To Object To Object To Object To Object To Object
AI6 AI7 AI8 AI9
Ctprim = 1250 not used not used not used
Ctsec = 1 A not used not used not used
CTStarPoint = To Object not used not used not used Set analogue voltage channels
AI10 AI11 AI12
Vtprim = not used not used not used
Vtsec = not used not used not used
5. Protection Settings
5.1. Setting of the Differential function data under T2WPDIF General settings.
Winding 1 (W1) Winding 2 (W2) RatedVoltageW1 11 kV RatedVoltageW2 6.3 kV RatedCurrentW1 315 A RatedCurrentW2 550 A ConnectTypeW1 D ConnectTypeW2 Y TconfigForW1 No TconfigForW2 No CT1ratingW1 750 A CT1ratingW2 1250 A
ZSCurrSubtrW1 Off ZSCurrSubtrW2 On
ClockNumberW2 11
Note : All other setting parameters under general setting are not relevant. Use default values.
5.2. Differential Protection Setting (87T) under T2WPDIF Setting group:
Operation = On
Operation of SOTF feature
SOTFMode = Off
Setting of differential current alarm
IDiffAlarm = 0.2 *Ibase Setting of time delay of differential current alarm
tAlarmDelay = 10 s
Setting of minimum differential operating current
IdMin = 0.3 *Ibase Setting of cross-over point between slope 1 and slope 2
EndSection1 = 1.25 Ibase Setting of slope 2 stabilisation, Slope 1 has fixed stabilization
SlopeSection2 = 40% *Ibias Setting of cross-over point between slope 2 and slope 3
EndSection2 = 3.00 Ibase Setting of slope 2 stabilisation
SlopeSection3 = 80% *Ibias
Setting of minimum differential operating current for unrestraint step Idunre = 20.00 *Ibase Set the operation of Cross Blocking logic On-Off
OpCrossBlock = On
Set the second and fifth harmonic stabilizing level when transformers are inside the zone
I2/I1Ratio = 15%
I5/I1Ratio = 25%
Set the operation of Negative sequence differential protection
NegSeqDiffEn = No
Setting of minimum negative sequence differential current level
IMinNegSeq = 0.04
Setting of the Relay operating angles
NegSeqROA = 60 deg
Set the operation of Open CT detection
OpenCTEnable = No
Note : All other setting parameters under this setting group are not relevant.
5.3. All other protection functions
Operation = Off
6. Assignment of Binary Input BIM_3
BIM_3.BI01 : Bucholz Trip
BIM_3.BI02 : Rapid Pressure Relay Trip
BIM_3.BI03 : Oil Level Low Low Trip
BIM_3.BI04 : Protective Relay Trip
BIM_3.BI05 : Oil Temperature Trip
BIM_3.BI06 : HV Winding Temperature Trip
BIM_3.BI07 : Not used
BIM_3.BI08 : Trip from Generator Protection (59BG)
BIM_3.BI09 : Trip from Generator Protection (52G Mech Fail)
BIM_3.BI10 : Trip from GSUT Protection
BIM_3.BI11 : Reset Lockout BIM_3.BI12 : Not used
BIM_3.BI13 : Not used
BIM_3.BI14 : Not used
BIM_3.BI15 : Not used
BIM_3.BI16 : Not used
7. Assignment of Binary Output BOM_4
BOM_4.BO01 : Transformer Differential Trip (T2WPDIF) BOM_4.BO02 : Not used
BOM_4.BO03 : Trip from Generator Protection
BOM_4.BO04 : Trip from UAT Transformer's Protection (Bucholz etc) BOM_4.BO05 : Not used
BOM_4.BO06 : Not used
BOM_4.BO07 : Not used
BOM_4.BO08 : Not used
BOM_4.BO09 : Transformer Differential Trip (T2WPDIF) BOM_4.BO10 : Not used
BOM_4.BO11 : Trip from Generator Protection
BOM_4.BO12 : Not used
BOM_4.BO13 : Trip from UAT Transformer's Protection (Bucholz etc) BOM_4.BO14 : Trip from GSUT Protection
BOM_4.BO15 : Transformer Differential Trip (T2WPDIF) BOM_4.BO16 : Not used
BOM_4.BO17 : Trip from GSUT Protection
BOM_4.BO18 : Trip from Generator Protection BOM_4.BO19 : Not used
BOM_4.BO20 : Not used
BOM_4.BO21 : Not used
BOM_4.BO22 : Not used
BOM_4.BO23 : Not used
BOM_4.BO24 : Not used
Setting of UAT-1 Protection Relay Type REF615
F5051 - Backup OC & EF Protection
1. Terminal identification
Station Name KERAMASAN
Bay Name: UAT-1
Relay Name REF615
Relay serial No
Frequency 50 Hz
Aux voltage 110 VDC
2. General Data
Transformer: UAT-1, two winding
Rated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kV
W1 rated current - Ir1 315 A W2 rated current - Ir2 550 A
Connection Dyn11 (resistive grounding at Y winding)
p.u. Impedance 0.08
at Base 6
CT ratio W1 (11kV) 750 / 1 A
CT ratio W2 (6.3kV) 1250 / 1 A
Short circuit data :
Three-phase short circuit current at 6.3kV busbar 9300 A Phase to Ground short circuit current at 6.3kV busbar 11 A Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 A measured at 6.3kV side
Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 A measured at 11kV side
Maximum tripping time for 6.3kV outgoing feeders Instantaneous
3. Setting Considerations
Protection Scheme- Low-set phase overcurrent (51) protection at 11kV side are used as backup protection for differential (87T) and REF (87REF) protection.
To maintain selectivity against downstream protection relays, a time delay of 0.5s on top of the downstream (6.3kV outgoing feeders) protection relays maximum operating time shall be introduced.
- Instantaneous-set overcurrent (50) at 11kV side is applied to protect the transformer during short circuit condition. Time delay shall be introduced to maintain selectivity from the fault which occur at the other parts of the system.
- Sensitive earth fault/SEF (50S) of this relay will be applied at 6.3kV to detect earth fault condition at 6.3kV system. To maintain selectivity against earth fault protection relay at 6.3kV outgoing feeders, a time delay of 0.5s on top of the
outgoing feeders tripping time is introduced. As the fault current is considerably small, a longer operating time is somehow still acceptable as long as not exceeding the rated time of NGR (10s).
- To avoid unwanted operation of the overcurrent and earth fault protection due to inrush current during transformer startup, the inrush detection element INRPHAR is activated to give a blocking signal to the overcurrent & earth fault element when inrush current is detected.
4. Setting of analogue input
Analog input settings, phase currentsSecondary current = 1 A
Primary current = 750 A
Amplitude corr. A = 1
Amplitude corr. B = 1
Amplitude corr. C = 1
Nominal current = 315 A {In}
Rated secondary value = 3 mV/Hz
Reverse polarity = 0 {False}
Analog input settings, residual currents
Secondary current = 1 A
Primary current = 1250 A
Amplitude corr. = 1
Reverse polarity = 0 {False}
5. General System Setting
Rated frequency = 50 Hz
Phase rotation = ABC
Blocking mode = Freeze timer
Bay Name = UAT2
IDMT saturation point = 50
6. Setting of Three Phase Overcurrent Function (PHxPTOC) on 11 kV side
6.1. PHIPTOC (Instantaneous) Non group settings:
Activation of the PHIPTOC function
Operation = 1 { 1=On }
Number of phases required for operate activation
Num of start phase = 1 { 1=1-out-of-3 }
Reset delay time
Reset delay time = 20 ms { instantaneous }
6.2. PHIPTOC (Instantaneous) Group settings:
Start values is set at 130% of transformer short circuit current to get selectivity with faults at 6.3kV. Start Value PHHPTOC = 130% x 3768.5 A
= 4899.1 A Start Value PHHPTOC = 15.6 x In Operate delay time
Operate delay time = 20 ms { instantaneous }
Note : All other setting parameters are not relevant. Default values can be used.
6.3. PHHPTOC (high-set) Non group settings:
Activation of the PHHPTOC function
Operation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
6.4. Setting of parameters for PHLPTOC (low-set) Non-group Setting
Activation of the PHLPTOC function
Operation = 1 { 1=On }
Number of phases required for activation
Num of start phase = 1 out of 3 Minimum operate time for IDMT curve
Min. oper. Time = 40 ms
Reset delay time
Reset delay time = 20 ms
Curve parameter for programmable curve
Curve parameter A, B, C, D, E = default {NA}
6.5. PHLPTOC (low-set) Group settings:
Start values is set at 110% of transformer rated current.
Start Value PHLPTOC = 120% x 315 A
= 378 A
Start Value PHLPTOC = 1.2 x In Multiplier for scalng the start value
Start value Mult = 1 Time multiplier setting (TMS)
Time multiplier = 1 {See note below}
Operate delay time
Time delay PHLPTOC = 400 ms {Not relevant for inverse type}
Operating curve type
Curve PHLPTOC = IEC Extremely Inverse Selection of reset curve type
Type of reset curve = 1 {Immediate}
Note : Time delayed PHLPTOC shall be set to operate in about 0.8 s at short circuit
current to give safe margin to the transformer main protection and other unit protection at the other part of the system.
Short circuit current = 3768.5 A = 12 x In
with start value = 1.2 x In
and set time multiplier = 1
for extremely inverse curve, the operating time t is : t = 0.814 s --> OK
7. Setting of Earth Fault Protection Function (EFxPTOC) on 6.3 kV side
7.1. EFIPTOC (Instantaneous) Non group settings:
Activation of the EFIPTOC function
Operation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.2. EFHPTOC (high-set) Non group settings:
Activation of the EFHPTOC function
Operation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.3. EFLPTOC (low-set) Non group settings:
Activation of the EFLPTOC function
Operation = 1 { 1=On }
Minimum operate time for IDMT curve
Min. oper. Time = 40 ms
Reset delay time
Reset delay time = 20 ms
Curve parameter for programmable curve
Curve parameter A, B, C, D, E = default {NA}
Selection for used Io signal
Io signal Sel = 1 {Measured Io)
7.3. EFLPTOC (low-set) Group settings:
Start value for earth fault is set at 50% of maximum earth fault current.
Start Value EFLPTOC = 50% x 11 A {See note below}
= 6 A
Start Value EFLPTOC = 0.02 x In Multiplier for scalng the start value
Start value Mult = 1 Time multiplier setting (TMS)
Time multiplier = 0.1 {See note below}
Operate delay time
Time delay EFLPTOC = 0.9 s Operating curve type
Curve EFLPTOC = Definite time Selection of reset curve type
Type of reset curve = 1 {Immediate}
8. Setting of Inrush Detector INRPHAR
8.1. Inrush Detector INRPHAR Group Setting
Ratio of the 2nd to the 1st harmonic leading to restraintStart value = 0.15 %
Operate delay time
Operate delay time = 20 ms
8.2. Inrush Detector INRPHAR Non Group Setting
Activation of the INRPHAR functionOperation = 1 { 1=On }
Reset delay time
Reset delay time = 20 ms
9. All other protection functions
Operation = 5 { 5=Off }
10. Assignment of Binary Input
Binary Input Terminal -X110_
BI1 : Not used
BI2 : Not used
BI3 : Not used
BI4 : Not used
BI5 : Not used
BI6 : Not used
BI7 : Not used
BI8 : Not used
BI9 : Not used
BI10 : Not used
Binary Input Terminal -X120_ BI1
BI2 BI3
BI4 : Reset lockout
11. Assignment of Binary Output
Binary Output Terminal -X100_
PO1 : Overcurrent Trip
(Operation of PHHPTOC, PHLPTOC) PO2 : SEF Trip
(Operation of EFLPTOC) SO1 : Overcurrent Trip
SO2 : SEF Trip PO3
PO4
Binary Output Terminal -X110_
SO1 : Overcurrent Trip SO2 : SEF Trip SO3
SO4
Equipment : Feeder : 1. Reference Drawing Schematic Diagram : Transformer Bay : 2. General Data Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests 3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
Protection Relay Test
Unit Aux. Transformer Differential Protection Relay RET670
UAT #1 KPP-00-TPS-W-141 11kV 6.3kV UAT #1 ABB RET670 F87T
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1 2 3 4 5 6 7
No. Procedure Injected Values
Secondary
Measured
Values Primary Remarks
Inject current phase R → A101 A A
Inject current phase R → A104 A A Inject current phase S → A105 A A Inject current phase S → A102 A A Inject current phase T → A103 A A
Inject current phase T → A106 A A Inject current Neutral → A107 A A
3.3 Deferential Protection Test
(1) Check on HV side Secondary Injection
No. Procedure Items to be verified. Remarks
1 Make sure that REF and OC / EF function are set to off.
2 Connect the test set for injection of 3 phase current to the current terminals of RET670 which are connected to the CT's on HV side of transformer
3 Increase the current in phase L1 until the protection operates and check
L1
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate 4 Increase the current in phase L2 until
the protection operates and check
L2 For stable condition,
Trip not operated
a) the operating current (Iop)
Operate / Not operate
For stable condition, Trip not operated
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Operate / Not operate Operate / Not operate 5 Increase the current in phase L3 until
the protection operates and check L3
(2) Check on LV side Secondary Injection
No. Procedure Items to be verified. Remarks
c) Alarm contact operation c) Alarm contact :
Operate / Not operate 1 Connect the test set for injection of 3
phase current to the current terminals of RET670 which are connected to the CT's on LV side of transformer
3 Increase the current in phase L2 until the protection operates and check
L2
Operate / Not operate 2 Increase the current in phase L1 until
the protection operates and check L1
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate
4 Increase the current in phase L3 until L3
c) Alarm contact operation c) Alarm contact :
Operate / Not operate 4 Increase the current in phase L3 until
the protection operates and check L3
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate
3.4 6.3kV Restricted EF Protection Test
(1) Secondary Injection
No.
4. Remarks :
Procedure Items to be verified. Remarks 1 Make sure that Differential protection
and OC/EF function are set to off.
2 Connect the test set for injection of neutral current to the current terminals of RET670 to which the NCT 20kV is connected
3 Increase the current in until the protection operates and check
L1
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Operate / Not operate
Equipment : Feeder : 1. Reference Drawing Schematic Diagram : Transformer Bay : 2. General Data Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests 3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
Protection Relay Test
Backup OC & EF Protection Relay REF615
UAT #1 KPP-00-TPS-W-141 11kV 6.3kV UAT ABB RET615 F5051 1VHR91059397
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1 2 3 4
No. Procedure Injected Values
Secondary
Measured
Values Primary Remarks
Inject current phase T A A
Inject current phase N A A
Inject current phase R A A
Inject current phase S A A
3.3 Testing of the phase overcurrent protection
The test is performed as a secondary test, by injecting current to the current energizing inputs with the setting values used during normal operation
No.
2 Inject the current (Ii) in phase L2
Procedure Items to be verified. Remarks 1 Inject the current (Ii) in phase L1
Ii = 2.5 * I > * rated current input Start of stage I > : .
I > setting : * In
Ii = 2.5 * I > * rated current input Start of stage I > : .
I > setting : * In Trip of stage I > : . t > setting : s Operation time : s Trip of stage I > : . t > setting : s Operation time : s
3 Inject the current (Ii) in phase L3
Ii = 2.5 * I > * rated current input Start of stage I > : .
I > setting : * In Trip of stage I > : .
t > setting : s
Operation time : s
4 Inject the current (Ii) in phase L1
Ii = 8 * I >>> * rated current input Start of stage I >>> : .
I >>> setting : * In Trip of stage I >>> : .
t >>> setting : s
Operation time : s
5 Inject the current (Ii) in phase L2
Ii = 8 * I >>> * rated current input Start of stage I >>> : .
I >>> setting : * In Trip of stage I >>> : .
t >>> setting : s
Operation time : s
6 Inject the current (Ii) in phase L3 5 Inject the current (Ii) in phase L2
Ii = 8 * I >>> * rated current input Start of stage I >>> : .
I >>> setting : * In Trip of stage I >>> : . t >>> setting : s Operation time : s
Contractor
3.4 Testing of the earth fault protection
The test is performed as a secondary test, by injecting current to the current energizing inputs with the setting values used during normal operation
No.
4. Remarks :
Start of stage I > : .
I0 > setting : * In Trip of stage I > :
.
2 Inject the current (Ii) in the earth fault
Procedure Items to be verified.
energizing input :
Ii = 2.5 * I0 >> * rated current input Start of stage I >> :
.
I0 >> setting : * In Trip of stage I >> :
.
t0 >> setting : s Operation time :
s
Remarks 1 Inject the current (Ii) in the earth fault
energizing input :
Ii = 2.5 * I0 > * rated current input
t0 > setting : s Operation time :
s
Setting of UAT-2 Protection Relay Type RET670
F87T - Unit Aux. Transformer Differential Protection
1. Terminal identification
Station Name : KERAMASAN
Bay Name: UAT-2
Relay Name RET 670
Relay serial No
Frequency 50 Hz
Aux voltage 110 VDC
2. General Data
Transformer: GSUT-2, two winding
Rated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kV
W1 rated current - Ir1 315 A W2 rated current - Ir2 550 A
Connection Dyn11 (resistive grounding at Y winding)
p.u. Impedance 0.08 at Base 6 CT ratio W1 (11kV) 750 / 1 A CT ratio W2 (6.3kV) 1250 / 1 A VT ratio W1 11 / 0.11 kV VT ratio W2/W3 6.3 / 0.11 kV
Short circuit data :
Three-phase short circuit current at 6.3kV busbar 9300 A Phase to Ground short circuit current at 6.3kV busbar 11 A Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 A measured at 6.3kV side
Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 A measured at 11kV side
3. Setting Considerations
Protection Scheme- Transformer 2 winding differential protection (87T) is applied as main
protection to mostly protect the transformer from internal phase to phase fault. Very small earth fault current due to resistive grounding makes REF protection will not be effective and sensitive enough to protect the transformer from internal earth fault. Therefore, sensitive earth fault protection relay shall then be provided in the backup protection relay.
Differential current setting (Idmin)
The usual practice for transformer protection is to set the bias characteristic to a value of at least twice the value of the expected spill current under
through faults conditions. Spill current may arise from several conditions such as : - transformer phase shift and ratio error
- current transformer ratio error - different CTs characteristic
Idmin of 0.3 x Ibase is normally recommended to be applied. Zero-sequence current substraction
A differential protection may operate unwanted due to external earth faults in cases where the zero sequence current can flow only on one side of the power transformer but not on the other side. This is the situation when the zero sequence current can not be properly transformed to the other side of the power transformer having a combined Y and D connection group. In such case, the zero sequence substraction function shall be set ON for Y winding and OFF for D winding.
4. Setting of analogue input
Configure analogue inputs for TRM1 (-X401) : Set analogue current channels
AI1 AI2 AI3 AI4 AI5
Ctprim = 750 750 750 1250 1250
Ctsec = 1 A 1 A 1 A 1 A 1 A
CTStarPoint = To Object To Object To Object To Object To Object
AI6 AI7 AI8 AI9
Ctprim = 1250 not used not used not used
Ctsec = 1 A not used not used not used
CTStarPoint = To Object not used not used not used Set analogue voltage channels
AI10 AI11 AI12
Vtprim = not used not used not used
Vtsec = not used not used not used
5. Protection Settings
5.1. Setting of the Differential function data under T2WPDIF General settings.
Winding 1 (W1) Winding 2 (W2) RatedVoltageW1 11 kV RatedVoltageW2 6.3 kV RatedCurrentW1 315 A RatedCurrentW2 550 A ConnectTypeW1 D ConnectTypeW2 Y TconfigForW1 No TconfigForW2 No CT1ratingW1 750 A CT1ratingW2 1250 A
ZSCurrSubtrW1 Off ZSCurrSubtrW2 On
ClockNumberW2 11
Note : All other setting parameters under general setting are not relevant. Use default values.
5.2. Differential Protection Setting (87T) under T2WPDIF Setting group:
Operation = On
Operation of SOTF feature
SOTFMode = Off
Setting of differential current alarm
IDiffAlarm = 0.2 *Ibase Setting of time delay of differential current alarm
tAlarmDelay = 10 s
Setting of minimum differential operating current
IdMin = 0.3 *Ibase Setting of cross-over point between slope 1 and slope 2
EndSection1 = 1.25 Ibase Setting of slope 2 stabilisation, Slope 1 has fixed stabilization
SlopeSection2 = 40% *Ibias Setting of cross-over point between slope 2 and slope 3
EndSection2 = 3.00 Ibase Setting of slope 2 stabilisation
SlopeSection3 = 80% *Ibias
Setting of minimum differential operating current for unrestraint step Idunre = 20.00 *Ibase Set the operation of Cross Blocking logic On-Off
OpCrossBlock = On
Set the second and fifth harmonic stabilizing level when transformers are inside the zone
I2/I1Ratio = 15%
I5/I1Ratio = 25%
Set the operation of Negative sequence differential protection
NegSeqDiffEn = No
Setting of minimum negative sequence differential current level
IMinNegSeq = 0.04
Setting of the Relay operating angles
NegSeqROA = 60 deg
Set the operation of Open CT detection
OpenCTEnable = No
Note : All other setting parameters under this setting group are not relevant.
5.3. All other protection functions
Operation = Off
6. Assignment of Binary Input BIM_3
BIM_3.BI01 : Bucholz Trip
BIM_3.BI02 : Rapid Pressure Relay Trip
BIM_3.BI03 : Oil Level Low Low Trip
BIM_3.BI04 : Protective Relay Trip
BIM_3.BI05 : Oil Temperature Trip
BIM_3.BI06 : HV Winding Temperature Trip
BIM_3.BI07 : Not used
BIM_3.BI08 : Trip from Generator Protection (59BG)
BIM_3.BI09 : Trip from Generator Protection (52G Mech Fail)
BIM_3.BI10 : Trip from GSUT Protection
BIM_3.BI11 : Reset Lockout BIM_3.BI12 : Not used
BIM_3.BI13 : Not used
BIM_3.BI14 : Not used
BIM_3.BI15 : Not used
BIM_3.BI16 : Not used
7. Assignment of Binary Output BOM_4
BOM_4.BO01 : Transformer Differential Trip (T2WPDIF) BOM_4.BO02 : Not used
BOM_4.BO03 : Trip from Generator Protection
BOM_4.BO04 : Trip from UAT Transformer's Protection (Bucholz etc) BOM_4.BO05 : Not used
BOM_4.BO06 : Not used
BOM_4.BO07 : Not used
BOM_4.BO08 : Not used
BOM_4.BO09 : Transformer Differential Trip (T2WPDIF) BOM_4.BO10 : Not used
BOM_4.BO11 : Trip from Generator Protection
BOM_4.BO12 : Not used
BOM_4.BO13 : Trip from UAT Transformer's Protection (Bucholz etc) BOM_4.BO14 : Trip from GSUT Protection
BOM_4.BO15 : Transformer Differential Trip (T2WPDIF) BOM_4.BO16 : Not used
BOM_4.BO17 : Trip from GSUT Protection
BOM_4.BO18 : Trip from Generator Protection BOM_4.BO19 : Not used
BOM_4.BO20 : Not used
BOM_4.BO21 : Not used
BOM_4.BO22 : Not used
BOM_4.BO23 : Not used
BOM_4.BO24 : Not used
Setting of UAT-2 Protection Relay Type REF615
F5051 - Backup OC & EF Protection
1. Terminal identification
Station Name KERAMASAN
Bay Name: UAT-2
Relay Name REF615
Relay serial No
Frequency 50 Hz
Aux voltage 110 VDC
2. General Data
Transformer: UAT-2, two winding
Rated data : Rated power 6 MVA
Voltage ratio 11 kV / 6.3 kV
W1 rated current - Ir1 315 A W2 rated current - Ir2 550 A
Connection Dyn11 (resistive grounding at Y winding)
p.u. Impedance 0.08
at Base 6
CT ratio W1 (11kV) 750 / 1 A
CT ratio W2 (6.3kV) 1250 / 1 A
Short circuit data :
Three-phase short circuit current at 6.3kV busbar 9300 A Phase to Ground short circuit current at 6.3kV busbar 11 A Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 6580 A measured at 6.3kV side
Phase current contribution of UAT for 3-Ph fault at 6.3kV busbar 3768.5 A measured at 11kV side
Maximum tripping time for 6.3kV outgoing feeders Instataneous
3. Setting Considerations
Protection Scheme- Low-set phase overcurrent (51) protection at 11kV side are used as backup protection for differential (87T) and REF (87REF) protection.
To maintain selectivity against downstream protection relays, a time delay of 0.5s on top of the downstream (6.3kV outgoing feeders) protection relays maximum operating time shall be introduced.
- High-set overcurrent (50) at 11kV side is applied to protect the transformer during short circuit condition. Time delay shall be introduced to maintain selectivity from the fault which occur at the other parts of the system.
- Sensitive earth fault/SEF (50S) of this relay will be applied at 6.3kV to detect earth fault condition at 6.3kV system. To maintain selectivity against earth fault protection relay at 6.3kV outgoing feeders, a time delay of 0.5s on top of the
outgoing feeders tripping time is introduced. As the fault current is considerably small, a longer operating time is somehow still acceptable as long as not exceeding the rated time of NGR (10s).
- To avoid unwanted operation of the overcurrent and earth fault protection due to inrush current during transformer startup, the inrush detection element INRPHAR is activated to give a blocking signal to the overcurrent & earth fault element when inrush current is detected.
4. Setting of analogue input
Analog input settings, phase currentsSecondary current = 1 A
Primary current = 750 A
Amplitude corr. A = 1
Amplitude corr. B = 1
Amplitude corr. C = 1
Nominal current = 315 A {In}
Rated secondary value = 3 mV/Hz
Reverse polarity = 0 {False}
Analog input settings, residual currents
Secondary current = 1 A
Primary current = 1250 A
Amplitude corr. = 1
Reverse polarity = 0 {False}
5. General System Setting
Rated frequency = 50 Hz
Phase rotation = ABC
Blocking mode = Freeze timer
Bay Name = UAT2
IDMT saturation point = 50
6. Setting of Three Phase Overcurrent Function (PHxPTOC) on 11 kV side
6.1. PHIPTOC (Instantaneous) Non group settings:
Activation of the PHIPTOC function
Operation = 1 { 1=On }
Number of phases required for operate activation
Num of start phase = 1 { 1=1-out-of-3 }
Reset delay time
Reset delay time = 20 ms { instantaneous }
6.2. PHIPTOC (Instantaneous) Group settings:
Start values is set at 130% of transformer short circuit current to get selectivity with faults at 6.3kV. Start Value PHHPTOC = 130% x 3768.5 A
= 4899.1 A Start Value PHHPTOC = 15.6 x In Operate delay time
Operate delay time = 20 ms { instantaneous }
Note : All other setting parameters are not relevant. Default values can be used.
6.3. PHHPTOC (high-set) Non group settings:
Activation of the PHHPTOC function
Operation = 5 { 5=Off }
6.4. Setting of parameters for PHLPTOC (low-set) Non-group Setting
Activation of the PHLPTOC function
Operation = 1 { 1=On }
Number of phases required for activation
Num of start phase = 1 out of 3 Minimum operate time for IDMT curve
Min. oper. Time = 40 ms
Reset delay time
Reset delay time = 20 ms
Curve parameter for programmable curve
Curve parameter A, B, C, D, E = default {NA}
6.5. PHLPTOC (low-set) Group settings:
Start values is set at 110% of transformer rated current.
Start Value PHLPTOC = 120% x 315 A
= 378 A
Start Value PHLPTOC = 1.2 x In Multiplier for scalng the start value
Start value Mult = 1 Time multiplier setting (TMS)
Time multiplier = 1 {See note below}
Operate delay time
Time delay PHLPTOC = 400 ms {Not relevant for inverse type}
Operating curve type
Curve PHLPTOC = IEC Extremely Inverse Selection of reset curve type
Type of reset curve = 1 {Immediate}
Note : Time delayed PHLPTOC shall be set to operate in about 0.8 s at short circuit current to give safe margin to the transformer main protection and other
unit protection at the other part of the system. Short circuit current = 3768.5 A
= 12 x In
with start value = 1.2 x In
and set time multiplier = 1
for extremely inverse curve, the operating time t is : t = 0.814 s --> OK
7. Setting of Earth Fault Protection Function (EFxPTOC) on 6.3 kV side
7.1. EFIPTOC (Instantaneous) Non group settings:
Activation of the EFIPTOC function
Operation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.2. EFHPTOC (high-set) Non group settings:
Activation of the EFHPTOC function
Operation = 5 { 5=Off }
Note : All other setting parameters are not relevant. Default values can be used.
7.3. EFLPTOC (low-set) Non group settings:
Activation of the EFLPTOC function
Operation = 1 { 1=On }
Minimum operate time for IDMT curve
Min. oper. Time = 40 ms
Reset delay time
Reset delay time = 20 ms
Curve parameter for programmable curve
Curve parameter A, B, C, D, E = default {NA}
Selection for used Io signal
Io signal Sel = 1 {Measured Io)
7.3. EFLPTOC (low-set) Group settings:
Start value for earth fault is set at 50% of maximum earth fault current.
Start Value EFLPTOC = 50% x 11 A {See note below}
= 6 A
Start Value EFLPTOC = 0.02 x In Multiplier for scalng the start value
Start value Mult = 1 Time multiplier setting (TMS)
Time multiplier = 0.1 {See note below}
Operate delay time
Time delay EFLPTOC = 0.9 s
Operating curve type
Curve EFHPTOC = Definite time Selection of reset curve type
Type of reset curve = 1 {Immediate}
8. Setting of Inrush Detector INRPHAR
8.1. Inrush Detector INRPHAR Group Setting
Ratio of the 2nd to the 1st harmonic leading to restraintStart value = 0.15 %
Operate delay time
Operate delay time = 20 ms
8.2. Inrush Detector INRPHAR Non Group Setting
Activation of the INRPHAR functionOperation = 1 { 1=On }
Reset delay time
Reset delay time = 20 ms
9. All other protection functions
Operation = 5 { 5=Off }
10. Assignment of Binary Input
Binary Input Terminal -X110_
BI1 : Not used
BI2 : Not used
BI3 : Not used
BI4 : Not used
BI5 : Not used
BI6 : Not used
BI7 : Not used
BI8 : Not used
BI9 : Not used
BI10 : Not used
Binary Input Terminal -X120_ BI1
BI2 BI3
BI4 : Reset lockout
11. Assignment of Binary Output
Binary Output Terminal -X100_
PO1 : Overcurrent Trip
(Operation of PHHPTOC, PHLPTOC) PO2 : SEF Trip
(Operation of EFLPTOC) SO1 : Overcurrent Trip
SO2 : SEF Trip PO3
PO4
Binary Output Terminal -X110_
SO1 : Overcurrent Trip SO2 : SEF Trip SO3
SO4
Equipment : Feeder : 1. Reference Drawing Schematic Diagram : Transformer Bay : 2. General Data Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests 3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
RET670
Protection Relay Test
Unit Aux. Transformer Differential Protection Relay RET670
UAT #2
KPP-00-TPS-W-141 11kV 6.3kV UAT #2
ABB F87T
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1 2 3 4 5 6 7
No. Procedure Injected Values
Secondary
Measured
Values Primary Remarks
Inject current phase T → A103 A A Inject current phase R → A104 A A Inject current phase R → A101 A A Inject current phase S → A102 A A
Inject current Neutral → A107 A A Inject current phase S → A105 A A Inject current phase T → A106 A A
3.3 Deferential Protection Test
(1) Check on HV side Secondary Injection
No. Procedure Items to be verified. Remarks
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate 1 Make sure that REF and OC / EF
function are set to off.
2 Connect the test set for injection of 3 phase current to the current terminals of RET670 which are connected to the CT's on HV side of transformer
c) Alarm contact operation c) Alarm contact :
Operate / Not operate 4 Increase the current in phase L2 until
the protection operates and check L2 3 Increase the current in phase L1 until
the protection operates and check L1
For stable condition, Trip not operated
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate
Operate / Not operate
For stable condition, Trip not operated
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate Operate / Not operate c) Alarm contact operation c) Alarm contact :
c) Alarm contact operation c) Alarm contact :
Operate / Not operate 5 Increase the current in phase L3 until
the protection operates and check L3
(2) Check on LV side Secondary Injection
No. Procedure Items to be verified.
a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Remarks 1 Connect the test set for injection of 3
phase current to the current terminals of RET670 which are connected to the CT's on LV side of transformer
2 Increase the current in phase L1 until the protection operates and check
L1
a) the operating current (Iop)
Operate / Not operate 3 Increase the current in phase L2 until
the protection operates and check L2
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Operate / Not operate 4 Increase the current in phase L3 until L3
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Operate / Not operate 4 Increase the current in phase L3 until
the protection operates and check L3
3.4 6.3kV Restricted EF Protection Test
(1) Secondary Injection
No.
4. Remarks :
Procedure Items to be verified. Remarks 1 Make sure that Differential protection
and OC/EF function are set to off.
2 Connect the test set for injection of neutral current to the current terminals of RET670 to which the NCT 20kV is connected
3 Increase the current in until the protection operates and check
L1
a) the operating current (Iop) a) Iop : A b) Trip contacts operation b) Trip contact :
Operate / Not operate c) Alarm contact operation c) Alarm contact :
Operate / Not operate
Equipment : Feeder : 1. Reference Drawing Schematic Diagram : Transformer Bay : 2. General Data Manufacture : Designation :
Type : Sereal No. :
3. Commissioning Tests 3.1 Visual Check
a) Physically Good ? :
b) Relay Healthy ? :
c) Mounting and wiring completed ? :
UAT #2
KPP-00-TPS-W-141 11kV 6.3kV UAT
ABB F5051
RET615
Protection Relay Test
Backup OC & EF Protection Relay REF615
c) Mounting and wiring completed ? :
3.2 Verifying the connections and the analog inputs
Apply input signals as needed and verify that signals are measured correctly
1 2 3 4
No. Procedure Injected Values
Secondary
Measured
Values Primary Remarks
Inject current phase R A A
Inject current phase N A A
Inject current phase S A A
Inject current phase T A A
3.3 Testing of the phase overcurrent protection
The test is performed as a secondary test, by injecting current to the current energizing inputs with the setting values used during normal operation
No. Procedure Items to be verified. Remarks
1 Inject the current (Ii) in phase L1
Ii = 2.5 * I > * rated current input Start of stage I > : .
I > setting : * In Trip of stage I > : .
t > setting : s
Operation time : s
2 Inject the current (Ii) in phase L2
Ii = 2.5 * I > * rated current input Start of stage I > : .
I > setting : * In Trip of stage I > : .
t > setting : s
Operation time : s
3 Inject the current (Ii) in phase L3
Ii = 2.5 * I > * rated current input Start of stage I > : .
I > setting : * In Trip of stage I > : .
t > setting : s
Operation time : s
4 Inject the current (Ii) in phase L1
Ii = 8 * I >>> * rated current input Start of stage I >>> : .
I >>> setting : * In Trip of stage I >>> : .
t >>> setting : s
Operation time : s
5 Inject the current (Ii) in phase L2 5 Inject the current (Ii) in phase L2
Ii = 8 * I >>> * rated current input Start of stage I >>> : .
I >>> setting : * In Trip of stage I >>> : .
t >>> setting : s
Operation time : s
6 Inject the current (Ii) in phase L3
Ii = 8 * I >>> * rated current input Start of stage I >>> : .
I >>> setting : * In Trip of stage I >>> : . t >>> setting : s Operation time : s
Contractor
3.4 Testing of the earth fault protection
The test is performed as a secondary test, by injecting current to the current energizing inputs with the setting values used during normal operation
No.
4. Remarks :
Remarks 1 Inject the current (Ii) in the earth fault
energizing input :
Ii = 2.5 * I0 > * rated current input Start of stage I > :
.
I0 > setting : * In Trip of stage I > :
.
t0 > setting : s Operation time :
s 2 Inject the current (Ii) in the earth fault
Procedure Items to be verified.
energizing input :
Ii = 2.5 * I0 >> * rated current input Start of stage I >> :
.
I0 >> setting : * In Trip of stage I >> :
.
t0 >> setting : s Operation time :
s