PROJECT : SM LIGHT RESIDENCES
LOCATION : BONI AVE. EDSA MANDALUYONG CITY SUBJECT : PRODUCTIVITY RATE
SCOPE OF WORK : INTERIOR PAINTING OF UNITS FINISH : SEMI-GLOSS (2 COATS)
PROCEDURE
1. SURFACE PREPARATION - Putty Works
- Sanding 2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex 3. FIRST COAT
- Application of Semi-Gloss 4. FINAL COAT
- Application of Semi-Gloss
PAINTING TO MASONRY WALL FLOOR : 17TH FLOOR UNIT NO. : 18 AREA : UNIT 46.9 m2 CR 8.86 m2 55.76 m2
DATE MANPOWER ACTIVITY MANHOUR
6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs 7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs 8-Nov Painter Primer - Application of Flat Latex 3.25 Man-Hrs 8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs 8-Nov Painter 1st Coat - Application of Semigloss 4.75 Man-Hrs 8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs TOTAL 37.75 Man-Hrs PRODUCTIVITY (Man-hr/m2) 0.6770 FLOOR : 17TH FLOOR UNIT NO. : 19 AREA : UNIT 46.9 m2 CR 8.86 m2 55.76 m2
6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs 7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs 8-Nov Painter Primer - Application of Flat Latex 4.25 Man-Hrs 8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs 8-Nov Painter 1st Coat - Application of Semigloss 3.75 Man-Hrs 8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs TOTAL 37.75 Man-Hrs PRODUCTIVITY (Man-hr/m2) 0.6770
PAINTING TO MASONRY WALL FLOOR : 17TH FLOOR UNIT NO. : 37-38 AREA : UNIT 93.8 m2 CR 17.72 m2 111.52 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter Surface Preparation - Putty Works 22 Man-Hrs 8-Nov Painter Surface Preparation - Sanding 8.5 Man-Hrs 8-Nov Painter Primer - Application of Flat Latex 4 Man-Hrs 9-Nov Painter Primer - Application of Flat Latex 3 Man-Hrs 10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 5.5 Man-Hrs 10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs 13-Nov Painter Final Coat - Application of Semigloss 12 Man-Hrs
TOTAL 61 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.5470
PAINTING TO MASONRY WALL FLOOR : 8TH FLOOR UNIT NO. : 21-22 AREA : UNIT 93.8 m2 CR 17.72 m2 111.52 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter Surface Preparation - Putty Works 14 Man-Hrs 8-Nov Painter Surface Preparation - Putty Works 10 Man-Hrs 8-Nov Painter Surface Preparation - Sanding 7.5 Man-Hrs 9-Nov Painter Primer - Application of Flat Latex 6 Man-Hrs 10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 13 Man-Hrs
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs Painter Final Coat - Application of Semigloss 12 Man-Hrs TOTAL 68.5 Man-Hrs PRODUCTIVITY (Man-hr/m2) 0.6142
AVERAGE PRODUCTIVITY (Man-hr/m2) 0.6288
FINISH : FLAT FINISH PROCEDURE
1. SURFACE PREPARATION - Putty Works
- Sanding 2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex 3. FINAL COAT
- Final application of flat latex PAINTING TO CONCRETE CEILING FLOOR : 17TH FLOOR
UNIT NO. : 18 AREA :
UNIT 12.8 m2
12.8 m2
DATE MANPOWER ACTIVITY MANHOUR
6-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs 7-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 2 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 0.75 Man-Hrs 7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs 8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs 8-Nov Painter Final Coat - Application of flat latex 1.25 Man-Hrs TOTAL 11.5 Man-Hrs PRODUCTIVITY (Man-hr/m2) 0.8984 FLOOR : 17TH FLOOR UNIT NO. : 19 AREA : UNIT 12.8 m2 12.8 m2
DATE MANPOWER ACTIVITY MANHOUR
6-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs 7-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs 7-Nov Painter 1 Surface Preparation - Sanding 2 Man-Hrs
7-Nov Painter 1 Primer - Application of Flat Latex 1 Man-Hrs 8-Nov Painter 2 Primer - Application of Flat Latex 0.75 Man-Hrs 8-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs 8-Nov Painter 1 Final Coat - Application of flat latex 1.25 Man-Hrs TOTAL 11.5 Man-Hrs PRODUCTIVITY (Man-hr/m2) 0.8984 FLOOR : 17TH FLOOR UNIT NO. : 37-38 AREA : UNIT 25.6 m2 25.6 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter 1 Surface Preparation - Putty Works 5.5 Man-Hrs 8-Nov Painter 1 Surface Preparation - Sanding 6 Man-Hrs 9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs 9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs 10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs TOTAL 19.5 Man-Hrs PRODUCTIVITY (Man-hr/m2) 0.7617 FLOOR : 8TH FLOOR UNIT NO. : 21-22 AREA : UNIT 25.6 m2 25.6 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter 1 Surface Preparation - Putty Works 9 Man-Hrs 8-Nov Painter 1 Surface Preparation - Sanding 4 Man-Hrs 9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs 9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs 10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs
TOTAL 21 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.8203
210 972.625 105 69.47321 0.330825 5 1 43.69 6 2 7 2 8 3 9 4 10 5 11 6