This method statement describes the methodology and procedure for flushing of chilled water system and to ensure that all concerned persons are familiar with the sequence of activities, utilization of resources, and execution of the works in compliance with applicable Safety and Quality Procedures, and Project Documents and Specification. Scope of Works
This method statement is intended to outline the activities and the methods used in cleaning and flushing of chilled water
system and its chemical treatment. All activities will be
carried out in accordance with the contract details and in full compliance to the project specifications. All work within the rights-of-way of the standards and specifications will be done in compliance with requirements issued by authorities.
Required Tools/Equipment Tool box Tool kit Meters/gauges Power Tools Temporary pump
HVAC Air Conditioning
www.siemens.com/climate-control Climate Control by Siemens - Save up to
60 percent of consumed energy
Chilled Water Flushing Procedure
Preparation: The following preparation checks / works shall be carried out prior to commencement of flushing and cleaning of chilled water system.
Check and ensure the system is hydro-statically pressure tested and verify test certificate. Check the provision of air vents at location as per approved drawings.
Check and ensure sufficient quantities of chemicals are available as per requirement. Place warning signs and warning tape as required.
Arrangements for draining the flushed water to be made before starting the flushing process. Drain should be connected to main drainage line or as directed by authorities.
Flushing & Cleaning Steps
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
of water as per applicable requirements in the contract.
Open the drain valves in the main lines and drain the water completely. Clean the strainers
During the above flushing process the drain valves shall be kept open while the pump is running, until the water appears clean.
Close all the drain valves
Cleaning With Cleaning Chemical
Desired water quality should be achieved before adding the chemical.
Refill the system with clean water and add cleaning chemical in required quantities as per Specialist supplier’s instructions i.e. 1Kg per cubic meter of system volume.
Once the cleaning process is started, samples of solution shall be collected from various parts of the system to ensure the chemical solution has reached all parts of the system.
Run the pump and circulate the water (with chemicals added) for a minimum period of 24 hours as per specialist supplier’s recommendations.
Samples to be taken and tested in 3rd party laboratory. The water quality must be achieved as per the requirements agreed in the contract or as applicable
Specialist contractor shall collect samples and conduct tests until satisfactory results are obtained as required which is a condition when no increase in iron level is observed and a level of iron less than 1ppm is achieved and the water is clear, colourless and odourless.
After the cleaning process is completed as described above the cleaning solution shall be flushed out. Addition of Corrosion & Scale Inhibitors
The entire system is re-filled with fresh and clean water and treated with corrosion and scale inhibiting treatment chemical at the rate of 3Kg per cubic meter of the system volume or as applicable depending upon the chemical concentration. After 24 hours of circulation samples are taken to ensure the concentration levels i.e. 800-100 ppm as NaNo2
Biological Control
Biological control chemical, shall be dosed at the agreed rate per cubic meter using the manual dosing pot. This is a shock dosing which shall be done after every three months.
Inspection
The inspection request shall be raised for consultant to witness the flushing and cleaning process at different stages and results shall be noted on checklists.
Tags: Chemical Treatment of chw piping, chw piping cleaning, Flushing Procedure For Chilled Water System
◀ METHOD STATEMENT FOR CONCRETE SAMPLING AND TESTING
Sample Forms & Checklists For HVAC Installation Testing & Commissioning▶
Search Search
Like Us To Support Us
Electrical Installation
www.siemens.ae/green-buildings Siemens Green Buildings - Save up to 60
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
Methodstatementhq
Like
One person likes Methodstatementhq.
F acebook social plugin
Other Method Statements
Testing & Commissioning Of Fire Suppression System
August 20th, 2013
The scope of method statements covers the planning, preparation, and conduct of fire suppression sys[...]
Welding Method Statement
August 13th, 2013
There are many different welding processes, but the most commonly used in the construction industry [...]
Installation Of Reinforcement Steel Bars For Footing, Strap Beam, Raft, Slab & All Structural Concrete - Steel Fixing
August 13th, 2013
The purpose of this method statement is to lay down the systematic procedures for the various activi[...]
Method Statement For Installation Testing & Commissioning Of BMS Building Management System
August 1st, 2013
Scope of Work This method statement is applicable for Installation, Testing & Commissioning of [...]
Chilled Water Balancing For HVAC System Method Statement
July 31st, 2013
The aim of chilled water balancing is to apply a disciplined procedure of adjustment to water flow r[...]
Method Statement For Air Balancing Of HVAC System FCU AHU Exhaust Fans & Pressurization Unit
July 31st, 2013
Air Balancing Method Statement Air Balancing For Fan Coil Units Check that all automatic contro[...]
Inspection Checklists / Forms For Electrical Works Installation Testing & Commissioning
July 31st, 2013
Below are the links for downloading the sample inspection and testing check sheets and forms which y[...]
Sample Forms & Checklists For HVAC Installation Testing & Commissioning
July 31st, 2013
You can download the sample forms and checklists for different activities which you can then customi[...]
METHOD STATEMENT FOR CONCRETE SAMPLING AND TESTING
July 29th, 2013
This method statement is applicable for collecting samples for concrete before and during concrete p[...]
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
Most Visited Tags
AC Ducting Method Statement blank performablank proformaBMS Testing ProcedureBuilding Management System BMS
Construction Method Statements Drainage Piping Installation Electrical Method Statements
for
GI Box Installation GI Conduit In T he Wallhvac HVAC Duct Work Installation Method Statement HVAC System Procedure installationInstallation of GI Conduits & Accessories
method
Method Of Statement
Method Statement
Method Statement For Drainage Piping method statement for drainage works Method Statement For GI Box & Conduit Installation method statement for Installation Method Statement For PVC Conduit Installation In Concrete Slab Method Statement TemplateMST MST For BMS MST For Conduiting Workof
Piping Installation Procedure pressurepumps PVC uPVC Underground Above Ground Piping Risk Assessment sample check listsample checksheetSample Format Electrical SOPstatement
swms templatetest Testing & CommissioningTesting & Commissioning Method StatementwaterHome
Privacy Policy Disclaimer