• No results found

Cogeneration in distribution system : planning, operation, transients

N/A
N/A
Protected

Academic year: 2020

Share "Cogeneration in distribution system : planning, operation, transients"

Copied!
219
0
0

Loading.... (view fulltext now)

Full text

(1)

Victoria University of Technology

Department of Electrical & Electronic Engineering

T 4 ^

2.

COGENERATION IN DISTRIBUTION SYSTEM:

PLANNING, OPERATION AND TRANSIENTS

Mahavir Singh

B.Sc. Honours, B.Sc. (Engg.), M . S .

(2)

The work presented in this thesis was carried out under the

supervision of Associate Professor Dr Akhtar Kalam, B.Sc, B.Sc.

(Engg.), M.S., Ph.D. of the Department of Electrical and

Electronincs Engineering, Victoria University of Technology,

Footscray. His guidance, assistance and encouragement from the

campus office as well as from overseas is highly appreciated. The

project was started at the Royal Melbourne Institute of

Technology under the supervision of Dr. Majid Al-Dabbagh to whom

I thank very much. I had to make a few trips to Sydney in the

initial phase of the project to consult Dr. Don Geddy, Planning

and Development Engineer, at the Electricity Commission of New

South Wales, to use the EMTP software. I thank him for offering

his valuable experience in this field.

To make the project more meaningful to the electrical industry,

I consulted Mr. Bob Coulter, Distribution Engineer at the State

Electricity Commission of Victoria, very often. His advice and

assistance have made this project valuable to electrical

industry. I thank him for all the time spent for this project. I

also thank Mrs Ann Pleasant, Senior Lecturer, who assisted me

during the period of Dr. Kalam's absence.

The technical staff of the University have been helpful whenever

problems with the functioning of the computer and software came

up. Mr Neil Larchin, Mr Zoltan Varga and Mr Foster Hayward were

(3)

of Protel and Word Perfect softwares. I acknowledge their

(4)

LIST OF CONTENTS page SUMMARY CHAPTER 1 1.1 1.2 INTRODUCTION Literature Survey Aims of the Thesis

1 4 4 30 CHAPTER 2.0 2 2 2 2 2 2 .1 2 ,3 .4 .5 .6 2.7 2.8 CHAPTER 3 3.0 3.1 3.2 3.3 CHAPTER 4 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8

MATHEMATICAL MODELLING 33

Introduction 33 The solution of transient phenomena 33

Single phase network 34 Branch equations 35 Nodal equations 41 Practical computation 43

Extension to multi-phase network 44 2.6.1 Lumped parameters with mutual couplings 44

Switches 47 Positive and zero sequence parameters of

single-circuit three-phase lines 49 CIRCUIT PARAMETERS 52

Introduction 52 Line impedance and formation of Pi-models 53

Computation procedure 54 3.2.1 Computation of line parameters 54

Format for entering the line parameters 61 ABNORMAL CONDITIONS: GRAPHICAL OUTPUTS 64

Introduction 64 Abnormalities at various points when ground

fault occurs at SYSTA 64 Abnormalities at various points when 2-phase

to ground fault occurs at P191 67 Abnormalities at various points when two phases

form short circuit on the generator's terminals and simultaneously open circuit on the load

side 69 Abnormalities at various points when a broken

conductor fault occurs at P191: induction

generator side of break contacting ground 70 Abnormalities at various points when a broken

conductor fault occurs at P191: system side of

break contacting ground 71 Abnormalities at different points of a feeder

when the generator is disconncted at the

terminal by an ideal three phase device 73 Abnormalities at different points of the feeder

when the generator is switched on to it by an

ideal three phase device 76 Abnormalities at different points of the feeder

(5)

supply system 78

CHAPTER 5

-5.0 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 5.10 5.11 5.12 5.13 5.14

PLANNING AND OPERATION OF DISTRIBUTION CIRCUITS

WITH DISPERSED STORAGE GENERATION 80

Introduction 80 Delivery system characteristics 80

5.1.1 Reserve capacity 80 5.1.2 Distribution reliability 81

5.1.3 Distribution losses 82 5.1.4 Radial operation 82 5.1.5 Thermal and voltage limitations 82

Distribution planning characteristics 83

5.2.1 Planning for peak load 83 5.2.2 Planning objectives 83 5.2.3 Planning criteria 84 5.2.4 Voltage and current criteria 85

Planning for normal and emergency conditions 86

5.3.1 Use of judgement and experience 86

5.3.2 Adoption of new technology 87

5.3.3 Planning horizon 87 Characteristics common to storage & generation 88

5.4.1 Impact on generation 88 5.4.2 Economy of scale capital cost 89

5.4.3 Operation and maintenance 89

Communications and Control 89

Interface 90 Reliability 90 Planning and operation with DSG 90

5.8.1 Supply-side device 90 5.8.2 Customer-side device 93

Interconnection 94 Power quality 95

5.10.1 Power factor correction 96 5.10.2 Voltage regulation 9 8

5.10.3 Harmonic distortion 101

5.10.4 Earthing 103 Protection of cogenerator's plant 106

Supply network interconnection circuits 107 5.12.1 Interconnection circuit protection

requirements 107 5.12.2 Autoreclose 110 5.12.3 Islanding operation 110

5.12.4 Supply network protection requirements

to allow for private generation 112

5.12.5 Customer plant protection 112

Safety 112 Metering 115 CHAPTER - 6 CONCLUSIONS AND FUTURE WORK

6.0 Introduction 6.1 Conclusions 6 .2 Future work

(6)
(7)

Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig.

2-1 2-2 2-3 2-4 2-5 2-6

2-7 2-8 3-1 4-1 4-1A 4-2 4-3 4-4

4-5

4-6

4-7

4-8

LIST OF FIGURES

Single-phase network 34

Equivalent circuit for lossless lines 37

Trapezoidal rule for integration 39 Equivalent circuit for inductance 39 Equivalent circuit for capacitance 41

Solving linear equations with changing right

side 43 Coupled R-L branches 45

Triangularization in two steps 48 Distribution circuit of SECV 52

Ground fault at SYSTA 64 Current flow during fault at SYSTA 66

Double line-to-ground fault 67 Phase to phase short circuit 69

Broken conductor at P191; induction generator

side of break grounded 70 Broken conductor at P191; system side of break

grounded 71 Generator disconnected at terminals of ideal

3-phase three phase switching device 73 Generator energisation: terminals of ideal

3-phase switching device closed 76

(8)

List of Principal Symbols

Instantaneous voltage at time t 33

Instantaneous current at time t 33 Very small interval of time 33

Instantaneous current entering node 1 34 Instantaneous current flowing from node 1

to node 2 34 Instantaneous current flowing from node 1

to node 3 35 Instantaneous current flowing from node 1

to node 4 35 Instantaneous current flowing from node 1

to node 5 35 Current entering node 1 at time t 35

Current between nodes 1 and 2 at time t 35 Current between nodes 1 and 3 at time t 35 Current between nodes 1 and 4 at time t 35

Current between nodes 1 and 5 at time t 35

Instantaneous voltage at distance x and time t 35

Inductace per unit length 35 Capacitance per unit length 35

Distance on the line from some arbitrary

chosen point 35 Propagation velocity 36

Time taken by a wave to travel from one

end of line to the other 37 Impedance of a line from one node to ground 3 8

Nodal admittance matrix 41 Column vector of n node voltages at time t 41

Column vector of n injected node currents at

time t 41 Constant column vector 41

Transformation matrix 49

Subscripts

Phases A, B and C

Self and mutual impedances

Zero, alpha and beta components

Zero value component of symmetrical components Positive value component of symmetrical

components

(9)

List Of Abbreviations

DSG PURPA NEAC FERC QF NGPA FUA CAA NAAQS PDS NSPS EPA LAER NEPA OSHA NECPA NPDES

IOU ITC COP AGC ATP DSSG DCSG PCC EPRI APPA

Dispersed storage and generation 5 Public Utility Regulatory Act 6 National Energy Advisory Committee 9

Federal Energy Regulatory Commission 10 Qualifying (cogeneration) facility 10

Natural Gas Policy Act 15

Fuel Use Act 15 Clean Air Act 17 National Ambient Air Quality Air Standards 17

Prevention Of Significant Deterioration 17

New Source Performance Standards 17 Environmental Protection Agency 18 Lowest Achievable Emission Rate 18 National Environment Policy Act 19 Occupational Service and Health Administration 19

National Energy Conservation Policy Act 19 National Pollution Discharge Elimination System 19

Investor-owned Utility 23 Investments Tax Credits 24 Current Operational Problems 27

Automatic Generation Control 28 Alternative Transient Program 31 Dispersed Supply-Side Storage and Generation 90

Dispersed Customer Side Generation 93

Point Of Common coupling 102 Electric Power Research Institute 102

(10)

Summary

Since the oil crisis of 1970's there has been an increasing

awareness of the need for energy efficiency and sufficiency.

Australia is also alert of the energy economy. The National

Advisory Committee recommended in 1983 that the Commonwealth should

urge the state governments to encourage the electricity supply

authorities to "facilitate greater use in the grid of privately

generated electricity" [68]. This law opened an opportunity for the

use of private generators, which had been on standby duties for use

only in emergency. They could become suppliers of electricity

without having to install transmission lines and other components.

Other dispersed sources which produce electric energy from

hydrogenerators, wind turbines, biomass, waste and other

non-conventional sources, could also be business partners of the

utility. These DSGs (dispersed storage and generation) are allowed

to use the transmission facilities built by the utility. The issue

has gained so much momentum that Bates says, "In this respect we

are totally at odds with the Industry Commission, which recommended

the breaking-up of the State Electricity utilities by the wholesale

selling-off of generating and distribution assets to the private

sector" [67].

This thesis relates to a study of abnormal conditions on a

(11)

Commission of Victoria (SECV) with several loads and a capacitor

bank. An induction generator, which plays the role of a dispersed

storage and generation unit, driven by a hydraulic turbine, which

is a common form of renewable energy scheme, is connected to the

distribution feeder through a A/Y transformer. Transients caused by

switching of the induction generator, by single line-to-ground

fault, double line-to-ground fault through contact resistances,

broken conductor touching the ground through a small resistance,

isolating the induction generator to form its own supply domain

(islanding) etc are investigated and interesting conclusions of

practical importance are derived.

The IBM PC version 4 of the ElectroMagneticTransient Program

-Alternative Transient Program (ATP), was used to solve this

problem. The program also gives output results for automatic

plotting in time domain. Accordingly, transient voltages at several

nodes and transient currents at interesting points were plotted

from the output results.

Planning and operational aspects like voltage control, reliability,

harmonics, earthing, and contractual matters between the private

generator and the utility are also considered. Technical aspects of

interconnections between the private generation and the utility has

been considered.

(12)

interrupting duty on circuit breakers, effect on response of

protective relays and automatic control systems are pointed out. It

also considers security to personnel and protection of metering

equipment. The thesis also offers guide for contractual matters

(13)

CHAPTER 1 INTRODUCTION

1.1 Literature Survey

If an induction motor is driven by an outside mechanical source

at speeds above synchronism, the power current component in the

stator reverses while the magnetising component remains in

magnitude and phase position. The machine thus is converted to

a generator, referred to as induction generator, and will deliver

active power when its shaft input has overcome its internal

losses. Induction generators are relatively smaller in sizes than

synchronous alternators; for although they supply active power,

they take reactive current from other synchronous machines. In

other words, irrespective of load conditions, the induction

generator must operate at leading power factor. The driving force

for the generator can be supplied by a low speed water turbine

or by high-speed steam and gas turbines. Induction generators in

combination with switched capacitor banks can be used in

relatively large-scale installations, provided they are tied to

a transmission network, at least partly supplied by synchronous

alternators to maintain frequency.

The West 59th Street power house of the Interborough Rapid

(14)

7500-kW exhaust turbine induction generator sets which operate

from the steam discharged by five 7500-kW 25-cycle

angle-compounded steam-engine alternators. This increased the

thermal efficiency of the plant and doubled its output. A large

number of induction motors were converted to induction generators

during World War II because of the limitations of power usage and

availability of induction motors as compared to synchronous

alternators [69].

Dispersed storage and generation (DSG) is an expression coined

by the Institute of Electrical & Electronic Engineers in an

attempt to clear up the semantic confusion between

interconnection and cogeneration [10]. DSG is also used by some

authors for the abbreviation of Distribution System Generation

[18] . The SECV uses the expression "Private generation" in place

of DSG [64] . They all give the same idea of generating

electricity from sources like wind power, water power, solar

power and bio-gas (obtained from agricultural digester) . DSGs may

be defined as any source of electrical energy (including storage

elements which act as sources at times) connected directly to a

utility distribution system or sub-transmission system.

The class of devices which comprise the DSGs are listed below

[5]':

* Hydroelectric

* Solar Thermal Electric

(15)

* Wind

* Storage Battery

* Hydroelectric Pumped storage

* Cogeneration

Among these cogeneration has become very important and

interesting too.

Since 1973 the oil embargo and the energy crisis generated by

that embargo, there has been much concern expressed over ways to

conserve and use energy more efficiently. One area of specific

investigation is cogeneration. The Public Utility Regulatory

Policy Act (PURPA) defines cogeneration as the production of

electric energy and other useful energy (such as heat), which are

used for industrial, commercial, heating, or cooling purposes

[70] .

Cogeneration is the combined production of two forms of energy,

electrical or mechanical power plus thermal energy, in one

technological process. The electrical power produced by a

cogenerator can be used on site or distributed through the

utility grid, or both. The thermal energy usually is used on site

for industrial process heat or steam, space conditioning, and/or

hot water. But, if the cogeneration system produces more useful

thermal energy than is needed on site, distribution of the excess

to nearby facilities can substantially improve the cogenerator's

(16)

The total amount of fuel needed to produce both electricity and

thermal energy in a cogenerator is less than the total fuel

needed to produce the same amount of electric and thermal energy

in separate technologies. It is primarily this greater fuel use

efficiency that has created a resurgence of interest in

cogeneration systems. However, cogeneration also can be

attractive as a means of adding electric generating capacity

rapidly at sites where thermal energy already is produced.

Cogeneration systems recapture otherwise wasted thermal energy,

usually from a heat engine producing electric power, and use it

for applications such as space heating, industrial process needs,

or water heating, or use it as an energy source for another

system component. This "cascading" of energy use is what

distinguishes cogeneration systems from conventional separate

electric and thermal energy system. Thus, conventional energy

systems supply either electricity or thermal energy while a

cogeneration system produces both.

Cogeneration technologies are termed "topping cycles" if the

electric or mechanical power is produced first, and the thermal

energy exhausted from power production is then captured and used.

"Bottoming cycle" cogeneration systems produce high-temperature

thermal energy first and then recover the waste heat for use in

generating electric or mechanical power plus additional, lower

temperature thermal energy.

(17)

Energy". In the late 1950's and early 1960's the "total energy"

concept was promoted by many of the gas companies and some

equipment suppliers [6-9].

Early in this century, at the time when electricity first became

widely used, many large industrial or commercial enterprises

maintained large steam boiler plants for space heating and/or

process heating. It was relatively an easy matter to boost the

boiler steam pressure somewhat beyond the process requirement,

insert a turbine which was connected to an electric generator,

and then use the steam for its original requirement after the

added energy was extracted to generate electricity. It was a

practical concept at that time [6] . The gas companies had

tremendous quantities of natural gas and this concept created an

almost constant demand for the natural gas to operate a

combustion turbine or gas-fired engine which produced the

electric energy required by the facility, and as a by-product,

the exhaust could be used to produce process heating or cooling.

The weak point in the total energy installation was that, for

economic reasons, the electrical demand curve had to coincide

with the heat energy [19-21].

The electric utilities did not want to lose their revenue. They

argued against the weak aspect of the total energy installations

and challenged the concept as uneconomical because of poor load

balance. The maintenance required for high reliability was very

costly and the supply of natural gas became very tight in 1971.

(18)

Herein, lies the difference between the total energy and

cogeneration. The appeal of the total energy was based on

complete independence from the electric utility and the utilities

fought it. Cogeneration as presently conceived, however, is based

on both parties participating in, and sharing the benefits of,

cogeneration and has received utility endorsement [6].

Between the late 1880's and early 1900's oil-and-gas-fired

cogeneration technologies were increasingly used throughout

Europe and the United States. In 1900, over 59 percent of total

U.S. electric generating capacity was located at industrial sites

[22-27] .

There has been a resurgence of interest in recent years in

cogeneration for industrial sites, commercial buildings, and

rural applications. In Australia, the National Energy Advisory

Committee (NEAC) recommended in 19 83 that the Commonwealth should

advise the state governments to encourage the electricity supply

authorities to permit the private generators to use their grid

[68] . In the U.S.A. cogenerators faced three major obstacles when

seeking interconnected operation with an electric utility. First,

utilities were often reluctant to purchase cogenerated

electricity at a rate that made interconnected cogeneration

economically feasible. Second, some utilities charged very high

rates for providing backup service to cogenerators. Third, a

cogenerator that sold electricity risked being classified as an

electric utility and was expected to be regulated under State and

(19)

cogeneration was not able to compete with electricity generated

in central station power plants.

A number of recent legislative initiatives are intended to

clarify the role of cogeneration within national energy and

environmental policy, and to encourage its use under those

circumstances, where it would save fuel or allow increased

efficiency in electric utilities' use of facilities and

resources. Utilities are required to purchase electricity from,

and provide backup service to cogenerators and at rates that are

just and reasonable, that are in the public interest, and that

do not discriminate against cogenerators. PURPA also allows

Federal Energy Regulatory Commission (FERC) to exempt

cogenerators from state regulation of utility rates and

financial organisation, and from Federal regulations under the

Federal and Public Utility Act [93-95].

"Qualifying cogeneration facility" (QF) is defined as one that

produces electricity and steam or other forms of useful thermal

energy for industrial, commercial, heating, or cooling purposes;

that meets the operating requirements prescribed by the

government. Electric utilities are also required to interconnect

with QF and must offer to operate in parallel with them.

Cogenerators must meet the operating requirements to qualify for

interconnections and other benefits.

An electric utility can participate in the ownership of a

(20)

company. Efficiency and operating standards are also prescribed

in the rules to distinguish bonafide cogenerators from

essentially single purpose facilities. This standard specifies

that at least 5% of a "topping cycle" cogenerator's total energy

output (on an annual basis) must be useful thermal energy. This

"topping cycle" efficiency standard is designed to ensure that

an oil or natural-gas-fired cogenerator will use these fuels more

efficiently than any combination of separately generated

electric and thermal energy using efficient state-of-the-art

technology. "Topping cycle" cogenerators that were installed

prior to 19 80, and those that use fuels other than oil and gas

do not have to meet any efficiency standards in order to qualify

under PURPA [71].

The 2-to-l weighting in favour of electricity production in these

"topping cycle" efficiency standards reflects the view that

systems with high electricity to heat ratios have the highest

energy efficiencies and their development and use should be

encouraged [96]. This weighting will be more equitable to the

various cogeneration technologies than a standard that simply

summed electric and thermal output on an equal basis, because the

latter would have made it relatively easy for steam turbines that

produce little electricity to qualify, but would have penalised

higher electricity-to-steam ratio systems through difficult heat

recovery requirements.

In this context "Avoided Cost" has been defined as the

(21)

capacity or both, which but for the purchase from a cogenerator

or small power producer, the utility would generate itself or

purchase from another source. The rules impose electric utilities

an obligation to purchase all electric energy and capacity made

available from a QF with which the electric utility is directly

or indirectly interconnected, except during system emergencies

or during light load periods. PURPA specifies that purchase power

rates must be just and reasonable to the electric utilities'

consumers and in the public interest, and must not exceed the

avoided cost to the utility of alternative electric energy.

"Capacity costs" are the costs associated with providing the

capability to deliver energy; they consist primarily of the

capital costs of generating and other facilities [72]. The energy

costs as aforementioned are the variable costs associated with

the production of electricity, and include the cost of fuel and

some operating and maintenance expenses. Thus, if by purchasing

electricity, from a qualifying facility, a utility can reduce its

energy costs or can avoid purchasing energy from another utility,

the rate for the purchase from the QF must be based on those

energy costs that the utility can thereby avoid. Similarly, if

the QF offers energy of sufficient reliability and guarantees of

deliverability to permit the purchasing utility to build a

smaller, less expensive plant, avoid the need to construct -a

generating unit, or reduce firm power from the grid, then the

purchase rates must be based on both the avoided capacity and

energy costs [72]. In each case, it is the incremental costs, and

(22)

There is a provision in the rules that a utility that receives

energy or capacity from a QF may, with the consent of the QF,

transmit that energy or capacity to a second utility. However,

if the QF does not consent to transmission to another utility,

the local utility retains the purchase obligation. Similarly, if

the local utility does not agree to transmit the QF's energy or

capacity, it retains the purchase obligation. Because the

transmission can only occur with the consent of the utility to

which the energy or capacity is first delivered, this rule does

not force wheeling of power [72].

The rule on transmission of cogenerated power specifies that any

electric utility to which such energy or capacity is delivered

must purchase that energy or capacity under the same obligations

and at the same rates as if the purchase were made directly from

the QF. These rates should take into account any transmission

losses or gains. If the electricity from the QF actually travels

across the transmitting utility's system, the amount of energy

delivered will be less than that transmitted, due to line losses,

and the purchase rate should reflect these losses [73].

Section 210(a) of PURPA also requires that each electric utility

offer to sell electric energy to a QF. This obligation to sell

power is interpreted as requiring utilities to provide four

classes of service to QF's [46, 58-60]:

(a) "Supplementary Power", which is energy or capacity used

(23)

(b) "Interruptable Power", which is energy or capacity that

is subject to interruption by the utility under

specified conditions, and is normally provided at a

lower rate than non-interruptable service if it

enables the utility to reduce peak loads

(c) "Maintenance Power", which is energy or capacity

supplied during scheduled outages of the QF,

presumably during periods when the utility's other

load is low

(d) "Backup Power", which is the energy or capacity supplied

during unscheduled outages

A utility may avoid providing any of these four classes of

service only if it convinces the Public Service Commission that

compliance would impair its ability to render adequate service

or would place an undue burden on the electric utility [74].

Interconnection costs must be assessed on a

non-discriminatory-basis with respect to non-cogenerating customers with similar

load characteristics, and may not duplicate any costs including

the avoided costs [75]. Standard or class charges for

interconnection may be included in purchase power tariffs for QFs

with a design capacity of 100 kW or less, and Public Service

Commissions may also determine interconnection costs for larger

facilities on either a class or individual basis.

Cogenerators' fuel choice may be influenced by the Fuel Use Act

(24)

pricing rules of Natural Gas Policy Act of 1978 (NGPA), as well

as by the environmental requirements and tax incentives.

A cogenerator may be subject to the FUA prohibitions if it has

a fuel heat input rate 100 of million Btu per hour or greater and

if it comes within the statutory definition of either a power

plant or a major fuel-burning installation. Under FUA, a power

plant includes "any stationary electric generating unit",

consisting of a boiler, a gas turbine, or a combined-cycle unit

that produces electric power for purposes of sale or exchange",

but does not include cogeneration facilities if less than half

of the annual electric output is sold or exchanged for resale.

A major fuel-burning installation is defined as "a stationary

unit consisting of a boiler, gas turbine unit, combined cycle

unit or internal combustion engine". However, the prohibition

against the use of oil and gas in new major fuel-burning

installations applies only to boilers.

FUA allows a permanent exemption for cogenerators for if the

"economic and other benefits of cogeneration are unobtainable

unless petroleum or other gas, or both, are used in such

facilities". The Department of Energy interprets the phrase

"economic and other benefits" to mean that the oil or gas to be

consumed by the cogenerator will be less than that which would

otherwise be consumed by the conventional separate electric and

thermal energy systems. Alternatively, if the cogenerator can

show that the exemption would be in the public interest (e.g.,

(25)

maintain employment in an urban area), the Department of Energy

will not require a demonstration of oil/gas savings [73]. The

regulation to implement the cogeneration exemption are subject

to change; therefore, it is uncertain how difficult it could be

to meet the exemption requirements, and thus how FUA will affect

the market penetration [75] .

Although the permanent exemption for cogeneration is likely to

be the preferred route for potential cogenerators subject to the

FUA prohibitions, several other exemptions may be applicable in

certain circumstances. First, a permanent exemption is available

to petitioners who propose to use a mixture of natural gas or

petroleum and alternate fuel. Under this mixtures exemption, the

amount of oil or gas to be used cannot exceed the minimum

percentage of the total annual Btu heat input of the primary

energy source needed to maintain operational reliability of the

unit consistent with maintaining a reasonable level of fuel

efficiency. Second, a temporary exemption is available to

petitioners who plan to use a synthetic fuel (derived from coal

or another fuel) by the end of the exemption period. Third, a

temporary public interest exemption may be obtained when the

petitioner is unable to comply with FUA immediately (but will be

able to comply by the end of the exemption) . One of the cases

where this public interest exemption may be granted is for the

use of oil or gas in an existing facility during the ongoing

construction of an alternate fuel-fired unit [63-66, 76].

(26)

its incremental pricing provisions to qualify cogeneration

facilities under PURPA. Thus, the potential lower gas prices

should not affect the relative competitiveness of gas-fired

cogeneration significantly. Moreover, plants burning intrastate

gas may not realise any savings because the fuel price is often

at the same level as the incremental price. In addition, the

deregulation could largely remove incremental pricing. These

uncertainties mean NGPA probably will not be a major factor in

cogeneration investment decisions [77] .

Cogeneration can have significant impacts on air quality,

especially in urban areas. Depending on cogenerator's size and

location, it may be subject to one or more of the Clean Air Act

(CAA) provisions, including New Source Performance Standards

(NSPS) and programs for meeting and maintaining the National

Ambient Air Quality Standards (NAAQS) in non-attainment and

Prevention of Significant Deterioration (PSD) areas.

At present, NSPS exist for two types of sources that might be

used for cogeneration, and have been proposed for a third. NSPS

have been implemented for electric utility steam units of greater

than 250-MMBtu/hr heat input. However, cogeneration facilities

in this category are exempt from NSPS if they sell annually less

than either 25 MW or one-third of their potential capacity. The

other promulgated NSPS is for gas turbines of greater than 10

MMBtu/hr heat input at peak-loads. NSPS have been proposed for

nitrogen oxide emissions from both gasoline and diesel stationary

(27)

greater than 560 cubic inch displacement per cylinder. Finally,

the Environmental Protection Agency (EPA) is considering NSPS

for small fossil fuel boilers. The EPA is reportedly considering

lower limits in the range of 50 to 100 MMBtu/hr heat input.

PSD would apply to fossil fuel boilers of greater than 250

MMBtu/hr heat input that emit more than 100 tons per year (tpy)

of any pollutant, and also to any stationary source that emits

more than 250 tpy of any pollutant (assuming that controls are

in place) . A PSD permit is only issued following a review of

project impacts on air quality based on modelling data and up to

one year of monitoring. These modelling and monitoring

requirements can be expensive. For instance, one estimate

suggests that the requisite modelling and other PSD requirements

add from $35,000 to $80,000 to the installation costs of a 3 MW

diesel cogenerator in New York City [78].

The application of the non-attainment area requirements to

cogenerators also depends on system size; here the trigger is the

capability of emitting 100 tpy of a pollutant. Sources with

higher emissions must meet the Lowest Achievable Emission Rate

(LAER), secure emission offsets, and demonstrate company wise

compliance with the CAA. Smaller sources must use reasonably

available control technology and are subject to the general

requirement for "reasonable further progress" toward the NAAQS

in non-attainment regions.

(28)

for cogenerators under the CAA, facility with any cooling water

discharges may also need National Pollution Discharge Elimination

System (NPDES) permits. The NPDES permit generally specifies the

applicable technological controls or effluent limitations

required to achieve the water quality standards for the receiving

waters. These permits are only likely to be required for large

industrial cogenerators [27].

Because the only major federal permit or authorisation

requirements for cogenerator are those under the Clean Air and

Water Acts, they are not likely to be subject to the National

Environment Policy Act (NEPA) process or to the other

environmental requirements applicable to station power plants.

However, operating cogeneration facilities can come under the

purview of Occupation Service and Health Administration (OSHA)

[27] .

General consideration related to financing and ownership of

cogeneration technologies include the ownership and purchase and

sale terms of PURPA, the utility financing provisions of the

National Energy Conservation Policy Act (NECPA) of 1978, tax

incentives of the National Energy Act, the Windfall Profits Tax

Act, and the Economic Recovery Tax Act, aspects of project

financing and lease relationships, and capital recovery factors.

The most important sections of the Energy Security Act for the

purposes of this assessment are in title IV which establishes

(29)

wind, ocean, organic wastes, and hydropower; only those

provisions related to the use of organic wastes as fuel are

applicable to cogenerators. It also sets up a Solar Energy and

Energy Conservation Bank in the Department of Housing and Urban

Development to make payments to financial institutions in order

to reduce either the principal or interest obligations of owners

or tenants loans for energy conserving improvements to

residential, multi-family, agricultural, and commercial

buildings. For commercial buildings, the eligible improvements

specifically include cogeneration equipment. Direct grants to

owners and tenants of residential or multi-family buildings also

were authorised but were limited to lower income people.

The Energy Security Act also amended NECPA to permit utilities

to supply, install and finance conservation improvements or

alternate energy systems (including cogenerators) as long as

independent contractors and local financial institutions are used

and no unfair competitive practices are undertaken by the

utility. Utilities are eligible to qualify as lenders and receive

subsidies to pass on to customers. Local governments and certain

non-profit organisations are eligible borrowers.

In addition to the regular investment tax credit of 10 percent

on most capital investments, several energy incentives have been

passed. Also, a number of "energy properties" are defined and set

aside for special treatment under the investment tax credit.

Property is not eligible for these special incentives to the

(30)

industrial development bonds) , or is used by a tax-exempt

organisation or governmental unit other than a cooperative.

Public utility property (that for which the rate of return is

fixed by regulation) is excluded from these energy incentives

even if it utilises solar, wind, biomass, or other alternative

sources of energy such as synthetic liquid or gaseous fuels

derived from coal.

The methods of project finance are particularly appropriate to

the financing of distributed electricity generation. Project

financing looks to the cash flow associated with the project as

a source of funds with which to repay the loan, and to assets of

the project as collateral. For successful project financing, a

project should be structured with as little resource as possible

to the sponsor, yet with sufficient credit support (through

guarantees or undertakings of the sponsor or third party) to

satisfy lenders. In addition, a market for the energy output

(electrical or thermal) must be assured (preferably through

contractual agreements), the property financed must be valuable

as collateral, the project must be insured, and all Government

approvals must be available [79-80]. With the adoption of PURPA,

a source of revenues (rates of power purchases) has become

available for small-scale energy project finance.

The capital recovery factor, as used hereafter, is the cost per

kilowatt hour which the owner of a cogenerator must receive to

recover its capital in a given period of time. Table 1 compares

(31)

reflect different income tax structures [81].

TABLE 1.1

(cents per year per kilowatthour, in 1980 cents)

Period

5 years

10 years

5 years

20 years

Non-Utility

Investor

3.6 cents

1.6 cents

1.1 cents

0.77 cent

High tax

rate

utility

4.2 cents

1.9 cents

1.2 cents

0.91 cents

Low tax

rate

utility

3.0 cents

1.5 cents

0.99 cents

0.74 cents

Non-tax

paying

utility

2.8 cents

1.4 cents

0.93 cents

0.70 cents

One way for an investor to get around high capital recovery

factors is to use long-term bond financing.

Continued federal and state government support of simultaneous

purchase and sale at full avoided costs is viewed by some as the

single most important factor in overcoming industry indecision

to cogeneration [82].

Existing and potential industrial cogeneration participants

include industrial parks, integrated pulp and paper mills, other

process industries (e.g., chemicals, petroleum refining, steel,

food processing, textiles etc.) and heavy oil recovery projects.

(32)

rest heavily on a comparison between the cost of cogenerated

electricity (especially, the fuel cost), and the price the

commercial cogenerator pays for its electricity and heat (on

comparative basis). Because of their smaller size, commercial

firms often do not have financial resources equivalent to those

of industrial firms and will be less interested in large scale

projects unless they can be cooperatively owned [83].

Because almost all electric Investors-Owned Utilities Ownership

(IOUs) are in the business of generating electricity, they are

logical potential owners of dispersed generation facilities. The

small size, shorter lead times, and lower capital requirements

of cogeneration systems may provide short-term advantages to

utilities in planning for uncertain demand growth. However, the

PURPA limitations on ownership discourages utility investment in

cogeneration. Moreover, most large utilities do not see dispersed

generating facilities, including cogeneration, as having the

ability to replace future central generating stations, and the

low-earned utility rates of return in recent years may not be

high enough to encourage investment in technologies with

uncertain electricity output.

Full utility ownership may be very advantageous if a utility

faces revenue losses due to industrial or commercial

cogeneration. Moreover, if potential industrial or commercial

cogenerators are unable to burn coal (e.g., due to space or

environmental limitations), or are unwilling to assume the risk

(33)

with electricity and steam distribution can centralise the burden

of using alternate fuels. However, the full incremental

Investment Tax Credits (ITC) is not available for utility owned

cogenerators nor are PURPA benefits available if an Investor

Owned Utility (IOU) owns more than 50 percent of the cogeneration

facility.

Alternatively, a utility may decide to participate in joint

venture for a cogeneration facility in order to structure the

ownership in such a way that the investment tax credit and other

tax benefits are diverted to the non-utility participants. In

addition, financing can be structured so that any debt related

to the facility will not appear on the utility's balance sheet.

This structuring would be appropriate for utility-financed

industrial cogeneration or biomass projects [27-29].

Industrial parks also are an excellent application in which

municipalities can foster the development of cogeneration.

Tax-exempt industrial development bonds can be issued without

limit under a specific exemption for the acquisition of land for

industrial parks and its upgrading including water, sewage,

drainage, communication, and power facilities prior to use.

Cogeneration facilities (including steam distribution lines)

presumably would fall into this specific exemption. The

requirements encourage joint ventures between the exempt entity

and business, but the funds must be used by the non-exempt entity

in a trade or business and payments secured by an interest in

(34)

prohibit municipalities from entering into corporate

relationships with the private sector, but independent public

authorities usually can be established to get around such

prohibitions [27] .

Rural electric co-operatives are finding it more difficult to

purchase additional electricity from their traditional sources

(IOUs and federal power authorities) and consequently are being

forced to build or participate in new generating capacity. Within

this context, dispersed facilities (including cogeneration) may

be advantageous due to the shorter construction times, greater

planning flexibility, and lower capital costs. In addition,

alternate energy projects are more readily financed at favourable

terms. As with other electric utilities, co-operatives will

prefer projects that provide most of their additional capacity

during peak demand periods and whose electricity output is not

intermittent (e.g., bio-mass, hydroelectric, and industrial

cogeneration projects) [27].

Integration of DSG

For effective operation as part of the utility, a DSG must be

integrated. Integration is defined as follows:

1) a DSG connection to a utility system in which provisions

are made for protection of the DSG as well as the system

2) the operation of the DSG as a managed part of the total

(35)

A single DSG unit of relatively small output, or a number of DSG

units of whose aggregate output is small, may be connected to a

system without being integrated [84] i.e, they may be connected

but not integrated as a managed part of the supply mix.

Integrated operations require interaction among the DSGs and the

power system, including the electric utility's bulk supply

systems.

Operational Problems

Cogeneration has impacted the utility generation due to their

base load mode of operation. This base load usually compounds the

utility's daily unit commitment problems associated with unit

cycling, control reserves, and minimum load. The utility

experiences a significant decrease in operating flexibility. Base

load cogeneration affectively removes constant load of this

utility. The worst case scenario is a cogenerator who sells to

the utility only during the off peak, termed off peak dumping.

To avoid this undesirable situation, four different types of

contracts are advised [31-33]:

Firm capacity contracts

Non-firm energy sales only contract

Wheeling contracts

Combination of the above

The operational problems from cogenerator's point of view are

that the basic philosophy behind design of QF generating

(36)

utilities. Where the utility must design to meet the growing and

periodically swinging electrical loads, the QF's concerns lie

primarily with meeting thermal demands of manufacturing

processes. Design of electrical capabilities then follows, but

does not usually constitute the primary design constraint.

It is often difficult to comply with the expectations of and

rules imposed by utilities. In some cases, this compliance is

realised at significant economic expenses [2,4].

IEEE formed a Working Group on Current Operational Problems

(COPS) with the goal of focusing attention of the industry on

problems faced by those who are involved in actual power. Eight

system operational areas are identified:

operations planning

normal systems operations

emergency system operations

system restoration

interconnections and pooling

dispatcher selection and training

system operations management

control centre design and maintenance

The group surveyed, conducted numerous technical sessions and

published papers [39-45]. The mathematical modelling aspects of

various types of cogeneration facilities along with the linear

program optimisation procedures implemented to arrive at optimum

(37)

The aspects of energy management most impacted by DSG are

associated with real time control. Automatic generation control

(AGO can be influenced by the addition of DSGs within the

control area. The position of a schedulable DSG is dependent upon

considerations of economic dispatch, and will also depend on the

resource of the DSG. AGC is affected in two ways by unschedulable

DSGs. First, the position in the loading order must be

determined, but unlike the case of a schedulable DSG, the

addition of a considerable penetration of uncontrollable power

sources could influence existing generation [5].

If a DSG has independent voltage control capability, it can and

must be operated cooperatively with any method of DSG voltage

control on existing power system. Protection of radial feeders

is generally by breakers or reclosures at the distribution

substation, tripped by the action of an overcurrent relay.

Protection of laterals and transformers is generally by use of

fuses, including current limiting types [5, 15-17, 57] . Intertie

protection schemes using undervoltage, overvoltage,

underfrequency, overfrequency, voltage-controlled or voltage

compensated, battery/DC undervoltage, reverse power are reported

by the Power System Relaying Committee of IEEE. The committee has

prepared a consumer-utility guide to establish a common

understanding amongst those involved in the intertie design [51,

52-56, 61].

Some changes in the safety practices and protection hardware are

(38)

switches and lock-out disconnect switches at the DSG

installations would reduce the size of feeder sections with DSG

and prevent the re-energisation of a de-energised feeder section

during maintenance. Because of DSG infeed to faults, fuse sizes

may need to be increased and reclosure settings delayed to

prevent damage to DSG devices operating out of-phase with the

utility system following the occurrence of a system disturbance.

The placement of capacitors to correct the power factor must take

into consideration the possibility of DSG islanding and resonant

overvoltage situations [28].

Automated systems and microprocessor-based protection packages

may be a more practical and safer method for controlling the

operation of DSG devices and protecting the distribution system.

DSG in significant concentrations can have beneficial effects at

the distribution feeder level in terms of reduced voltage drop,

losses, and breaker currents [28].

Before 1970 utilities used traditional planning that stabilised

along a number of lines [29, 36]:

* Cost of fuel was constant or declining in real and often in

current dollars;

* Economics of scale dictated even larger power plants;

* Financing needs were well understood, relatively stable, and

(39)

* Heat rate improved regularly as power plant design was

improved;

* The price of electricity declined;

* Load grew at 7% each year;

* Regulatory/industry interactions and dynamics evolved

accordingly.

* Utilities were financially sound, and concern was for minimal

consumer cost.

As uncertainty is the very essence of the problems facing utility

management today, a new approach for planning evolved, known as

the SMARTE (Simulation, Modelling and Regression, and Tradeoff

Evaluation) strategic planning methodology. SMARTE was developed

specifically to address decisions involving conflicting

objectives, uncertainties, as such disparate issues as fuel,

economics, environmental implications, reliability, etc

[47-50,30,35].

Transient studies due to switching, fault conditions and

islanding on a distribution feeder connected to DSG are

negligible so far [11-15, 3] .

1.2 Aims of the thesis

The thesis describes in detail the modelling of a three phase

multi-section distribution feeder, using PI configuration and

mutual couplings between phases, from the line constants. It also

(40)

phase induction generator, several inductive loads, a capacitor

bank and circuit breakers connected to the distribution feeder.

The fourth version of the IBM-PC Electro-Magnetic Transients

Program, known as Alternative Transient Program (ATP4) was used

to study the fault and switching transient analysis of the

distribution feeder. The main objectives are:

(1) To develop mathematical and digital techniques to

simulate distribution feeder of industry like SECV

connected to a DSG like induction generator.

(2) To display graphically the transient voltages and

currents at interesting points on the feeders under

several types of fault and switching conditions.

(3) To create situation for islanding of the induction

generator and display graphically the current

supplied by the generator to the loads.

(4) To study the effect of two induction generators,

connected to the feeder at two points, on fault

transients and the essential need to modify the

capacitor bank.

(5) To investigate the changes needed in the protection

components as a result of the connection of the DSG

(41)

(6) To report the operation and planning aspects of the

power supplied to feeder connected to DSG.

The mathematical theory on which the models are based and the

explanation of the Alternative Transient Program are described

in Chapter 3.

The data used and the mathematical computations are shown in

Chapter 4.

Chapter 5 contains the graphical plots of transient voltages and

currents during switching and fault conditions. It also offers

an explanation to the shape of the plots and draws valuable

conclusions.

Chapter 6 deals with the operational, control and planning

aspects of the distribution feeder connected to the DSG. It

includes voltage control, reliability, harmonics, earthing, and

contractual matters between the private generator and the

utility. Technical aspects of interconnections are also

considered.

Chapter 7 derives the conclusion of the research and also offers

(42)

2.0 Introduction

Transient phenomena plays an important role in power system

networks. This chapter describes a method which was developed

for solving transient phenomena in multi-phase system on a

digital computer [34]. The method is based on step-by-step

integration procedure for lumped parameters and on Bergeron's

idea [98] for lossless lines. Switches with changing positions

are included in the study. The line parameters, which are part

of the input data are for the transient study, are obtained by

calculation. The formatting for computations in ATP4 is given

in Appendix A.

2.1 The solution of transient phenomena

The problem of transient phenomena is to find the voltages u(t)

or current i(t) as a function of time t for a given network.

It is obvious that a discretisation of the problem is necessary

when using digital computers. Instead of a continuous history

in time t, only a sequence of snapshot pictures at discrete

intervals At is obtained. The discretisation interval At is

(43)

approximated by simple differences

2.2 Single-phase network

The method, which will first be described for single-phase

networks, can solve any linear network consisting of branches:

1. resistance R

2. inductance L

3. capacitance C

4. lossless lines (distributed constants L', C, per

unit length).

>

* _ - i

Fig. 2-1. Single-phase network

The configuration of Fig. 2-1 will be used for illustration.

It contains all four types of branches and may be a part of a

larger network. Suppose that the instantaneous voltages and

currents have already been calculated at time intervals At up

(44)

step-width At will be assumed constant. At any time t the sum of the

currents leaving node 1 through the connected branches must be

equal to the injected current i1#

1 1-2 <t> + i » ) J (t) ^ (t) _ J (t) M )

+ 1^3 + i1 - 4 + 1^5 - i1 u ;

Nodal equations will be used. For node 1 it is found by

expressing the individual branch currents in equation (1) as

a function of node voltages.

2.3 Branch equations

(a) Lossless line.

For the lossless lines equation (2) exists

du=L/di

' dx dt (2)

di _r/du ' dx~ dt

with x = distance on the line from some arbitrary chosen

point

u = u(x,t) = instantaneous voltage at distance x and

time t

L' = inductance per unit length

C = capacitance per unit length.

(45)

dPu _L/C,d 2

u

dx2 dt2

(3)

dx2 dt2

The general solution, first given by D'Alembert, is:

i = F(x - vt) + f(x + vt) (4a)

u = ZF(x - vt) - Zf(x + vt) (4b)

with F(x - vt) and f(x + vt) being arbitrary functions of the

variable x - vt and x + vt. F(x - vt) can be interpreted as a

wave travelling at velocity v in the forward direction and

f (x + vt) as a wave travelling in the opposite direction. In

equation (4) new parameters have been introduced, namely

surge impedance = / (L'/C) (5a)

and velocity of wave propagation

v - 1/ V(L'C') (5b)

Equations (4a) and (4b) can be algebraically changed in the

following forms:

u + Zi = 2ZF(x - vt) (6)

u - Zi = -2Zf(x + vt) (7)

u + Zi is constant when x - vt is constant and u - Zi is

constant when x + vt is constant, x - vt and x + vt are called

the characteristics of the differential equations.

Equation (6) may be interpreted in the following way: Let a

(46)

with wave velocity v. Then x - vt and consequently u + Zi

along the line will be constant for the observer. Let the

travel time T be defined as the time it takes a wave to travel

from one end of the line to the other,

r = 1/v = 1//(L'C) ( 8 )

where 1 is the length of the line. Then, on line section 2-1

in Fig. 2-1, the expression u + Zi encountered by the observer

when leaving node 2 at time t -r must be the same when arriving

in node 1, that is,

u2 (t

"T) + Z.i^""^ = Ul (t>

+ Z.{-±^) (9)

From equation (9) the branch equation for i,,_2 is obtained,

±^2it} = (1/Z) . u /0 + const1.2(t-T> (10a)

with a constant term, the value of which is known from the

"past history" at time t - T,

const1.2<t"T) = -[(1/Z). u2(t_T) + izV**0 ] <10b)

Equation (10) is an exact solution for the lossless line in

terminal 1. This was the expression used by Bergeron for his

graphical method [85].

l

2 - l

(t)

- >

U (t )

"V-B

^A-}^

G=l/Z

L

1-2

_Ct)

U

(t)

A= const2.1

(t

"r) ; B= const1.2 (t

"T)

(47)

Fig. 2-2 shows the equivalent circuit for the terminals, which consists of a conductance G = l/z from each node to ground. The nodes are linked only indirectly by means of fictitious

current sources with known values, determined from the past history of the opposite terminal.

(b) Inductance L

For inductance L of branch 1-3 in Fig. 2-1, equation (11) is obtained:

u

i~u3 = L'—jf- (Ha)

from which i ^ at time t is obtained by integration:

ii? =iiVAt,+-|. / (u±-u3)dt (lib)

t-At

Since the voltage drop u, - u3 is only defined at discrete

points, an interpolation between t - At and t is necessary. With linear interpolation equation (lib) becomes

i

i-3(t) - ii-s""*0 +(At/2L){Ul (t

-At> -u3 (t

-At> + U l c t )

- u3 (t

>} (12)

(48)

expected to decrease by a factor of 1/8. The trapezoidal rule

for integrating equation (lib) is identical with replacing the

differential quotient in equation (11a) by a central difference

quotient at midpoint between t-At and t with linear

interpolation for u. Equation (12) gives the branch equation

for i,,_3 :

i ^ 0 = (At/2L) [u/0- u3

(t)

] + const,. (13a)

I J C t ?

** *?%*--**

«£-Mr-W-Mr-Mr-M--Mi-M-M'M--3t-Mr-Mr-M--M-»«-M-34-»tM'-M-««-i

t r a p e z o i d r e p l « c I n s i n t e y r a 1 y ( t ) d t

»***+e+e•»*••»«•*€--»«•*«•»«•**••*••€••*-»€• •*•»«•#«•«•••* *«•#*+€

t - •^N, *

"I* r*u n c a -fc I o n fsv-tymr

TL >

Fig. 2-3. Trapezoidal rule for integration

The constant term is again known from the past history:

(t-At)

u (t-At) ] (13b)

const^1"4 0 = i1.3 (t

-At)+(At/2L) [Ul

An equivalent circuit corresponding to equation (13) is shown

in Fig. 2-4. It is a conductance G = At/2L between nodes 1 and

3 with a parallel fictitious current source of known value.

( t - - ^ t )

G = C _ ^ t ) / 2L

<r

(t)

l

3 - l

(49)

(c) Capacitance C

For the capacitance C of branch 1-4 in Fig. 2-1, the integral

form is:

r - u r =

U l

^ « -

U 4

^ «

+ (

- | ) . / i^dt d4)

ux (t)

-u4 {t)

= u1

( f c

-A f c )-u4 ( f c

-A f c ) + (At/2C) [i^l+il^] (15)

This indicates linear interpolation for i. The truncation error

is analogous to that of the inductance. From equation (15) the

branch equation for i1-4 is obtained:

i^l = (2C/Afc) [u1 (t,

-l^(th+coI2sfc1

(

£At, (16a)

with the constant term :

const¥;Lt) = -(2C/AC) [ui-At)-u4(fc-At)]-iifc4"At) <16b)

An equivalent circuit corresponding to equation (16) is shown

in Fig. 2-5. Its form is identical with that for the

conductance. A conductance G = 2C/At between nodes 1 and 4 has

a parallel fictitious current source of known value.

(d) Resistance

For the resistance R of branch 1-5 in Fig. 2-1 the current is

given by :

i ^ w = (l/R) [u/r) - u5

ct

(50)

(t- - ^ t )

G = 2 C/£± t

4 y . (t

Fig. 2-5. Equivalent circuit for capacitance

2.4 Nodal equations

Inserting equations (10), (13), (16) and (17) into (1) gives the linear equation for node 1:

[1/Z + At/2L + 2C/At +1/R] .u/0 - (At/2L) .u3 (t)

- (2C/At) .u4 (t)

-(1/R) .u5

(t)

= i / " - [const,.^*"0 + const^^'^ + const,./*"*0] (18)

For a general network with n nodes a system of such linear equations can be formed; in matrix notation

Y.U(t) = I(t) - K (19)

where Y

a(t)

j(t)

K

= nodal admittance matrix

= column vector of the n node voltages at time t = column vector of the n injected node currents at

time t

(51)

made up of the "past-history terms" const.

The admittance matrix Y remains constant as long as At remains

unchanged. It is real symmetric because the network is purely

resistive with the equivalent circuits of Figs. 2-2, 2-4 and

2-5. Its formation follows the same rules known for the nodal

admittance matrix in steady state analysis. The building

algorithm can be shown more systematically with the use of

incidence matrices, relating branch quantities to node

quantities and vice versa.

In equation (19) part of the voltages will be given and the

others will be unknown. Let the matrices and vectors be

subdivided accordingly into a subset 'a' for nodes with unknown

voltages and subset 'b' for nodes with known voltages. Then

equation (19) becomes

Yaa Yah

^ba. ^bb\ *

'u^'

ui'\

r r < t ) '

-'•a

r(fc)

b

Ka

K

>

from which the unknown vector Ua

(t)

will be found by solving

Ua(t) _ [Ia(t) . Kg . Yab.Ub(t) }/ Yag (21)

This is simply the solution of a system of linear equations for

each time step with a constant coefficient admittance matrix

Y , provided At is not changed. The right sides must be

calculated for each step with the injected currents in Ia(t),

the voltage sources in Ub

(t)

(52)

2.5 Practical computation

The problem of solving eqn. (21) is analogous to the steady

state load flow solution with the impedance matrix or the

triangularised admittance matrix. Instead of the iteration

steps in the load flow solution time steps has been used.

Equation (21) is best solved by initially triangularising Yaa

once and for all and extending the triangularisation process

to the right sides in each step with back substitution to get

Ua (t)

[Fig. 2-6] .

(2)

/1\

Initially:

(1) t r i a n g u l a r i r a t i o n Ya a

\|/

">v

a a In each step :

1. t r i a n g u l a r i z a t i o n process on right sides

2. hacksuhstitutiun

Fig. 2-6. Solving linear equations with changing right side

Only a few elements in Yaa are non-zero. This sparsity should

be exploited by storing only the non-zero elements of the

triangularised matrix in compressed form. The savings in

computer storage and computing time are impressive and can be

optimised with an ordered elimination scheme.

Should the nodes be connected exclusively via lossless lines,

with lumped parameters R, L, C only from nodes to ground, then

Y becomes a diagonal matrix. As a consequence the equations

(53)

technique automatically leads to this simplification, without

having to restrict the generality of the network.

The construction of the column vector for the right sides in

each is mainly an organisational problem. The given node

currents are entered into Ia

(t>

and the given node voltages into

Ub(t). The values may be read in point by point or calculated

with standardised functions (sine curve, rectangular wave

etc.). There are cases where the excitation may come from

voltages only (i = 0) or from currents only (all nodes belong

to subset 'a' then) or where there is no excitation at all

(e.g. discharge of capacitors). Lighting strikes might best be

represented as current sources. The past history is entered

into Ka.

2.6 Extension to multi-phase network

The method can be used to include multi-phase circuits by

formally replacing scalar quantities with matrix quantities.

This generalisation is straight forward for lumped parameters.

For lossless multi-phase lines the coupled phases quantities

will be transformed into decoupled modal quantities. This

linear transformation is similar to that of symmetrical

components in steady state analysis.

2.6.1 Lumped parameters with mutual couplings

Figure

TABLE 1.1
TABLE 3-2  BUS TO _BUS R (Q)
Fig. 5-4 shows customer zone substation for a typical high
Table 1. DELTAT (cols. 1-8) is the size of the time step of the

References

Related documents

It is common to apply underfrequency load shedding in distribution substations. The operation of the underfrequency relays will trip the feeder circuit breakers disconnecting the

An analysis of the economic contribution of the software industry examined the effect of software activity on the Lebanese economy by measuring it in terms of output and value

Nabi (Sallalahu-alayhe-wasallam) cursed the man who puts on woman’s clothing and the woman who puts on man’s clothing [AD] When wearing new clothes Nabi

Christ before Pilate at the trial of Jesus revealed one of his last claims. Jesus and his word are ultimate truth. The Pontius Pilate and Jesus exchange set the two positions

Mere is that way [masculine] on and off the field. But Mere can’t say that she’s lesbian. In 20xx, her uncle found out that she was lesbian. … She got chased from her home and went

Compensation Regulations at Annual and Supplemental Assessment Stages Students must pass modules totaling at least 50 ECTS credits and have an overall average mark of 40%. If

Findings show that during the period examined in 2011, videos employing a sequential (or, in other words, expository) structure already outnumbered the sum total of those based on

sustainable production of Regional digital goods and services, the development of cultural industries and the inclusion of local content in delivery of information.  Guide