ES050 – Introductory Engineering Design and Innovation Studio
Civil Engineering Design
Prof. Jon Southen
November 18, 2009
Goals and Objectives of this lecture
Provide introduction to engineering design
as practiced in Civil engineering
Provide context regarding the environment
Provide context regarding the environment
in which Civil engineering design takes
place
Provide examples of engineering graphics
Civil Engineering Design
The Civil engineering project Types of project
Principal players
General design process General design process Design considerations
Codes, regulations, guidelines Constructability
Validation techniques Design delivery
Drawings
Civil Engineering Projects
Civil Engineering oldest discipline Civil-Military distinction
Wide variety within Civil Structural Structural Environmental Geotechnical Wind Etc.
Basic design considerations, techniques
C
IVIL
E
NGINEERING
W
ORLD
C
IVIL
E
NGINEERING
W
ORLD
(
REAL
)
Civil Engineering Mechanical Eng. Elect. Eng. Politicians Urban planners Economists Politicians Lawyers Bankers ArchitectsCivil Engineering Design
Project-Based
Physical nature of the product Large, heavy, and expensive Each project is unique
A large part of the components are manufactured elsewhere
A large part of the components are manufactured elsewhere Ultimate use of the product
a means to further production
an addition to or improvement of the infrastructure of the economy a social investment (e.g. hospitals)
an investment for direct enjoyment (e.g. housing) Demand for and price of the product
The Construction Project
A project (construction or otherwise) is
defined by the following characteristics:
A defined goal or objective
A defined goal or objective
Specific tasks not routinely performed
A defined beginning and end
Defined deliverables
Categories Of Construction
Projects
Building Construction Projects
• Office buildings, large apartment buildings, shopping malls, etc.
• Large segment of market, but heavily • Large segment of market, but heavily
dependent on local economy
• Designed by architects with engineering support
• Built by general contractors • Privately funded
• Greater technical and investment
Categories Of Construction
Projects
Heavy Construction Projects
• Infrastructure – roadways, bridges, dams, tunnels, canals
tunnels, canals
• Designed by civil engineers
• Built by heavy construction contractors with engineering background or support
• Typically publicly funded
Categories Of Construction
Projects
Industrial Construction Projects
• Steel mills, petroleum refineries, chemical plants, automobile plants, etc.
automobile plants, etc.
• Defined more by the production activities than by the facility itself
• Privately funded
• Quality and time are most important
• Very technical – few companies, cooperation important throughout the project
Principal Players
1)Owner
2)
Design Professional
3)Constructor
Principal Players
1)
Owner
Also called the client
Pays the bills and receives the benefit
Pays the bills and receives the benefit
Determines scope, schedule and
budget (either in-house or with outside
assistance) – i.e. defines need
Principal Players
2)
Design Professional
Engineers
, architects, consultants
Assists the owner in developing the
Assists the owner in developing the
scope, schedule and budget
Prepares construction documents that
are used to build the project
Responsible for the physical integrity
Principal Players
3)
Constructor
Contractor, general contractor, prime
contractor, builder, construction
contractor, builder, construction
manager
Interprets the contract documents and
physically constructs the project
Linear Project Life Cycle
Project Formulation Phase Planning Process Engineering And Design Process Construction Process Use Management Process Disposal Process User Requirements Project Feasibility and Scope Project Engineering and Design Project Field Engineering Facility Use and Management Facility Demolition or Conversionand Scope and Design Engineering
and Construction Management or Conversion Awareness of Need Project Concept Formulation Project Scope Definition Full Project Description Project Completion and Acceptance for Use Fulfillment of Need
Clicker Question
The principal players in a typical
construction project include all of the
following EXCEPT:
following EXCEPT:
A. The owner
B. The design professional C. The public
Civil Engineering Design
The Civil engineering project
Types of project
Principal players
General design process
General design process
Design considerations
Codes, regulations, guidelines Constructability
Validation techniques
Design delivery
Drawings
Civil Engineering Design
Considerations
Owner requirements basis for problem
definition – refined by feasibility study
phase
phase
Objectives and constraints influenced by
owner requirements as well as outside
factors – codes, regulations, guidelines
Building Codes
Used locally to regulate building construction Intent is to protect public health and safety National Building Code
National Building Code
of Canada 2005
“Model” building code Ontario Building Code
Regulated building code
Building Codes
Set minimum standard of construction
quality
Includes definition of occupancy groups
and construction types, with corresponding
Includes definition of occupancy groups
and construction types, with corresponding
limitations on building size, components,
construction methods, etc.
Other codes pertain to specific building
Canadian Highway Bridge Design
Code
CAN/CSA-S6-06 Canadian Highway
Bridge Design Code
Used in all Provinces to
Used in all Provinces to
design bridges over 3m
span
Design Guidelines and Manuals
Various organizations have developed
guidelines and design manuals to assist engineers in designing components not covered in general building codes.
covered in general building codes.
E.g. Concrete Design Handbook
(Canadian Cement Institute), Canadian Foundation Engineering Manual
(Canadian Geotechnical Society)
Provide specific guidelines for designing
Regulations
Civil engineering designs often directly
related to public activities
Regulations may dictate many aspects of
Regulations may dictate many aspects of
design, especially environmental
E.g. landfill design – Ontario Regulation
O.Reg. 232/98 – Landfill Design –
Groundwater Protection
O.Reg. 232/98 – Landfill Design –
Groundwater Protection
O.Reg. 232/98 – Landfill Design –
Groundwater Protection
O.Reg. 232/98 – Landfill Design –
Groundwater Protection
Alternatively, a site-specific design for
groundwater protection may be used,
provided it can be demonstrated that the
provided it can be demonstrated that the
design meets the Ontario Reasonable Use
Guidelines pertaining to groundwater
Civil Engineering Design
Specific elements of the overall project are
designed with due consideration of applicable codes, guidelines and regulations
Engineering judgment required to assess what is Engineering judgment required to assess what is
applicable and whether the proposed design meets requirements
Engineering science principles not expressed in
codes, etc. must be adapted and applied to specific design constraints
Goal is to ensure project objectives are met
Cost Analysis
Often primary basis for choosing among
several viable design alternatives
Preliminary designs offer basis for
Preliminary designs offer basis for
estimating construction costs – estimating
Value engineering takes cost implications
into consideration throughout the design
iteration process
Constructability
Constructability (how easily the proposed
design can actually be built) is often a key
factor in project cost
Often the involvement of a construction
Often the involvement of a construction
manager is incorporated in the design
phase to ensure constructability is
considered and thus enhance the value
engineering process
Clicker Question
Which of the following does not
significantly influence the objectives and
constraints of a Civil engineering design?
A. Government regulations B. Building codes
C. End user requirements
D. Constructability considerations
E. All of these influence objectives and
Civil Engineering Design
The Civil engineering project
Types of project
Principal players
General design process
General design process
Design considerations
Codes, regulations, guidelines
Constructability
Validation techniques
Design delivery Drawings
Design Delivery
Client (owner) retains designer (engineer)
to prepare bid package for constructor
(contractor)
Bid package (final design) fully describes
Bid package (final design) fully describes
project such that contractor can construct
the design and estimate cost to do so (i.e.
prepare bid for owner)
Final design consists of drawings and
Civil Engineering Drawings
Civil engineers typically use
two-dimensional representations to describe
designs
designs
What must be described and the level of
detail is dependent on the current phase of
the project
Civil Engineering Drawings
Topographic Base Maps
Created based on site investigations and
surveys surveys
Used during feasibility and conceptual
planning stages of project
Shows contours (grade), control points,
Civil Engineering Drawings
Planning-level drawings
Used early in project to describe concepts Limited engineering analysis to support
Limited engineering analysis to support May be simple sketch, or include key
dimensions where cost information necessary
Civil Engineering Drawings
Conceptual-level drawings
Developed to compare costs, evaluate
relative advantages/disadvantages and relative advantages/disadvantages and
identify flaws so a preferred concept can be selected
Drawings more detailed than planning-level,
but not suitable for construction
Civil Engineering Drawings
Final design drawings
Used by contractor to construct design Contain all necessary information (with
specifications) to bid and build project specifications) to bid and build project
Used to support permit applications
Used to prepare accurate estimate of costs More detailed and more drawings typically
Final Design Drawings
Typically a set of drawings is required to fully
characterize the project, e.g.
1. Title Sheet
2. Abbreviations / Legend / General Notes 2. Abbreviations / Legend / General Notes 3. Existing Conditions
4. Subsurface Conditions
5. Group Drawings (Civil, Structural, Mech., etc.)
General Layout Plans Detailed Layout Plans
Sections and Details Sheets
Design Controls
A set of benchmarks, coordinate grids, control
points, baselines, centrelines, etc.
Used to
determine the design alignment and dimensions
avoid interference between different members of the
design team
Civil Engineering Drawings
A number of typical 2-D views are used by Civil
engineers to represent a 3-D design
3-D views (e.g. isometric, oblique) are usually
not used in Civil drawings not used in Civil drawings
Various views are used: Plan View
Section View Elevation View Profile View Detail View
Plan View
Typically most
important view – all others are supplemental Depicts the
Depicts the
design in
context with the existing site
Section View
Also called a cross section, basically a cut
through a structure
Shows the internal relationships among various
components of a structure
Adequate number required to show all internal
Elevation
View
Shows the vertical
relationship of various features
Is an external view of
the side – not a cut
Is an external view of
the side – not a cut like a section view
More common for
concrete and mechanical structures
Profile View
Essentially a long section view along an entire
structure
Useful for highways, tunnels, pipelines, etc. Usually has different horizontal and vertical
Detail View
Show design features and
requirements when
overall plan, section and other views do not have other views do not have proper scale and
resolution to do so
Essentially enlargements
of design features,
Technical Specifications
Used in conjunction with drawings to fully
describe all of the technical requirements necessary to complete a project
Should not overlap information with drawings Should not overlap information with drawings Includes things like material requirements,
testing requirements for quality control,
installation procedures and tolerances, schedule requirements, safety issues and responsibilities etc.
Clicker Question
A drawing consists of a plan and typical cross section
view of a canal project; included are representative
dimensions, material types and thicknesses, freeboard requirements and a rough indication of the existing
ground surface. The drawing described would be ground surface. The drawing described would be described as a:
A. conceptual-level drawing B. final design drawing
C. regulatory-review drawing D. planning-level drawing
Civil Engineering Design
The Civil engineering project Types of project
Principal players
General design process General design process Design considerations
Codes, regulations, guidelines Constructability
Validation techniques Design delivery
Drawings