Project : PROPOSED REPLACEMENT OF DON PABLO LORENZO STREET PIPELINE Location Don Pablo Lorenzo Street, Zamboanga City

Project Description : Installation of 451.00 Linear Meters, 150mmØ PVC Distribution Line & Appurtenances

from PPA to Inter. Don P. Lorenzo St.-Saavedra St. Scope of Work :

Mobilization

Supply & Installation of 150mmØ, 451.00 Linear Meters, PVC Distribution Line

Supply & Installation of 100mmØ, 2 - Units Fire Hydrants

Supply & Transfer of 7 unitsExisting Service Connections Demolition of 474.00 Square Meters, Concrete & Asphalt Pavement Supply & Restoration of 54.00 Cubic Meters, Concrete Pavement Supply/Construction of 7 units Valve Box

Demobilization

Cost of Project : 0.00

Qty. Unit Cost

I. MOBILIZATION: 15,000.00

II. PIPELINES & APPURTENANCES:

A. LAYING OF 150mmØ PVC PIPELINE W/ PARTIAL BACKFILLING:

a. Materials :

150mmØ x 6.00m, PVC Pipe, Class 150, B/S with R.R. 75 pcs. 4,500.00 337,500.00

50mmØ x 60m PE Tubing SDR-11, 7.5 rolls 7,278.00 54,585.00 392,085.00 b. Labor:

2 Pipe fitter 15 days 341.00 5,115.00

20 Laborer 15 days 317.00 4,755.00 9,870.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 Back Hoe 7 days 10,000.00 70,000.00

1 Dump Truck 7 days 9,000.00 63,000.00

1 Payloader w/operator & fuel 7 days 8,000.00 56,000.00

Diesel Fuel 360 liters 49.00 17,640.00

Engine Oil 7 liters 120.00 840.00 207,480.00

609,435.00

B. HYDRO TESTING & DISINFECTION WORKS: a. Materials :

Chlorine Powder 1 kg. 120.00 120.00

Potable Water 27 cu.m. 36.00 972.00 1,092.00

b. Labor:

1 Pipe fitter 3 days 347.00 1,041.00

4 Laborer 3 days 317.00 3,804.00 4,845.00

c. Vehicle/Equipment/Fuel/Oil/Lubricants:

1 Unit - Hydrotesting Machine 1 day 500.00 500.00

1 Unit - Generator Set 1 day 500.00 500.00

Gasoline 6 liters 60.00 360.00

Engine Oil 1 liter 120.00 120.00 1,480.00

7,417.00 C. VALVES & FITTINGS:

a. Materials :

150mmØ C.I. Body Gate Valve, (NRS), F/F 9 pcs. 10,290.00 92,610.00

50mmØ C.I. Body Gate Valve, (NRS), F/F 1 pc. 4,444.00 4,444.00

200mmØ C.I. Sleeve Type Flexible Coupling, (Std.) 1 pc. 3,379.00 3,379.00

150mmØ C.I. Sleeve Type Flexible Coupling, (Std.) 9 pcs. 2,225.00 20,025.00

50mmØ C.I. Sleeve Type Flexible Coupling, (Std.) 7 pcs. 749.00 5,243.00

150mmØ C.I. Sleeve Type Flexible Coupling, (Spl.) (PVC-C.I.) 13 pcs. 3,420.00 44,460.00

50mmØ C.I. Sleeve Type Flexible Coupling, (Spl.) (PVC-C.I.) 1 pc. 800.00 800.00

150mmØ x 150mmØ C.I. Cross Tee, M/M 4 pcs. 6,618.00 26,472.00

200mmØ x 150mmØ C.I. Tee, M/F 1 pc. 4,442.00 4,442.00

150mmØ x 150mmØ C.I. Tee, M/F 7 pcs. 4,960.00 34,720.00

150mmØ x 50mmØ C.I. Tee, M/F 2 pcs. 3,899.00 7,798.00

150mmØ C.I. Adaptor, F/P 1 pc. 2,610.00 2,610.00

50mmØ C.I. Adaptor, F/P 1 pc. 2,835.00 2,835.00

150mmØ Mech. End Cap 1 pc. 1,985.00 1,985.00

200mmØ x 150mmØ PVC Reducer, Class 150, B/S with R.R. 1 pc. 786.50 786.50

150mmØ x 90o Long Sweep PVC Bend, Class 150, B/S with R.R. 1 pc. 2,500.00 2,500.00

150mmØ x 45o PVC Bend, Class 150, B/S with R.R. 17 pcs. 2,300.00 39,100.00

Thrust Block

Portland Cement 9 bags 226.00 2,034.00

Sand 0.50 cu.m. 900.00 450.00

Gravel 1.00 cu.m. 900.00 900.00 297,593.50

b. Labor:

2 Pipe fitter 10 days 341.00 6,820.00

8 Laborer 10 days 317.00 25,360.00 32,180.00

329,773.50

TOTAL DIRECT COST OF PIPELINES & APPURTENANCES 946,625.50

ZAMBOANGA CITY WATER DISTRICT Pilar Street, Zamboanga City

1,829,464.00

Php 1,829,464.00

BILL OF MATERIAL AND COST ESTIMATES Item Description

(2)

III. FIRE HYDRANTS: a. Materials :

150mmØ x 100mmØ C.I. Tee, M/F 1 pcs. 4,280.00 4,280.00

150mmØ C.I. Sleeve Type Flexible Coupling, STD. 1 pc. 2,225.00 2,225.00

100mmØ C.I. Body Gate Valve, F/F (NRS) 1 pcs. 6,570.00 6,570.00

150mmØ PVC Telescopic Valve Extension w/ Steel Cover 1 unit 1,580.00 1,580.00

213mmØ (O.D.) x 113mmØ (I.D.) x 16mm thk. w/ 4-16mmØ 2 pcs. 470.00 940.00

Bolt Holes

6mm thk. Rubber Gasket 1 kg. 70.00 70.00

16mmØ x 75mm Hex. Head Stainless Bolt w/ Nut and Washer 8 pcs. 60.00 480.00

100mmØ x 900 G.I. Elbow, Sch. 40 1 pcs. 420.00 420.00

100mmØ x 6.00m G.I. Pipe, Sch. 40 1 pc. 4,660.00 4,660.00

25mm Teflon Tape 4 rolls 22.00 88.00

100mmØ Fire Hydrant w/ 63mmØ Hose Connector 1 pc. 6,620.00 6,620.00

16mmØ x 6.00m Deformed Reinforcing Steel Bars 3 pcs. 370.00 1,110.00

12mmØ x 6.00m Deformed Reinforcing Steel Bars 1 pcs. 219.00 219.00

10mmØ x 6.00m Deformed Reinforcing Steel Bars 4 pcs. 122.00 488.00

#16 G.I. Tie-wire 1 kgs. 65.00 65.00

Portland Cement 4 bags 226.00 904.00

Sand 0.50 cu.m. 900.00 450.00

Gravel 1 cu.m. 900.00 900.00

Concrete Neutralizer 1 qrt. 84.00 84.00

Liquid Tile Primer 1 qrt. 156.00 156.00

Liquid Tile Top Coat White Gloss 0.50 gal. 787.00 393.50

Red Tinting Color 1 pint 100.00 100.00

Thalo Blue Tinting Color 1 pint 100.00 100.00

Raw Sienna 1 pint 100.00 100.00

Lamb Black 1 pint 100.00 100.00

Red Lead Paint 0.50 gal. 440.00 220.00

Paint Blue (QDE) 0.50 gal. 520.00 260.00

Liquid Tile Reducer 1 qrt. 92.00 92.00

2" Paint Brush 2 pcs. 28.00 56.00 12mm thk x 1.20m x 2.40m Ordinary Plywood 1 pc. 550.00 550.00 3pcs. - 2" x 2" x 8' Coco Lumber 8 bd.ft. 17.00 136.00 1" C.W. Nail 0.50 kgs. 65.00 32.50 4" C.W. Nail 0.50 kgs. 65.00 32.50 34,481.50 b. Labor:

1 Pipe fitter 3 days 341.00 1,023.00

4 Laborer 3 days 317.00 3,804.00 4,827.00

TOTAL DIRECT COST OF FIRE HYDRANTS 39,308.50

IV. TRANSFER OF SERVICE CONNECTIONS (INDIVIDUAL TYPE TAPPED ON THE SECONDARY LINE): a. Materials :

50mmØ C.I. Body Gate Valve, (NRS), F/F 2 pcs. 2,990.00 5,980.00

50mmØ x 6.00m G.I. Pipe, Sch. 40 1 pc. 1,940.00 1,940.00 50mmØ x 50mmØ G.I. Tee, Sch.40 29 pcs. 290.00 8,410.00 50mmØ x 90o G.I. Elbow, Sch. 40 4 pcs. 60.00 240.00 12mmØ x 90o G.I. Elbow, Sch. 40 58 pcs. 30.00 1,740.00 50mmØ x 12mm G.I. Bushing, Sch. 40 29 pcs. 80.00 2,320.00 50mmØ G.I. Nipple, Sch. 40 29 pcs. 110.00 3,190.00 12mmØ G.I. Nipple, Sch. 40 29 pcs. 20.00 580.00

12mmØ Brass Ball Valve 29 pcs. 430.00 12,470.00

12mmØ Brass Nipple ( Tail Piece) 58 pcs. 70.00 4,060.00

19mmØ x 12mmØ x 90o G.I. Reducing Elbow, Sch. 40 30 pcs. 30.00 900.00

19mmØ Brass Single Adaptor ( for P.E. tubing) ISO 29 pcs. 180.00 5,220.00

19mmØ x 150.00m P.E. Tubing, SDR 11 3 rolls 4,050.00 12,150.00 59,200.00

b. Labor:

1 Pipe fitter 8 days 341.00 2,728.00

6 Laborer 8 days 317.00 15,216.00 17,944.00

TOTAL DIRECT COST OF (INDIVIDUAL TYPE TAPPED ON THE SECONDARY LINE) 77,144.00

V. STEEL WORKS (CLUSTER PROTECTOR):

a. Materials : (2 Clusters-estimated)

6mm thk x 38mm x 38mm x 6.00m MS Angle Bar 2.5 5 lgths. 852.00 4,260.00 #4 x 50mm x 50mm x 1.22m x 2.44m Steel Matting 1.5 3 shts. 1,600.00 4,800.00 19mmØ x 300mm MS Plain Round Bar 0.05 1 lgths. 568.00 568.00 19mmØ x 400mm Sch. 40 G.I. Pipe 0.07 1 lgths. 423.00 423.00 10mmØ x 20mm SS Triangular Head Bolt w/Nut 4 8 pcs. 64.00 512.00

3mm Ø Welding Rod 0.5 1 kgs. 130.00 130.00

Welding Glass #12 0.1 1 pcs. 15.00 15.00

Acetylene Content 1 2 cyl. 1,400.00 2,800.00

Oxygen Content 2 4 cyl. 700.00 2,800.00

Hacksaw Blade 0.5 1 pcs. 50.00 50.00

Portland Cement 1.5 3 bags 230.00 690.00

Washed Sand 0.075 1 cu.m 900.00 900.00

Gravel (G1) 0.15 1 cu.m 900.00 900.00

10mmØ x 6.00m Rebars 3.2 6 lgths. 161.00 966.00

Ga. 16 Tie Wire 0.5 1 kgs. 70.00 70.00

12mm thk x 1.22m x 2.44m Ord. Plywood 0.4 1 shts. 556.00 556.00 6lngths.-2" x 3" x 8' Coco Lumber 4.8 10 bdft. 18.00 180.00 6lngths.-2" x 2" x 8' Coco Lumber 3.2 6 bdft. 18.00 108.00 4" Common Wire Nail 0.1 0.5 kgs. 55.00 27.50 2½" Common Wire Nail 0.05 0.5 kgs. 55.00 27.50 1½" Common Wire Nail 0.02 0.5 kgs. 55.00 27.50

(3)

Acrylic Paint (ZCWD) 0.25 1 gals. 850.00 850.00

Acrylic Thinner 1.25 3 gals. 426.00 1,278.00

Steel Brush 0.2 1 pcs. 20.00 20.00

# 150 Sand Paper 0.2 1 pcs. 13.00 13.00 23,671.50

b. Labor:

1 Mason 10 days 341.00 3,410.00

4 Laborer 10 days 317.00 12,680.00 16,090.00

TOTAL DIRECT COST OF TRANSFER OF STEEL WORKS (CLUSTER PROTECTOR) 39,761.50

VI. CONCRETE CUTTING & DEMOLITION: a. Labor:

1 Concrete Cutter operator 6 days 341.00 2,046.00

1 Jackhammer Operator 6 days 341.00 2,046.00

3 Contractual Laborers 6 days 317.00 5,706.00 9,798.00

b. Equipment Rental/Fuel/Oil & Lubricants:

2 units - Concrete Cutter 6 days 2,000.00 24,000.00

1 unit - Backhoe w/ mounted Jack hammer w/operator 6 days 10,000.00 60,000.00

Engine Oil 6 liters 120.00 720.00

Gasoline 48 liters 60.00 2,880.00

Diesel Fuel 330 liters 49.00 16,170.00 103,770.00

c. Concrete Cutting/Demolition & Excavation Fee 236.25 sq.m. 40.00 9,450.00 9,450.00

TOTAL COST OF CONCRETE CUTTING & DEMOLITION 123,018.00

VII. VALVE BOXES: 7 a. Materials:

Portland Cement 0.8485 59 bags 230.00 13,570.00

Washed Sand 3 cum. 850.00 2,550.00

Gravel (G1) 6 cum. 850.00 5,100.00

16mmØ x 6.00m Def. Steel Bar 20 140 pcs. 330.00 46,200.00 20mmØ x 6.00m Def. Steel Bar 2.25 16 pcs. 590.00 9,440.00 150mmØ PVC Telescopic Valve Extension w/ Steel Cover 10 units 1,580.00 15,800.00

Add Mix 59 pcs. 65.00 3,835.00

Water Proofing Compound 59 pcs. 65.00 3,835.00

Hacksaw Blade 30 pcs. 60.00 1,800.00

No. 16 G.I. Wire 3 25 pcs. 75.00 1,875.00 104,005.00

b. Labor:

2 Steelmen 12 days 337.00 8,088.00

1 Masons 12 days 337.00 4,044.00

6 Contractual Laborers 12 days 250.00 18,000.00 30,132.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 Unit -Concrete Vibrator 9 days 500.00 4,500.00

1 unit - 1 Bagger Concrete Mixer 9 days 1,500.00 13,500.00

Gasoline 72 liters 60.00 4,320.00 22,320.00

TOTAL DIRECT COST OF VALVE BOXES 156,457.00

VIII. BACKFILLING & CONCRETE RESTORATION: a. Materials:

Portland Cement 473 bags 220.00 104,060.00

Washed Sand 22 cu.m. 900.00 19,800.00

Gravel (G1) 44 cu.m. 900.00 39,600.00

Item 201 75 cu.m. 800.00 59,748.48

Item 200 77 cu.m. 800.00 61,740.10

Sand (Sand Bedding) 26 104 cu.m. 900.00 93,600.00 378,548.58 b. Labor:

2 Masons 15 days 337.00 10,110.00

12 Contractual Laborers 15 days 250.00 45,000.00 55,110.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 Unit - Plate Compactor 8 days 500.00 4,000.00

2 Units - 1 Bagger Concrete Mixer 8 days 1,500.00 24,000.00

Gasoline 64 liters 60.00 3,840.00 31,840.00

TOTAL DIRECT COST OF BACKFILLING & CONCRETE RESTORATION 465,498.58

(4)

I. MOBILIZATION: 15,000.00 II. PIPELINES & APPURTENANCES: 946,625.50

III. FIRE HYDRANTS: 39,308.50

IV. TRANSFER OF SERVICE CONNECTIONS (INDIVIDUAL TYPE TAPPED ON THE SECONDARY LINE): 77,144.00 V. STEEL WORKS (CLUSTER PROTECTOR): 39,761.50

VI. CONCRETE CUTTING & DEMOLITION: 123,018.00

VII. VALVE BOXES: 156,457.00

VIII. BACKFILLING & CONCRETE RESTORATION: 465,498.58

IX. DEMOBILIZATION: 15,000.00

SUB-TOTAL 1,877,813.08

Overhead Expenses, Price & Physical Cont. & Misc. (48,349.08)

TOTAL PROJECT COST Php 1,829,464.00 1,829,464.00

Php0.00

Prepared by : Reviewed & Checked by : Submitted by:

MARLI ACOSTA-DE FIESTA Officer-In-Charge Planning and Design Division

Approved by: Certified as to Availability of Funds: Recommending Project Implementation:

CARLOS L. PEREZ, SR. ROBERTO R. MENDOZA

Officer-In-Charge Assistant General Manager, FAG Assistant General Manager, Operations Engineering Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ General Manager FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO

Job Order Worker, CE Officer-In-Charge

Planning & Development Section Planning and Development Section

ALEJO S. ROJAS, JR. S U M M A R Y

(5)

Project : PROPOSED REPLACEMENT OF DON PABLO LORENZO STREET PIPELINE Location Don Pablo Lorenzo Street, Zamboanga City

Project Description : Installation of 451.00 Linear Meters, 150mmØ PVC Distribution Line & Appurtenances

from PPA to Inter. Don P. Lorenzo St.-Saavedra St. Scope of Work :

Mobilization

Supply & Installation of 150mmØ, 451.00 Linear Meters, PVC Distribution Line

Supply & Installation of 150mmØ, 1 - Unit Fire Hydrant

Supply & Transfer of 7 units Existing Service Connections Demolition of 208.00 Square Meters, Concrete & Asphalt Pavement Supply & Restoration of 54.00 Cubic Meters, Concrete Pavement Supply/Construction of 7 units Valve Box

Demobilization

Cost of Project : 0.00

Qty. Unit Cost

I. MOBILIZATION: 15,000.00

II. PIPELINES & APPURTENANCES:

A. LAYING OF 150mmØ PVC PIPELINE W/ PARTIAL BACKFILLING:

a. Materials :

150mmØ x 6.00m, PVC Pipe, Class 150, B/S with R.R. 75 pcs. 4,500.00 337,500.00

50mmØ x 60m PE Tubing SDR-11, 7.5 rolls 7,278.00 54,585.00

Detectable Underground Warning Tape, 3"W x 1000ft/roll 2 rolls 3,500.00 7,000.00

Polyethelyne Warning Tape, "Attention Water Main", 3"W x 1000ft/roll 2 rolls 3,500.00 7,000.00 406,085.00 b. Labor:

2 Pipe fitter 15 days 341.00 5,115.00

20 Laborer 15 days 317.00 4,755.00 9,870.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 Back Hoe 5 days 10,000.00 50,000.00

1 Dump Truck 5 days 9,000.00 45,000.00

Diesel Fuel 260 liters 49.00 12,740.00

Engine Oil 5 liters 120.00 600.00 108,340.00

524,295.00

B. HYDRO TESTING & DISINFECTION WORKS: a. Materials :

Chlorine Powder 1 kg. 120.00 120.00

Potable Water 27 cu.m. 36.00 972.00 1,092.00

b. Labor:

1 Pipe fitter 3 days 347.00 1,041.00

4 Laborer 3 days 317.00 3,804.00 4,845.00

c. Vehicle/Equipment/Fuel/Oil/Lubricants:

1 Unit - Hydrotesting Machine 1 day 500.00 500.00 500.00 6,437.00 C. VALVES & FITTINGS:

a. Materials :

150mmØ C.I. Body Gate Valve, (NRS), F/F 9 pcs. 10,290.00 92,610.00

50mmØ C.I. Body Gate Valve, (NRS), F/F 1 pc. 4,444.00 4,444.00

200mmØ C.I. Sleeve Type Flexible Coupling, (Std.) 1 pc. 3,379.00 3,379.00

150mmØ C.I. Sleeve Type Flexible Coupling, (Std.) 9 pcs. 2,225.00 20,025.00

50mmØ C.I. Sleeve Type Flexible Coupling, (Std.) 7 pcs. 749.00 5,243.00

150mmØ C.I. Sleeve Type Flexible Coupling, (Spl.) (PVC-C.I.) 13 pcs. 3,420.00 44,460.00

50mmØ C.I. Sleeve Type Flexible Coupling, (Spl.) (PVC-C.I.) 1 pc. 800.00 800.00

150mmØ x 150mmØ C.I. Cross Tee, M/M 4 pcs. 6,618.00 26,472.00

200mmØ x 150mmØ C.I. Tee, M/F 1 pc. 4,442.00 4,442.00

150mmØ x 150mmØ C.I. Tee, M/F 7 pcs. 4,960.00 34,720.00

150mmØ x 50mmØ C.I. Tee, M/F 2 pcs. 3,899.00 7,798.00

150mmØ C.I. Adaptor, F/P 1 pc. 2,610.00 2,610.00

50mmØ C.I. Adaptor, F/P 1 pc. 2,835.00 2,835.00

150mmØ Mech. End Cap 1 pc. 1,985.00 1,985.00

200mmØ x 150mmØ PVC Reducer, Class 150, B/S with R.R. 1 pc. 786.50 786.50

150mmØ x 90o Long Sweep PVC Bend, Class 150, B/S with R.R. 1 pc. 2,500.00 2,500.00

150mmØ x 45o PVC Bend, Class 150, B/S with R.R. 17 pcs. 2,300.00 39,100.00

Thrust Block

Portland Cement 9 bags 220.00 1,980.00

Sand 0.50 cu.m. 800.00 400.00

Gravel 1.00 cu.m. 800.00 800.00 297,389.50

b. Labor:

2 Pipe fitter 10 days 341.00 6,820.00

8 Laborer 10 days 317.00 25,360.00 32,180.00

329,569.50

TOTAL DIRECT COST OF PIPELINES & APPURTENANCES 860,301.50

III. FIRE HYDRANTS: a. Materials :

150mmØ x 150mmØ C.I. Tee, M/F 1 pcs. 4,441.50 4,441.50

150mmØ x 100mmØ C.I. Tee, M/F 2 pcs. 4,280.00 8,560.00

150mmØ C.I. Sleeve Type Flexible Coupling, STD. 3 pc. 2,225.00 6,675.00

150mmØ C.I. Body Gate Valve, F/F (NRS) 1 pcs. 6,570.00 6,570.00

1,829,464.00

1,829,464.00 Php

BILL OF MATERIAL AND COST ESTIMATES Item Description

ZAMBOANGA CITY WATER DISTRICT Pilar Street, Zamboanga City

(6)

150mmØ PVC Telescopic Valve Extension w/ Steel Cover 1 unit 1,580.00 1,580.00

168mmØ (I.D.) x 268mmØ (O.D.) x 16mm thk. w/ 6-19mmØ 2 pcs. 470.00 940.00

Bolt Holes

6mm thk. Rubber Gasket 1 kg. 70.00 70.00

16mmØ x 75mm Hex. Head Stainless Bolt w/ Nut and Washer 8 pcs. 60.00 480.00

150mmØ x 900 G.I. Elbow, Sch. 40 1 pcs. 420.00 420.00

150mmØ x 6.00m G.I. Pipe, Sch. 40 1 pc. 4,660.00 4,660.00

25mm Teflon Tape 4 rolls 22.00 88.00

150mmØ Dry Type Fire Hydrant w/ 63mmØ Hose Connector and 1 unit 98,000.00 98,000.00

1-100mmØ Hose Pumper Outlet (Commercial Type)

16mmØ x 6.00m Deformed Reinforcing Steel Bars 3 pcs. 370.00 1,110.00

12mmØ x 6.00m Deformed Reinforcing Steel Bars 1 pcs. 219.00 219.00

10mmØ x 6.00m Deformed Reinforcing Steel Bars 4 pcs. 122.00 488.00

#16 G.I. Tie-wire 1 kgs. 65.00 65.00

Portland Cement 4 bags 220.00 880.00

Sand 0.50 cu.m. 800.00 400.00

Gravel 1 cu.m. 800.00 800.00

Concrete Neutralizer 1 qrt. 84.00 84.00

Liquid Tile Primer 1 qrt. 156.00 156.00

Liquid Tile Top Coat White Gloss 0.50 gal. 787.00 393.50

Red Tinting Color 1 pint 100.00 100.00

Thalo Blue Tinting Color 1 pint 100.00 100.00

Raw Sienna 1 pint 100.00 100.00

Lamb Black 1 pint 100.00 100.00

Red Lead Paint 0.50 gal. 440.00 220.00

Paint Blue (QDE) 0.50 gal. 520.00 260.00

Liquid Tile Reducer 1 qrt. 92.00 92.00

2" Paint Brush 2 pcs. 28.00 56.00 12mm thk x 1.20m x 2.40m Ordinary Plywood 1 pc. 550.00 550.00 3pcs. - 2" x 2" x 8' Coco Lumber 8 bd.ft. 17.00 136.00 1" C.W. Nail 0.50 kgs. 65.00 32.50 4" C.W. Nail 0.50 kgs. 65.00 32.50 138,859.00 b. Labor:

1 Pipe fitter 3 days 341.00 1,023.00

4 Laborer 3 days 317.00 3,804.00 4,827.00

TOTAL DIRECT COST OF FIRE HYDRANTS 143,686.00

IV. TRANSFER OF SERVICE CONNECTIONS (INDIVIDUAL TYPE TAPPED ON SECONDARY LINE): a. Materials :

50mmØ x 25mmØ C.I. Saddle Clamp w/Stainless Bolts, Nuts & Washers 1 pc. 670.00 670.00

50mmØ x 19mmØ C.I. Saddle Clamp w/Stainless Bolts, Nuts & Washers 11 pcs. 586.00 6,446.00

25mmØ Brass Corporation Cock, ISO 1 pc. 1,000.00 1,000.00

19mmØ Brass Corporation Cock, ISO 11 pcs. 519.00 5,709.00

25mmØ Brass Single Adaptor, Pack Joint/Clamp Type, ISO 1 pc. 386.00 386.00

19mmØ Brass Single Adaptor, Pack Joint/Clamp Type, ISO 11 pcs. 180.00 1,980.00

25mmØ x 12mmØ G.I. Coupling, Sch. 40 1 pc. 30.00 30.00

19mmØ x 12mmØ G.I. Reducer, Sch. 40 11 pcs. 25.00 275.00

25mmØ x 90o G.I. Elbow, Sch. 40 4 pcs. 30.00 120.00

12mmØ x 90o G.I. Elbow, Sch. 40 44 pcs. 25.00 1,100.00

25mmØ x 101mm G.I. Nipple, Sch. 40 (threaded both ends) 2 pcs. 30.00 60.00

12mmØ x 101mm G.I. Nipple, Sch. 40 (threaded both ends) 22 pcs. 25.00 550.00

25mmØ x 151mm G.I. Nipple, Sch. 40 (threaded both ends) 2 pcs. 35.00 70.00

12mmØ x 151mm G.I. Nipple, Sch. 40 (threaded both ends) 22 pcs. 30.00 660.00

25mmØ x 406mm G.I. Nipple, Sch. 40 (threaded both ends) 2 pcs. 55.00 110.00

12mmØ x 406mm G.I. Nipple, Sch. 40 (threaded both ends) 22 pcs. 50.00 1,100.00

25mmØ Brass Ball Valve 1 pc. 600.00 600.00

12mmØ Brass Ball Valve 11 pcs. 430.00 4,730.00

25mmØ Safety Valve (Key Type) 1 pc. 600.00 600.00

12mmØ Safety Valve (Key Type) 11 pcs. 430.00 4,730.00

25mmØ x 63mm Brass Nipple ( Tail Piece) 2 pcs. 80.00 160.00

12mmØ x 63mm Brass Nipple ( Tail Piece) 22 pcs. 70.00 1,540.00

Water Meter Sealing Wire 12 pcs. 14.00 168.00

19mm Teflon Tape 5 18.00 90.00

19mmØ x 150.00m P.E. Tubing, SDR 11 1 roll 4,050.00 4,050.00

Portland Cement 5 bags 220.00 1,100.00

Sand 0.50 cu.m. 800.00 400.00

Gravel 0.50 cu.m. 800.00 400.00 38,164.00

b. Labor:

1 Pipe fitter 8 days 341.00 2,728.00

4 Laborer 8 days 317.00 10,144.00 12,872.00

TOTAL DIRECT COST OF (INDIVIDUAL TYPE TAPPED ON SECONDARY LINE) 51,036.00

V. CONCRETE CUTTING & DEMOLITION: a. Labor:

1 Concrete Cutter operator 6 days 366.00 2,196.00

1 Jackhammer Operator 6 days 366.00 2,196.00

3 Contractual Laborers 6 days 317.00 5,706.00 10,098.00

b. Equipment Rental/Fuel/Oil & Lubricants:

2 units - Concrete Cutter 6 days 1,500.00 18,000.00

1 unit - Backhoe w/ mounted Jack hammer w/operator 6 days 10,000.00 60,000.00

Engine Oil 6 liters 120.00 720.00

Gasoline 48 liters 60.00 2,880.00

Diesel Fuel 240 liters 49.00 11,760.00 93,360.00

(7)

TOTAL COST OF CONCRETE CUTTING & DEMOLITION 112,908.00

VI. VALVE BOXES: 9

a. Materials:

Portland Cement 0.8485 76 bags 220.00 16,720.00

Washed Sand 4 cum. 800.00 3,200.00

Gravel (G1) 8 cum. 800.00 6,400.00

16mmØ x 6.00m Def. Steel Bar 20 180 pcs. 330.00 59,400.00

20mmØ x 6.00m Def. Steel Bar 2.25 20 pcs. 590.00 11,800.00

150mmØ PVC Telescopic Valve Extension w/ Steel Cover 10 units 1,580.00 15,800.00

Add Mix 76 pcs. 65.00 4,940.00

Water Proofing Compound 76 pcs. 65.00 4,940.00

Hacksaw Blade 25 pcs. 60.00 1,500.00

No. 16 G.I. Wire 3 25 pcs. 75.00 1,875.00 126,575.00

b. Labor:

2 Steelmen 13 days 366.00 9,516.00

1 Masons 13 days 366.00 4,758.00

4 Contractual Laborers 13 days 317.00 16,484.00 30,758.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 Unit -Concrete Vibrator 7 days 500.00 3,500.00

1 unit - 1 Bagger Concrete Mixer 7 days 1,500.00 10,500.00

Gasoline 56 liters 60.00 3,360.00 17,360.00

TOTAL DIRECT COST OF VALVE BOXES 174,693.00

VII. BACKFILLING & CONCRETE RESTORATION: a. Materials:

Portland Cement 473 bags 220.00 104,060.00

Washed Sand 22 cu.m. 900.00 19,800.00

Gravel (G1) 44 cu.m. 900.00 39,600.00

Item 201 75 cu.m. 800.00 59,748.48

Item 200 77 cu.m. 800.00 61,740.10

Sand (Sand Bedding) 26 104 cu.m. 800.00 83,200.00 368,148.58

b. Labor:

2 Masons 15 days 366.00 10,980.00

10 Contractual Laborers 15 days 250.00 37,500.00 48,480.00

c. Equipment Rental/Fuel/Oil & Lubricants:

1 Unit - Plate Compactor 8 days 500.00 4,000.00

2 Units - 1 Bagger Concrete Mixer 8 days 1,500.00 24,000.00

Gasoline 40 liters 60.00 2,400.00 30,400.00

TOTAL DIRECT COST OF BACKFILLING & CONCRETE RESTORATION 447,028.58

VIII. DEMOBILIZATION: 15,000.00

I. MOBILIZATION: 15,000.00

II. PIPELINES & APPURTENANCES: 860,301.50

III. FIRE HYDRANTS: 143,686.00

IV. TRANSFER OF SERVICE CONNECTIONS (INDIVIDUAL TYPE TAPPED ON SECONDARY LINE): 51,036.00

V. CONCRETE CUTTING & DEMOLITION: 112,908.00

VI. VALVE BOXES: 174,693.00

VII. BACKFILLING & CONCRETE RESTORATION: 447,028.58

VIII. DEMOBILIZATION: 15,000.00

SUB-TOTAL 1,819,653.08

Overhead Expenses, Price & Physical Cont. & Misc. 9,810.92

TOTAL PROJECT COST Php 1,829,464.00 1,829,464.00

Php0.00

Prepared by : Reviewed & Checked by : Submitted by:

MARLI ACOSTA-DE FIESTA Officer-In-Charge Planning and Design Division

Approved by: Certified as to Availability of Funds: Recommending Project Implementation:

CARLOS L. PEREZ, SR. ROBERTO R. MENDOZA

Officer-In-Charge Assistant General Manager, FAG Assistant General Manager, Operations Engineering Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ General Manager

S U M M A R Y

ALEJO S. ROJAS, JR.

Job Order Worker, CE Officer-In-Charge

Planning & Development Section Planning and Development Section FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO

(8)

Project : PROPOSED REPLACEMENT OF MAYOR CESAR C. CLIMACO AVENUE PIPELINE Location Mayor Cesar C. Climaco Avenue, Zamboanga City

Project Description : 743 Linear Meters Asphalt Overlay

from Inter. of Gov. Alvarez St.-M.D. Jaldon St. to Inter. Don P. Lorenzo St.-Valderoza St. Scope of Work: :

Mobilization

Restoration of 743 Linear Meters Asphalt Overlay Demobilization

Cost of Project :

Qty. Unit Unit Cost Cost

I. MOBILIZATION: 35,000.00

Republic of the Philippines ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

1,485,189.00 Php

BILL OF MATERIALS AND COST ESTIMATES Item Description

(9)

Materials:

Item 302 (Bituminous Tack Coat) 2 drums 10,790.00 21,580.00 21,580.00 Vehicle/Equipment:

1 Asphalt Kettle w/ operator & fuel 0.5 day 1,500.00 750.00

1 Air Compressor 0.5 day 1,500.00 750.00 1,500.00

Manpower :

2 Masons 0.5 day 337.00 168.50

6 Laborers 0.5 day 317.00 158.50 327.00

Item 310 (Bituminous Concrete Surface Course, 5-8% Asphalt) Materials:

Asphalt 56 drums 10,300.00 576,800.00

SFO-Bunker Fuel 3370 liters 49.00 165,130.00

Portland Cement 176 bags 230.00 40,480.00

Composite Aggregate 67 cu.m 1,000.00 67,000.00 849,410.00

Manpower :

2 Masons 5 days 337.00 1,685.00

6 Laborers 5 days 250.00 1,250.00 2,935.00

Vehicle/Equipment:

1 Payloader 5 days 8,800.00 44,000.00

1 Pneumatic Roller 5 days 8,000.00 40,000.00

1 Asphalt Batching Plant 5 days 6,000.00 30,000.00

1 Dump truck 5 days 9,060.00 45,300.00 159,300.00

TOTAL DIRECT COST OF ASPHALT OVERLAY 1,035,052.00

X. MOBILIZATION: 35,000.00

I. MOBILIZATION: 35,000.00

II. ASPHALT OVERLAY : 1,035,052.00

IX. DEMOBILIZATION 35,000.00

SUB-TOTAL 1,105,052.00

OVERHEAD,CONTINGENCIES & MISCELLANEOUS 110,505.00

CONTRACTOR'S PROFIT 110,505.00

TAXES (12%) 159,127.00

TOTAL PROJECT COST Php 1,485,189.00

(10)

Project : PROPOSED REPLACEMENT OF MAYOR JALDON STREET PIPELINE Location Mayor Jaldon Street, Zamboanga City

Project Description : 1,366 Linear Meters Asphalt Overlay

from Inter. of Gov. Alvarez St.-to Inter. Gov. Camins Road Scope of Work :

Mobilization

Restoration of 1,366 Linear Meters Asphalt Overlay Demobilization

Cost of Project :

Qty. Unit Unit Cost Cost

I. MOBILIZATION: 35,000.00

Republic of the Philippines ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

2,690,091.00 Php

BILL OF MATERIALS AND COST ESTIMATES Item Description

(11)

Materials:

Item 302 (Bituminous Tack Coat) 3 drums 10,790.00 32,370.00 32,370.00 Vehicle/Equipment:

1 Asphalt Kettle w/ operator & fuel 0.5 day 1,500.00 750.00

1 Air Compressor 0.5 day 1,500.00 750.00

1 Service Vehicle 0.5 day 1,800.00 900.00 2,400.00

Manpower :

2 Masons 0.5 day 337.00 168.50

6 Laborers 0.5 day 317.00 158.50 327.00

Item 310 (Bituminous Concrete Surface Course, 5-8% Asphalt) Materials:

Asphalt 107 drums 10,300.00 1,102,100.00

SFO-Bunker Fuel 6205 liters 49.00 304,045.00

Portland Cement 323 bags 230.00 74,290.00

Composite Aggregate 124 cu.m 1,000.00 124,000.00 1,604,435.00

Manpower :

2 Masons 9 days 337.00 3,033.00

6 Laborers 9 days 250.00 2,250.00 5,283.00

Vehicle/Equipment:

1 Payloader w/operator 9 days 8,800.00 79,200.00

1 Pneumatic Roller 9 days 8,000.00 72,000.00

1 Asphalt Batching Plant 9 days 6,000.00 54,000.00

1 Dump truck 9 days 9,060.00 81,540.00 286,740.00

TOTAL DIRECT COST OF ASPHALT OVERLAY 1,931,555.00

III. DEMOBILIZATION: 35,000.00

I. MOBILIZATION: 35,000.00

II. ASPHALT OVERLAY : 1,931,555.00

III. DEMOBILIZATION: 35,000.00

SUB-TOTAL 2,001,555.00

PRICE & PHYSICAL CONTINGENCIES 200,156.00 CONTRACTOR'S PROFIT 200,156.00

TAXES (12%) 288,224.00

TOTAL PROJECT COST Php 2,690,091.00

(12)

Project : PROPOSED REPLACEMENT OF SAN JOSE ROAD PIPELINE

Location San Jose Road, Zamboanga City

Project Description : 755 Linear Meters Asphalt Overlay

from Junct. Don Basilio Navarro Street to Junct. Baliwasan Chico Scope of Work :

Mobilization

Restoration of 755 Linear Meters Asphalt Overlay Demobilization

Cost of Project :

Qty. Unit Unit Cost Cost

I. MOBILIZATION: 35,000.00

Republic of the Philippines ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

1,519,584.00 Php

BILL OF MATERIALS AND COST ESTIMATES Item Description

(13)

Materials:

Item 302 (Bituminous Tack Coat) 1 drum 10,790.00 10,790.00 10,790.00 Vehicle/Equipment:

1 Asphalt Kettle w/ operator & fuel 0.5 day 1,500.00 750.00

1 Air Compressor 0.5 day 1,500.00 750.00

1 Service Vehicle 0.5 day 1,800.00 900.00 2,400.00

Manpower :

2 Masons 0.5 day 337.00 168.50

6 Laborers 0.5 day 317.00 158.50 327.00

Item 310 (Bituminous Concrete Surface Course, 5-8% Asphalt) Materials:

Asphalt 59 drums 10,300.00 607,700.00

SFO-Bunker Fuel 3429 liters 49.00 168,021.00

Portland Cement 179 bags 230.00 41,170.00

Composite Aggregate 68 cu.m 1,000.00 68,000.00 884,891.00

Manpower :

2 Masons 5 days 337.00 1,685.00

6 Laborers 5 days 250.00 1,250.00 2,935.00

Vehicle/Equipment:

1 Payloader w/operator 5 days 8,800.00 44,000.00

1 Pneumatic Roller 5 days 8,000.00 40,000.00

1 Asphalt Batching Plant 5 days 6,000.00 30,000.00

1 Dump truck 5 days 9,060.00 45,300.00 159,300.00

TOTAL DIRECT COST OF ASPHALT OVERLAY 1,060,643.00

III. DEMOBILIZATION: 35,000.00

I. MOBILIZATION: 35,000.00

II. ASPHALT OVERLAY: 1,060,643.00

III. DEMOBILIZATION: 35,000.00

SUB-TOTAL 1,130,643.00

PRICE & PHYSICAL CONTINGENCIES 113,064.00 CONTRACTOR'S PROFIT 113,064.00

TAXES (12%) 162,813.00

TOTAL PROJECT COST Php 1,519,584.00

(14)

Project : PROPOSED REPLACEMENT OF DON PABLO LORENZO STREET PIPELINE Location Don Pablo Lorenzo Street, Zamboanga City

Project Description : 451 Linear Meters Asphalt Overlay

from PPA to Inter. Don P. Lorenzo St.-Saavedra St. Scope of Work :

Mobilization

Restoration of 451 Linear Meters Asphalt Overlay Demobilization

Cost of Project :

Qty. Unit Unit Cost Cost

I. MOBILIZATION: 20,000.00

835,131.00 Php

BILL OF MATERIAL AND COST ESTIMATES Item Description

Republic of the Philippines ZAMBOANGA CITY WATER DISTRICT

(15)

Materials:

Item 302 (Bituminous Tack Coat) 1 drum 10,790.00 10,790.00 10,790.00 Vehicle/Equipment:

1 Asphalt Kettle w/ operator & fuel 0.5 day 1,500.00 750.00

1 Air Compressor 0.5 day 1,500.00 750.00

1 Service Vehicle 0.5 day 1,800.00 900.00 2,400.00

Manpower :

2 Masons 0.5 day 337.00 168.50

6 Laborers 0.5 day 317.00 158.50 327.00

Item 310 (Bituminous Concrete Surface Course, 5-8% Asphalt) Materials:

Asphalt 35 drums 10,300.00 360,500.00

SFO-Bunker Fuel 1361 liters 49.00 66,689.00

Portland Cement 71 bags 230.00 16,330.00

Composite Aggregate 27 cu.m 1,000.00 27,000.00 470,519.00

Manpower :

2 Masons 3 days 337.00 1,011.00

6 Laborers 3 days 250.00 750.00 1,761.00

Vehicle/Equipment:

1 Payloader w/operator 3 days 8,800.00 26,400.00

1 Pneumatic Roller 3 days 8,000.00 24,000.00

1 Asphalt Batching Plant 3 days 6,000.00 18,000.00

1 Dump truck 3 days 9,060.00 27,180.00 95,580.00

TOTAL DIRECT COST OF ASPHALT OVERLAY 581,377.00

III. DEMOBILIZATION: 20,000.00

I. MOBILIZATION: 20,000.00

II. ASPHALT OVERLAY: 581,377.00

III. DEMOBILIZATION: 20,000.00

SUB-TOTAL 621,377.00

PRICE & PHYSICAL CONTINGENCIES 62,138.00 CONTRACTOR'S PROFIT 62,138.00

TAXES (12%) 89,478.00

TOTAL PROJECT COST Php 835,131.00

(16)

PROJECT

:

PROPOSED REPLACEMENT OF MAYOR CESAR C. CLIMACO AVENUE PIPELINE

Location

:

Mayor Cesar C. Climaco Avenue, Zamboanga City

Project Cost

:

Project Duration

:

60 WORKING DAYS

I. MOBILIZATION:

7

#

II. PIPELINES & APPURTENANCES:

A. LAYING OF 200

mm

Ø PVC PIPELINE:

20

B. HYDRO TESTING & DISINFECTION WORKS:

3

C. VALVES & FITTINGS:

8

III. BRIDGE CROSSING:

5

IV. FIRE HYDRANTS:

3

V. TRANSFER OF SERVICE CONNECTIONS CLUSTER TYPE:

20

VI. STEEL WORKS (CLUSTER PROTECTOR):

20

VII. CONCRETE CUTTING & DEMOLITION:

17

VIII. VALVE BOXES:

17

IX. BACKFILLING & CONCRETE RESTORATION:

22

IX. DEMOBILIZATION

8

TOTAL PROJECT COST

150

CASH OUTLAY REQUIREMENT

TARGETED COMPLETION THIS PERIOD

COMMULATIVE COMPLETION TO DATE

Prepared by:

Reviewed & Checked by:

135,826.58

Php

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

GANTT CHART

Php4,875,948.00

Particulars

Amounts

WORKING DAYS

169,310.14

Php

15

103,152.65

Php

300,546.00

Php

383,940.51

Php

220,000.78

Php

789,724.33

Php

41,918.83

Php

1,924,355.56

Php

10,113.22

Php

761,128.50

Php

35,930.42

Php

4,875,948.00

Php

Php992,338.94

20.35%

20.35%

FELIXBERTO R. CAARE, JR.

MARIE CLAIRE C. BONGO

Researcher/Analyst A (J.O.)

Officer-In-Charge

Planning & Development Section

(17)

ALEJO S. ROJAS, JR.

(18)

PROPOSED REPLACEMENT OF MAYOR CESAR C. CLIMACO AVENUE PIPELINE

# # # # # #

# # # # # # # # # # # # # # # # # # # #

# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

Submitted by:

Approved by:

MARLI P. ACOSTA - DE FIESTA

Engineering Department

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

WORKING DAYS

30

45

60

15

Php992,338.94

Php2,057,309.09

Php1,539,093.00

Php287,206.00

20.35%

42.19%

31.57%

5.89%

20.35%

62.54%

94.11%

100.00%

CARLOS L. PEREZ, SR.

Officer-In-Charge

Officer-In-Charge

Planning & Design Division

(19)

LEONARDO REY D. VASQUEZ

General Manager

(20)

Engineering Department

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

WORKING DAYS

60

Php287,206.00

5.89%

100.00%

CARLOS L. PEREZ, SR.

Officer-In-Charge

(21)
(22)
(23)
(24)
(25)

PROJECT

:

PROPOSED REPLACEMENT OF MAYOR JALDON STREET PIPELINE

Location

:

Mayor Jaldon Street, Zamboanga City

Project Cost

:

Project Duration

:

76 WORKING DAYS

I. MOBILIZATION:

5

#

II. PIPELINES & APPURTENANCES:

A. LAYING OF 200mmØ PVC PIPELINE:

36

B. HYDRO TESTING & DISINFECTION WORKS:

6

C. VALVES & FITTINGS:

14

III. FIRE HYDRANTS:

6

IV. TRANSFER OF SERVICE CONNECTIONS (CLUSTER TYPE):

40

V. STEEL WORKS (CLUSTER PROTECTOR):

40

VI. CONCRETE CUTTING & DEMOLITION:

24

VII. VALVE BOXES:

20

VIII. BACKFILLING & CONCRETE RESTORATION:

29

IX. DEMOBILIZATION:

6

TOTAL PROJECT COST

226

CASH OUTLAY REQUIREMENT

TARGETED COMPLETION THIS PERIOD

COMMULATIVE COMPLETION TO DATE

Prepared by:

Reviewed & Checked by:

Approved for Project Implementation:

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

GANTT CHART

315,884.14

Php

275,845.90

Php

101,956.77

Php

969,495.49

Php

Php7,707,029.00

Particulars

Amounts

WORKING DAYS

19

59,075.23

Php

3,778,774.54

Php

26,672.47

Php

567,920.00

Php

173,214.49

Php

1,379,114.89

Php

59,075.23

Php

7,707,029.00

Php

Php1,908,182.72

24.76%

24.76%

FELIXBERTO R. CAARE, JR.

MARIE CLAIRE C. BONGO

Researcher/Analyst A (J.O.)

Officer-In-Charge

Planning & Development Section

Recommending Approval for Project Implementation:

(26)
(27)

PROPOSED REPLACEMENT OF MAYOR JALDON STREET PIPELINE

# # # #

# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

# #

# #

# #

# # # #

# # # #

# # # # # #

# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

Submitted by:

Approved by:

MARLI P. ACOSTA - DE FIESTA

Engineering Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

WORKING DAYS

19

38

57

Php1,908,182.72

Php2,920,240.69

Php1,976,365.00

24.76%

37.89%

25.64%

24.76%

62.65%

88.29%

CARLOS L. PEREZ, SR.

Officer-In-Charge

Officer-In-Charge

(28)
(29)

# # # # # # # # # # # # # # # # # # # # # #

Engineering Department

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

WORKING DAYS

57

76

Php1,976,365.00

Php902,241.00

25.64%

11.71%

88.29%

100.00%

CARLOS L. PEREZ, SR.

Officer-In-Charge

(30)
(31)
(32)
(33)
(34)

PROJECT

:

PROPOSED REPLACEMENT OF SAN JOSE ROAD PIPELINE

Location

:

San Jose Road, Zamboanga City

Project Cost

:

Project Duration

:

68 WORKING DAYS

I. MOBILIZATION:

5

#

II. PIPELINES & APPURTENANCES:

A. LAYING OF 200mmØ PVC PIPELINE:

20

B. HYDRO TESTING & DISINFECTION WORKS:

3

C. VALVES & FITTINGS:

5

III. FIRE HYDRANTS:

5

IV. TRANSFER OF SERVICE CONNECTIONS CLUSTER TYPE:

50

V. STEEL WORKS (CLUSTER PROTECTOR):

40

VI. CONCRETE CUTTING & DEMOLITION:

14

VII. VALVE BOXES:

15

VIII. BACKFILLING & CONCRETE RESTORATION:

25

IX. DEMOBILIZATION:

6

TOTAL PROJECT COST

188

CASH OUTLAY REQUIREMENT

TARGETED COMPLETION THIS PERIOD

COMMULATIVE COMPLETION TO DATE

Prepared by:

Reviewed & Checked by:

Approved for Project Implementation:

322,697.82

Php

Php1,816,770.61

33.09%

33.09%

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

17

WORKING DAYS

Pilar St., Zamboanga City

GANTT CHART

Php5,489,587.00

Particulars

Amounts

57,722.74

Php

2,169,359.07

Php

694,854.79

Php

57,722.74

Php

5,489,587.00

Php

11,365.61

Php

306,971.84

Php

98,218.70

Php

1,312,638.18

Php

345,527.74

Php

112,507.39

Php

FELIXBERTO R. CAARE, JR.

MARIE CLAIRE C. BONGO

Recommending Approval for Project Implementation:

ALEJO S. ROJAS, JR.

Researcher/Analyst A (J.O.)

Officer-In-Charge

(35)
(36)

PROPOSED REPLACEMENT OF SAN JOSE ROAD PIPELINE

# # # #

# # # # # # # # # # # # # # # # # # # #

# # #

# # # # #

# # # # #

# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #

Submitted by:

Approved by:

MARLI P. ACOSTA - DE FIESTA

Engineering Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ

Php918,798.00

16.74%

Php429,886.00

7.83%

Php1,816,770.61

33.09%

33.09%

Php2,001,434.24

36.46%

69.55%

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

17

34

51

68

WORKING DAYS

Pilar St., Zamboanga City

86.29%

94.12%

CARLOS L. PEREZ, SR.

Officer-In-Charge

Officer-In-Charge

(37)
(38)

# # # # # # # # # # # # # # # # # #

Engineering Department

Php5,166,888.85

Php429,886.00

7.83%

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

68

WORKING DAYS

Pilar St., Zamboanga City

94.12%

CARLOS L. PEREZ, SR.

Officer-In-Charge

(39)
(40)
(41)
(42)
(43)

PROJECT

:

PROPOSED REPLACEMENT OF DON PABLO LORENZO STREET PIPELINE

Location

:

Don Pablo Lorenzo Street, Zamboanga City

Project Cost

:

1,829,464.00

Project Duration

:

46 WORKING DAYS

1,819,653.08

9,810.92

0.005391645

I. MOBILIZATION:

7

# # # # # # #

II. PIPELINES & APPURTENANCES:

A. LAYING OF 150mmØ PVC PIPELINE W/ PARTIAL BACKFILLING:

15

# # # # # # # # # # # # # # #

B. HYDRO TESTING & DISINFECTION WORKS:

3

# # #

C. VALVES & FITTINGS:

10

# # # # # # # # # #

III. FIRE HYDRANTS:

3

# # #

IV. TRANSFER OF SERVICE CONNECTIONS (INDIVIDUAL TYPE TAPPED ON SECONDARY LINE):

8

# # # # # # # #

V. CONCRETE CUTTING & DEMOLITION:

6

# # # # # #

VI. VALVE BOXES:

13

# # # # # # # # # # # #

VII. BACKFILLING & CONCRETE RESTORATION:

15

VIII. DEMOBILIZATION:

7

#

TOTAL PROJECT COST

87

CASH OUTLAY REQUIREMENT

TARGETED COMPLETION THIS PERIOD

COMMULATIVE COMPLETION TO DATE

Prepared by:

Reviewed & Checked by:

Submitted by:

Approved by:

FELIXBERTO R. CAARE, JR.

MARIE CLAIRE C. BONGO

MARLI P. ACOSTA - DE FIESTA

CARLOS L. PEREZ, SR.

Researcher/Analyst A (J.O.)

Officer-In-Charge

Officer-In-Charge

Officer-In-Charge

Planning & Development Section

Planning & Design Division

Engineering Department

Recommending Project Implementation:

Approved for Project Implementation:

ALEJO S. ROJAS, JR.

LEONARDO REY D. VASQUEZ

Assistant General Manager for Operations

General Manager

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

527,121.81

Php

6,471.71

Php

331,346.42

Php

144,460.70

Php

15,080.87

Php

GANTT CHART

Php1,829,464.00

Particulars

Amounts

23

WORKING DAYS

46

15,080.87

Php

51,311.17

Php

113,516.76

Php

175,634.88

Php

52.75%

46.51%

52.75%

449,438.80

Php

99.26%

Php965,067.55

Php850,886.08

1,829,464.00

Php

(44)

# # # # # #

WORKING DAYS

46

46.51%

99.26%

Php850,886.08

References