• No results found

Extradosed Bridge Midas

N/A
N/A
Protected

Academic year: 2021

Share "Extradosed Bridge Midas"

Copied!
49
0
0

Loading.... (view fulltext now)

Full text

(1)
(2)

2

I.

Introduction

II.

Case Study

a. Bridge Information

b. Construction Methods

c. Structural Analysis Comparison

d. Economic Comparison

III. Modeling

a. Section Property Definition

b. Bridge Wizard

IV. Initial Cable Forces

a. Ideal State

b. Methods

c. Cable Tuning with ULF

Contents:

V. Construction Stage (CS) Analysis

a. Backward CS Analysis

b. Forward CS Analysis

1) Using Backward CS Analysis results

2) Using Lack of fit force

3) Using Unknown load factor

VI. Nonlinear Effects

a. P-∆ Effects

b. Large Deformations

VII. Results

a. Deformation

b. Camber Computation

1) Construction Camber

2) Manufacture Camber

c. Cable Forces and Stresses

(3)

II.

Case Study

III. Modeling

IV. Initial Cable Forces

V. Construction Stage Analysis

VI. Nonlinear Effects

VII. Results

(4)

Benefits with Extradosed Bridge

Ordinary prestressed girder bridge with internal or external tendons having cables installed

outside and above the main girder and deviated by short towers located at supports.

=>Construction & appearance

: Cable Stayed Bridge

=>Structural properties & design specifications

: PSC girder bridge

Reduced girder depth

=>

Reduced self weight

of the structure

Longer spans possible with the use of cables

=>

H/L

of extradosed bridges:

1/15 to 1/35

=>

H/L

of box girder bridges:

1/15 to 1/17

Lower main tower

=>

H/L

of extradosed bridges:

1/15

=>

H/L

of cable stayed bridges:

1/5

=>

Smaller stress variation

in stay cables

=>

Reduced fatigue failure

of stay cables

(5)

I.

Introduction

III. Modeling

IV. Initial Cable Forces

V. Construction Stage Analysis

VI. Nonlinear Effects

VII. Results

(6)

a. Bridge Information

(7)

a. Bridge Information

Location Total Length: L=1085m Road expansion: B=30m, L=692m Main Bridge: B=24m, L=225m Connection Bridge: B=15m, L=168m

(8)

a. Bridge Information

Cable arrangements FAN arrangement Harp arrangement Number of Cables 7 lines on one side (0.6”-27) (0.6”-29) (0.6”-31) Main Tower Height H=10,12,14m L=105.0m (L/8~L/12) Section Uniformed section H=2.5m L=105.0m (L/30~L/60) Cable arrangement:

FAN arrangement (one sided) Number of Cables: 7 lines (0.6”-29EA) Height of the Main Tower:

H=12.0m (L/8.75)

Section: Uniformed Section 2.5m(L/40) Optimum Design of Bridge

P relim in ar y Desig n Sectional Elevation

(9)

a. Bridge Information

Side Perspective

(10)

b. Construction Methods

Name

Characteristics of the Construction Method

Restrictions Duration Economic Constructability

F.S.M

Restrictions by the bottom conditions are crucial, depending on the supporting system.

Construction is fast due to the lumped pouring method.

Economical efficiency is determined by the height of the supporting. Lower pier is more cost-effective

There are plenty of international bridges constructed by this method. Easy to construct

F.C.M Less restrictions by the bottom

condition.

Slow construction due to forward construction stage method

Cost-effective if higher pier or if there is limited space underneath the bridge. For instance, bridge over rail road, bridge over the sea.

Construction management is complicated due to having measurements of each stage

1) Construction method of EXTRADOSED PSC BOX GIRDER Bridge

Construction Methods

F.S.M

F.C.M

Full Staging Method

(11)

b. Construction Methods

FSM

FCM

Low cost of equipment, simple method of construction Cost effective for level ground and low bridges

Fast construction, stable supports during construction

Little effect of supporting conditions

Possible for constructing long suspension bridge without heavy duty equipment Accuracy of the construction can be enhanced by the correction of errors at each construction stage.

Precise construction and management needed due to changes in the structural system by each construction stage.

(12)

b. Construction Methods

FSM Extradosed Bridge - Sequential Construction Stages in midas Civil (1/2)

1stConstruction Stage: Model and activate side span temporary supports by Elastic link and Support

2ndConstruction Stage: Remove side span temp. supports, and activate temp. supports of main span

(13)

b. Construction Methods

FSM Extradosed Bridge - Sequential Construction Stages in midas Civil (2/2)

4thConstruction Stage: Complete diagonal Tension Cables, and remove temp. supports of main span

5thConstruction Stage : Pavement and Finishing => Completion of Construction

Design Condition

① Structure: 3 span continuous EXTRADOSED P.S.C BOX Bridge ② Grade: Excellent

③ Dimensions: L = 60.0 + 105.0 + 60.0 = 225.0 m ③ Bridge Width: B = 23.740 m (4 lanes both way) ⑤ Thickness: H = 2.50 m (equal section) ⑥ Inclination: S = (±) 0.5 %

⑦ Plane surface alignment: R = ∞ ⑧ Construction method: F.S.M (Full Staging Method ) ⑨ Prestress construction: Post-Tensioning Method

(14)

b. Construction Methods

FCM Extradosed Bridge - Sequential Construction Stages in midas Civil (1/2)

1stConstruction Stage: Construct Main Pier and Pylon

`

2nd~9thConstruction Stage: Employ F/T Seg. Construct Diagonal cables

(15)

b. Construction Methods

FCM Extradosed Bridge - Sequential Construction Stages in midas Civil (2/2)

11thConstruction Stage: Connect Key Seg. of Main Span

12thConstruction Stage: Completion of Construction

Design Condition

① Structure: 3 span continuous EXTRADOSED P.S.C BOX Bridge ② Grade: Excellant

③ Dimension: L = 60.0 + 105.0 + 60.0 = 225.0 m ④ Bridge Width: B = 23.74 m (4 lanes both way) ⑤ Thickness: H = 2.50 m (equal section) ⑥ Inclination: S = (±) 0.5 %

⑦ Plane surface alignment: R = ∞(Straight line) ⑧ Construction method: FCM (Free Cantilever Method) ⑨ Prestress construction: Post-Tensioning Method

(16)

c. Structural Analysis Comparison

Dead Load

F.C.M: Maximum negative moment on supports are relatively greater than Maximum positive moment in the middle point. The moments are concentrated to the supports. F.S.M: The moment of the supports and the middle point are relatively balanced.

Moment after 10,000 days

Method F. S. M F. C. M Dead Load ` Mid-point 255,900 kN-m 22,540 kN-m Support -384,800 kN-m -531,500 kN-m

(17)

c. Structural Analysis Comparison

Tendon Primary

For F.C.M construction Cantilever Tendon is added on the upper part to resist excessive negative moment.

(Efficient to place internal tendon especially bottom tendon)

For F.S.M. construction it is difficult to place certain tendon at the negative and positive moment.

Comparing the sum of moment F.C.M. shows more efficient aspect on Positive and Negative moment.

Moment after 10,000 days

Method F. S. M F. C. M

Tendon Primary

Mid-Point -70,400 kN-m Total : -21,560 kN-m -57,830 kN-m Total : -30,270 kN-m

(18)

c. Structural Analysis Comparison

Tendon Secondary

 Tendon Secondary Moment is decided by placement and the amount of tendon. F.S.M. shows efficiency in both positive and negative moment.

 However, in the total sum F.C.M. shows efficiency in analysis.

Moment after 10,000 days

Method F. S. M F. C. M

Tendon Secondary

Mid-Point 33,390 kN-m Total : 11,830 kN-m 38,940 kN-m Total : 8,670 kN-m

(19)

c. Structural Analysis Comparison

Creep Secondary

 Creep Secondary Moment behaves similar to the case of Dead Load.

 In the total sum of positive moment F.C.M. shows efficiency but, in the negative moment since the Creep Secondary acts F.S.M. show efficiency.

Moment after 10,000 days

Method F. S. M F. C. M

Creep Secondary

Mid-Point 4,639 kN-m Total : 16,469 kN-m 0 kN-m Total : 8,670 kN-m

(20)

c. Structural Analysis Comparison

Shrinkage Secondary

 Shrinkage Secondary Moment shows similarity in both method.

 Similar to Creep Secondary moment the total sum of positive moment F.C.M. shows efficiency but, in the negative moment since the Creep Secondary acts F.S.M. show efficiency.

Moment after 10,000 days

Method F. S. M F. C. M

Shrinkage Secondary

Mid-point 9,980 kN-m Total : 26,449 kN-m 9,177 Kn-m Total : 17,847 kN-m

(21)

c. Structural Analysis Comparison

Conclusion of Stress analysis

 Structural analysis shows that on the final combination both Method of construction has similar results.

 For stress aspect F.S.M. shows greater and conservative. However since the placement of Continuity Tendon is functioned to greater section force, it is inefficient for placing tendon.

Special Loads (D + CF + LI + PS1 + PS2 + CRSH2 + SD) Method F. S. M F. C. M Upper limit stress (MPa) Bottom limit stress (MPa)

(22)

d. Economic Comparison & Conclusion

Cost effective  For applying F.S.M. there has been 10% reduction of the construction Cost.

Construction

 F.C.M has a long term of construction since it requires accuracy of managing Camber and several Seg. Construction stage.

(23)

I.

Introduction

II.

Case Study

IV. Initial Cable Forces

V. Construction Stage Analysis

VI. Nonlinear Effects

VII. Results

(24)

a. Section Definition

Database

Draw section shape using CAD

Import CAD file through SPC

Import section properties

(25)

b. Bridge Wizard

FSM Bridge Wizard FCM Bridge Wizard

(26)

b. Bridge Wizard & Manual Modeling

Cable Stayed Bridge Wizard

Manual modeling

(27)

I.

Introduction

II.

Case Study

III. Modeling

V. Construction Stage Analysis

VI. Nonlinear Effects

VII. Results

(28)
(29)

b. Methods

1. Simple supported Beam

Bridge segment is a simple beam supported by cables.

2. Continuous Beam

(30)

b. Methods

3. Unit Load Method

Unit load cases equal to the number of fixed ideal moment points (for dead load) are defined. Xi is the

unknown to be multiplied to the unit load to achieve the ideal moment distribution.

4. Additional Constraint Method

Extension of Unit load method to time dependent effects and non-linear effects.

5. Unknown Load Factor

User defined displacement/reaction/force constraint. Using vector and matrix calculations the cables’

forces are adjusted to satisfy the constrained condition(s).

(31)

c. Cable Tuning with ULF

Importance of Cable Tuning

ULF calculates the value of cable pretension for a particular constraint. That cable pretension (or Load

Factor) might not be practical or might exceed the cable force tolerance limit. Thus force can be adjusted

using Cable Tuning.

Procedure

1. Use Unknown Load Factor to

calculate the cable pretension (or

Load Factor).

2. Adjust the cable pretension (or load

factor) using the table or bar graph.

3. Select the result item for which the

effects of the cable pretension are to be

checked.

4. Produce the results graph for the result

item selected from step 3.

5. Save the adjusted pretension forces in

a load combination or apply the new

pretension forces to the cables directly

using the pre-programmed buttons.

(32)

I.

Introduction

II.

Case Study

III. Modeling

IV. Initial Cable Forces

VI. Nonlinear Effects

VII. Results

(33)

a. Backward CS Analysis

Significance

Cable prestress, introduced during

the construction of cable-stayed

bridge, could be calculated by

Backward CS Analysis from the

final stage.

Limitations

Does not consider Time Dependent

Effects and Non-Linearity Effects.

(34)

b. Forward CS Analysis

1) Using Backward CS Analysis Results (Preferred for Multiple Pretension Loads for single cable)

Obtain cable pretension load using unknown load

factor and cable tuning after final stage analysis

Perform Backward CS Analysis applying the

pretension load obtained from last step

Obtain cable forces in each CS after performing

Backward construction stage analysis

Apply cable forces as Pretension Loads in each

construction stage

Perform CS analysis with cable pretension force

(35)

b. Forward CS Analysis

2) Using lack of fit force (No time dependent effects considered)

Obtain initial pretension load using Unknown Load

Factor on final stage

Fine tune the cable forces using “Cable Force

Tuning”

Apply initial prestress force to cables for

construction stage analysis

Turn on “Lack of fit force Control” option in

construction stage analysis control

Perform construction stage analysis to obtain

jacking forces of cables at each construction stage

(36)

b. Forward CS Analysis

3) Using Unknown Load Factor (Not suitable for Cables)

Perform CS analysis with self weight and unit

pretension load

Calculate Unknown Load Factor for the stages of

cable force activation

Perform iterative analysis using Unknown Load

Factor to modify the cable forces

Further modify cable pretension load using cable

tuning

Check the jacking forces of cables at each CS in

results > forces > truss forces.

(37)

I.

Introduction

II.

Case Study

III. Modeling

IV. Initial Cable Forces

V. Construction Stage Analysis

VII. Results

(38)

a. P-∆ Effects

 Considered for both construction stage and final stage.

 Can’t be run with Tension Only Cable Element in Final Stage Analysis.

(39)

b. Large Deformations

 Considered for main span length generally longer than 600m.

 Considered for both construction stage and final state.

(40)

I.

Introduction

II.

Case Study

III. Modeling

IV. Initial Cable Forces

V. Construction Stage Analysis

VI. Nonlinear Effects

(41)

a. Deformation

Pylons

Pylon construction

tolerance is as shown:

(42)

a. Deformation

Pylons

Pylon maximum lateral deformation

= 13.249mm < 38mm => OK

(43)

a. Deformation

Bridge Deck

(44)

a. Deformation

Bridge Deck

(45)

b. Camber Computation : Construction Camber

Construction Camber is shown as the

net displacement results in Midas Civil

(46)

Manufacture Camber

To see real displacement in the results, check

“Initial Tangent Displacement for Erected Structures”

option in CS Analysis Control Data.

(47)

b. Camber Computation

(48)

c. Cable Forces & Stresses

(49)

Bridging Your Innovations to Realities

Thank You!

References

Related documents

For the analytical solution, the measured data have been rotated slightly (approximately 10 ◦ ) into the mean wind direction to fit the meteorological coordinate sys- tem with

Different from the above researches, Cai(2010) from a different perspective with asymmetric base demand in two channels and explores this feature in situation with and

With the Hospitality Home Menu, hotels can provide guests with a simple home screen that displays a live channel stream and shows additional information such as the time and date, a

• A basket credit derivative is a contract whose payoff • A basket credit derivative is a contract whose payoff depends on the default of several underlying credits2. example:

Info-Tech -enabled English language teaching environment does not only provide opportunity for the development of critical thinking skills, but also paves the way for

The present study revealed the traditional medicinal knowledge of treating various kinds of ailments using different animal and their products by the local Garasiya people

An intervention proposal that includes dietary adapta- tions and a PA program with a net caloric balance close to zero will result in no changes (or minimum changes) in the body