Project Title: PROPOSED TWO (2) STOREY LTO BUILDING
Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN
Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch)
14 GENERAL REQUIREMENTS Qty 1.00 lot 1.0 Mobilization/Demobilization Php 2.0 Temporary Facilities a.) Bunkhouse/Office/Warehouse Php b.) Temporary Lightings Php c.) Temporary Water Php Php II. EARTHWORKS
1.0 Excavation Works/Backfill and Compaction Qty 52.13 cu.m
A. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman Php 450.00 /day Php
1 H.E. Operator Php 400.00 /day Php
6 Laborer Php 250.00 /day Php
Php
Php 2,950.00 x 1.5 day Php
B. EQUIPMENT EXPENSES (RENTAL)
1 unit Backhoe/Loader Php 7,000.00 /day Php
Fuel, oil, lub.,etc Php 1,750.00 /day Php
Php
Php 8,750.00 x 1.5 days Php
A. LABOR COST Php
B. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 20,182.50 / 52.13 cu.m Php Total Item Cost = Php 387.15 x 52.13 cu.m Php
III. CONCRETE WORKS Qty 30.22 cu.m A. MATERIAL COST
303.0
bags Portland Cement @ Php 225.00 /bag Php
32.0
cu.m Screened Gravel Php 400.00 /cu.m Php
16.0
cu.m Washed Sand Php 450.00 /cu.m Php
Php B. LABOR COST
1.0 Project Engineer @ Php 600.00 /day Php
1.0 Construction Foreman Php 450.00 /day Php
2.0 Mason Php 375.00 /day Php
8.0 Laborer Php 250.00 /day Php
Php
Php 3,800.00 x 8.0 days Php
C.
EQUIPMENT EXPENSES (RENTAL)1 unit One Bagger Concrete Mixer Php 400.00 /day Php
Fuel, oil, lub.,etc Php 100.00 /day Php
Php
Php 500.00 x 8.0 days Php
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 140,961.25 / 30.22 cu.m Php Total Item Cost = Php 4,665.27 x 30.22 cu.m Php
IV. REINFORCE STEEL BARS Qty 4,171.30 kgs A. MATERIAL COST 2,157.6 kgs 16mmØ Def. bars Php 40.00 /kg Php 381.9 kgs 12mmØ Def. bars Php 40.00 /kg Php 1,631.8 kgs 10mmØ Def. bars Php 40.00 /kg Php 75.2
kgs # 16 G.I. tie wire Php 60.00 /kg Php
Php B. LABOR COST
1.0 Project Engineer @ Php 600.00 /day Php
1.0 Construction Foreman Php 450.00 /day Php
4.0 Steelman Php 300.00 /day Php
9.0 Laborer Php 250.00 /day Php
Php
Php 4,500.00 x 12.0 days Php
C.
EQUIPMENT EXPENSES (RENTAL)1 unit Bar cutter Php 200.00 /day Php
Php
Php 200.00 x 12.0 days Php
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php Unit Cost = Php 261,926.60 / 4,171.30 kgs Php Total Item Cost = Php 62.79 x 4,171.30 kgs Php
V. FORMS AND SCAFFOLDINGS Qty 1.00 lot
A. MATERIAL COST 25.0
pcs 1/2"x4'x8' Form Plywood @ Php 560.00 /pc Php
4,000.0
bd.ft Asst. Form lumber @ Php 24.00 /bd.ft Php
80.0
kgs Asst. CWNail @ Php 75.00 /kg Php
20.0
bd.ft # 16 G.I. tie wire @ Php 60.00 /kg Php
Php B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
4 Carpenter @ Php 375.00 /day Php
S U M M A R Y
3 Laborer @ Php 250.00 /day Php Php Php 3,300.00 x 12.0 days Php A. MATERIAL COST Php B. LABOR COST Php Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php
Unit Cost = Php 180,320.00 / 1.00 lot Php Total Item Cost = Php 180,320.00 x 1.00 lot Php
VI. MASONRY WORKS (CHB laying w/ Plastering) Qty 185.14 sq.m
A. MATERIAL COST 350.0
bags Portland Cement @ Php 225.00 /bag Php
29.0
cu.m Washed sand @ Php 400.00 /cu.m Php
2,450.0
pcs 5" CHB @ Php 10.50 /pc Php
518.0
kgs 10mmØ Def. bars @ Php 40.00 /kg Php
6.0
bd.ft # 16 G.I. tie wire @ Php 60.00 /kg Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman Php 450.00 /day Php
4 Mason Php 375.00 /day Php 6 Laborer Php 250.00 /day Php Php Php 4,050.00 x 12.0 day Php A. MATERIAL COST Php B. LABOR COST Php Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php Unit Cost = Php 213,618.25 / 185.14 sq.m Php Total Item Cost = Php 1,153.82 x 185.14 sq.m Php
VII. TILE WORKS Qty 82.40 sq.m
A. MATERIAL COST 15.0
bags Tile Adhessive @ Php 190.00 /bag Php
3.0
cu.m Washed sand @ Php 400.00 /cu.m Php
4.0 pc 4"Ø Diamond cutter @ Php 450.00 /pc Php 428.0 pcs 16"x16" Granite tile @ Php 85.00 /pc Php 60.0 pcs 16"x16" Outdoor tile @ Php 65.00 /pc Php 20.0 kgs Tile Grout @ Php 25.00 /kg Php Php S U M M A R Y S U M M A R Y
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Mason @ Php 375.00 /day Php
4 Laborer @ Php 250.00 /day Php
Php
Php 3,175.00 x 5.0 day Php
C.
EQUIPMENT EXPENSES (RENTAL)1 unit Electric Grinder Php 150.00 /day Php
Php
Php 150.00 x 5.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C.
EQUIPMENT EXPENSES (RENTAL) PhpPhp plus: 7% OCM Php 8% CP Php 12% VAT Php Php Unit Cost = Php 72,743.25 / 82.40 sq.m Php Total Item Cost = Php 882.81 x 82.40 sq.m Php
VIII. CARPENTRY AND JOINERY WORKS (2ND Floor Ceiling only) Qty 82.40 sq.m
A. MATERIAL COST 16.0
pcs Hardiflex ceiling board @ Php 420.00 /pc Php
48.0
pcs 0.40mm 19mm x 50mm x 5m @ Php 115.00 /pc Php
Double furring channel 8.0 pcs 0.80mm 12mm x 38mm x 5m @ Php 140.00 /pc Php Carrying Channel 15.0 pcs 0.40mm 25mm x 25mm x 3m @ Php 85.00 /pc Php Wall angle 290.0 pcs W-Clip @ Php 8.00 /pc Php 1.0 kgs 1-1/2" Concrete nail @ Php 90.00 /kg Php 2.0
pcs 4"Ø Diamond grinding disc @ Php 65.00 /pc Php
2.0
box Blind rivets @ Php 500.00 /box Php
800.0
bd.ft Asst. Form lumber (Scaffoldings) @ Php 24.00 /bd.ft Php
Php B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Carpenter @ Php 375.00 /day Php
2 Laborer @ Php 250.00 /day Php
Php
Php 2,675.00 x 5.0 days Php
C.
EQUIPMENT EXPENSES (RENTAL)1 unit Electric Grinder Php 150.00 /day Php
Php
Php 150.00 x 5.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C.
EQUIPMENT EXPENSES (RENTAL) Phpplus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 59,225.00 / 82.40 sq.m Php Total Item Cost = Php 718.75 x 82.40 sq.m Php
IX. DOORS AND WINDOWS Qty 1.00 lot
A. MATERIAL COST 2.0
sets D-1, Panel type door w/ 2"x 6" jamb with @ Php 5,300.00 /set Php Complete accessories (0.90x2.10mts.)
1.0
sets D-2, Flush type door w/ 2"x 5" jamb with @ Php 4,000.00 /set Php Complete accessories (0.80x2.10 mts.)
2.0
sets W-1, Steel casement window with 3/16" @ Php 3,780.00 /set Php thk. Clear glass (1.80x1.40mts)
2.0
sets W-2, Steel casement window with 3/16" @ Php 2,520.00 /set Php thk. Clear glass (1.20x1.40mts)
Php B. LABOR COST (Installation only)
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
1 Carpenter @ Php 375.00 /day Php
1 Welder @ Php 375.00 /day Php
1 Glass Installer @ Php 300.00 /day Php
5 Laborer @ Php 250.00 /day Php
Php
Php 3,350.00 x 2.0 days Php
C.
EQUIPMENT EXPENSES (RENTAL)1 unit Electric Grinder Php 150.00 /day Php
Php
Php 150.00 x 2.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C.
EQUIPMENT EXPENSES (RENTAL) PhpPhp
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 39,330.00 / 1.00 lot Php Total Item Cost = Php 39,330.00 x 1.00 lot Php
X. PAINTING WORKS (Concrete wall & Hardiflex Ceiling board) Qty 460.08 sq.m
A. MATERIAL COST 5.0
tin Flat Latex paint @ Php 1,810.00 /tin Php
10.0
tin Semi-gloss Latex paint @ Php 2,370.00 /tin Php
4.0
lits Latex color @ Php 120.00 /lit Php
4.0
gal. Masonry putty @ Php 15.00 /gal Php
20.0
kgs Patching compound @ Php 15.00 /lit Php
8.0
lits Stickwel @ Php 195.00 /lit Php
7.0
17.0 pcs Paint brush @ Php 45.00 /pc Php 100.0 pcs Sandpaper @ Php 25.00 /pc Php 15.0 pcs Stupa Rag @ Php 20.00 /kg Php Php B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Painter @ Php 350.00 /day Php 4 Laborer @ Php 250.00 /day Php Php Php 3,100.00 x 5.0 day Php A. MATERIAL COST Php B. LABOR COST Php Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php Unit Cost = Php 63,152.25 / 460.08 sq.m Php Total Item Cost = Php 137.26 x 460.08 sq.m Php
XI. TRUSS WORKS Qty 1.00 lot
A. MATERIAL COST 23.0
pcs 1.5mm x 2"x6" CEE purlins (truss) @ Php 650.00 /pc Php 12.0
pcs 1.0mm x 2"x4" CEE purlins @ Php 397.00 /pc Php
3
5.0 pcs 10mmØ Plain Round bar @ Php 138.00 /pc Php9.0
pcs 1/4" x 10"x10" Base plate @ Php 250.00 /pc Php 3.0
box Welding rod @ Php 1,200.00 /box Php
36.0
pcs 12mmØ x 10" Anchor bolts w/
Nut and washer @ Php 120.00 /pc Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
2 Welder @ Php 375.00 /day Php
2 Laborer @ Php 250.00 /day Php
Php
Php 2,300.00 x 4.0 day Php
1 unit Welding Machine Php 450.00 /day Php
Php
Php 450.00 x 4.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php S U M M A R Y
Unit Cost = Php 47,810.10 / 1.00 lot Php Total Item Cost = Php 47,810.10 x 1.00 lot Php XII. ROOFING WORKS
Qty 48.50 l.m A. MATERIAL COST
48.5
l.m Rib-type Roofing sheet (.5mm thk.) @ Php 420.00 /l.m Php
48.5
l.m One sided Alum. Insulation (9mm thk) @ Php 450.00 /l.m Php 5.0 pcs Wall flashing @ Php 450.00 /pc Php 5.0 pcs 3"Ø PVC pipe @ Php 460.00 /pc Php 6.0 pcs 3"Ø PVC Elbow 1/4 bend @ Php 53.00 /pc Php 3.0 pcs Gutter @ Php 450.00 /pc Php 300.0 pcs Tekscrew @ Php 1.75 /pc Php 4.0
tube Silicon Sealant @ Php 150.00 /tube Php
1.0
box Blind Rivets @ Php 500.00 /box Php
Php B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Roof Installer @ Php 350.00 /day Php
4 Laborer @ Php 250.00 /day Php Php Php 3,100.00 x 4.0 day Php S U M M A R Y A. MATERIAL COST Php B. LABOR COST Php Php plus: 7% OCM Php 8% CP Php 12% VAT Php Php Unit Cost = Php 71,803.70 / 48.50 l.m Php Total Item Cost = Php 1,480.49 x 48.50 l.m Php
XIII. TINSMITRY WORKS (Stair Railings) Qty 1.00 lot
A. MATERIAL COST 4.0
pcs 2"Ø Stainless Steel pipe @ Php 3,250.00 /pc Php
4.0
pcs 3/16"x1" Flat bar @ Php 235.00 /pc Php
15.0
pcs 3/4"x3/4" Square bar @ Php 245.00 /pc Php
1.0
lot Welding rod/Accessories @ Php 3,000.00 /lot Php
2.0
pc 4"Ø Grinding disk @ Php 65.00 /pc Php
Php B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
1 Welder @ Php 375.00 /day Php
3 Laborer @ Php 250.00 /day Php
Php
Php 2,175.00 x 3.0 day Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Welding Machine Php 450.00 /day Php
Php
Php 450.00 x 3.0 days Php
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 32,913.00 / 1.00 lot Php Total Item Cost = Php 32,913.00 x 1.00 lot Php XIV. ELECTRICAL WORKS
Qty 1.00 lot A. MATERIAL COST
6.0
sets 2x40W FL lamp w/ housing @ Php 1,500.00 /set Php
5.0
sets 25W CFL @ Php 60.00 /set Php
5.0
sets 4"x4" Pinlight @ Php 250.00 /set Php
6.0
pcs Receptacle 4"Ø @ Php 50.00 /pc Php
2.0
sets Single pole switch @ Php 120.00 /set Php
3.0
sets Two pole switch @ Php 165.00 /set Php
2.0
sets 3-Way switch @ Php 210.00 /set Php
11.0 pcs 4"x4" Junction box @ Php 35.00 /pc Php 15.0 pcs 2"x4" Utility box @ Php 35.00 /pc Php 34.0 pcs 1/2"Ø PVC pipe x 3.00 mts. @ Php 61.00 /pc Php 2.0
rolls 3.5mm² THHN wire @ Php 3,207.50 /roll Php
20.0
mts 14mm² THHN wire @ Php 85.84 /mt Php
4.0
pcs 1'Ø PVC pipe x 3.00 mts. @ Php 102.00 /pc Php
2.0
pcs 1"Ø Long sweep elbow @ Php 38.00 /pc Php
22.0
pcs 1/2"Ø PVC Long sweep elbow @ Php 25.00 /pc Php
1.0
pc 1"Ø RSC pipe x 3.00 mts. @ Php 420.00 /pc Php
1.0
sets 1"Ø Entrance cap @ Php 65.00 /set Php
1.0
set 3-Pole secondary rack @ Php 285.00 /set Php
1.0
pc 1"Ø Long sweep elbow (RSC) @ Php 85.00 /pc Php
10.0
rolls Electrical tape @ Php 45.00 /roll Php
Php B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
1 Electrician @ Php 325.00 /day Php
3 Laborer @ Php 250.00 /day Php
Php
Php 2,125.00 x 4.0 day Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Electric drill Php 150.00 /day Php
Php
Php 150.00 x 4.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
/set Php
Main ACB/ 6-branches, w/ 1-20 AT, 2P,
5-20 AT, 2P Php 1,850.00
1.00
Php
Unit Cost = Php 41,871.27 / 1.00 sets Php Total Item Cost = Php 41,871.27 x 1.00 sets Php
20,000.00 50,000.00 30,000.00 10,000.00 110,000.00 600.00 450.00 400.00 1,500.00 2,950.00 4,425.00 7,000.00 1,750.00 8,750.00 13,125.00 4,425.00 13,125.00 17,550.00 1,228.50 1,404.00 2,106.00 20,182.50 387.15 20,182.50
302.15
68,175.00 12,800.00 7,200.00 88,175.00 600.00 450.00 750.00 2,000.00 3,800.00 30,400.00
0.344768925
400.00 100.00 500.00 4,000.00 S U M M A R Y88,175.00 30,400.00 4,000.00 122,575.00 8,580.25 9,806.00 14,709.00 140,961.25 4,665.27 140,961.25 86,302.10 15,276.32 65,273.76 4,510.08 171,362.26 600.00 450.00 1,200.00 2,250.00 4,500.00 54,000.00
0.315121897
200.00 200.00 2,400.00 171,362.26 54,000.00 2,400.00 227,762.26 15,943.36 18,220.98 27,331.47 261,926.60 62.79 261,926.60 14,000.00 96,000.00 6,000.00 1,200.00 117,200.00 600.00 450.00 1,500.00 S U M M A R Y S U M M A R Y750.00 3,300.00 39,600.00
0.337883959
117,200.00 39,600.00 156,800.00 10,976.00 12,544.00 18,816.00 180,320.00 180,320.00 180,320.00 78,750.00 11,600.00 25,725.00 20,720.00 360.00 137,155.00 600.00 450.00 1,500.00 1,500.00 4,050.00 48,600.000.354343626
137,155.00 48,600.00 185,755.00 13,002.85 14,860.40 22,290.60 213,618.25 1,153.82 213,618.25ground floor/second floor
stairs
2,850.00
12.50
13.00
80
1,200.0020.00
20.00
260
2.4
1,800.0014.70
15.00
82.4
36,380.00 3,900.0012.50
13.00
195
500.005.00
5.00
46,630.005.33
6.00
60
S U M M A R Y S U M M A R Y600.00 450.00 1,125.00 1,000.00 3,175.00 15,875.00
0.340446065
150.00 150.00 750.00 46,630.00 15,875.00 750.00 63,255.00 4,427.85 5,060.40 7,590.60 72,743.25 882.81 72,743.25ground floor/second floor
6,720.0012.50
13.00
5,520.0020.00
20.00
1,120.0014.70
15.00
1,275.00 2,320.0012.50
13.00
35.42
53.13
90.005.00
5.00
17.71
130.00 1,000.005.00
5.00
19,200.00 37,375.005.33
6.00
600.00 450.00 1,125.00 500.00 2,675.00 13,375.000.357859532
150.00 150.00 750.00 37,375.00 13,375.00 750.00 51,500.003,605.00 4,120.00 6,180.00 59,225.00 718.75 59,225.00 10,600.00
5,300.00
4,000.004,000.00
7,560.002.52
1500
3,780.00
5,040.001.68
1500
2,520.00
27,200.00 600.00 450.00 375.00 375.00 300.00 1,250.00 3,350.00 6,700.000.246323529
150.00 150.00 300.00 27,200.00 6,700.00 300.00 34,200.00 2,394.00 2,736.00 4,104.00 39,330.00 39,330.00 39,330.00 9,050.0012.34267
23,700.00 480.00 60.00 300.00 1,560.00 700.00765.00 2,500.00 300.00 39,415.00 600.00 450.00 1,050.00 1,000.00 3,100.00 15,500.00
0.3932513
39,415.00 15,500.00 54,915.00 3,844.05 4,393.20 6,589.80 63,152.25 137.26 63,152.25 14,950.00 4,764.0016.57
690.009.94
2,250.006.62
3,600.003.31
4,320.001
30,574.0037.44
6.24
600.00 450.00 750.00 500.00 2,300.00 9,200.000.300909269
450.00 450.00 1,800.00 30,574.00 9,200.00 1,800.00 41,574.00 2,910.18 3,325.92 4,988.88 47,810.10 S U M M A R Y47,810.10 47,810.10 20,370.00 21,825.00 2,250.00 2,300.00 318.00 1,350.00 525.00 600.00 500.00 50,038.00 600.00 450.00 1,050.00 1,000.00 3,100.00 12,400.00
0.247811663
50,038.00 12,400.00 62,438.00 4,370.66 4,995.04 7,492.56 71,803.70 1,480.49 71,803.70 13,000.000.625
940.0016.57
8.333333
3,675.0013.25
3,000.009.94
130.006.62
20,745.0046.38
7.73
600.00 450.00 375.00 750.00 2,175.00 6,525.000.314533623
450.00 450.00 1,350.00 20,745.00 S U M M A R Y6,525.00 1,350.00 28,620.00 2,003.40 2,289.60 3,434.40 32,913.00 32,913.00 32,913.00 9,000.00
0.625
300.0016.57
8.333333
1,250.0013.25
300.0013.25
240.0013.25
495.00 420.0013.25
13.25
13.25
385.00 525.00 2,074.00 6,415.00 1,716.80 408.00 76.00 550.00 420.00 65.00 285.00 85.00 450.00 27,309.8096.07
16.01167
600.00 450.00 325.00 750.00 2,125.00 8,500.000.311243583
150.00 150.00 600.00 27,309.80 8,500.00 600.00 36,409.80 2,548.69 2,912.78 4,369.18 1,850.0041,871.27 41,871.27 41,871.27
1,355,857.17
27
9
27
9
3
1
0.333333
0.111111
0.037037
Project Title: PROPOSED TWO (2) STOREY LTO BUILDING
Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN
Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch)
Item No.
UNIT
QTY
UNIT COST
AMOUNT
I
GENERAL REQUIREMENTS
lot
1.00
110,000.00
110,000.00
II
EARTHWORKS
cu.m
52.13
387.15
20,182.50
III.
CONCRETE WORKS
cu.m
30.22
4,665.27
140,961.25
IV
REINFORCE STEEL BARS
kgs
4,171.30
62.79
261,926.60
V
FORMS AND SCAFFOLDINGS
lot
1.00
180,320.00
180,320.00
VI
MASONRY WORKS
sq.m
185.14
1,153.82
213,618.25
VII
TILE WORKS
sq.m
82.40
882.81
72,743.25
VIII
CARPENTRY AND JOINERY WORKS
sq.m
82.40
718.75
59,225.00
IX
DOORS AND WINDOWS
lot
1.00
39,330.00
39,330.00
X
PAINTING WORKS
sq.m
460.08
137.26
63,152.25
XI
TRUSS WORKS
lot
1.00
47,810.10
47,810.10
XII
ROOFING WORKS
l.m
48.50
1,480.49
71,803.70
XIII
TINSMITRY WORKS
lot
1.00
32,913.00
32,913.00
XIV
ELECTRICAL WORKS
lot
1.00
41,871.27
41,871.27
TOTAL PROJECT COST
1,355,857.17
BILL OF QUANTITIES
DESCRIPTION
EARTHWORKS EXCAVATION WORKS F-1 1.50 1.50 1.50 6.00 20.25 FTB 5.00 0.25 1.10 3.00 4.13 4.00 0.25 1.10 4.00 4.40 GB 5.00 0.20 0.25 3.00 0.75 4.00 0.20 0.25 4.00 0.80 TOTAL 30.33 BACKFILL/COMPACTION F-1 1.50 1.50 0.30 6.00 4.05 FTB 5.00 0.25 0.30 3.00 1.13 4.00 0.25 0.30 4.00 1.20 GB 5.00 0.20 0.25 3.00 0.75 4.00 0.20 0.25 4.00 0.80 COLUMN 0.30 0.30 1.10 6.00 0.59 TOTAL 8.52 Excavation = 30.33 Backfill/Compaction 21.81 cu.m GRAVEL BEDDING F-1 1.50 1.50 0.10 6.00 1.35 FTB 5.00 0.25 0.10 3.00 0.38 4.00 0.25 0.10 4.00 0.40 GB 5.00 0.20 0.10 3.00 0.30 4.00 0.20 0.10 4.00 0.32 Area-1 8.00 5.00 0.10 1.00 4.00 Area-2 2.00 1.20 0.10 1.00 0.24 TOTAL 6.99 MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR STRUCTURE TOTAL VOLUME (m³) LENGTH (m.) WIDTH (m.) HEIGHT (m.) MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR STRUCTURE TOTAL VOLUME (m³) LENGTH (m.) WIDTH (m.) HEIGHT (m.) MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR STRUCTURE TOTAL VOLUME (m³) LENGTH (m.) WIDTH (m.) HEIGHT (m.)
5.00 16.67 13.33 16.67 13.33 5.00 16.67 13.33 1.00
V - MASONRY WORKS
GROUND FLOOR
perimeter wall 26.00 3.50 1.00 91.00 less opening 7.29 7.29 Total area 83.71 185.14 perimeter wall 26.00 3.50 1.00 91.00 4.40 1.00 1.00 4.40 5.00 3.00 1.00 15.00 less opening 8.97 8.97 Total area 101.43 No. of pcs 6” CHB 2,406.82 say 2,450.00 pcsCement 187.55 say 190.00 bags
Sand 15.63 say 17.00 m³
Vert. Reinforcement 394.35
Hor. Reinforcement 398.05
792.40/ 5.7m = 139.0174035
say 140 pcs 10mmØ 518.00
GI Tie Wire 4.44 say 6 kgs
Plastering
perimeter wall 83.71 101.43 1.00 185.14
370.28
370.28
Cement 159.22 say 160 bags
Sand 9.26 say 12 cu.m.
Summary Cement 350.00 Sand 29.00 No. of pcs 6” CHB 2,450.00 RSB Reinforcement 518.00 GI Tie Wire 6.00
10MMØ
0.616 6.00 3.70 0.616 7.50 4.62 0.616 9.00 5.54 0.616 10.50 6.47 0.616 12.00 7.39 REBAR WORKS F1 top-tranverse 16 1.50 8.00 6.00 48.00 bottom-longitudinal 12 1.50 8.00 48.00 Footing C1 vertical bar 16 9.00 8.00 2.00 16.00 8.30 outer ties 10 1.20 49.80 99.60 inner ties 10 1.00 49.80 99.60 C2 vertical bar 16 9.00 8.00 2.00 16.00 8.45 outer ties 10 1.20 50.70 101.40 inner ties 10 1.00 50.70 101.40 C3 vertical bar 16 9.00 8.00 2.00 16.00 8.61 outer ties 10 1.20 51.66 103.32 inner ties 10 1.00 51.66 103.32 FTB straight bars 16 6.00 6.00 3.00 18.00 5.00 stirrups 10 1.10 36.00 108.00 FTB straight bars 16 4.50 6.00 4.00 24.00 4.00 stirrups 10 1.20 27.00 108.00 GB straight bars 16 6.00 4.00 3.00 12.00 5.00 stirrups 10 0.90 36.00 108.00 GB straight bars 16 4.50 4.00 4.00 16.00 4.00 stirrups 10 0.90 27.00 108.00 B-1 straight bars 16 6.00 4.00 2.00 8.005.00 top cut bars 16 1.50 2.00 4.00
MARK LOCATION BAR
SIZE
FOR 1 STRUCTURE NO. OF
SIMILAR STRUCT URE TOTAL NO.OF PCS ONE BAR LENGTH NUMBER OF PCS
bott. Cut bars 16 3.00 1.00 2.00
stirrups 10 1.20 36.00 72.00
B-1 straight bars 16 4.50 4.00 4.00 16.00
4.00 top cut bars 16 1.20 2.00 8.00
bott. Cut bars 16 2.50 1.00 4.00
stirrups 10 1.20 27.00 108.00
B-2 straight bars 16 6.00 4.00 1.00 4.00
5.00 top cut bars 16 1.50 4.00 4.00
bott. Cut bars 16 3.00 2.00 2.00
stirrups 10 1.40 36.00 36.00
B-3 straight bars 16 6.00 4.00 1.00 4.00
5.00 top cut bars 16 1.50 2.00 2.00
bott. Cut bars 16 3.00 1.00 1.00
stirrups 10 1.10 36.00 36.00
B-4 straight bars 16 2.50 4.00 1.00 4.00
2.12 top cut bars 16 0.75 2.00 2.00
bott. Cut bars 16 1.50 1.00 1.00
stirrups 10 0.90 15.00 15.00 LB-1 straight bars 12 2.50 4.00 1.00 4.00 2.00 stirrups 10 1.00 15.00 15.00 CB-1 straight bars 12 1.50 4.00 1.00 4.00 1.20 stirrups 10 1.00 9.00 9.00 RB-1 straight bars 12 6.00 4.00 2.00 8.00
5.00 top cut bars 12 1.50 2.00 4.00
bott. Cut bars 12 3.00 1.00 2.00
stirrups 10 0.90 36.00 72.00
straight bars 12 4.50 4.00 4.00 16.00
4.00 top cut bars 12 1.20 2.00 8.00
bott. Cut bars 12 2.50 1.00 4.00
stirrups 10 0.90 27.00 108.00
RB-2 straight bars 16 6.00 4.00 1.00 4.00
5.00 top cut bars 16 1.50 2.00 2.00
bott. Cut bars 16 3.00 1.00 1.00
stirrups 10 1.10 36.00 36.00 RB-3 straight bars 12 6.00 4.00 1.00 4.00 5.00 stirrups 10 0.70 36.00 36.00 straight bars 12 2.50 4.00 1.00 4.00 2.12 stirrups 10 0.70 15.00 15.00 LB-2 straight bars 12 2.50 4.00 1.00 4.00 2.00 stirrups 10 0.80 15.00 15.00 CB-2 straight bars 12 1.50 4.00 2.00 8.00 1.20 stirrups 10 0.80 9.00 18.00
SLAB ON FILL longitudinal 10 8.00 20.00 1.00 20.00
cross section 10 5.00 12.50 12.50
SUSPENDED SLAB top bars(longitudinal) 10 5.00 16.67 1.00 16.67
top bars (cross section) 10 8.00 26.67 26.67
cut bars(longitudinal) 12 1.25 10.00 10.00
cut bars (cross section) 12 4.00 10.00 10.00
bent up bars(longitudinal) 10 5.00 16.67 16.67
MB-1 (30.00m) straight bars 16 30.83 4.00 3.00 12.00 @ GL A web bars 12 30.83 2.00 6.00 stirrups 10 1.40 784.00 2,352.00 MB-2(20.00m) straight bars 16 20.83 4.00 3.00 12.00 @ GL 1 web bars 12 20.83 2.00 6.00 stirrups 10 1.40 162.00 486.00 MB (30.00m) straight bars 16 30.83 4.00 1.00 4.00 @ GL A web bars 12 30.83 2.00 2.00 stirrups 10 1.40 184.00 184.00 Midbeam RB-1 (20.00m) straight bars 16 20.83 4.00 1.00 4.00 @ GL 1 web bars 12 20.83 2.00 2.00
top cut bars-end support 16 0.93 2.00 2.00 4.00
top cut bars-middle support 16 1.65 2.00 2.00 4.00
top cut bars-middle support 16 2.90 2.00 1.00 2.00
top cut bars-middle support 16 2.28 2.00 2.00 4.00
bottom cut bars 16 1.50 2.00 4.00 8.00
bottom cut bars 16 3.00 2.00 2.00 4.00
stirrups 10 1.40 162.00 162.00
RB-1 (30.00m) straight bars 16 30.83 4.00 1.00 4.00
web bars 12 30.83 2.00 2.00
top cut bars-end support 16 1.98 2.00 1.00 2.00
top cut bars-middle support 16 1.78 2.00 1.00 2.00
top cut bars-middle support 16 1.90 2.00 23.00 46.00
top cut bars-middle support 16 1.55 2.00 7.00 14.00
bottom cut bars 16 1.80 2.00 24.00 48.00
bottom cut bars 16 1.50 2.00 8.00 16.00
stirrups 10 1.40 784.00 784.00
RB-2 (20.00m) straight bars 16 20.83 4.00 4.00 16.00
web bars 12 20.83 2.00 8.00
top cut bars-end support 16 0.93 2.00 2.00 16.00
top cut bars-middle support 16 1.65 2.00 2.00 16.00
top cut bars-middle support 16 2.90 2.00 1.00 8.00
top cut bars-middle support 16 2.28 2.00 2.00 16.00
bottom cut bars 16 1.50 2.00 4.00 32.00
bottom cut bars 16 3.00 2.00 2.00 16.00
S.Angle (20.00m) straight bars 16 20.83 4.00 4.00 16.00
@ GL A web bars 12 20.83 2.00 8.00
top cut bars-end support 16 0.93 2.00 2.00 16.00
top cut bars-middle support 16 1.65 2.00 7.00 56.00
bottom cut bars 16 1.50 2.00 8.00 64.00
stirrups 10 1.40 184.00 736.00
roofbeam
Ground Slab transverse 12 92.00 41.00 1.00 41.00
92 x 20 longitudinal 12 20.00 185.00 185.00
Ground Slab transverse 12 42.00 41.00 1.00 41.00
42 x 20 longitudinal 12 20.00 85.00 85.00
12MMØ
16MMØ
0.888 6.00 5.33 1.578 6.00 9.47 0.888 7.50 6.66 1.578 7.50 11.84 0.888 9.00 7.99 1.578 9.00 14.20 0.888 10.50 9.32 1.578 10.50 16.57 0.888 12.00 10.66 1.578 12.00 18.94 72.00 6.00 12.00 12.00 384.00 227.23 2.17 72.00 6.00 227.23 2.1786
16MMØ 227.23 TIE WIRE 2.17 144.00 9.00 16.00 16.00 1,593.60 227.23 9.02 119.52 6.00 19.92 20.00 73.92 99.60 6.00 16.60 17.00 62.83 144.00 9.00 16.00 16.00 1,622.40 227.23 9.18 121.68 6.00 20.28 21.00 77.62 101.40 6.00 16.90 17.00 62.83 144.00 9.00 16.00 16.00 1,653.12 227.23 9.36 123.98 6.00 20.66 21.00 77.62 103.32 6.00 17.22 18.00 66.53 1,103.04 27.56 16MMØ 681.70 10MMØ 421.34 TIE WIRE 27.56 108.00 6.00 18.00 18.00 648.00 170.42 3.67 118.80 6.00 19.80 20.00 73.92 108.00 9.00 12.00 12.00 648.00 170.42 3.67 129.60 6.00 21.60 22.00 81.31 496.08 7.34 16MMØ 340.85 10MMØ 155.23 TIE WIRE 7.34 72.00 6.00 12.00 12.00 432.00 170.42 2.45 97.20 6.00 16.20 17.00 62.83 72.00 9.00 8.00 8.00 432.00 113.62 2.45 97.20 6.00 16.20 17.00 62.83 409.70 4.89 16MMØ 284.04 10MMØ 125.66 TIE WIRE 4.89 48.00 6.00 8.00 8.00 504.00 75.74 2.85 6.00 6.00 1.00 1.00 9.47 TOTAL NO. OF COMML LENGTH COMML LENGTH NO. OF VER/LONG BAR NO. OF HOR/TRANS BAR TOTAL BAR INTERSECTIO N6.00 6.00 1.00 1.00 9.47 86.40 6.00 14.40 15.00 55.44 72.00 9.00 8.00 8.00 756.00 151.49 4.28 9.60 6.00 1.60 2.00 18.94 10.00 7.50 1.33 2.00 18.94 129.60 6.00 21.60 22.00 81.31 24.00 6.00 4.00 4.00 360.00 37.87 2.04 6.00 6.00 1.00 1.00 9.47 6.00 6.00 1.00 1.00 9.47 50.40 6.00 8.40 9.00 33.26 24.00 6.00 4.00 4.00 252.00 37.87 1.43 3.00 6.00 0.50 1.00 9.47 3.00 6.00 0.50 1.00 9.47 39.60 6.00 6.60 7.00 25.87 10.00 7.50 1.33 1.50 105.00 17.75 0.59 1.50 6.00 0.25 0.50 4.73 1.50 6.00 0.25 0.50 4.73 13.50 6.00 2.25 3.00 11.09 10.00 7.50 1.33 1.50 60.00 6.93 0.34 15.00 6.00 2.50 3.00 11.09 6.00 6.00 1.00 1.00 36.00 5.33 0.20 9.00 6.00 1.50 2.00 7.39 48.00 6.00 8.00 8.00 504.00 42.62 2.85 6.00 6.00 1.00 1.00 5.33 6.00 6.00 1.00 1.00 5.33 64.80 6.00 10.80 11.00 40.66 72.00 9.00 8.00 8.00 756.00 85.25 4.28 9.60 6.00 1.60 2.00 10.66 10.00 6.00 1.67 2.00 10.66 97.20 6.00 16.20 17.00 62.83 24.00 6.00 4.00 4.00 252.00 37.87 1.43 3.00 6.00 0.50 0.50 4.73 3.00 6.00 0.50 0.50 4.73 39.60 6.00 6.60 7.00 25.87 24.00 6.00 4.00 4.00 144.00 21.31 0.82 25.20 6.00 4.20 5.00 18.48 10.00 7.50 1.33 2.00 60.00 13.32 0.34 10.50 6.00 1.75 2.00 7.39 10.00 7.50 1.33 1.50 60.00 9.99 0.34 12.00 6.00 2.00 2.00 7.39 12.00 6.00 2.00 2.00 72.00 10.66 0.41 14.40 6.00 2.40 2.50 9.24 1,096.91 22.19 16MMØ 472.22 12MMØ 227.38 10MMØ 397.32
TIE WIRE 22.19 100.00 5.60 17.86 18.00 250.00 66.53 1.42 100.00 6.00 16.67 17.00 62.83 133.33 6.00 22.22 23.00 988.89 85.01 5.60 133.33 5.60 23.81 24.00 88.70 40.00 6.00 13.33 14.00 74.59 12.50 6.00 4.17 5.00 26.64 133.33 6.00 22.22 23.00 85.01 0.00 133.33 5.60 23.81 24.00 88.70 578.02 7.01 12MMØ 101.23
18.99
10MMØ 476.78128.86
TIE WIRE 7.01 16MMØ 151.52 12MMØ 53.30 10MMØ 55.50 TIE WIRE 4.00168.00 7.50 6.00 784.00 14,112.00 1,988.70 95.86 84.00 7.50 559.65 588.00 6.00 2,175.60 24.00 12.00 6.00 162.00 2,916.00 454.56 19.81 12.00 12.00 127.92 41.00 6.00 151.70 8.00 12.00 6.00 184.00 1,104.00 151.52 7.50 4.00 12.00 42.64 46.00 6.00 170.20 5,822.49 387.48
69
8.00 12.00 8.00 162.00 1,296.00 151.52 8.80 4.00 12.00 42.64 1.00 6.00 9.47 1.00 7.50 11.84 1.00 6.00 9.47 1.00 10.50 16.57 2.00 6.00 18.94 2.00 6.00 18.94 41.00 6.00 151.70 56.00 7.50 8.00 784.00 6,272.00 662.90 42.60 28.00 7.50 186.55 1.00 7.50 11.84 0.00 16.00 6.00 151.52 2.00 12.00 37.88 10.00 9.00 142.05 4.00 6.00 37.88 196.00 6.00 725.20 32.00 12.00 8.00 162.00 5,184.00 606.08 35.21 16.00 12.00 170.56 4.00 6.00 37.88 4.00 7.50 47.35 4.00 6.00 37.88 4.00 10.50 66.29 8.00 6.00 75.76 8.00 6.00 75.76 41.00 6.00 151.7032.00 12.00 8.00 41.00 1,312.00 606.08 8.91 16.00 12.00 170.56 16.00 6.00 151.52 8.00 12.00 151.52 16.00 6.00 151.52 184.00 6.00 680.80 5,568.17 95.53
92
328.00 12.00 41.00 185.00 7,585.00 3,496.48 51.52 370.00 10.50 3,451.18 246.00 7.50 41.00 85.00 3,485.00 1,638.98 23.67 170.00 10.50 1,585.68 10,172.31 75.1976
#REF!
#REF!
FINISHING WORKS PLASTERING WORKS walls Exterior/Interior Plastering Total
Computation:
Cement 834.98 say 835.00 bags Sand 46.39 say 50.00 m³
TILE WORKS
Ground Floor
24"x24"Homogenous floor tiles
Library 10.00 7.00 16.67 17.00 Moot Court 9.30 7.00 15.50 16.00 SBO/SAS office 4.25 7.00 7.08 8.00 Deans office 6.75 5.00 11.25 12.00 12"x12"Homogenous floor tiles
Comport room (floor) 6.75 5.00 22.50 23.00 Comport room (floor) 6.75 5.00 22.50 23.00 Comport room (wall) 14.00 2.20 46.67 47.00 Comport room (wall) 10.00 2.20 33.33 34.00 Comport room (wall) 4.60 2.20 15.33 16.00 Comport room (wall) 5.00 2.20 16.67 17.00 24"x24"Homogenous floor tiles
Class room 10.00 7.00 16.67 17.00 4.00 10.00 6.67 7.00 9.30 7.00 15.50 16.00 9.30 7.00 15.50 16.00 hallways 3.00 50.00 5.00 5.00 lobbies 5.15 7.00 8.58 9.00 porch 2.00 6.00 3.33 4.00 platform 10.00 4.20 16.67 17.00 balcony 6.20 6.00 10.33 11.00 Entry along canopy area 6.00 6.00 10.00 10.00
MARK LENGTH WIDTH (length) no. of
pcs. say
MARK LENGTH HEIGHT NO. OF
fire scape areas 2.00 5.00 3.33 4.00 stair & landing 7.00 4.50 11.67 12.00 3.70 4.50 6.17 7.00
2nd Floor
24"x24"Ceramic floor tiles
area-1 8.00 7.00 13.33 14.00 cement fin. w/ h2o proofing
area-1 3.00 4.50
3rd Floor
24"x24"Ceramic floor tiles
area-1 8.00 7.00 13.33 14.00 cement fin. w/ h2o proofing
area-1 3.00 4.50
roof deck
cement fin. w/ h2o proofing 8.00 7.00 area-1 3.00 4.50
CEILING WORKS
2nd floor hardiflex ceiling board
open ceiling 8.50 5.00 1.20
2.00
total
2nd floor double furring channel
open ceiling 8.50 5.00 21.25 22.00 1.20
2.00 1.20 2.00
total
2nd floor wall angle
open ceiling 42.40 3.00 14.13 15.00
total
2nd floor carrying channel
open ceiling 8.50 5.00 7.08 8.00
total
PAINTING WORKS
ceiling area 89.80mark 1st coating 2nd coating 3rd coating
MARK LENGTH WIDTH (length) no. of
pcs. say MARK LENGTH comm'l. length (length) no. of
pcs. say MARK LENGTH WIDTH (length) no. of
pcs. say MARK LENGTH WIDTH (length) no. of
Flat latex paint
3.592.99
2.57Masonry putty
4.49latex color
0.45sand paper
5.99roller brush
paint brush
stupa rug
PAINTING WORKS
wall area 370.28mark 1st coating 2nd coating 3rd coating
Flat latex paint
14.81Semi-gloss Latex
14.8112.34
12.34Easytite with hardener
latex color
3.70sand paper
74.06roller brush
paint brush
stupa rug
Painting
door area 27.00mark 1st coating 2nd coating 3rd coating
QDE paint
0.900.54
Easytite with hardener
0.36Paint thinner
0.50tinting color
0.11sand paper
5.40roller brush
paint brush
stupa rug
Painting
Metal 336.34mark 1st coating 2nd coating 3rd coating
QDE paint
11.216.73
Easytite with hardener
3.36Paint thinner
84.09tinting color
sand paper
roller brush
paint brush
stupa rug
mark 1st coating 2nd coating 3rd coating
Flat latex paint
54.67Semi-gloss Latex
54.6741.00
32.80latex color
8.20Patching Compound
sand paper
164.02roller brush
paint brush
stupa rug
Painting
Exposed Conc. 56.89mark 1st coating 2nd coating 3rd coating
Flat latex paint
1.90Semi-gloss Latex
1.901.42
1.14latex color
0.28sand paper
5.69roller brush
paint brush
stupa rug
TOILET PARTITIONS Phenolic board female 1.50 1.60 4.00 20.16 0.20 1.60 2.00 1.34 0.40 1.60 3.00 4.03 male 1.50 1.60 2.00 10.08 0.20 1.60 2.00 1.34 0.40 1.60 1.00 1.34 urinal partitions 0.45 0.90 6.00 5.10 total 43.41 DOORS Phenolic board female 0.60 1.60 4.00 8.06 male 0.60 1.60 2.00 4.03 total 12.10 DECORATIVE STONE wall angle Area-1 9.00 1.00 36.00 36.00 Area-2 1.75 5.00 17.50 18.00 Area-3 9.50 2.00 38.00 18.00MARK LENGTH WIDTH total Area (m²) say MARK LENGTH WIDTH total no. of unit total
Area (m²) MARK LENGTH WIDTH total no. of unit total
Area-4 9.50 1.00 19.00 19.00 Area-5 9.00 0.60 10.80 11.00 total 102.00 25.50 ALUM. CLADDING wall angle Area-1 5.70 1.50 34.20 18.00 5.70 0.50 11.40 3.00 Area-2 17.70 1.50 53.10 54.00 total 75.00
FINISHING WORKS(Second floor) PLASTERING WORKS
walls
Exterior/Interior Plastering #REF! #REF! #REF! 2.00 Total
Computation:
Cement #REF! say 500.00 bags
Sand #REF! say 35.00 m³
TILE WORKS Ground Floor concrete pavers 27.50 2.40 24"x24"Granite tiles gen. merch. 10.00 4.00 16.67 17.00 asessment area 5.00 5.20 8.33 9.00 souvinir area 7.00 4.20 11.67 12.00 photocopy/printing 12.00 8.00 20.00 20.00 300x300mm tile 1.60 1.50 5.33 6.00 Toilet 5.90 1.60 400x400mm tile 1.60 1.50 5.33 6.00 Stairs
Peeble washed out 11.00 2.00
mezz. Floor
concrete pavers
27.50 2.40 24"x24"Granite tiles
open room storage 4.00 3.00 1,2,3,4 16.00 6.00 Corridor
MARK LENGTH WIDTH (length) no. of
pcs. say
MARK LENGTH HEIGHT NO. OF
SIMILAR FACE MARK LENGTH WIDTH total Area (m²) say
plain cement fin. 29.00 2.25 Stairs
Peeble washed out 11.00 2.00
2nd floor
plain cement fin.
corridor-1 27.50 2.25 corridor-2 27.50 2.40 24"x24"Granite tiles dig./audio visual 8.00 8.00 photo studio 4.00 8.00 wellness room 4.00 8.00 office 4.00 8.00 300x300mm tile toilet 1.50 1.45 5.00 5.00 Toilet 5.90 1.60 CEILING WORKS 4th floor .19mx3mts long Hall way-1 37.40 2.00 Hall way-2 20.70 2.00 Hall way-3 32.00 2.00 Hall way-4 13.00 2.00 Hall way-5 10.00 4.00 1/4"thk. Hardiflex hall way 2.00 2.00 6.00
MARK LENGTH WIDTH (length) no. of
total
double furring channel
hallway 280.00 2.00 2,800.00 5.00
total
wall angle
hallway 560.00 3.00 186.67 187.00
total 560.00 187.00
total area(m²) length/sq.m comm'l. length
carrying channel 24.00 1.50 5.00 7.20 double furring clip 5.00 15.00
total area(m²) no. of pcs./sq.m
blind rivets 24.00 20.00 480.00
total lenght(l.m²) kgs./l.m
1" conc. Nail 560.00 0.03 14.00
Painting
ceiling area 24.00mark 1st coating 2nd coating 3rd coating
Flat latex paint
0.80Semi-gloss Latex
0.800.60
0.40Easytite with hardener
0.24latex color
0.12sand paper
2.40roller brush
paint brush
stupa rug
Painting
door area #REF!mark 1st coating 2nd coating 3rd coating
QDE paint
#REF!#REF!
Easytite with hardener
#REF!Paint thinner
0.75tinting color
#REF!sand paper
#REF!roller brush
paint brush
stupa rug
MARK LENGTH comm'l.
length(m)
total length
(l.m) say MARK LENGTH WIDTH total length
(l.m)
comm'l. length(m)
Painting
Metal 139.20mark 1st coating 2nd coating 3rd coating
QDE paint
4.642.78
Easytite with hardener
1.39Paint thinner
0.46tinting color
sand paper
roller brush
paint brush
stupa rug
Painting
Interior wall #REF!mark 1st coating 2nd coating 3rd coating
Flat latex paint
#REF!Semi-gloss Latex
#REF!#REF!
#REF!latex color
#REF!sand paper
#REF!roller brush
paint brush
stupa rug
TOILET PARTITIONS Phenolic board female 1.50 1.60 4.00 20.16 0.20 1.60 2.00 1.34 0.40 1.60 3.00 4.03 male 1.50 1.60 2.00 10.08 0.20 1.60 2.00 1.34 0.40 1.60 1.00 1.34 urinal partitions 0.45 0.90 6.00 5.10 total 43.41 DOORS Phenolic board female 0.60 1.60 4.00 8.06 male 0.60 1.60 2.00 4.03 total 12.10 DECORATIVE STONEMARK LENGTH WIDTH total Area (m²) say MARK LENGTH WIDTH total no. of unit total
Area (m²) MARK LENGTH WIDTH total no. of unit total
wall angle Area-1 9.00 1.00 36.00 36.00 Area-2 1.75 5.00 17.50 18.00 Area-3 9.50 2.00 38.00 18.00 Area-4 9.50 1.00 19.00 19.00 Area-5 9.00 0.60 10.80 11.00 total 102.00 25.50 ALUM. CLADDING wall angle Area-1 1.50 16.00 48.00 48.00 Area-2 1.50 14.00 42.00 42.00 Area-3 7.00 4.00 28.00 28.00 total 118.00
Quantity of cement and sand for plaster per square meter area
Mixture
class
8 mm
12mm
A
0.144 0.216B
0.096 0.144C
0.072 0.108D
0.06 0.09Sand
0.008 0.012 1,855.51 11.67 12.00 204.00 70.00 11.67 12.00 192.00 65.10 11.67 12.00 96.00 29.75 8.33 9.00 108.00 600.00 33.75 16.67 17.00 391.00 391.00 33.75 16.67 17.00 391.00 391.00 33.75 782.00 7.33 8.00 376.00 30.80 58.23 7.33 8.00 272.00 22.00 7.33 8.00 128.00 10.12 7.33 8.00 136.00 912.00 11.00 11.67 12.00 204.00 70.00 16.67 17.00 119.00 40.00 11.67 12.00 192.00 65.10 11.67 12.00 192.00 65.10 83.33 84.00 420.00 150.00 11.67 12.00 108.00 36.05 10.00 10.00 40.00 12.00 7.00 7.00 119.00 42.00 10.00 10.00 110.00 37.20 10.00 10.00 100.00 36.00say total no. of pcs. total no. of pcs. total area (m²) (width) no. of pcs.
Cement in bags Thickness of Plaster
8.33 9.00 36.00 10.00 7.50 8.00 96.00 31.50 7.50 8.00 56.00 1,792.00 16.65 11.67 12.00 168.00 56.00 168.00 13.50 11.67 12.00 168.00 56.00 182.00 168.00 #REF! 13.50 #REF! 56.00 13.50 69.50
42.50
14.76
15.002.40
0.83
1.0044.90
16.00 pcs 21.25 22.00 44.00 21.25
12.50
265.63
270.00 1.20 2.00 4.00 3.005.00
15.00
20.00 48.00 pcs 290.00 pcs 15.0015.00
42.50
8.00
42.50
8.00
3rd coating gal say unit
say total no. of pcs. total area (m²) no. of pcs. say (width) no. of pcs.
say total no. of pcs. total area (m²) no. of pcs. say (width) no. of pcs.
say total no. of pcs. no. of pcs. say furring clip (width) no. of pcs.
say total no. of pcs. total area (m²) no. of pcs. say (width) no. of pcs.
9.15 4.00 0.90 1.00 tin 4.00 - 4.00 gal 1.00 lits 20.00 pcs 5,716.80 114.34 2.00 pcs 5.00 pcs 5.00 kg
1
Acrylic semi-gloss latext paint finish, boysen white
3rd coating gal say unit
4.00 3.70 4.00 tin 39.50 4.00 9.87 10.00 tin 4.00 lits 80.00 pcs 5,716.80 114.34 5.00 pcs 12.00 pcs 10.00 kg
1
Acrylic semi-gloss latext paint finish, boysen white
2
Flat latex paint boysen white
3
Flat wall enamel paint
3rd coating gal/tin say unit
4
Q.D.E. Paint Boysen
1.44
2.00 gal 5
Masonry putty
1.00
gal
6
Easytite w/ Hardiner
1.00
gal
7
Perlite (patching compound)
0.50 lits
8
Stikwel
20.00 pcs9
Sand paper
pcs10
Paint Rower
4.00 pcs11
Paint Brush
2.00 kg12
Paint Thinner
13
Consumable like tinting colors
3rd coating gal/tin say unit
17.94 4.00 4.48 5.00 tin gal 5.00 gal 2.00 lits pcs 4.00 pcs 10.00 pcs 5.00 kg
3rd coating gal say unit 4.00 13.67 14.00 tin 15.00 128.48 4.00 32.12 35.00 tin 37.00 9.00 lits 2.00 sacks 200.00 pcs 8.00 pcs 15.00 pcs 10.00 kg
3rd coating gal say unit
4.00 0.47 1.00 gal 4.46 4.00 1.11 2.00 gal 10.00 lits 10.00 pcs 1.00 pcs 2.00 pcs 3.00 kg m² unit say say
917.40 811.80 224.40 26.00 6.80 1,953.60 7.00 m² m² #REF! #REF! #REF! 66.00 6.67 7.00 119.00 40.00 8.67 9.00 81.00 26.00 7.00 7.00 84.00 29.40 13.33 14.00 280.00 96.00 191.40 sq.m 5.00 5.00 30.00 2.40 sq.m 9.44 sq.m 5.00 5.00 30.00 2.40 sq.m 11.84 22.00 sq.m 66.00 12.00 96.00 108.00
say total no. of pcs. total no. of pcs. total area (m²) (width) no. of pcs. AREA (m²) unit
65.25 65.25 sq.m 22.00 sq.m 61.88 66.00 127.88 sq.m 64.00 32.00 32.00 32.00 160.00 sq.m 4.83 5.00 25.00 2.18 sq.m 9.44 sq.m 11.62 sq.m
Quantity of cement and sand for plaster per square meter area
Mixture
class
8 mm
12mm
A
0.144 0.216B
0.096 0.144C
0.072 0.108D
0.06 0.09Sand
0.008 0.01274.80
131.23
132.0041.40
72.63
73.0064.00
112.28
113.0026.00
45.61
46.0040.00
70.18
71.00246.20
435.00
24.00
8.33
9.00 say (width) no. of pcs. say total no. of pcs. total area (m²) no. of pcs.24.00
8.33
9.00 pcs 560.00 560.00 pcs 560.00 3,500.00 907.00 560.00 pcs pcs pcs 4.00 pcs 75.00 240.00 pcs 0.50 kgs3rd coating gal say unit
4.00 0.20 2.00 gal 1.80 4.00 0.45 4.00 gal 4.00 gal 2.00 lits 30.00 pcs 5,716.80 114.34 2.00 pcs 5.00 pcs 5.00 kg
1
Acrylic semi-gloss latext paint finish, boysen white
2
Flat latex paint boysen white
3
Flat wall enamel paint
3rd coating gal/tin say unit
4
Q.D.E. Paint Boysen
#REF! 4.00 #REF! 3.00 tin 5
Masonry putty
4.00
gal
6
Easytite w/ Hardiner
4.00
gal
7
Perlite (patching compound)
1.00 lits
8
Stikwel
50.00 pcs9
Sand paper
pcs10
Paint Rower
8.00 pcs11
Paint Brush
10.00 kg12
Paint Thinner
13
Consumable like tinting colors
unittotal no. of
3rd coating gal/tin say unit 7.42 4.00 1.86 8.00 gal 3.00 gal 5.00 gal lits pcs pcs 5.00 pcs 5.00 kg
3rd coating gal say unit
4.00
#REF! 10.00 tin #REF! 4.00 #REF! 22.00 tin
6.00 lits 330.00 pcs 15.00 pcs 20.00 pcs 20.00 kg unit say say
m² 917.40 811.80 224.40 26.00 6.80 1,953.60 7.00 m² unit
Quantity of cement and sand for plaster per square meter area
16mm
20mm
25mm
0.288 0.36 0.45 0.192 0.24 0.3 0.144 0.18 0.225 0.12 0.15 0.188 0.016 0.02 0.025 59.00 3.67 4.00 472.00Acrylic semi-gloss latext paint finish, boysen white
Acrylic semi-gloss latext paint finish, boysen white
gals
10.00
5.00 50.00Flat latex paint boysen white
gals
6.00
5.00 30.00Flat wall enamel paint
gals
2.00
5.00 10.00Q.D.E. Paint Boysen
gals
1.00
5.00 5.00Masonry putty
gals
1.00
5.00 5.00Easytite w/ Hardiner
ltrs
2.00
5.00 10.00Perlite (patching compound)
ltrs
10.00
5.00 50.00lits
1.00
5.00 5.00Sand paper
pcs
150.00
5.00 750.00Paint Rower
pcs
2.00
5.00 10.00Paint Brush
pcs
5.00
5.00 25.00Paint Thinner
gals
2.00
5.00 10.00Quantity of cement and sand for plaster per square meter area
16mm
20mm
25mm
0.288 0.36 0.45 0.192 0.24 0.3 0.144 0.18 0.225 0.12 0.15 0.188 0.016 0.02 0.025Acrylic semi-gloss latext paint finish, boysen white
gals
10.00
5.00 50.00Flat latex paint boysen white
gals
6.00
5.00 30.00Flat wall enamel paint
gals
2.00
5.00 10.00Q.D.E. Paint Boysen
gals
1.00
5.00 5.00Masonry putty
gals
1.00
5.00 5.00Easytite w/ Hardiner
ltrs
2.00
5.00 10.00Perlite (patching compound)
ltrs
10.00
5.00 50.00lits
1.00
5.00 5.00Sand paper
pcs
150.00
5.00 750.00Paint Rower
pcs
2.00
5.00 10.00Paint Brush
pcs
5.00
5.00 25.00Paint Thinner
gals
2.00
5.00 10.00CONCRETE WORKS F-1 1.50 1.50 0.30 6.00 4.05 4.05 FTB 5.00 0.25 0.30 3.00 1.13 4.00 0.25 0.30 4.00 1.20 2.33 GB 5.00 0.20 0.25 3.00 0.75 4.00 0.20 0.25 4.00 0.80 1.55 C-1 0.30 0.30 8.30 2.00 1.49 C-2 0.30 0.30 8.45 2.00 1.52 C-1 0.30 0.30 8.61 2.00 1.55 4.56 B-1 5.00 0.25 0.35 2.00 0.88 4.00 0.25 0.35 4.00 1.40 B-2 5.00 0.30 0.40 1.00 0.60 B-3 5.00 0.25 0.30 1.00 0.38 B-4 2.12 0.20 0.25 1.00 0.11 3.36 LB-1 2.00 0.20 0.30 1.00 0.12 0.12 CB-1 1.20 0.20 0.30 2.00 0.14 0.14 RB-1 5.00 0.20 0.25 2.00 0.50 4.00 0.20 0.25 4.00 0.80 RB-2 5.00 0.25 0.30 1.00 0.38 RB-3 5.00 0.15 0.25 1.00 0.19 RB-4 2.12 0.15 0.20 1.00 0.06 1.93 LB-2 2.00 0.15 0.25 1.00 0.08 0.08 CB-2 1.20 0.15 0.25 2.00 0.09 0.09 SLAB ON FILL 8.00 5.00 0.10 1.00 4.00 1.20 2.00 0.10 1.00 0.24 4.24 SUSPENDED SLAB 5.00 4.00 0.10 1.00 2.00 5.00 1.88 0.10 1.00 0.94 2.12 2.00 0.10 1.00 0.42 1.20 2.00 0.10 1.00 0.24 3.60 STAIRS 3.20 2.13 0.13 1.00 0.85 1.20 9.00 0.10 1.00 1.08 1.93 Total 27.98 30.22 say MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR STRUCTURE TOTAL VOLUME (m³) LENGTH (m.) WIDTH (m.) HEIGHT (m.)
36.45 2.03 4.05 37.00 2.50 5.00 20.93 1.16 2.33 21.00 1.50 3.00 13.95 0.78 1.55 14.00 1.00 2.00 41.08 2.28 4.56 42.00 2.50 5.00 30.20 1.68 3.36 31.00 2.00 4.00 1.08 0.06 0.12 2.00 0.10 0.20 1.30 0.07 0.14 2.00 0.10 0.20 17.33 0.96 1.93 18.00 1.00 2.00 0.68 0.04 0.08 1.00 0.05 0.10 0.81 0.05 0.09 1.00 0.05 0.10 38.16 2.12 4.24 39.00 2.50 5.00 32.44 1.80 3.60 17.39 0.97 1.93 39.00 2.50 5.00 302.15 15.11 30.22 303.00 16.00 32.00 351.00