• No results found

Scada Siemens

N/A
N/A
Protected

Academic year: 2021

Share "Scada Siemens"

Copied!
308
0
0

Loading.... (view fulltext now)

Full text

(1)

Distribution Network

Automation & Control

Seminar

Jan 29/30, 2008

Tehran/Iran

(2)

Seminar

Substation Substation Substation

Outstation Outstation Outstation Outstation Outstation Outstation Outstation Outstation Control Center

ƒ

Strategies for distribution automation

ƒ

Control in substations and outstations

ƒ

Communication

ƒ

Process optimization in the Control

(3)

Seminar Contents (I)

Section 6: Distribution automation standards

Section 5: Selection criteria for hardware, software and communications

Section 4: Which parameters should be measured or controlled ? Section 3: Selection of substations to work under automation –

automation layout

Section 2: Impacts on planning of distribution automation Section 1: Goal, task and aspects of distribution automation

(4)

Seminar Contents (II)

Section 7: SCADA functionalities

Section 8: DMS functionalities

Section 9: Case study presentation

Section 11: Maintenance and support procedures

Section 10: Distribution system automation personnel skills

(5)

Seminar Contents (I)

Section 6: Distribution automation standards

Section 5: Selection criteria for hardware, software and communications

Section 4: Which parameters should be measured or controlled ? Section 3: Selection of substations to work under automation –

automation layout

Section 2: Impacts on planning of distribution automation

Section 1: Goal, task and aspects of distribution automation

(6)

Mission of the Electricity Supply System

The primary aim of an electricity supply system is to meet the

customer’s demands for energy (in sufficient quantity and quality, at the required time and at an acceptable price)

Similarity to other goods consumption processes, the Electricity Business comprises 4 basics components

„ Demand

„ Production (Generation)

„ (Sub-)Transmission

(7)

Requirements to the Distribution System

Supplier’s View

„ high efficiency with low losses

„ few assets

„ easy service

„ less maintenance

„ fast fault detection

Customer’s View

„ high availability

„ no faults

„ high power quality

„ low price

(8)

Customer Requirements and Supply Standards

Availability

„ no interrupts i.e. continuity of supply

Power Quality

„ Voltage

„ Frequency

„ Harmonics

„ Transients

Definitions of supply reliability are quite different

„ therefore statistic values can not be compared exactly

„ most countries count outages longer than 3 minutes, some define a 1 minute limit (Great Britain, Portugal)

„ Continuity indicators are calculated in a different way

„ Weighted by the number of customer

„ Weighted by the power affected (Spain, Portugal)

(9)

Power Quality Standards

Voltage in Europe

„According IEC 61000

Voltage in the USA : the American National Standard Institute (ANSI) defines "Voltage Range " as:

„ 120/240V ±5% at the user's service entrance, and

„ 120/240V ±8,33% at the point of utilisation.

Frequency

„ The vast majority of equipment appliances are not much sensitive to variation of frequency. Furthermore, in interconnected networks (e.g. UCPTE,..) the

frequency (50 Hz or 60 Hz) is generally very stable and secondly source of problems.

Quality

(10)

Power Interrupt Statistic in Europe

Length of power interrupts in minutes per year (1999) in some countries

15 25 57 63 152 180 191 157 364 0 50 100 150 200 250 300 350 400

GER NLD FRA GBR SWE NOR ITA SPA POR

Country T im e [m in ]

Customer-weighted indicators Power-weighted

(11)

Domestic $ 0.15 / kW + $ 0.30 / kWh Agricultur e $ 0.75 / kW + $ 2.50 / kW h Large Ind ustry $ 2.70 / kW + $ 3.00 / kWh Small Indu stry $ 1.35 / kW + $ 5 .25 / k Wh Trad e & Serv ices $ 1.9 5 / k W + $ 9 .60 / kW h Customer’s Cost for an Unexpected Outage [ $ per Interrupted kW ] Outage’s Duration

Swedish nationwide survey for unexpected outages, 1993

Social Cost for Unplanned Outage

1 2 3 4 5 6 7

(12)

Transmission 33 - 420 kV 27% Distribution 1-22 kV 73% Distribution 1-22 kV Transmission 33 - 420 kV

Energy not Supplied due to Fault Outages

(13)

Why to Improve the Distribution System

The transmission and the sub-transmission system have already high reliability

Therefore:

„ Distribution Automation has the best ratio Improvement to Invest

Strategies to optimize the distribution system

„ n-1 strategies are very expensive

„ structure of the system can not be changed easily

But even with rather cheap measures one can reduce the outage times dramatically

(14)

Maintenance Erection Commissioning Assembly Design Equipment 5% 10% 25% 10% 40% 10% 10kV Overhead Line Diminishing Returns ∆C1 = ∆C2 ∆Rel1 >> ∆Rel2 ∆C1 ∆Rel1 ∆C2 ∆Rel2 0 0.2 1.0 0.4 0.6 0.8 Investment [C] Re lia bility [ R e l]

Reliability vs Investment Cost

(15)

Costs

Supply Quality vs. Cost:

A Macro Economic Consideration

Cost for Interrupts

(Less Sold, Penalties)

Cost

for Invest and Maintenance

Macro Economic Costs

Limits

(16)

What is ‘Distribution Automation’

There is no fixed definition of the term.

Definition from EPRI 2004: The objective of (Advanced) Distribution Automation Function is to enhance

„ the reliability of power system service,

„ power quality, and

„ power system efficiency,

by automating the following three processes of distribution operation control:

„ data preparation in near-real-time;

„ optimal decision-making; and

„ the control of distribution operations in coordination with transmission and generation systems (Note: Distributed Energy Resources !) operations

Others (e.g. CIRED AD HOC Working Group 2 ) add topics such as ‚establish closer and more responsive relationship with customers‘.

(17)

“ Improved automated workflow of the Operation and Planning Department ”

( North York Hydro )

“ Improved supply quality and minimising of not sold kWh “ (CIRED 1987)

“ Improved efficiency and quality of service, more rational use of energy “ (ENEL)

(18)

Customer Interface, Management

& Control

Loads and Meters Readings Control Customer Trouble Information Billing & Settlement

Distribution Automation

Main Function Sets

Network Operation Operational Planning, Optimization Data Management Operation Statistics and Reporting Fault Management Power Import Scheduling and Optimization Network Operation Monitoring Network Operation Simulation Technical Data Management Network Control Switching Actions Scheduling Dynamic Data Management

Source: CIRED Ad Hoc Working Group 2

Geographical Displays Management Information System Maintenance Management Operation Feedback Analysis Maintenance Works Scheduling and Control

(19)

Benefits in Network Operation (I)

Improving the quality of service

„Data acquisition, monitoring and remote control also at remote sites allows responding to alert and emergency conditions quickly and confidently and with the correct action, e.g.

„ low voltage

„ unbalanced flows

„ low power factor

„ overload

„Less and shorter outages lead to increased revenue

Better network supervision means less equipment failure

„Equipment lifetime is lengthened

(20)

Increased safety and security

„Operation of any electrically controllable device can be securely inhibited at the SCADA master station

„Remote outstations can be monitored for intrusion

Reduction of staff in remote outstations

Power Quality Calculations (Power Auditing)

„the open market imposes penalties for quality of service not compliant with minimum characteristics.

Energy and Power Balances

„some utilities have high amount of energy losses. The first step for

correcting this problem is to determine where losses larger than normal are located, this includes both technical and non-technical losses

(21)

Improve Quality of Service

„SPM: Operator always has a clear picture about the current status and further planned steps of each switching sequence – faster switching at lower risk

„Floc / FISR: Shorten interruption time by automatically identifying candidate switching actions for

„isolation of faults

„restoration of supply

„switching back to normal

„DSPF: Detection of Limit Violations that would occur after planned

switching actions – avoiding overloads and accidental customer supply interruptions

Improve Efficiency of Network Operation

„VVC/OFR: Keep the system at the minimum of technical losses thus reducing cost

Fichtner Consulting estimates reduction of losses gained from

Fichtner Consulting estimates reduction of losses gained from

Benefits in Network Operation (III)

(22)

Customer Interface, Management

& Control

Loads and Meters Readings Control Customer Trouble Information Billing & Settlement

Distribution Automation

Main Function Sets

Network Operation Operational Planning, Optimization Data Management Operation Statistics and Reporting Fault Management Power Import Scheduling and Optimization Network Operation Monitoring Network Operation Simulation Technical Data Management Network Control Switching Actions Scheduling Dynamic Data Management

Source: CIRED Ad Hoc Working Group 2

Geographical Displays Management Information System Maintenance Management Operation Feedback Analysis Maintenance Works Scheduling and Control

(23)

Benefits from Automatic Meter Reading (AMR) Systems

„Loss identification Æ Loss reduction Æ Revenue enhancement „Operational Efficiency and Asset Utilization

„Monitor energy balance & peak demand reduction

„Faster response time to customers

„Earn from innovative services to consumers e.g.

„Load profile via web access

„Security services e.g. door control

„By using the AMR infrastructure

(24)

Customer Interface, Management

& Control

Loads and Meters Readings Control Customer Trouble Information Billing & Settlement

Distribution Automation

Main Function Sets

Network Operation Operational Planning, Optimization Data Management Operation Statistics and Reporting Fault Management Power Import Scheduling and Optimization Network Operation Monitoring Network Operation Simulation Technical Data Management Network Control Switching Actions Scheduling Dynamic Data Management

Source: CIRED Ad Hoc Working Group 2

Geographical Displays Management Information System Maintenance Management Operation Feedback Analysis Maintenance Works Scheduling and Control

(25)

Benefits from Real Time Energy Management System

(RTEMS)

„Integration of meter-to-bill processes and systems

¾Improve cash flow, and system reliability

„Consolidation of customer data and meter data repositories

¾Improve trust and reduce cost

„Allowing web-based display and usage of energy demand and consumption information at the consumer‘s site

¾Reduce cost, improve customer retention / satisfaction and quality

„Enabling real time monitoring of power quality information and automated response to energy distribution events

(26)

Customer Interface, Management

& Control

Loads and Meters Readings Control Customer Trouble Information Billing & Settlement

Distribution Automation

Main Function Sets

Network Operation Operational Planning, Optimization Data Management Operation Statistics and Reporting Fault Management Power Import Scheduling and Optimization Network Operation Monitoring Network Operation Simulation Technical Data Management Network Control Switching Actions Scheduling Dynamic Data Management

Source: CIRED Ad Hoc Working Group 2

Geographical Displays Management Information System Maintenance Management Operation Feedback Analysis Maintenance Works Scheduling and Control

(27)

Obtain more information from the network for a safer, more reliable and more efficient operation

„extremely useful for cost efficient network planning because information on real equipment loading avoids over-sizing e.g. for installed transformer capacity

„planning of just-in-time maintenance based on actual equipment stress

„generation of logs and reports for after-the-fact system analysis and

management information; everybody can create the reports he/she needs (no software or database knowledge required, only brief handling training)

„Precise, on-time, and comprehensive information increases management awareness of actual situation and increases efficiency of department co-operation

Calculation of Quality of Service Indices for individual distribution

A distribution utility has reported a 100,000 US$/per year saving

because new distribution substations could be better planned - at the right time at the right place.

(28)

Minimization of non-in-time delivered energy

„reduce by 20% the current values (conservative figure)

Network losses minimization

„reduce by 5% the current values (conservative figure)

Improved Operation efficiency

„10% of the Operation’s budget

Improved Image

„equivalent or better market penetration with reduced marketing costs

Improved working conditions and environment

„stable personnel, less recruitment costs (and related training)

Distribution Automation

(29)

Seminar Contents (I)

Section 6: Distribution automation standards

Section 5: Selection criteria for hardware, software and communications

Section 4: Which parameters should be measured or controlled ? Section 3: Selection of substations to work under automation –

automation layout

Section 2: Impacts on planning of distribution automation

Section 1: Goal, task and aspects of distribution automation

(30)

Impacts on planning of distribution automation (I)

The general benefits from distribution automation have been clarified in

Section 1. This has answered the WHY of distribution automation.

The utility‘s priority of goals defines WHAT shall be done i.e. what is

more important to achieve:

„

increasing supply reliability

„

increasing power quality

„

decreasing cost

„

decreasing loss of revenue

„

etc

This priority list will guide the selection of the most suitable program

for distribution automation i.e. what will be done first.

(31)

Impacts on planning of distribution automation (II)

After the utility has answered the strategic WHAT question the next

question is HOW the distribution automation solution shall be

implemented i.e. what are technical / environmental / legal / …

constraints. This concerns issues such as:

„

overhead vs. underground networks

„

availability of communication technology

„

available (inter-)national standards

„

already existing automation / communication infrastructure

„

accessibility of substations

„

current and future importance of substations

(32)

Impacts on planning of distribution automation (III)

Normally there will be several proposals for achieving the ‘WHAT

goals’ considering the ‘HOW constraints’.

Besides the achievement of the strategic WHAT criteria there are

general criteria for selecting the most suitable distribution automation

proposal:

„

flexibility of the distribution automation solution in case of changing

strategic goals of the utility

„

flexibility for adding more services/business in the future

„

expandability of the distribution automation solution in case of

growing system size e.g. due to mergers with other utilities

„

reliability of the distribution automation solution itself

„

investment cost & cost for operation and maintenance of the

(33)

Components of a distribution automation solution (I)

A properly selected distribution automation solution will comprise

answers to the following questions:

„

Which substations should be automated to what extent ?

¾

Remote metering/monitoring

¾

Remote switch control

„

Which data shall be collected from which substation ?

„

Which control centers shall be built/used (centralized/distributed) ?

„

Which redundancy concepts shall be implemented ?

„

Which communication media shall be built/used for which type of

link?

„

Which communication configuration shall be built (point-to-point,

(34)

Components of a distribution automation solution (II)

„

Which software packages are required ?

„

Which interfaces are required ?

¾

to external control centers

¾

to external applications, such as GIS, CRM, etc

„

Which metering, accounting, settlement and billing process shall be

applied ?

(35)

Components of a distribution automation solution (III)

„

What is the capital expenditure for such a system ?

„

Which achievements are expected with regard to the strategic WHAT

goals ?

¾

reduction of outage frequency

¾

reduction of outage duration

¾

cost reduction

¾

etc

„

How can such a system be implemented and maintained ?

„

How can databases be populated and maintained ?

„

How can the implementation be split in several phases for early

benefit achieving ?

„

Which training is needed at what time for operational staff and

(36)

Anticipated Problems with Distribution Automation

#1: Centralized Control System

Apprehension: „Due to the automation of distribution networks the

number of data points and RTU lines to be processed increases

dramatically and thus exceeds the processing capabilities of

centralized systems“

„

large amount of data is not any more limiting the processing

capabilities of modern SCADA/DMS

„

modern process interfaces can handle hundreds of RTU lines,

furthermore there are possibilities for

¾

running several RTU servers in parallel

¾

‚lean‘ RTU interfacing by means of TCP/IP based

protocols

¾

use of modem pools

¾

cascading of RTUs, i.e. small field RTUs talk ‚through‘

(37)

Anticipated Problems with Distribution Automation

#2: Communication

Apprehension: „The automation of distribution networks fails due to

insufficient communication lines.”

„

cascading of RTUs reduces the number of communication lines

needed

„

alternative communication media are available

„

power line carrier over distribution lines

„

mobile phone networks such as GSM, GPRS

(38)

Anticipated Problems with Distribution Automation

#3: Cost

Apprehension: „The automation of the entire distribution network is too

expensive.”

„

in the course of energy market liberalization the pressure for cost

reduction from regulation authorities on distribution companies will

constantly grow and justify ever more investment in distribution

automation

„

cost for energy automation equipment and communication

equipment is decreasing particularly for compact RTUs and dial-up

connections via mobile telephone systems

„

distribution automation does not come as ‚big bang‘; it rather grows

over time closely coordinated with investment / maintenance

programs for substations

(39)

Seminar Contents (I)

Section 6: Distribution automation standards

Section 5: Selection criteria for hardware, software and communications

Section 4: Which parameters should be measured or controlled ?

Section 3: Selection of substations to work under automation automation layout

Section 2: Impacts on planning of distribution automation Section 1: Goal, task and aspects of distribution automation

(40)

The Last Meters: Low Voltage

115 V /125 V Systems

„

Mainly used in USA, Canada, Brasilia, Mexico, Saudi Arabia, Korea,

Philippines

„

typical 60 Hz and

„

requires transformer nearby the consumer

„

main distribution to the end consumer is done by the MV grid

230 V / 400 V Systems

„

Mainly used in Europe

„

typical 50 Hz

„

Ohmic power losses enable distance up to 2 km to the next MV / LV

transformer

(41)

Structure of the Power System in USA

115 V

Transmission National / International Subtransmission Regional Low Voltage Distribution System

(42)

Structure of the Power System in Europe

230 / 400 V

Transmission National / International Subtransmission Regional Low Voltage Distribution System

(43)

Typical sub-transmission/distribution configuration

220KV

220KV/33KV Rec. Stn

33KV

33KV/11KV Rec. Stn.

Compact Distribution Station – Ring Main Units

11KV

X X X

X X

X X X X

(44)

Urban underground MV networks

110/20kV 20/0,4kV 20/0,4kV A B C D S c d Circuit breaker Load-breaking switch Fuse S Isolation point

At a suitable point on the network the loop is opened by a sectionalising device S. This may be a circuit breaker, switch, fuse or link. The system then effectively

(45)

Overhead rural MV networks

The figure shows schematically typical arrangements for a rural overhead radial feeder, with some of the manually operated disconnectors omitted for simplicity. It will be noted that each main trunk feeder has a number of lateral spurs.

(46)

Substations of type 1 establish permanent

communication between the control centre and the

distribution substation e.g. by means of optical fibres. Often the fibres of a

secondary communication network are interconnected with a node (receiving

station) of the primary fibre optic ring. Applications such as RTU and AMR use

TCP/IP. IEC 60870-5-104 is recommended for RTU

communication. Of course, other communication media / Battery 24/48V DC Battery charger RTU (IEC…104) Meter

Control & Monitor switch states, Short circuit indicators

CT, VT

motorized 11kV Switchgear Fibre panel 1 (2) *24

8 port Ethernet HUB

FO from R/S, S/S FO to next S/S

Fibre optic to UTP Media Converters

Substation type #1 with permanent data access

(47)

Battery 24/48V DC Battery charger RTU (IEC…101) Dial up Modem (WLL/Fixed wired) Energy Meter

Control & Monitor switch states, Short circuit indicators

CT, VT

motorized 11kV Switchgear

24/48 V DC

Substations of type 2 use switched telephone

communication facilities (fixed wired or mobile

communication) to transfer data on demand. The

demand for data exchange can be initiated by the

control centre or the

distribution substation itself. The control centre needs to control switchgears

remotely, to ask for data update or just to test the connection. The substation need to call in the control centre if there is some

urgent data to transfer, for example a fault indication

Substation type #2 with temporary data access

(48)

Steps of Distribution Automation

Step 0: Centralization of distribution system operation

„

centralized distribution system operation is less costly

„

centralized distribution system operation reduces time to restore

supply after disturbances

„

existing mixed structures of local and centralized operation often

have grown over time but do not have justification as of today

„

mixed structures in case of disturbances, i.e. local operation only

(49)

Steps of Distribution Automation

Step 1a: Automation of feeder heads in HV/MV substations

„in case of a new HV/MV substation the whole scope of automation shall be built in:

„ remote signaling of all switching element statuses

„ remote control of circuit breakers

„ digital protection devices provide analog measurements in normal operation and fault operation

„in case of retrofitting HV/MV substations the following priority applies

„ must: fault information from protection equipment per field

„ optional: remote control of circuit breakers

analog measurements of feeder currents

„ nice-to-have: more switching status information (isolator, earthing switch, ...)

(50)

Steps of Distribution Automation

Step 1b: Automation of major switching substations

Major switching substation:

„

three (3) outgoing feeders or more

„

circuit breaker and protection

In case of a new switching substation the whole scope of

automation shall be built in (see Step 1a)

In case of retrofitting switching substations the same priorities apply

as in Step 1a.

(51)

Steps of Distribution Automation

Step 1c: Remote signaling of selected fault current sensors

With this step the utility has reached the level of

automated centralized fault location:

„

evaluation of topology information

„

evaluation of fault impedances

„

evaluation of fault current sensor information

(52)

Steps of Distribution Automation

Step 2a: Automation of selected MV/LV substations

Selected MV/LV substations:

„

‘normally open’ section point

„

midway of long feeders

Remote control of load switches

(53)

Steps of Distribution Automation

Step 2b: Automation of selected customer substations

Selected customer substations:

„

high-volume consumer

„

high-sensitive consumer

„

remote signaling of fault information

„

remote switching

„

remote signaling of analog measurements

This enables new business opportunities for providing high-quality

power supply services to those customers.

(54)

Selection of distribution substations for automation

For the selection of distribution substations for automation two main

questions have to be answered:

„

(A) What is the most reasonable and beneficial

rate of automation for distribution substations?

„

(B) Which dedicated distribution substations shall be automated ?

The goal of distribution substation automation is basically to reduce the

average interruption time of energy supply in the distribution network.

In case of a feeder trip the SCADA/DMS operators get fault indication

from automated distribution substations.

Within a short time a part of the affected consumers can be re-supplied

by reconfiguring the distribution network by remote control actions from

the SCADA/DMS. DMS applications will support the operator in

(55)

Selection of distribution substations for automation

Question (A): Automation Rate (I)

A fault on a cable section causes the feeder to trip. Two

distribution substations will send fault

indications and fault-direction to the control centre. Based on this information the operator can re-supply ~ 50% of the affected consumers by performing switching actions 2 - 5. This can be done within a time period of 3 minutes.

Normally open point

1. trip 2. open 4. open 5. close 650 feeders 4099 distribution substations D6,5 substations / feeder 2,2 million consumers D537 consumers / substation R/S feeder R/S feeder Fault indicator Automated substation 3. close

About 50% of the affected customers re-supplied after 3 minutes.

Automation rate assumed to be 25%.

(56)

Selection of distribution substations for automation

Question (A): Automation Rate (II)

Compared to non-automation, the

restoration crew can work faster since the area of intervention is only a part of the feeder. Fault

isolation and service restoration are done by conventional methods. The crew on site can be supported by the

operators in the control centre. Average

conventional restoration time is estimated to be reduced by 50 % (40 minutes Î 20 minutes).

Remaining 50% of the affected customers re-supplied after 20 minutes.

R/S feeder R/S feeder

Fault indicator Automated substation

(57)

Selection of distribution substations for automation

Question (A): Automation Rate (III)

As result of this scenario the service restoration time will be reduced from approximately 40 minutes to approximately 11 Minutes.

50 % of consumers are re-supplied after 3 minutes 50 % of consumers are re-supplied after 20 minutes

=> average interruption time ~11 minutes

This kind of estimation of outage time reduction can be repeated for other values of the automation rate.

The diagram on the next page indicates the average interruption time as function of the number of automated substations (magenta) taken from a study case. Relevant study case data are given on the following page.

The blue curve is representing the Net Present Value (cost/benefit ratio). The costs are based on the substation adaptation investments, the benefits are calculated from more energy sold due to reduced average interruption time.

(58)

„

Detailed Case Study on

Cost-Benefit-Analysis of Distribution Automation with

different Automation Rates in Section 9.

Selection of distribution substations for automation

Question (A): Automation Rate (IV)

(59)

Selection of distribution substations for automation (VI)

Question (B): Selection of Substations

The selection of dedicated substations for automation does not follow a strict and simple algorithm. It is rather guided by fuzzy criteria on two levels:

„ Feeder level

Such feeders will be preferred that have

¾ higher load density

¾ higher fault density than others

„ Substation level

Obviously the substation with ‚normal open points‘ will be automated first on a selected feeder.

As regards other substations, the leading criterion is the load that can be affected i.e. those substations will be preferred that have

¾large industrial consumers connected

¾spur lines with high load connected

Finally, the time needed for manual switching plays a role i.e. those substations will be preferred that have

(60)

Seminar Contents (I)

Section 6: Distribution automation standards

Section 5: Selection criteria for hardware, software and communications

Section 4: Which parameters should be measured or controlled ?

Section 3: Selection of substations to work under automation – automation layout

Section 2: Impacts on planning of distribution automation Section 1: Goal, task and aspects of distribution automation

(61)

Data to be collected from HV/MV Substations

„

Active Power, Reactive Power, Voltages, Currents from all

¾

incoming feeders

¾

outgoing feeders

¾

capacitor banks

¾

etc

„

Switch Positions of the

¾

Isolators (Single Pole)

¾

Circuit Breakers (Double Pole)

„

Indications of other auxiliary devices such as UPS, Battery

system, Chargers, Communication Devices etc.

„

Status from the protection devices

(62)

Data to be collected from Distribution S/S

Alarm Charger failure

Alarm Power supply failure

Battery System

Alarm Fault current sensors

Alarm Phase-to-ground short circuit

Alarm Phase-to-phase short circuit

Protection (each feeder)

Measured Value I / P / Q / V Analogs (Command) Status Load switches Command Status Circuit breakers Switches

Output from SCADA Input to SCADA

(63)

Step 2:

Line/cable segment engineering data Typical load curves for

load transformers 220 kV bus 33 kV bus 33 kV bus 11 kV bus M M M M

Data to be collected for distribution automation

Step 0: SCADA data model Step 0: SCADA data model Receiving Substation Bulk supply Substation

1. Extend by SCADA data model of distribution feeders (topology, switches) Î enabling Operation Applications (Section 8)

2. Extend by engineering data of line/cable segments and load models Î enabling Distribution Network Applications (Section 8)

Step 1: Extended SCADA Data Model M M M M Step 3: Measurements from distribution automation

(64)

I> (t)

t dt

pick-up time dt

selectable: 40 oder 80 ms

enveloping of failure current

IS1 selected pick-up current

criterion Is1 and dt fullfilled -> indication is activated

Integrative measurement avoids erroneous indication!

Red signal curves must not activate the indicator

Short-circuits and earth-faults indicators

For effective failure detection and

location short-circuits and earth-faults must be observed. Combined short-circuit and earth-fault indicators are most economical. Indicators can be installed on outgoing feeders of RMUs. The fault detection facility generates alarms in case of high current peaks. However, the facility shall prevent faulty indications due to magnetizing-inrush currents, other transient and no-fault conditions.

(65)

Knotenpunktstation nodal point substation

I>> Ie RMU RMU I>> Ie RMU RMU RMU RMU RMU Umspannwerk Power substation I>> Ie I>> Ie I>> Ie I>> Ie I>> Ie I>> Ie I>>Ie

Fault detection in low resistance terminated

networks by means of short-circuit indicators

(66)

Typical Repairing of Permanent Faults

„

Protection has tripped circuit breaker CB

„

Transient fault? Automatic recovery?

„

Localize fault

¾

phone calls, relay data, Remote Terminal Units (RTU),

visually

„

Open isolator and ground equipment

„

Restore supply as much as possible

„

Do nessesary repair work

„

Fault removed, line repaired

„

Remove grounding and close isolator or replace fuse

(67)

Urban vs. Rural Regions

Urban

ƒ

underground cables with less external faults

Rural

ƒ

a lot of overhead lines

ƒ

intermediate short circuits

ƒ

birds

ƒ

trees

ƒ

wind

(68)

Distribution Automation

in Urban Areas

Example for

(69)

OC OC

FI

Typical open ring configuration

OC: over current protection FI: fault indicator

(70)
(71)

-Q0 1 -A5 1 3 -T1 -T5 -Q0 1 -A5 1 3 -T1 -T5 -Q0 1 -A5 1 -F1 Ring Unit 1 Ring Unit 2 Feeder to LV trans-M M M Double indications:

Ring unit 1 isolator On/OFF Earth switch 1 On/OFF Ring unit 2 isolator On/OFF Earth switch 2 On/OFF

Feeder On/OFF

Earth switch Feeder On/OFF

Single indications:

Short circuit indicator RK1 Short circuit indicator RK2 Fuse blown

Grouped Indication Auxiliary power failure Transformer temperature alarm

Remote control off UPS failure

Station open

Meters (optional):

Meter feeder

Double commands:

Ring unit 1 isolator On/OFF Ring unit 2 isolator On/OFF Feeder On/OFF

Analogs (optional):

Ring unit 1 Current Phase L2 Ring unit 1 Voltage L2-N Ring unit 2 Current Phase L2 Ring unit 2 Voltage L2-N

Typical mini RTU solutions

Ring main unit with one feeder

(72)

Automation in a MV Ring (1)

Example of network configuration. The network is divided into four sections. In the example is there a fault between SB21 and SB22.

A central control unit is placed with the circuit breakers (E1,E2). The circuit breakers could be taken in and out from the central control unit.

Decentral control units are placed with the line switches in each section (SB11,SB-R,SB21 and SB22) .These units get information from a voltage

sensing system and control each line switch. In a ring configuration it is a must to have a voltage sensing system on both sides of the line switch.

20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(73)

Automation in a MV Ring (2)

With a fault in the network configuration, the protection relay will take the circuit breaker (E2) out. The central control unit will try to put the circuit breaker in, but in a faulty network configuration the protection relay will take out the circuit

breaker again. 20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(74)

Automation in a MV Ring (3)

This procedure indicates to all units (SB21,SB22 and SB-R) that the network configuration is faulty, and the automatic sectioning starts.

All decentral control units (SB21 and SB22) take out the line switches .

20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(75)

Automation in a MV Ring (4)

The central control unit closes the circuit breaker after 20 seconds, to test the first part of the network configuration .

20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(76)

Automation in a MV Ring (5)

After 40 seconds the decentral control unit (SB21) closes the line switch.

20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(77)

Automation in a MV Ring (6)

Because this part of the configuration (SB21 – SB22) is faulty, the central unit will take out the circuit breaker. The decentral control unit (SB21) discovers that the voltage only was in for a short time, and then takes out the line switch and locks it. 20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(78)

Automation in a MV Ring (7)

The decentral control unit (SB22) discovers that the voltage was in only for a short time, and because of the voltage sensing system of both sides of the switch, the unit knows that the fault is between SB21 and SB22. The decentral control unit (SB22) will then lock the line switch.

20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(79)

Automation in a MV Ring (8)

The decentral control unit (SB-R) have detect the start of the automatic sectioning.

The decentral control unit (SB-R) has not detected any voltage on the side SB-R – SB22. After a time (60 seconds) the unit knows that the fault is between SB21 and SB 22, and the line switch (SB-R) is closed.

Now at this time the part between SB21 and SB22 (the faulty) is disconnected

20 0 40 60 [sec] E1 E2 SB11 SB21 SB22 SB-R

(80)

Distribution Automation

in Rural Areas

(81)

Sectionalizing in Overhead Lines

Sectionalizer enable a system for automatic sectioning in a

network configuration. Automatic sectioning is based on

switching on and out line switches and circuit breaker in a

controlled sequence to find errors in the network. When the

errors are found, the system will take out the faulty part of the

configuration.

(82)

Sectionalizing in Overhead Lines

Example of network configuration.

The network is divided into six sections (S1 – S6)

Circuit breaker Load-breaking

switch Power Transformer Voltage sensing system E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(83)

Sectionalizer (1)

With at fault in the network configuration, the protection relay will take out the circuit breaker. 20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(84)

Sectionalizer (2)

The central control unit (E1) will try to put the circuit breaker in but in a faulty network configuration. 20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(85)

Sectionalizer (3)

The protection relay will take out the circuit breaker again.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(86)

Sectionalizer (4)

This procedure indicates to all units (E1 and L1 .. L5) that the network configuration is faulty, and the automatic sectioning starts.

The automatic sectioning starts at relative time 0 seconds.

All decentral control units (L1 .. L5) take out the line switches

.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(87)

Sectionalizer (5)

The central control unit closes the circuit breaker after 20 seconds, to test the first part of the network configuration (S1).

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(88)

Sectionalizer (6)

After 40 seconds the decentral control unit (L1) closes the line switch.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(89)

Sectionalizer (7)

Because this part of the configuration (S2) is faulty, the central unit (E1) will take out the circuit breaker.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(90)

Sectionalizer (8)

The decentral control unit (L1) discovers that the voltage only was in for a short time, and then takes out the line switch and locks it. At this time the section S2 (the faulty) is disconnected from the healthy part of the network configuration.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(91)

Sectionalizer (9)

After 60 seconds the central unit (E1) closes the circuit breaker.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(92)

Sectionalizer (10)

The decentral control unit (L2) closes the line switch in due to the voltage sensing system. 20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(93)

Sectionalizer (11)

After 80 seconds the decentral unit (L3) close the line switch in due to the voltage sensing system.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(94)

Sectionalizer (12)

After 100 seconds the decentral unit (L4) close the line switch in due to the voltage sensing system.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(95)

Sectionalizer (13)

Because this part of the configuration (S4) is faulty, the central unit (E1) will take out the circuit breaker.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(96)

Sectionalizer (14)

The decentral control unit (L4) discovers that the voltage only was in for a short time, and then takes out the line switch and locks it. At this time the section S4 (the faulty) is disconnected from the healthy part of the network configuration.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(97)

Sectionalizer (15)

After 120 seconds the central unit closes the circuit breaker and the automatic sectioning is finished. The decentral control unit (L5) could be designed to close the line switch after 120 seconds.

20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(98)

Sectionalizer (16)

The central control unit sets outputs (lamps) for each section (S1 – S6) which is faulty.

It is also possible to send this information to a network control system via IEC 6870-5-101 protocol, or/and send SMS messages.

See next page 20 40 0 60 80 100 120 140 [sec] E1 L1 L2 L4 L5 S2: 250 kW S3: 375 kW S5: 250 kW S6: 150 kW S1: 500 kW L3 S4: 250 kW e. g. 110/ 20kV

(99)

Sectionalizer: Switch and Control

Line Switch with voltage transformer

Electronic with storage battery, local control and

(100)

Seminar Contents (I)

Section 6: Distribution automation standards

Section 5: Selection criteria for hardware, software and communications

Section 4: Which parameters should be measured or controlled ?

Section 3: Selection of substations to work under automation – automation layout

Section 2: Impacts on planning of distribution automation Section 1: Goal, task and aspects of distribution automation

(101)

Business Services IT Integration ASP Administration Operation E-Commerce Maintenance Field data acquisition,

local control & automation Communication Network control & supervision

(single-or multi-utility)

Added value network management &

optimization

(applications and systems)

Integrated utility business operation xxxx x xxx xxx xx Meters Substation automation Protection Local automation RTUs Power Exchange

$

$

Trader Partner, market, etc. Multi-site SCADA etc. DB Network planning Network information Meter data management

...

Advanced applications (EMS, DMS, EBM, Trading)

Information gateway

...

Asset Management Energy Sales & Care

Enterprise Integration Bus

Data Warehouse MIS

F&A

Gateway

Power Systems Control and Energy Management

Multi-Level Environment

(102)

Optical Fiber

Radio

Copper Cable

Power Line

Public Network

GSM/CDMA –

Network

Communication Media

(103)

Backbone

Network

RTU RTU RTU RTU MV - Line RTU MV - Line

(104)

Control Center

TCI

No. 1

No. Z

MV - Line RTU RTU MUX

Optical Fibre

(105)

Aspects of Network Design

Costs

Reliability

Performance

Regulations

(106)

Communication Selection Criteria

Leased Public Line

„The telephone company provides direct point-to-point connectivity between the RTU location and the control centre. On both end of the communication, a suitable modem appropriate to bandwidth (9600 bauds, 86 Kbps) is required.

„The cost of the communication of this nature comprises the fixed cost to be paid as one-time charges (for Registration fees, Installation fees of the

equipment) and the operational charges (for periodical subscription as well as usage).

„Though this type of communication facility seems to be economical, on a long term it may not turn up to be cost-effective, since one has to pay the

periodical operation charges.

„The other disadvantage is due to frequent failures of the lines, dependence of third party state-owned service provider.

(107)

Communication Selection Criteria

Dial-up Public Line

„Few telephones / modems are provided having dial-up facility at the control centre end, whereas at the RTU / mRTU ends the modems are to be

provided with answering facility.

„For a real-time operation, this kind of communication is not preferred due to the time consuming dial-up and answering process. However, for Automated Meter Reading or for checking the status of reclosers after disturbances dial-up communication can be effectively utilized.

„The cost of the communication of this nature comprise of the fixed cost to be paid as one time Registration fees, Installation fees of the equipment) and the periodical subscription as well as usage charges.

„Disadvantages, however, are the same as indicated above for the ’Leased line communication’.

(108)

Communication Selection Criteria

GSM Mobile Communication

„With the advent of mobile telephony, usage of GSM communication is

becoming quite popular and widely used for data communication. Using GSM modems at the RTU end and the Control Centre end the data exchange can be introduced using urban mobile (GSM) networks.

„While considering the GSM network as a feasible solution one has to be sure that mobile connectivity is available at all the RTU locations.

„GPRS is also an acceptable solution.

„Disadvantages are similar as indicated above for leased line communication. Even more, GSM networks tend to be overloaded during peak hours and

(109)

Communication Selection Criteria

Digital Networks via Fiber Optic

„It is required to lay extensive FO cables connecting primary stations, sub-divisions and the control centre. Such systems, though “The Best” technical option to establish a TCP/IP network, requires considerably high cost.

„In addition to establishing of an extensive FO network, the associated

terminating equipment and multiplexers are required at all the location from where the data is to be collected or to be dropped in.

„Though the solution does not look to be cost effective at first sight due to high initial costs, it may turn out to be cost effective, if the utility makes use of the extra fibers of the FO cable for other communication facility requirements such as voice, Fax, other IT applications.

„With the establishment of an own FO network, the utility has the responsibility for operation and maintenance of the network, but at the same time it has full control of system expansion in case of increasing number of (field-) RTUs.

„Fast wireless Ethernet modems are gradually becoming popular. The Ethernet modems are available in the rated range of 5 miles to 25 miles. Making use of such Ethernet modems together with FO based

communication network as backbone, makes an ideal communication

(110)

Communication Selection Criteria

Radio Communication

„The communication system using radio requires considerably high costs associated with procurement of radio systems, installation of towers and masts for antennas etc.

„However, once installed and put into operation, the communication system has low, annual costs for operations and maintenance. Thus it helps the utility to establish its own communication network.

„It is necessary to obtain the frequency allotment / approval from the wireless agency or the prescribed authority as nominated by the state / govt. In

general, yearly subscription fees for utilizing the frequency are required to be paid.

„Before implementing the solution, a detailed Sight of Line study is required to be carried out for the feasibility of the solution in a particular town / city.

Obstruction make occur due to high rise buildings (also by not yet existing ones !).

(111)

Costs

„

Hardware

„

Commissioning / Installation

„

Base fees

„

Connection fees

„

Excavation work

(112)

0% 200% 400% 600% 800% 1000% 1200% 1400% 1600% 1800% Radio (no t ower) Radio BTC GSM New pilot cable Leas ed lin e (loc al) Leas ed lin e (far ) Dial mode line DCS CDC DCS CDI Transmission method

Telecontrol service (RTU) and remote load profile reading Connection fee

Base fee Assembly/commisioning Hardware cable Hardware equipment 9 km MV line with 4 kiosks Over 5 years 12 polling per day

Invest for assembly and operation

PLC

PLC overoverMedium Medium VoltageVoltage

*) This calculation depends on the regional conditions, the example based on the European / African market.

(113)

Data Transmission with Distribution Line Carrier

(DLC)

(114)

The coupling transformer encloses the earthing strap of the MV cable

Conductor 1 Conductor 2 Conductor 3

Sealing end Earthing strap CDI (ferrite ring) Earthing bar BU

Data Transmission with Distribution Line Carrier

(DLC) - Inductive coupling device

(115)

CDC Conductor 1 Conductor 2 Conductor 3

Bracket or separate supporting bar for CDC Earthing bar

Connecting element

Data Transmission with Distribution Line Carrier

(DLC) - Capacitive coupling device

(116)

„

Communication

„

Multi carrier principle

„

Transmission in the frequency range of

CENELEC

„

Uniform hardware for Master & Slave

„

Transmission rates up to 28.8kbit/s

(depending on the line)

„

Bypass of MV switchgear

„

Simple & complex: MV line, tree or ring

networks

„

Interfaces

„

Telecontrol per IEC 60870-5-101 or DNP 3.0

„

Meters per IEC 61107

„

Medium-voltage line and telecontrol line

Data Transmission with Distribution Line Carrier

(DLC) – Basic Unit

(117)

Pole mounted switch 1 BU Control center Distribution point MV Line V.24 IEC 60870-5-101 MV Line

MV substation automation - field trail

ƒ DLC runs with microRTU and control center by using

IEC communication standard

ƒ Test with out-door CDC coupling units

ƒ Transmission rate 9.6kBd

Pole mounted repeater

BU Master-BU V.24 IEC 60870-5-101 BU V.24 IEC 60870-5-101

Pole mounted switch 2

Data Transmission with Distribution Line Carrier

(DLC) – Sample project: MEA Bangkok/Thailand

(118)

Mounting a BU cabinet on an overhead line pole

Pole mounted cabinet including DCS3000 BU

Fully-installed cabinet, with

DCS 3000 BU and SICAM microRTU

Data Transmission with Distribution Line Carrier

(DLC) – Sample project: MEA Bangkok/Thailand

(119)

Business Services IT Integration ASP Administration Operation E-Commerce Maintenance Field data acquisition,

local control & automation Communication Network control & supervision

(single-or multi-utility)

Added value network management &

optimization

(applications and systems)

Integrated utility business operation xxxx x xxx xxx xx Meters Substation automation Protection Local automation RTUs Power Exchange

$

$

Trader Partner, market, etc. Multi-site SCADA etc. DB Network planning Network information Meter data management

...

Advanced applications (EMS, DMS, EBM, Trading)

Information gateway

...

Asset Management Energy Sales & Care

Enterprise Integration Bus

Data Warehouse MIS

F&A

Gateway

Power Systems Control and Energy Management

Multi-Level Environment

(120)

Basic SCADA/EMS/DMS System Architecture

DW Operational Database Transmission NA Distribution DMS DSM Generation PA SA RO DW EA ELCOM ICCP DTS DW ORACLE Interfaces Front End BASE SCADA HIS SDM Base Interfaces

(121)

Sample SCADA/EMS/DMS Modularity

SCADA SCADA UI UI FA FA DSM DSM PA PA Base Base IS&R IS&R Multi BCK Multi BCK OA OA TS TS CFE CFE GEI GEI Elcom Elcom Data Data DNA DNA GIS GIS LTOP LTOP GSA GSA TNA TNA EMM EMM SDT SDT IndC IndC ICCP ICCP

ƒMultiBck Multisite/Backup System

ƒBase Base System

ƒCFE Communication Front End

ƒData Data Engineering

ƒDNA Distribution Network Applications

ƒDSM Demand Side Management

ƒELCOM Electricity Utilities Communication

ƒEMM Energy Market Management

ƒFA Forecasting Applications

ƒGEI General External Interface

ƒGIS Interface to GIS

ƒGSA Generation Scheduling Applications

ƒICCP Inter Control Center Protocol

ƒIndC Industrial Communication

ƒIS&R Information Storage & Retrieval

ƒLTOP Long-Term Operation Planning

ƒOA Operational Applications

ƒPA Power Applications

ƒSCADA Supervisory Control & Data Acquisition

ƒSDT Software Development Tools

ƒTNA Transmission Network Applications

ƒTS Training System and Simulation

Transmission

Distribution Generation

References

Related documents

For example, the latent variables can be used to represent the similarities and dissimilarities between the samples: Figure 4 illustrates the difference in the sample

Sales teams may want to thank their marketing counterparts for providing the relevant content to help generate new leads, as the number of people using the web for initial

strain NL10 in 5 ml PAS buffer was inoculated into sterilized natural soil, and (7) Control, 5 ml PAS buffer was added into natural soil. A follow-up experiment was conducted in

Out of the full set of recursive sites that were identified across all three methods, we filtered down to a final set of sites with the following criteria: (1) in genes with TPM ≥ 1

These features suggest that our model should include perceived usefulness (also called performance expectancy), perceived ease of use (also called effort expectancy), attitude

H 1 : There is a significant positive difference in the relationship between the number of trauma programs attended and the risk for violence, as measured by the assessment scores

On 17 September 2015, the CJ delivered its judgement in joined cases J. The case deals with refund requests of the Netherlands 15% withholding tax imposed on dividends paid to