• No results found

The Benefits of Demand Response

N/A
N/A
Protected

Academic year: 2021

Share "The Benefits of Demand Response"

Copied!
12
0
0

Loading.... (view fulltext now)

Full text

(1)

Contracts Meeting

Walid M. Daniel , PE, CEM

Department of Mines, Minerals, and Energy Manager – Virginia Energy Management Program

804-692-3225

(2)

Overview

• 1. Demand Response pays large facilities to reduce KWH. • 2. No risk, no fees, virtually no obligation, no cap-ex.

• 3. Why – to reduce grid ops cost, avoid new construction. • 4. Who – EnergyConnect, PJM, and You.

• 5. EnergyConnect client base – VCU, UVA, Sears Tower, Regan National Airport, US Steel, etc.

• 6. How – Engineering support, Leading online software suite. • 7. How Much – Largest city facilities could earn $1M+

annually

(3)

The Benefits of Demand Response

Lowers Wholesale Energy Costs Flexibility to Meet Demand at Low Costs Reduces Power Grid Outages Positive Impact on Community nvironmentally Responsible Financial Incentive

Risk & Resource Management Lowers Wholesale Energy Costs Flexibility to Meet Demand at Low Costs Reduces Power Grid Outages

Power Grid Benefits Electric Customer Benefits

Positive Impact on Community Environmentally Responsible Financial Incentive

Risk & Resource Management

Demand Response is one of the few “technologies” available that can address energy and environmental issues positively while

(4)

What is Demand Response?

Historically – service interruption events deployed by the utility for a reduced retail rate and

penalties for failure to comply.

Today – Power Grid operators

directly rewarding individual retail consumers to shift, reduce,

(5)

How It Works

Hour 500 1000 1500 2000 2500 3000 3500 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 0 Load (kW) Actual Load Baseline

y

• Deploy load reduction strategies when market prices

provide incentives to facility.

Estimated Load

(6)

Event Based Programs Voluntary Capacity Ancillary Services Energy Characteristics Longer notification

Longer event duration

Very short notification

Short event duration You make the call when the price is right

Notification Time 2 hours 10 to 30 minutes Voluntary (Day ahead bid or real time bid)

Curtailment Duration 6 hours < 1 hour 1 hour blocks

Payments Standby payments plus

energy payments

Standby payments plus energy payments

Energy payments (at premium rates)

Compliance Penalties Zero Payment Zero Payment None

Event Limits 10 Events Limited number of events Completely voluntary

Compensation Range $12K - $80K per MW $20K - $110K per MW $0.10 - $1.00 per kWh

Types of DR Programs

Programs and pricing can vary by geography .

(7)

PJM Presentation of DR Benefits

.

2008 payments through 9/30 are $21.4M EnergyConnect clients represent

well over 50% of this total.

We achieve this through cutting edge technology and engineering services.

(8)

• In 2008, PJM has fine tuned the Demand Response program to enhance the program’s effectiveness.

EnergyConnect software platform is readily modifiable to incorporate these changes.

• Changes include:

– More precise CBL – now 4 of 5 days in a 45-60 day window – Limit on participation to 70% of a 30 day window

– Enhanced documentation required, greater focus on price response – Possible Weather Sensitive Adjustments

– PJM screening should reduce LSE/EDC denials

• The program remains a financial incentive to support the grid when under stress as reflected by high Real Time

prices, and EnergyConnect is now the leading provider of PJM Economic CSP services.

PJM fine tunes program, ECI

responds

(9)

New tool for more precise participation Price Forecast and Response Notifier

Facility: Target Date: LMP: 0 1 2 4 5 7 8 10 13 14 15 16 17 18 19 20 21 22 23 Price Forecast $44 $39 $36 $38 $47 $58 $61 $66 $82 $86 $85 $88 $84 $77 $85 $103 $70 $52 $49 Recommended Sched. X X X X X X

If you are an authorized user registered in eServices click the link below to login to eServices to enter the recommended reduction schedule, or view/change the existing schedule(s). NOTE: action is required to schedule the reduction.

X $34 $60 $64 $72 3 6 9 11 12 $76 Minimum Hours 11 18 $75 2 Hour Beginning =>

Price Forecast and Response Notification Report

University of Abcdefg Monday, September 22, 2008 APS

Welcome to the eServices price response notification report.

Energy price forecasts have met or exceeded the trigger criteria for the target date, as incidated by the x's in the table below:

Click here to login to eServices

Schedule Trigger Criteria From Hour Through Hour Price

• EnergyConnect now sends the Day Ahead price for the following day to participants via email. This allows the participant to plan to better focus efforts on the hours most likely to be valuable to the grid and to the participant.

(10)

Curtailment & Reduction Strategies Commercial Buildings Industrial Facilities Shopping Malls Restaurants Hotels / Motels Hospitals Agricultural Facilities

Turn off decorative lighting √ √ √ √ √ √ √

Turn off non-essential lighting √ √ √ √ √ √ √

Turn off decorative fountains √ √ √ √ √ √

Adjust thermostat settings √ √ √ √ √ √

AC or fan cycling – deploy

VFD √ √ √ √ √ √

Adjust chilled water temp √ √ √ √ √ √

Reduced elevator usage √ √ √ √

Delay dishwashing √ √ √ √

Delay laundry processes √ √ √ √

Turn of ice machines √ √ √ √

Delay use of battery chargers √ √

Turn off non-essential

pumping √ √

(11)

Voluntary Participation in Energy Programs

Customers decide when to participate based on market prices or estimated market prices

Automated software confirms a DR transaction directly to the gridVerification and settlement with grid embedded in the process

(12)

References

Related documents

It is with pleasure that I present the third Annual Report for the University of California (University) Office of Ethics and Compliance Services (ECS), which outlines

to the telephone call from the caller to produce instruction messages over the telephone line to the caller informing the caller of the manner of obtain ing the subschedule

The results of this study suggest that online learning was a valuable method for teaching dental terminology and is particularly beneficial for students with no other

Onsite training supervised by a state-approved licensed/certified school guidance counselor is required; currently, 600 hours minimum, 240 of which must be in direct service

The aim of the study is to assess the potential of solar energy in averting the water borne disease burden in the rural areas of Zambia, through improved access to safe clean

It is seen that when the wheel set mass is small, the resonance frequency is so high that the embedded rail system will give an amplification of the ground borne noise level. In

Solar panels placed on public road in Shtimje are subject to the study of current and voltage intensity and the amount of pollution collected on the surface of solar panels.

Kosovo's political class who signed the agreement claims that the establishment of the Association will make it possible for the Serb-majority municipalities to create