Number:
04.04.001.107
Revision 0.2
Publication: 8/1/2014
Effective Date: 3/26/2013
Next Review Date: 8/1/2017
Procedure: Initiating a Change to a Contract 31 Requirement
1. PurposeThis document describes the procedure for initiating a requirement change in the Department of Energy (DOE) contract that defines the operational parameters for Lawrence Berkeley National Laboratory. 2. Applicability – who this is for
This process applies primarily to LBNL persons who have responsibility for review and implementation of DOE contract requirements.
2.1 Exceptions none
3. Pre-requisites
Users of this procedure should review the Requirements Management Process, 04.04.001.003, and the Managing Contract Deliverables Process, 04.04.001.104.
4. Definitions
Term Definition
Case An instance of change or focused discussion of one or more institutional requirements and/or
institutional documents. This is a RM and RMS term.
Change Refers to (a) introduction of a new item, (b) retirement of an existing item, or (c) modification
of an existing item
Contract 31 “Contract 31” refers to Contract No. DE‐AC02‐05CH11231, the contract between the U.S.
Department of Energy and the University of California (UC) describing the terms for UC to
manage Berkeley Lab. The contract includes a statement of work (SOW) for the science
missions, and details the requirements for managing the operations and business of Berkeley
Lab.
Contract 31
Modification
Refers to a formal agreement of change to Contract 31. Signed by DOE site office (BSO) and
formally accepted by UCOP. Contract Mods are numbered and dated. The Mod address
impact on any associated Contract deliverables. A Mod may contain any number of changes
to the Contract.
Deliverable Any measurable, tangible, verifiable outcome, product, result, or item that must be produced
to satisfy a requirement under the terms of an agreement, contract, or implementing
mechanism. These include but are not limited to reports, plans, inventories, inspections,
assessments, documents, procedures, programs, data, etc. A requirement specifies a
Term Definition
Modification Used interchangeably with “Change”. Record of
Decision (ROD)
A summary statement that describes a specific decision about an institutional requirement
and/or document and/or implementation. The decision is based on analysis as described by
the RM Analysis procedure (see Section 7.2 this document).
Requirement
A specific obligation to perform an action mandated by LBNL senior management or the
federal, state, or local government; or to comply with the Laboratory’s contract with the
Department of Energy; or to comply with agreements made between the Laboratory and its
corporate manager, the University of California.
RMS database Requirements Management System ‐the database tool for managing requirements and
related information, including tracking requirements, their associated owners, records of
implementing mechanisms, and their flow down to implementing documents. The RM
Program Manager is responsible for managing the RMS.
Tri‐party Refers to a group with representatives from BSO, UC Office of the President, and Berkeley Lab
5. Roles and Responsibilities
These are adopted from LBNL Requirements Management Governance, Document 04.04.001.002, and emphasize
responsibilities pertinent to this procedure. Refer to the Governance document for the most comprehensive, up‐to‐
date version.
Role Responsibilities
Subject Matter
Expert (SME)
A Laboratory employee or consultant with specialized knowledge about a certain
topic or field of interest.
Provides technical expertise to the RMC and/or Working Group as it relates to the
interpretation and implementation of requirements, including the development and
review of policies and implementing documents.
May be a Working Group member, may be an author or reviewer
Working Group (WG)
Comprised of members from affected and/or responsible divisions, having related
special knowledge on the particular requirement or case in question.
Members are recommended by SME, RMC in collaboration with Laboratory standing
committee(s).
Recommendations for WG member and SME participation are approved by
respective Senior Line Managers.
Perform detailed analyses, and determine detailed and practical implementation
plans, with consideration of cost, simplicity, impact, and overall risk.
Make recommendations in a timely fashion to the RMC, RM PM, Sr. Line Manager,
and if applicable, the WG’s sponsoring standing committee.
Sr. Line Manager Has full responsibility and authority to make and enforce policies related to his/her
respective area of expertise and responsibility.
Has ownership and accountability for the technical content, accuracy and
completeness of respective Function’s documents. Ensures compliance with LBNL
requirements and document management policies and procedures. Approves
institutional documents upon completion of required reviews.
Ensures compliance with LBNL requirements and document management policies
and procedures.
Works with the RM PM and RMC to resolve issues that may arise in the process of
Role Responsibilities
Requirements
Management
Program Manager
(RM PM)
Manages the Laboratory’s requirements management and institutional document
management processes. Is the main driver and champion of these processes. Has
author/review/recommendation responsibilities for quality and completeness of RM
process and institutional document management process documentation.
Serves as the Laboratory’s contact point on requirements and institutional
document management‐related matters.
Oversees management of Laboratory’s policy manual.
Maintains the Requirements Management (RM) database for tracking requirements,
their associated policy areas (PA), owners, records of implementing mechanisms,
and their flow down to implementing documents. Maintains accuracy and currency
of the RM tracking system. Has review/approval responsibility for quality and
completeness of requirement, policy, and document metadata.
Requirements
Management
Committee (RMC)
Reviews and oversees disposition of Requirements Review Cases related to
requirements, Laboratory policies, and on a case‐by‐case basis Laboratory
implementing documents.
Applies cross‐functional knowledge on requirements matters.
Assesses the Laboratory wide impacts of new or changed requirements, and
adopts a holistic response.
Reviews and recommends best qualified team members to address
requirements analyses, implementation mechanisms and plans, policy and
procedure documents.
Such team members include Working Group (WG) members, and
subject matter experts (SME), and stakeholders. Ensures teams are cross‐functionally represented. Recommends collaboration with other Laboratory standing
committees whenever possible.
Advises responsible Sr. Line Manager on WG/ SME work products.
Reports to ALDO/COO.
Champions RM and institutional document management processes.
RMC Representative Represents a specific division or function on the RMC
Fulfills the responsibilities described for RMC.
University of
California Office of
the President (UCOP)
Is the corporate entity responsible for the management of Berkeley Lab
Has authority to negotiate/agree with BSO on matters regarding Contract 31.
DOE/Berkeley Site
Office (BSO)
Reviews and approves those non‐policy institutional documents that are explicitly
delineated by Contract 31 requirements as needing DOE review.
BSO SME Has oversight responsibilities for specific Lab function or division
BSO Contracting
Officer (CO)
Has approval authority regarding contents of Contract 31.
6. Procedure
Figure 1 highlights (a) where this procedure fits in the overall RM process flow (see document number 04.04.001.003) and (b) the pertinent steps of this procedure.
FIGURE 1
Step Role Action
1 SME, Sr. LM Determine during Requirement Analysis process that there is reason to question the requirement and/or deliverable.
2 SME Informs RMC Rep and RM PM
3 SME/WG Prepares analysis package for BSO SME review
4 SME If… Then…
BSO SME concurs Proceed with Step 7
BSO SME does not concur Seek assistance of RMC Rep, RM PM, Line Manager
5 SME, RMC Rep, RM PM, Evaluate and consider whether to continue to pursue RMC, Sr. LM, review analysis (RM Process) SME/WG interprets, analyzes impact, recommends SME/WG delineate deliverables. Review with BSO
SME. Does this req
have associated Deliverables no yes Is there reason to question req? SME/WG prepare analyses (cost, risk, applicability) for BSO
SME review.
BSO SME concurrence?
Lab SME, BSO SME present to BSO Contracting Officer yes SME informs RMC rep or RM PM yes BSO CO concurrence? SME informs RMC rep or RM PM. yes no SME seeks assistance RMC rep, RM PM, Line Mgr SME revises package. Presents to BSO SME Continue pursuit? yes no no no RM PM submits formal request Continue RM Process Initiate Develop Review Approve Close Outside RM Scope KEY:
SME provides final package (approvals, analyses,ROD, plan) to
RMC rep or RM PM
RM PM or RMC rep logs ROD, uploads
analysis, plan. RM PM updates Deliverables. End RM Process no C31 change recommended? yes (Go to BSO-UCOP-Lab Contract Mod process)
11Step Role Action
BSO SME, go to step 4
Stop pursuit Continue along main RM process flow (see 04.04.001.00x)
7 Lab SME, BSO SME Present analysis to BSO Contracting Officer
8 SME If… Then…
BSO CO concurs Proceed with Step 9
BSO CO does not concur Seek assistance of RMC Rep, RM PM, Line Manager, go to Step 5
9 SME Informs RM PM and RMC Rep of result
10 RM PM If… Then…
No C31 changes Proceed with Step 11
C31 change recommended Submit formal request to BSO-UCOP-Lab Contract Mod process
11 SME Completes final RM Case package per RM Process, including Record of Decision. Gives to RMC Rep or RM PM
12 RM PM or RMC Rep Complete upload of information into RMS database
7. References
7. 1 Source Requirements Documents
Requirement ID Title
04.04.001.000 Requirements Management Policy
10.06.001.000 Document Management Policy
04.04.001.003 Requirements Management Process Description
04.04.001.104 Contract Deliverables Management Process
7. 2 Related Implementing Documents (including procedures, forms, training)
Document Number Title
04.04.001.101 Procedure - Analyzing Requirements and Determining Significance Rating from Impact and Risk Analysis
04.04.001.201 Form - Analyzing Requirements
04.04.001.206 Form – Significance Rating
04.04.001.208 Form - Record of Decision
8. Contact
Email: [email protected]
Requirements Management Program Manager LBNL Office of Contractor Assurance
9. Revision History
Date Revision By whom Revision Description Sections affected
8/1/2014 0.2 L. Young Review to release. Add #s to diagram Diagram 3/22/13 0.1 L.Young Initial Amend dwg