Introduction to Solar Energy
Solar Energy
An in-exhaustible source of Energy
which God has bestowed on us
Solar Energy is a Electro Magnetic
Wave Radiation
• Radiation emanated from the sun at a temperature of 5000 o K
• Magnetic Wave travels a distance of 1.5 * 10 8 km
• The Sun subtends and angle of 32’ with the earth
• Solar Constant i.e. Solar Radiation of 1395 W / m 2 in space
Electro Magnetic Wave Radiation
• Gamma Rays 10
– 8to 10
– 4µ m
• X – rays 10
– 5to 10
– 2µ m
• Ultraviolet 10
– 2to 1 µ m
• Visible Spectrum 0.38 to 0.78 µ m
• Thermal Radiation – near infrared and far infrared 1 to 10
+ 3µ
m
Azimuth angle of the sun:
Often def ined as the angle f rom due north in a clockwise direction. (sometimes f rom south)
Zenith angle of the sun:
Def ined as the angle measured f rom v ertical downward.
Position of the Sun
Declination = 23.45 * Sin (360*(284+n)/365) Optimum Tilt angle = Latitude
for the ma ximum collection through out the year §Sea son Optimization tilt = (La titude - Declination) Elevation and Azimuth
Cos θZ = Si n δ * Si n φ + Cos δ * Cos φ * Cos ω α = 90 - θZ
Solar Path Diagram
Horizontal & Vertical Shadow
http://andrewmarsh.com/blog/2010/01/10/horizont al-and-vertical-shadow-angles 2/6/201 3 9 Corpora te CommunicationSolar Radiation
GlobalDirect
Diffused
© 2011 Underwriters Laboratories Inc.
Photovoltaic
n-type se miconductor p-type se miconductor + + + + + + + + + + + + + + + - - - - - -Physics of Photovoltaic Generation
How PV Cell produce Electricity:
► When rays of sunlight hit the solar cell electrons are ejected from the atoms.
► Electrons are knocked loose from their atoms, which allow them to flow through the PN Junction to
produce electricity.
2/6/201 3 31 Corpora te Communication
Solar PV Markets Capacity installed in 2011
PV Module Production, Supply, and Demand
Metrics
22
2/6/201 3 43 Corpora te Communication 1,920.00 1,940.00 1,960.00 1,980.00 2,000.00 2,020.00 2,040.00 2,060.00a-si Cd-Te CIS Mono-si Poly -si HIT 1,990.20 2,028.60 2050.7 2,053.10 2053.1 1966.4 El e ct ri ci ty E xp o rt e d t o T h e G ri d (M W h ) Fo r Fi xe d T ilt
Output vs Technology at Leh, Jammu & Kashmir State
1,600.0 1,650.0 1,700.0 1,750.0 1,800.0 1,850.0 1,900.0 1,950.0
a-si Cd-Te CIS Mono-si Poloy-si HIT 1,862.5 1,820.4 1,712.0 1,750.0 1,750.0 1,905.2 E le c tr ic it y E x p o rt e d t o T h e G ri d (M W h ) F o r F ix e d T il t
Output vs Technology at Bangalore, Karnataka State 1,600.0 1,650.0 1,700.0 1,750.0 1,800.0 1,850.0 1,900.0 1,950.0
a-si Cd-Te CIS Mono-si Poloy-si HIT 1,879.4 1,830.4 1,710.1 1,751.5 1,751.5 1,928.0 El e ct ri ci ty E xp o rt e d t o T h e G ri d (M W h ) Fo r Fi xe d T ilt
Output vs Technology at Bellary, Karnataka State
1,550.0 1,600.0 1,650.0 1,700.0 1,750.0 1,800.0 1,850.0 1,900.0 1,950.0
a-si Cd-Te CIS Mono-si Poloy-si HIT 1,866.6 1,814.7 1,690.0 1,732.5 1,732.5 1,917.5 El e ct ri ci ty E xp o rt e d t o T h e G ri d (M W h ) Fo r Fi xe d T ilt
Output vs Technology at Charanka, Gujarat State
1,600.0 1,650.0 1,700.0 1,750.0 1,800.0 1,850.0 1,900.0 1,950.0
a-si Cd-Te CIS Mono-si Poloy-si HIT 1,893.1 1,845.1 1,726.0 1,767.2 1,767.2 1,941.0 El e ct ri ci ty E xp o rt e d t o T h e G ri d (M W h ) Fo r Fi xe d T ilt
Output vs Technology at Jaisalmer, Rajasthan State
Bangalor e Charanka Leh 0.0 500.0 1,000.0 1,500.0 2,000.0 2,500.0 a-si Cd Te CIS Mo no-si Pol y- si HIT Bangalor e 1,8621,8201,7121,7501,7501,905 Br llar y 1,8791,8301,7101,7511,7511,928 Charanka 1,8661,8141,6901,7321,7321,917 Jaisalmer 1,8661,8141,6901,7321,7321,917 Leh 1,9902,02820512,0532053 1966 E le c tr ic it y E x p o rt e d t o t h e G rid (M W h )
Output vs Technology for Fixed Tilt
2/6/201 3 44 Corpora te Communication 0.0 10.0 20.0 30.0 40.0
a-si CdTe CIS Mono-si Poly -si HIT 21.0 21.3 21.7 21.5 21.5 20.9 30.4 30.3 30.2 30.3 30.3 30.4 35.4 35.2 34.9 35.0 35.0 35.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Leh, Jammu & Kashmir One-axis Polar Two-axis 0.0 5.0 10.0 15.0 20.0 25.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 22.5 22.6 22.8 22.7 22.7 22.4 24.0 24.0 23.9 23.9 23.9 24.0 27.4 27.3 27.1 27.2 27.2 27.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Bangalore, Karnataka One-axis Polar Two-axis 0.0 5.0 10.0 15.0 20.0 25.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 22.1 22.3 22.6 22.4 22.4 22.0 24.3 24.3 24.3 24.3 24.3 24.4 27.9 27.8 27.6 27.7 27.7 28.0 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Bellary, Karanataka One-axis Polar Two-axis 0.0 5.0 10.0 15.0 20.0 25.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 21.0 21.2 21.6 21.4 21.4 20.9 25.5 25.5 25.5 25.5 25.5 25.5 29.4 29.3 29.0 29.1 29.1 29.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Charanka, Gujarat One-axis
Polar Two-axis 0.0 10.0 20.0 30.0 40.0
a-si CdTe CIS Mono-si Poly -si HIT 21.0 21.3 21.7 21.5 21.5 20.9 30.4 30.3 30.2 30.3 30.3 30.4 35.4 35.2 34.9 35.0 35.0 35.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Leh, Jammu & Kashmir One-axis Polar Two-axis 0.0 5.0 10.0 15.0 20.0 25.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 22.5 22.6 22.8 22.7 22.7 22.4 24.0 24.0 23.9 23.9 23.9 24.0 27.4 27.3 27.1 27.2 27.2 27.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Bangalore, Karnataka One-axis Polar Two-axis 0.0 5.0 10.0 15.0 20.0 25.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 22.1 22.3 22.6 22.4 22.4 22.0 24.3 24.3 24.3 24.3 24.3 24.4 27.9 27.8 27.6 27.7 27.7 28.0 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Bellary, Karanataka One-axis Polar Two-axis 0.0 5.0 10.0 15.0 20.0 25.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 21.0 21.2 21.6 21.4 21.4 20.9 25.5 25.5 25.5 25.5 25.5 25.5 29.4 29.3 29.0 29.1 29.1 29.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Charanka, Gujarat One-axis
Polar Two-axis 0.0 10.0 20.0 30.0 40.0
a-si CdTe CIS Mono-si Poly -si HIT 21.0 21.3 21.7 21.5 21.5 20.9 30.4 30.3 30.2 30.3 30.3 30.4 35.4 35.2 34.9 35.0 35.0 35.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Leh, Jammu & Kashmir One-axis Polar Two-axis 0.0 10.0 20.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 22.5 22.6 22.8 22.7 22.7 22.4 24.0 24.0 23.9 23.9 23.9 24.0 27.4 27.3 27.1 27.2 27.2 27.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Bangalore, Karnataka One-axis Polar Two-axis 0.0 10.0 20.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 22.1 22.3 22.6 22.4 22.4 22.0 24.3 24.3 24.3 24.3 24.3 24.4 27.9 27.8 27.6 27.7 27.7 28.0 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Bellary, Karanataka One-axis Polar Two-axis 0.0 10.0 20.0 30.0
a-si CdTe CIS Mono-si Poly -si HIT 21.0 21.2 21.6 21.4 21.4 20.9 25.5 25.5 25.5 25.5 25.5 25.5 29.4 29.3 29.0 29.1 29.1 29.5 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Charanka, Gujarat One-axisPolar
Two-axis 0.0 10.0 20.0 30.0 40.0
a-si CdTe CIS Mono-si Poly -si HIT 21.5 21.7 22.1 21.9 21.9 21.3 26.8 26.8 26.7 26.8 26.8 26.8 30.9 30.7 30.4 30.5 30.5 31.0 P e rc e n ta ge I n cr ea se in O ut p u t
Percentage Increase vs Technology at Jaisalmer, Rajasthan
One-axis Polar Two-axis
2/6/201 3 45 Corpora te Communication 0.00 0.20 0.40 0.60 0.16 0.20 0.23 0.40 0.33 0.34 0.20 0.25 0.28 0.49 0.40 0.41 0.21 0.26 0.30 0.52 0.43 0.45 0.22 0.27 0.31 0.54 0.45 0.46 O u tp u t M W h /s q .m tr .
Output MWh/sq.mtr. vs Technology at Leh, Jammu & Kashmir Fixed One-axis Polar 0.0 0.2 0.4 0.6 0.2 0.2 0.2 0.3 0.3 0.3 0.2 0.2 0.2 0.4 0.3 0.4 0.2 0.2 0.2 0.4 0.4 0.4 0.2 0.2 0.2 0.4 0.4 0.4 O u tp u t M W h /s q .m tr .
Output MWh/sq.mtr. vs Technology at Bangalore, Karnataka Fixed One-axis Polar 0.00 0.20 0.40 0.60 0.15 0.18 0.19 0.34 0.28 0.34 0.19 0.22 0.24 0.42 0.35 0.41 0.19 0.23 0.24 0.43 0.35 0.42 0.20 0.23 0.25 0.44 0.36 0.43 O u tp u t M W h /s q .m tr .
Output MWh/sq.mtr. vs Technology at Bellary, Karnataka Fixed One-axis Polar 0.00 0.10 0.20 0.30 0.40 0.50 0.15 0.18 0.19 0.34 0.28 0.33 0.18 0.22 0.23 0.41 0.34 0.40 0.19 0.23 0.24 0.43 0.35 0.42 0.20 0.23 0.25 0.44 0.36 0.43 O u tp u t M W h /s q .m tr .
Output MWh/sq.mtr. vs Technology at Charanka, Gujarat FixedOne-axis
Polar Two-axis 0.00 0.20 0.40 0.60 0.15 0.18 0.20 0.35 0.29 0.34 0.19 0.22 0.24 0.42 0.35 0.41 0.20 0.23 0.25 0.44 0.44 0.43 0.20 0.24 0.26 0.45 0.45 0.44 O u tp u t M W h /s q .m tr .
Output MWh/sq.mtr. vs Technology at Jaisalmer, Rajasthan Fixed One-axis Polar
Performance rating
Technical Commercial 5.00 7.00 9.00 11.00 13.00 15.00 17.00 19.00a-Si CdTe CIS mono-Si Poly-Si HIT
Performance rating for fixed tilt at different places
Bellary Bijapur Charanka Jaisalmer Leh 5.00 7.00 9.00 11.00 13.00 15.00 17.00 19.00
a-Si CdTe CIS mono-Si Poly-Si HIT
Cost Driven rating for fixed tilt at different places
Bellary Bijapur Charanka Jaisalmer Leh
© 2011 Underwriters Laboratories Inc.
Inspection
Plan of
Civil Foundations
for Solar Power Plants
IS 1498:1970 – Classification & identification of soils for Engineering purposes IS: 1199 – 1959 – Tests on fresh concrete
IS: 13311 (Part 1,2) – 1992 – Tests on hardened concrete IS 516:1959 – Methods of tests for strength of concrete
IS: 2720 (Part II) – 1973 – Tests on soil – To determine w ater content in soil IS: 2720 (Part 4) – 1985 - To determine the particle size distribution of soil IS: 2720 (Part 5)–1985-To determine the liquid limit and plastic limit of soil IS: 2720 (Part 8) – 1983 - To determine the maximum dry density and the
optim um m oisture content of soil
Contents:
► Introduction to soil types for foundations ► Introduction to foundations
► Foundations types used for Solar power plants
3
Introduction to Soil
types for Foundations
5 5
Soil Map of INDIA:
What is Soil?
Mineral
45%
Air
25%
Water
25%
Organics
5%
7
GRAVEL
SAND
Clay
Silt
Minerals
Soil Groups
Soil Type Gradation Plasticity Gravel – G Sand – S Silt – M Clay – C Organic – O Well Graded – W Poorly Graded – P High Plasticity – H Low Plasticity – L
Soil type & particle size distribution as follows:
• Gravel : 80 – 4.75 mm
• Sand : 4.75mm – 0.075mm (75 micron) • Silt : 75 – 2 micron
9 9
Soil Type Allowable Bearing (lb/ft2 - Pound per square foot )
Drainage BEDROCK 4,000 to 12,000 Poor GRAVELS 3,000 Good SAND 2,000 Good SILT 1,500 Medium CLAY 1,500 Medium ORGANICS 0 to 400 Poor
Estimated Soil Load Bearing Capacities
11
Sand and gravel –
Best
Medium to hard clays –
Good
Soft clay and silt –
Poor
Organic silts and clays –
Undesirable
Peat –
No Good / Avoid
Peat is an accumulation of partially decayed vegetation matter or organic matter.
Soil Strength Classification for Foundations
Laboratory tests for Soil
Follow ing laboratory tests are to be carried out to determine the physical and engineering properties of soil samples:
1. Dry density and moisture content - (IS 2720 part – 2 & 29) 2. Particle size analysis - (IS 2720 part – 4:1985) 3. Specific gravity - (IS 2720 part– 3/sec2:1980) 4. Shear test - (IS 2720 part – 11:1986) 5. Consolidation test - (IS 2720 part – 15:1986)
6. Free swell test - (IS 2720 part – 40:1977 & 41:1977) 7. Consistency Limits
Soil Samples
Disturbed samples: which do not represent exactly how the soil was in its natural state before sampling.
► Disturbed samples are used for the more simple tests that will be
performed and particularly for those tests which can be performed by self in the field.
Undisturbed samples: which represent exactly how the soil was in its natural state before sampling.
► Undisturbed samples are necessary for the more sophisticated tests
which must be performed in the laboratory for more detailed physical and chemical
analyses. Undisturbed samples must be collected with greater care for they should represent exactly the nature of the soil.
13
© 2011 Underwriters Laboratories Inc.
Introduction to Foundations
The soil beneath the structures responsible for carrying the loads is called FOUNDATION.
The general misconception is that the structural element which transmits the load to the soil(such as a footing) is the foundation. The figure below clarifies this point.
Forces acting onto Foundation
17
Classification of Foundations
► Shallow foundations are placed at a shallow depth beneath the soil
surface. They include footings and soil retaining structures. The depth is generally less than the width of the footing and less than 3m.
Shallow Foundations
Deep Foundations
► Deep foundations are commonly using piles. They are embedded very
deep into the soil. They are usually used when the top soil layer have low bearing capacity. Deep foundations are usually at depths deeper than 3m.
19 Footing Footing
D
fB
Footing
Ground Surface C o lu m nP
For Shallow Foundation = Df < 4B
Shallow Foundation
21
Pile
HammerShaft
Pre bored hole Poured in place fillDeep Foundations
Ground Surface
Df
B
For Deep Foundation = Df > 4B
Laboratory tests for Concrete foundations
► Tests on Fresh Concrete
1. Slump test: To determine the strength of fresh concrete by slump test as per IS: 1199 - 1959.
2. Compacting factor test: To determine the strength of fresh concrete by compacting factor test as per IS: 1199 - 1959.
3. Vee-Bee test: To determine the strength of fresh concrete by using a Vee-Bee consistometer as per IS: 1199 - 1959.
23 23
Laboratory tests for Concrete foundations
► Tests on Hardened Concrete:
1. Non-destructive tests
a. Rebound hammer test: To assess the likely compressive strength of concrete by using rebound hammer as per IS: 13311 (Part 2) - 1992. b. Ultrasonic pulse velocity test: To assess the quality of concrete
by ultrasonic pulse velocity method as per IS: 13311 (Part 1) - 1992. 2. Compression test(Destructive): To determine the compressive
strength of concrete specimens as per IS: 516 – 1959.
Clear horizontal distance between reaction supports
and test foundation
a) For pad and chimney, grillages, concrete block foundations or buried anchors:
L = e + 0,7 x a (m)
Where,
e is the width of foundation in metres; a is the depth of foundation in metres;
L is the distance between nearest points of reaction supports.
b) For concrete piers, driven piles, drilled and grouted piles, or helix anchors:
Figures:
25
Types of PV Foundation used for Solar Power Plants:
This includes any of the following foundations:
Concrete pier Driven post Screw piles
Precast or cast-in-place concrete ballast
27
Concrete pier
o Make sure the bottom of the footing rests on undisturbed soil
free of organic material.
o Uses reinforcing bar to firmly
connect the footing at the base to the concrete pier.
o At the top, a metal post base
connects the concrete pier to the mounting structure.
Driven pile systems
29
Driven pile systems are often found to be the more favorable choice based on cost, installation time, materials, and environmental impact.
Screw piles
• Screw piles are a steel
screw-in piling and ground anchoring system used for structure foundations.
• The pile shaft transfers a
structure's load into the pile.
• Screw piles are also
Screw piles or Ground screws
Helical steel plates are welded to the pile shaft in accordance with the intended ground conditions.
31
Precast or cast-in-place concrete ballast
Ballasted footings are designed for mounting photovoltaic
solar panels quickly.
Capable of relocation and reuse, the footings are intended for
use in demanding applications, where panels need to be
Pile Foundation for Solar PV - Video
33
© 2011 Underwriters Laboratories Inc.
© 2011 Underwriters Laboratories Inc.
Solar Photovoltaic (PV)
System and Safety Measures
1
Key Elements of a PV System
load Energy source power conditioning Energy conversion Inverter Charge Controller PV Array Energy distribution load center Battery Energy storage Electric utility network
3
Solar PV Safety involves
1. Working safely with photovoltaic systems 2. Conducting a site assessment
3. Selecting a system design
4. Adapting the mechanical design to the site 5. Adapting the electrical design to the site 6. Installing subsystem & components at site 7. Performing a system checkout and inspection 8. Maintaining and troubleshooting the system
OSHA* Safety Categories
> Personal Protection Equipment (PPE) > Electrical
> Falls
> Stairways and Ladders > Scaffolding
> Power Tools > Materials Handling > Excavation
5
Personal Protection Equipment (PPE)
Personal Protection Equipment
Responsibilities
Employer
Assess workplace for hazards.
Provide personal protective equipment (PPE). Determine when to use.
Provide PPE training for employees and instruction in proper use.
Employee
Use PPE in accordance with training received and other instructions.
7
Examples of PPE
Eye
Safety Glasses, Goggles
Face
Face Shields
Head
Hard Hats
Feet
Safety Shoes
Hands and arms
Gloves
Bodies
Vests
Hearing
Earplugs, Earmuffs
Body Part Protection
Equipment
9
Preventing Electrical Hazards:
PPE
Proper foot protection (not tennis shoes)
Hard hat(insulated - nonconductive)
Rubber insulating gloves, hoods, sleeves, matting, and blankets
Selecting the Right Hard Hat
Class A
>General service (building construction, ship building, lumbering)
> Good impact protection but limited voltage protection
Class B
> Electrical/utility work
> Protects against falling objects and high-voltage shock and burns
Class C
> Designed for comfort, offers limited protection
> Protects against bumps from fixed objects, but does not protect against falling objects or electrical shock
11
Hand Protection
Electrical Injuries
There are three main types of
electrical injuries:
> Electrocution or death due to
electrical shock
> Severe burns
13
Dangers of Electrical Shock
> Currents above 10 mA* can paralyze or “freeze” muscles.
> Currents more than 75 mA can cause a rapid, ineffective heartbeat & death will occur in few minutes unless a
defibrillator is used.
> 75 mA is not much current – a small power drill uses 30 times as much.
* mA = milliampere = 1/1000 of an ampere
Personal Fall Arrest System
(PFAS)
Guardrails Safety Net
Fall Protection Options
15
Must be independent of
any platform anchorage
and capable of
supporting at least 5,000
pounds (2268 kg)
Safety Line Anchorages
Ladder Angle
Non-self-supporting ladders
(that lean against a wall or
other support):
Position at an angle where
the horizontal distance from
the top support to the foot of
the ladder is 1/4 the working
length of the ladder.
17
Grounding
> Grounding creates a low -resistance path from a tool to the earth to disperse unwanted current.
> When a short or lightning occurs, energy flows to the ground, protecting you from electrical shock, injury and death.
Improper Grounding
>Tools plugged into improperly grounded circuits may become energized.
>Broken wire or plug on extension cord
*Some of the most frequently violated OSHA standards
Unsafe Installation Practices - Photos
19
© 2011 Underwriters Laboratories Inc.
Site Selection, Resource Assessment
&
Energy Yield Estimation
Site Selection
3 Good Layout
Good Layouts Hapezoidal Layouts
Improper Site Selection
Plan for Rock Blasting
Compromising With Placing Modules
Good Topography
Site Survey & Investigation
Some of the other major factors that are to be considered
are
• Atmospheric effect on Solar Radiation
• Daily and Seasonal Temperature Variations
• Site proximity to natural disaster prone areas
• Site climatic conditions with regards to wind speeds,
saline atmosphere conditions etc.
• Site land topography. This will impact on the civil
foundation requirements
• Proximity for power evacuation
• Proximity to polluting industries
• Easy site access
Cognizance for site selection
13
Solar Resource Assessment
Step 1Type the following link in the web browser
Solar Resource Assessment
Step 2
Click on Meteorology and Solar Energy section. The page as detailed below will be displayed
15
Solar Resource Assessment
Step 3
• Click on Enter Latitude and
Longitude part of Data tables for
a particular location. The following page will be displayed • This is known as Login screen. User has to enter
– E-Mail ID
– Password of his choice – Re enter the same password in third field
Solar Resource Assessment
Step 4
After entering all the details, by clicking on Submit button, the following screen will appear
17
Solar Resource Assessment
Step 5
• If the user is interested in solar radiation assessment in Delhi, one has to enter the following values in the latitude and longitude field of the screen.
Latitude : 28.38 N Longitude : 77.12 E
After entering the values, the screen will be as shown. Then, Click on Submit
Solar Resource Assessment
Step 6
Choose parameters as per your requirement
19
Solar Resource Assessment
Step 7
Energy Yield Estimation
The following stage of evaluation is to carried out while designing / verifying
• Weather data NASA / METEORNOM • Simulation programme
• Choice of system components (Max. efficiency components) • Software to be used
- PVsyst - RETScreen
- System Advisory Model - TRANSYS
- PYSOL • Simulation • Analysis of yield
21
Energy Yield Estimation
Case StudyTo design a 5MWp solar PV grid-connected power plant at a designated location in Bangalore
Design Inputs • Site Details
– Bangalore , Latitude-13 0 Longitude- 77 0
• DC Plate Rating – 5 MWp
• Technology
– Thin Film Technology • Inverter
– Central Inverter
Energy Yield Estimation
Option : Project design, System : Grid-Connected
23
Energy Yield Estimation
Click on ProjectEnergy Yield Estimation
Select ‘New Project’ enter the relevant data and then click ‘Site and Meteo’
25
Energy Yield Estimation
Enter relevant dataEnergy Yield Estimation
Click ‘Open’ to enter the Location parameters of the site
27
Energy Yield Estimation
Geographical ParametersEnter Latitude, Longitude, Altitude etc. and go to ‘Monthly meteo’ tab to see the irradiation data
Energy Yield Estimation
Irradiation DataIrradiation unit can be chosen as required and click ‘OK’.
29
Energy Yield Estimation
Situation & MeteoEnergy Yield Estimation
Operating temperatureDepending on site choose summer operating temperature for Vmpp Min design (the default is 60⁰ C) and click ‘OK’
31
Energy Yield Estimation
OrientationEnergy Yield Estimation
Tilt• Click ‘Unlimited Sheds’ enter the ‘Plane Tilt’, ‘Pitch’, ‘Coll. band width’ and select the ‘Electrical Effect’ and click ‘Show Optimisation’
33
Energy Yield Estimation
Shading lossShading Loss is displayed in this window. Close this window and ‘OK’
Energy Yield Estimation
SystemClick ‘System’
35
Energy Yield Estimation
Module and Inverter selectionEnergy Yield Estimation
String definitionSelect ‘Mod. In series’, enter ‘No. strings’ and click ‘Detailed Losses’
37
Energy Yield Estimation
PV Filed losses (Thermal)Enter ‘NOCT coefficient’ as given in Module datasheet and go to ‘Ohmic Losses’ tab
Energy Yield Estimation
PV Field - losses (Ohmic)Enter ‘DC circuit loss fraction at STC’, choose ‘Significant length’ and enter ‘Loss fraction’, ‘External transformer’ and enter the ‘Iron loss’ & Inductive loss’ also enter the Vac and go to ‘Module Quality -
Mismatch’ tab.
39
Energy Yield Estimation
PV Field – losses (Module Mismatch)Energy Yield Estimation
PV Field - Losses (Soiling)Select the ‘Soiling Loss’ of 3% and go to ‘IAM Losses’ tab
41
Energy Yield Estimation
IAM LossesEnergy Yield Estimation
Click OK43
Energy Yield Estimation
SimulationEnergy Yield Estimation
Simulation ParametersClick ‘Simulation’
45
Energy Yield Estimation
Simulation ProgressEnergy Yield Estimation
Simulation ResultsClick ‘Report’
47
Energy Yield Estimation
PVSYST Design ReportEnergy Yield Estimation
PVSYST Design Report49
Energy Yield Estimation
PVSYST Design Report© 2011 Underwriters Laboratories Inc.
PHOTOVOLTAIC (PV)
– INSTALLER
GUIDE
Objective
• Verify System Design
• Managing the project
• Installing electrical components
• Installing Mechanical components
• Completing system Installations
Introduction
Balance of system (BOS) component include all mechanical of electrical equipment and hardware used to assemble and integrate the major components in a PV system
Example of BOS components include:
3
Verify system Design
• Determine Clients Need
Review Site Survey
• Obtaining the necessary information during a site survey helps plan and
execute PV installations in a timely and cost effective manner.
7
Array Location
9 1. Enough Area to get maximized energy 2. Is it shaded?3.Is the structure strong enough?
5. How far the array will be mounted from other equipments? 4. How will the array be mounted?
Array Location
How will the array be installed & maintained? Will the array be subjected
to damage or accessible to unqualified person?
Are there any local codes or wind load concerns for areas of PV installation?
Are there additional safety, installation or maintenance concern?
Array Area
For multiple rows of tilted racks or for tracker installation additional
spacing is required between each array mounting structure to prevent the row to row shading.
Additional area is required for installation of other equipments. Usually
for 1 KW dc crystalline power plant we need approximately 80 to 100 sf of surface area.
As a thumb rule we can say that for 1 KW power plant approximately 16
square meter area is required.
11
Perform a shading analysis
• PV array should be unshaded at least 6 hours during the middle of the day to produce the maximum energy possible.
• Ideally there should be no shadow between 9 a.m. and 3 p.m. solar time over the year, since the majority of solar radiation and peak system output occur during this period.
Sun Path finder
13
Array mounting method.
• PV array can be mounted on the ground, rooftops and other structures that
provide adequate protection, support and solar access. The site conditions and Results of the site survey usually distance the best mounting system location and approach to use.
Array mounting systems
15
Building integrated
Mounting System
Roof Structure and conditions
Key points:
1. Check out the roof’s load bearing capacity and its underlying structures so that it can bear the additional load.
2. A civil engineer need to calculate the load with respect to local code compliance. We can also refer to standard ASCE 7 – minimum loads for buildings and other structures.
3. A standard roof mounting structure weighs between 3 and 5 pounds per square feet which is fine for most roofs designed to recent standards.
4. A span table can help to quantify the load bearing capabilities of roof trusses or beams. The website for this is www.solarabcs.org.
Roof Structure and conditions
1. Wind loads are the primary concern for roof top m ounting systems. For hurricane prone regions the design wind load can be as high as 150 m ph w hich can exceed the actual wind load of 50 PSF and m ore in some corners of roof or structure. A structure engineer is required for the approval of the structures w ith respect to the wind load design of the array.
2. Before deciding the PV array mounting system verify with the m ounting system supplier that the hardware is appropriate for the given application.
3. For com m ercial roof m ounting system we can use the ballasted mounting system. This is significantly heavier than mounting system designed for direct structural attachments. But this system needs special load calculation. The m ain advantage is the possibility of roof leaks is greatly diminished.
17
BOS Location
1. Selection of appropriate location for all the BOS.
2. The BOS have to e w eather resistant. They may need to be installed in the w eather resistant enclosures. For this w e can refer to article 110 from NEC. 3. Avoid installing electrical equipments in locations exposed to high
tem perature and direct sunlight and provide adequate ventilation and cooling for heat generating equipments like inverters, generators, charge controllers etc. It is always better to have proper IP rating for these equipments to avoid damage from rain, dust, chemical and other environmental factors.
4. Battery location should be protected from extreme cold area because this will reduce the available capacity. They should be installed as per NEC 480. 5. Protection should be taken to prevent the attack from insects, rodents and
Confirm System Sizing : Size module mounting Area
• If site is selected for array location, it is necessary to determine whether the place is enough for the proposed number of PV modules.
• For Areas with NON-rectangular shapes, determine the amount of usable area can be challenged.
• Access to the modules must be provided in case system maintenance is needed.
• Smaller array surface area are required to generate the same amount of power with higher efficiency modules.
19
Confirm System Sizing : Arrange Modules in mounting area
• S itting the PV array in the available Mounting area can have a large impact on the performance of a PV array.
• Each set of modules in a series string must be oriented in the same direction if the string is to produce its full output potential.
• Is it possible to split a string between two roof faces, provided the modules keep the exact same orientation
21
Confirm System Sizing :Review Energy Storage Systems
• Capacity is a measure of battery energy storage, commonly rated in Ampere-hour
• Rate of charge or discharge is expressed as a ratio of the nominal battery capacity to the charge of discharge time period in hours.
• Usable capacity is always less than the rated battery capacity. Operational factors that effect available battery capacity include discharge rate, cut-off voltage, temperature and Age of battery
• A nominal 100 Ah battery discharged at 5 amps for 20 hours is considered a C/20, or 20 hour discharge rate
Confirm System Sizing :Review Energy Storage Systems
23
• The battery state of charge is related to the concentration of sulfuric acid
concentration. This is measured by specific gravity.
• Specific gravity is the ratio of the density of a solution to the density of
water.
• A fully charged lead acid cell has a typical specific gravity between 1.26
and 1.28 at room temperature.
• The specific gravity may be increased for lead-acid battery used in cold
weather applications. Conversely, the specific gravity can be decreased for application in warm climate.
• In very cold climate the battery should be protected from freezing by
limiting minimum temperature in a suitable enclosure or by limiting the Depth of Discharge.
Confirm System Sizing :Review Energy Storage Systems
Depending on the application or site requirement many factors are considered to select the battery and for system design as follows:
• Electrical properties: voltage, capacity, charge/discharge rates • Performance: cycle life vs. DOD, system autonomy
• Physical properties: size and weight • Maintenance requirements: flooded or VRLA
• Installation: Location, structural requirements, environmental conditions • Safety and auxiliary systems: racks, trays, fire protection, electrical BOS • Costs, warranty and availability.
Confirm System Sizing: Review Energy Storage System
25 Electrical Properties: voltage, capacity, charge/discharge rates Performance: cycle life Vs. DOD, system autonomyPhysical properties: Size and weight
Maintenance requirements: Flooded or VRLA
Installation: location, structural requirements, environmental conditions
Safety and auxiliary systems: racks, trays, fire protection, electrical BOS
Costs, w arranty
and availability
Confirm System Sizing :Review Energy Storage Systems
• Racks and trays are used to support battery systems and provide electrolyte containment
• Racks can be made from metal, Fiberglass or other structural non conductive material.
• Metal racks must be painted.
• Due to potential for ground faults, metals or other conductive battery tracks are not allow ed for open Vent flooded lead acid batteries more than 48 Volts nominal.
• If batteries are connected in series to produce more than 48 V, then the batteries must be connected in a manner that allow s the series strings of batteries to be separated into strings of 48 V or less for maintenance. • Overcurrent protection device or other such protective equipment's should be
Charge controller operations
• A battery charge controller limits the Voltage and current delivered to battery
from a charging source to regulate state-of-charge.
• A CC is required in most PV systems that use battery storage.
• PV array must not be capable of generating voltage or current that will
exceed the CC input voltage & current
• The CC rated continuous current must be 125% of the PV array Shot circuit
O/p current.
• The CC maximum i/p voltage should be greater than the maximum system
voltage
27
Charge controller operations : Set points
Set Point:
Set points are the battery voltage levels at w hich a charge controller performs regulation or control functions. The [proper regulation set points are critical for optim al battery charging.
1. Regulation Voltage (VR) is the maximum v oltage set point the controller allows the battery to reach bef ore the array current is disconnected or limited. 2. The array Reconnect Voltage (ARV) – f or interrupting ty pe controllers, is the v oltage set point at which the array is reconnected to charge the battery
3. Low Voltage Disconnect (LVD)
– def ines the maximum battery depth of
discharge at the giv en discharge rate. 4. Load Reconnect Voltage (LRV)- the set point where load are For a ty pical lead acid cell a LVD set point of 1.85
VPC to 1.91 VPC corresponds to a DOD of 70 to 80% at C/20 discharge rates or lower.
Load
Battery Bank
Charge controller operations : PWM VS Advance CC
:
29
Charge controller operations
• The temperature Compensation is a feature of CC that automatically adjusts charge regulation voltage for battery temperature changes.
• The sensors can be internal or may be fixed to batteries.
• Temperature compensation is recommended for all types of sealed batteries, which are more sensitive to overcharging than flooded type.
• Temperature compensation Helps to fully charge a battery during colder conditions, and helps protect it from Overcharge and Over discharge.
• For larger systems, the O/p of multiple CC may be connected in parallel and used to charge a single battery bank.
• A diversionary CC diverts excess PV array power to Auxiliary loads when primary battery is fully charges.
Maximum power point tracking (MPPT)
• A MPPT Charge controller operates PV arrays at Maximum power under all operating conditions independent of battery voltage.
• MPPT can improve array utilization and allow non-stnadard and higher array operating voltages, requiring smaller conductors and fewer source circuit to charge lower voltage battery bank.
• Normally the O/p current of a MPPT will be less than or equal to the I/p Current.
• If a MPPT CCU is used it is important to consult the Manufacturer’s spec to determine the Maximum O/p load.
31
Parallel connections
33
PV Inverter
Stand Alone inverter: operates from battery and supply power independent of the electrical utility system. They may also include battery charger to operate from an independent AC source such as generator.
Bi-m odal inverter: battery based interactive inverter acts as diversionary charge controllers by producing AC power o/p to regulate PV array battery charging and sends excess power to the grid when energized.
PV Inverter
Utility-interactive or grid connected inverter: operates from PV arrays an supply pow er in parallel w ith an electrical production and distribution network.
Types:
1. Module level inverter: They include AC modules and micro inverters. They are sm all and rated for 200 to 300W m aximum. Advantages of these inverters are, they include individual m odule MPPT and better energy harvest from partially shaded and m ulti directional arrays. More safer than string inverters as the m axim um dc voltage on array is for a single module (35 -60V).
2. String Inverter: small inverters in the 1 KW to 12 KW size range, intended for residential and small commercial applications. Generally single phase and lim ited to 1 to 6 parallel connected source circuits.
35
Different types of Grid interactive inverters.
Specification of inverters
37
Review Wiring and conduit size calculations
Determine circuit current :
PV Power S ource Maximum circuit current :
Inverter output circuit current :
39
Calculate required ampacity of the conductor (Wire)
The required ampacity of conductors is based on : • Maximum Circuit current
• Size of overcurrent protection device • Ambient temperature of the conductor • Type of conductor and insulation • The conduit fill of the conductor
Calculate Voltage Drop
45
47
PV string cables, PV array cables and PV DC main cables shall be selected and erected so as to minimize the risk of earth faults and short-circuits.
Wire Management: Array conductors are neatly and professionally held in
place
Wiring systems shall withstand the expected external influences such as
wind, ice formation, temperature and solar radiation.
49
Install Wiring systems
Install Wiring systems
Protection by use of class II or equivalent
insulation should preferably be adopted on the
DC side
.
Common Installation Mistakes with Wire Management:
1. Not enough supports to properly control cable. 2. Conductors touching roof or other abrasive
surfaces exposing them to physical damage. 3. Conductors not supported within 12 inches of
boxes or fittings.
4. Not supporting raceways at proper intervals. 5. Multiple cables entering a single conductor cable
gland (aka cord grip)
5. Pulling cable ties too tight or leaving them too loose.
6. Bending conductors too close to connectors. 7. Bending cable tighter than allowable bending
Install Grounding system
51
Installing Mechanical Components
53
Install PV modules
55
Install PV modules
57
Visual Inspection
59
© 2011 Underwriters Laboratories Inc.
IEC 62446: Grid Connected Photo Voltaic Systems – Minimum Requirements for System Documentation, Commissioning Tests and Inspection
Learning Objective
.
commissioning tests
inspection criteria documentation
To verify the safe installation and correct
operation of grid connected solar Power
Content
Clause 4: System documentation requirements Clause 4.2: System Data
Clause 4.3: Wiring diagram Clause 4.4: Datasheets
Clause 4.5: Mechanical design information Clause 4.6: Operation and maintenance information Clause 4.7: Test results and commissioning data Clause 5 :Verification
Clause 5.2:Inspection Clause 5.2: Testing
Clause 5.2: Verification reports
3
Clause 4: System
5
4.2 System data - Basic system information
Project identification reference (where applicable)
.
Rated system power (kW DC or kVA AC).PV modules and inverters - manufacturer, model and quantity.
Installation date.
Commissioning date.
Customer name
.
Site address.
4.2.2 System designer information
Information shall be provided for all bodies responsible for the design of the system. Where more than one company has responsibility for the design of the system, information's together with a description of their role in the project.
7 System designer,
company.
System designer, contact person. System designer, postal address, telephone number and e-mail address.
4.2.3 System installer information
Information shall be provided for all bodies responsible for the installation of the system. Where more than one company has responsibility for the installation of the system, information should be provided for all companies together with a description of their role in the project.
System installer, company
System installer, contact person. System installer, postal address, telephone number and e-mail address.
4.3 Wiring diagram
9 Array - general specifications PV string information Array electrical details Earthing and overvoltage protection a) Module type(s) b) T otal number of modules c) Number of strings d) Modules per string a) String cable specifications – size and type. b) String over-current protective device specifications c) Blocking diode type (if relevant).a) Array main cable specifications – size and type. b) Array junction box locations c) DC isolator type, location and rating d) Array over-current protective devices – type, location and rating (voltage / current). a) Details of all earth / bonding conductors b) Details of any connections to an existing Lightning Protection System (LPS). c) Details of any surge protection device installed (both on AC and DC lines) to include location, type and rating. AC system a) AC isolator location, type and rating. b) AC overcurrent protective device location, type and rating. c) Residual current device location, type and rating (where fitted).
4.4 Datasheets
Datasheets shall be provided for the following system components NOTE The provision of datasheets for other significant system
components should also be considered.
11
Module datasheet for all types of
modules used in the system - to
the requirements of IEC 61730-1.
Inverter datasheet for all types of
inverters used in the system.
4.5 Mechanical design information
4.6 Operation and maintenance information
Operation and maintenance information shall be provided and shallinclude, as a minimum, the following items:
13 Procedures f or v erif ying correct sy stem operation. A checklist of what to do in case of a sy stem f ailure. Emergency shutdown / isolation procedures Maintenance and cleaning recommendat ions (if any).
Considerations for any future building works related to the PV array (e.g. roof works). Warranty documentation for PV modules and inverters - to include starting date of warranty and period of warranty. Warranty Documentation on any applicable workmanship or weather-tightness warranties.
Clause 5 : Verification
5.3 Inspection (Requirements)
PV array design and installation
PV system - protection against overvoltage / electric
shock
PV system - AC circuit special considerations
PV system - labelling and identification
PV system - general installation (mechanical)
15
PV array design and
installation.
Stand Alone SPV power Plant
17
Field Inspection Checklist for Array:
1. Number of PV modules and model number matches plans and spec
sheets
2. with the module model number and quantity of modules confirmed, the
physical layout of the array should match the supplied site plan. Common Installation Mistakes with Array Modules and Configurations: 1. Changing the array wiring layout without changing the submitted electrical
diagram.
2. Changing the module type or manufacturer as a result of supply issues. 3. Exceeding the inverter or module voltage due to improper array design. 4. Putting too few modules in series for proper operation of the inverter during
high summer array temperatures.
19
Ratings for DC Components
• DC components rated for current and voltage maxima (Voc stc corrected for local temperature range and module type; current at Isc @ stc × 1.25
Note:
1) Overload protection may be omitted to PV string and PV array cables when the continuous current-carrying capacity of the cable is equal to or greater than 1,25 times ISC STC at any location. 2) Overload protection may be omitted to the PV main cable if the
continuous current-carrying capacity is equal to or greater than 1,25 times ISC STC of the PV generator.
Array Junction Box/ Main Junction Box/Combiner Box
21
Fuse
Surge Protector DC Disconnect device
Incoming String Wires (L+ & L-) going to
inverter
Wiring systems
PV string cables, PV array cables and PV DC main cables shall be
selected and erected so as to minimize the risk of earth faults and short-circuits.
Wire Management: Array conductors are neatly and professionally held in
place
Wiring systems shall withstand the expected external influences such as
DC Cables.
Protection by use of class II or equivalent
insulation should preferably be adopted on the
DC side
.
Common Installation Mistakes with Wire Management:
1. Not enough supports to properly control cable. 2. Conductors touching roof or other abrasive
surfaces exposing them to physical damage. 3. Conductors not supported within 12 inches of
boxes or fittings.
4. Not supporting raceways at proper intervals. 5. Multiple cables entering a single conductor cable
gland (aka cord grip)
5. Pulling cable ties too tight or leaving them too loose.
6. Bending conductors too close to connectors. 7. Bending cable tighter than allowable bending
radius.
8. Plug connectors on non--‐locking connectors not fully engaged
23
DC Conductors earthing.
Earthing of one of the live conductors of the DC
side is permitted, but there must be a simple
separation between the AC side and DC side.
DC switch disconnector
In every PV installation it is
necessary to isolate the
photovoltaic panel from the
rest of the system.
DC Isolators must have a
higher performance than the
traditional AC Isolators
because breaking direct
current is more difficult than
breaking alternating current.
DC switch disconnector
should be fitted to the DC side
of the inverter.
25
415V, 63A, 3pole AC MCB
Example to calculate the disconnect devices
• Example of PV sizing of disconnect switches.Determine the minimum size in terms of Voltage and current of the disconnect based on follow ing informations:
Maximum input operating range : 300 -480 V dc Maximum input voltage (Voc) : 600V
Maximum rated input current : 800A (DC)
Maximum input Isc rating : 1200 A (DC)
Example to calculate the disconnect devices
Solution :
• PV Disconnect
Maximum continuous input current = maximum input short circuit current rating * 125%
= 1200A * 125% = 1500A (DC) Maximum input Voltage (Voc) = 600 V (DC)
The PV disconnect switch must be rated for minimum of 1500A (dc) @ 600 V (dc).
PV disconnect devices for 1000Vdc shall be evaluated under UL98B.
27