METHOD STATEMENT FOR FIRE
PROOFING WORKS FOR PRESSURE VESSEL
SKIRTS
Client
:
Kuwait Oil Company (K.S.C.)
Contract No.
:
11050146
Project No.
:
EF/1772
Location
:
Burgan Field and South East Kuwait Fields
Job No.
:
101920
TABLE OF CONTENTS
1.
Purpose --- 3
2.
Scope --- 3
3.
Definitions --- 3
4.
References --- 3
5.
Responsibilities --- 3
6.
Procedure --- 6
7.
Documentation --- 6
8.
Attachments --- 6
The purpose of this method statement is to detail the scope of fireproofing works of Pressure Vessel Skirts only as per specifications
SCOPE:
This method statement shall cover the activities and requirements in carrying out the works for Fireproofing works of Pressure Vessel Skirts only at The Contractor will be responsible for arranging all construction equipment, materials for civil work and manpower to perform all works described herein and in accordance with the contract specification, approved procedure/method statement and approved drawings.
2. DEFINITIONS: Company: Contractor: . Sub-contractor: 3. REFERENCES
4.1 Approved Construction Drawings 4.2 Codes & Standards Applicable 4.3 KOC Standard, Doc. No. KOC-C-027
4. RESPONSIBILITIES:
5.1 Field Engineers and Supervisors shall be responsible for:
a) Referring to Approved Construction Drawings prior to commencement of Civil Work. b) Application and receipt of Work permits from the Company or Nominated Permit Issuer. c) Lead subcontractor's work permit timely, ensuring that all permits required are
authorized prior to start of any activity.
d) Compliance to Construction Procedure approved by the Company. e) Prepare the Job Safety Analysis (JSA) Report.
f) Ensure compliance to KOC Fire and Safety Regulations,Pptw System and Approved JSA
5.2 Subcontractor's Field Supervisors and Site Surveyor shall be responsible for:
a) Referring to Approved Construction Drawings prior to commencement of civil work. b) Site Preparation for commencing the construction activities.
c) Raise necessary Work Permit prior to start of any work. d) Comply with the Job Safety Analysis (JSA) Report. e) Ensuring Safety Requirements at site working crew.
5.3 HSE Supervisor shall be present at all times during construction activities.
5. PROCEDURE: 6.1 Material to be used:
All materials to be used shall have Company approval and shall comply with KOC-C-027. Fireproofing material shall be vermiculite cementitious material FENDOLITE MII. (Manufactured by: Promat Fireprotection LLC, (formerly M/s. Cafco International, UK).
6.2 Material Storage:
The materials shall be kept dry until ready for use. They shall be stored off the ground, under cover and away from wet or damp surfaces. Storage temperature is not critical as long as dry conditions are maintained.
Packing Damaged Fire proofing material shall be discarded.
6.3 Application Procedure:
Fireproofing material will be FENDOLITE MII. The Fire rating for the above material shall be 2 (two) Hours, for an application thickness of 50 mm thk.
6.3.1 Surface Preparation:
Prior to application of Keycoat, the paint system shall be check for compatibility incase of materials selected other than in-situ dence / light weight concrete as per Claus 10.1.5 of KOC-C-027 Rev 2
No field welding shall be carried out on skirts or legs of any equipment without prior approval from company.
Substrate surfaces shall be inspected thoroughly prior to application. Surface must be free from contamination, mud ,cracking, loose paint or conditions likely to impair adhesion of the Fendolite MII.
Surface shall be manually cleaned to remove any dust, dirt, sand and oil contamination by cotton rag prior to application of the Fireproofing material. Thinner shall be used for
To apply one coat of 50 micron keycoat PSK 101 over already primed surface. This coat will function as sealer before application of Fendolite MII.
The reinforcement of 50 mm x 50 mm x 1.6 mm plastic coated wire mesh shall be fixed or held in position on stud already welded by vessel manufacturer at vessel skirts and secured with washers. The reinforcing mesh must be positioned so as to lie substantially within mid third of the applied Fendolite MII thickness.
Reinforcement installation shall be complying with Company standard KOC-C-027.
Anchor bolts shall be coated with grease prior to applying fire proofing as per KOC-C-027.
6.3.2 Mixing and Application:
Fireproofing material Fendolite MII manufactured by M/s. Promat Fire Protection LLC (formerly M/s. Cafco International, UK / M/s. Mandoval Coatings Ltd., UK) is premixed at the factory and it is only necessary to mix it with water to a pumpable consistency.
Bags of pre-mixed vermiculite cement shall be kept dry until ready for use.Stored off the ground under cover and way from wet or damp surfaces or areas of high humidity.
The pre-mix shall be used within six momnths of manufacture.
One 20 kg bag of Fendolite MII requires approx. 15 to 19 litres of water to obtain the correct consistency. Mixing time in the mechanical mixer is 3 minutes minimum to ensure correct property of the mix.
The vermiculite cement shall be mixed to the specific quantity required and no further water shall be added to make the mix more workable.
The wet mix shall be applied by spraying, machine based on mono pump of speed in the range of 100 - 600 rpm upto 15 mm thick for each coat, to have a total thickness of 50 mm (2 hours fire rating).
It is important that the preceding coats if any should be well scratched to ensure good bonding. The final finished surface of Fendolite MII will be lightly trowelled to have a reasonably smooth finish. Air pressure should not be more than 2 bar at the nozzle. No rebound materials shall be used.
The applicator should be approved by the Manufacturer having minimum three years of experience with profound track record.
6.3.3 Curing:
Curing shall be done similar to curing of any concrete~ procedure by which the applied fireproofing material is kept damp / wet for atleast 4 days. It can be achieved by spraying water, covering the exposed surface with polythene sheeting to retain moisture or wrapping with wet jute sack.
Use of trowel, roller or brush shall be made to achieve the final finish typically within 1 to 2 hrs after application of the Fire proofing material. A 15 mm deep by 15 mm wide rebate Joint sealant shall be applied at the termination point with metal surface to achieve proper sealing.
Repair of Fire proofing shall be in accordance with Company standard KOC-C-027.Clause 11.0
6.3.5 Safety:
All Works shall be carried out in accordance with koc Fire and Safety Regulations,PTW and approved JSA.
6.3.6 Housekeeping:
All over sprayed fire proofing materials / Empty bags shall be cleared and area shall be cleaned on daily basis.
6. DOCUMENTATION:
For the purpose of reviewing the status of each stage of work/site tests, it is necessary that the site survey report, daily activity report, if any, shall be prepared every day by the Supervisor and kept separately.
All test reports and certificates during the construction phase will be issued to the Company for review and at the end of the Project all reports and certificates will be included and submitted to the Company in the final project documents.
7.1 Request for Inspection:
Inspection notification of witness point shall be notified to the Company.
Surveillance inspection shall be notified verbally to the company Representative.
7.2 Site Record:
Site Record for Fire proofing shall use KOC-C-027, Appendix 1 as a guide for Site Record Form.
7. ATTACHMENTS