• No results found

Communication between

N/A
N/A
Protected

Academic year: 2021

Share "Communication between"

Copied!
9
0
0

Loading.... (view fulltext now)

Full text

(1)

HMA HC800

Communication between

Dynamic Positioning System

and

Power Management System

What is needed?

DOCUMENT HISTORY Revision

Index

Chapter Description of changes Prepared Checked Approved Date

01 Document first issue KH/HMA 2012-04-25

02 Updated KH/HMA 2013-02-02

(2)

INDEX

1  INTRODUCTION...3 

1.1  INTENTION AND SCOPE...3 

1.2  NOTICE...3 

1.3  ABBREVIATIONS AND DEFINITIONS...3 

1.4  RELATED DOCUMENTS...3 

2  GENERAL...5 

2.1.1  The redundancy aspect...6 

2.1.2  List of HMA vessels not having communication between DP and PMS ...8 

(3)

1 Introduction

1.1 Intention

and

scope

The intention of this document is to emphasize and support the fact that DP systems and the PMS systems should be independent from each other rather than connected together. This document further describes in text and pictures the use of a non-existing communication between the DP system and the PMS. At last but not least there is a list of vessels showing the vessels delivered with HMA PMS that do not have any communication what so ever, between the DP and PMS. These systems are working independently.

1.2 Notice

The information in this document is subject to change without notice and should not be construed as a commitment by Høglund Marine Automation AS. HMA will not and cannot be held responsible for any changes that might occur. Copyright © 2012 Høglund Marine Automation AS.

1.3 Abbreviations

and

definitions

HMA Høglund Marine Automation AS

DP Dynamic positioning System

PMS Power Management System

DP Dynamic Positioning

MTBF Mean Time Between Failure

1.4 Related

documents

(4)

ANY

INTERFACE

REQUIERED?

(5)

2 General

Due to the fact that some companies want to mystify this subject in order to deliver an integrated DP-PMS-ICAS solution, a demand for this clarification document has risen.

There is a huge misunderstanding in this subject to day.

Many engineers among ship owners and yards believe that a communication between the DP and the PMS is crucial for a safe operation of the vessel.

This is mainly caused by lack of detailed knowledge and experience in this field.

The truth is:

NO INTERFACE FROM PMS TO DP IS NEEDED AT ALL !

How is this possible?

The only signals needed by the DP, is the power signals from each generator. In a systems with a bus tie breaker, a connected signal from bus tie is also needed.

For many decades there have been delivered systems with the demand for generator power information. It became a common practice to install several power transducers in the switchboard for this information. The reason for this is that in the early days, it was each consumer that had to limit its own power and protect the generators from overload.

Typically this have been done for propellers (pitch controlled) compressors, pumps, drilling drives, and other large consumers.

All this consumers would get an own generator power signal for load control.

This was also the case with the first DP systems as diesel electric propulsion become more common. The DP system got its own power converter for each generator, and in some cases also the “connect” signal from the breaker. The “connect” signal from the breaker is not necessary, as the power signal will give a clear indication on the status of the generator breaker, because the power signal will be above zero KW when it is connected.

There are other PMS information that might be sent from the PMS to the DP, however most of the installed DP systems do not need such information for operating. This information must be understood as “nice to have” only.

(6)

2.1.1 The redundancy aspect

The DP system is 100% dependent of the load status of the generators in order to operate.

If this information is sent to the DP system from the PMS, the total operation of the vessel is dependent on a fully operational PMS.

Any failure of the PMS or any PMS component will be crucial for the DP, as the generator power load situation will be uncertain.

(7)

In addition to the necessary power information there are additional information that might be sent between the PMS and the DP:

PMS to DP

• Number of available generators in the system • Critical failures in a running generator

• Any load limitations on the connected generators • Status of other essential consumers requesting power DP to PMS

• DP – out of position • Requested power • Force preference trip

All this information is optional and rarely used, and may be sent via standard I/O signals, or a simple NMEA or Modbus line.

(8)

2.1.2 List of HMA vessels not having communication between DP and PMS

There are hundreds of vessels in operation to day, where there is no communication between the DP and the PMS. The following list just shows some of this vessels where HMA has been involved in delivering the PMS.

None of the following vessels have any communication between DP and PMS.

Vessel Shipyard Owner Type

Crystal Sea (BW Carmen) Aker Langsten DOF (BW Offshore) FPSO

Sea Launch Rig Kværner Rosenberg Kværner Launch Rig Sea Launch Ship Kværner Rosenberg Kværner Launch Support Vessel Fresnel Ulstein Verft Diesel Electric Cable Layer Crystal Ocean Kvaerner Govan Brøvig Diesel Electric Offshore Vessel Bideford Dolphin Harland Wolf Fred Olsen Energy Drilling Rig

Normand Cutter Ulstein Verft Solstad Offshore Cable layer Yatzy Boelverf, Belgium Dimond Drilling Oil Rig Skandi Carla Aker Aukra DOF ROV IRM Normand Clipper Ulstein Verft Solstad Offshore Cable layer

Stril Poseidon Aker Langsten Møkster Standby Vessel Tulpar Ulstein Verft BUE Marine UK Ice Supply

Seaway Petrel Aker Yards, Brattvaag Uksnøy Petrel AS Diesel Electric Offshore Vessel Skandi Sotra Myklebust DOF Diesel Electric Offshore Vessel Viking Avant Aker Langsten Eidesvik Supply

Bibby Sapphire Aker Langsten Volstad Diesel electric ROV Vessel Strilmøy Aker Langsten Møkster Diesel Electric Supply Havila Harmony Havyard Havila Diesel electric Supply Vessel Siem Louisa Aker Aukra Siem Offshore Supply

Siem Danis Aker Aukra Siem Offshore Supply SBS Typhoon Aker Aukra SBS Marine Supply

Pacific Endurance Aker Langsten Prisco Swire Offshore Diesel Electric Ice supply Pacific Enterprise Aker Langsten Prisco Swire Offshore Diesel Electric Ice supply Siem Sophie Aker Langsten Siem Offshore Supply Stril Odin Aker Langsten Møkster Diesel Electric Supply Far Swan (prev Sical Torino) Aker Langsten Siem Offshore Supply

Pacific Endeavour Aker Yards, Langsten Prisco Swire Offshore Diesel Electric Ice supply Lewek Atlas (ex Siem Mollie) Aker Aukra Siem Offshore Supply

(9)

Skandi Arctic STX Søviknes Doftech DA Diving vessel

Skandi Salvatore Fittjar Mek DOF Offshore Vessel Skandi Flora Aker Aukra DOF Offshore Vessel Skandi Vitoria Aker Promar DOF Offshore Vessel Atlantis Dweller WestCon Møkster ROV/Diving

Lewik Atria (Trico Star) Tebma Shipyard, India Emas Offshore VS470 MK2 Supply Abyss Dweller WestCon Møkster

VS470 MK2 Tebma Shipyard, India Trico Marine VS470 MK2 Supply West Epsilon Seadrill Upgrade IAS-F&G-ESD Stril Merkur Astilleros Gondan Simon Møkster Shipping VS-482.II FSV Stril Orion STX Søviknes Simon Møkster Shipping PSV

Stril Polar STX Søviknes Simon Møkster Shipping PSV SCI Pawan Cochin AHTS

Skandi Sotra Bergen DOF Uppgrade IAS-PMS SCI Kundan Cochin AHTS

BW Athena BW Offshore FPSO - Upgrade Cargo Control VS470 MK2 Tebma Shipyard, India Trico Marine VS470 MK2 Supply

2.1.3 Contact details

Høglund Marine Automasjon AS Carl XV`s gate 19

N-3150 Tolvsrød Norway

References

Related documents