FPSO Operational Problems
Don Smith OGP
Analysis of Accident Statistics for Floating
Monohull and Fixed Installations
• UK HSE Study
• Analysis of offshore accident statistics from 1996 – 2002 (6
years period):
– No fatalities
– 21 accidents involving hospitalisation
– 85 3-day off work
Dangerous Occurrences for Floating
Production Systems 1996-2002*
Hydrocarbon Releases 48% Diving 1% Wells 0% Biological 0% Stability 0% Collision 2% Electrical 4% Evacuation 1% Potential Collision 3% Lifting Machinery 8% Pressure 5% Pipeline 4% Fire/Explosion 8% Substance 3% Collapse 1% Positioning/Dropped Object/Adverse Weather 12% (37% total population)Total Number of Dangerous Occurrences 317 * Provisional
FPSO Dangerous Occurrence Categories
• Riser/Turret/Swivel
• Vessel SW/COW/Vent
• Offloading System
• Moorings/DP
• Collision/Stability
Distribution of FPSO Dangerous Occurrences
Riser/Turret/Swivel
33%
(26)
Offloading System
22%
(17)
Motion Related Incident
15%
(12)
Moorings/DP
9%
(7)
Vessel SW/COW/Vent
10%
(8)
Collision/Stability
11%
(9)
Wave Related Incidents (1995 – 2000)
0 1 2 3 4 5 N u m b er of Inc ide nt s 1995 1996 1997 1998 1999 2000 Year
17 Greenwater, 2 Wave Slam
0.28 incidents per vessel year
Comparison of Accident Rates
(per installation type)
0 5 10 15 20 25 30 35 40 45 50 Accident Rate (per installation) 96/97 97/98 98/99 99/00 00/01 01/02 Year FPSO All
Comparison of Accident Rates
(per 100,000 Workers)
0 1000 2000 3000 4000 5000 6000 7000 Accident Rate (per 100,000 Workers) 96/97 97/98 98/99 99/00 00/01 01/02 Year All FPSOA summary Report on FPSO Lessons Learned,
gathered from 4 Norwegian FPSOs – May 2002
Prepared for the Norwegian Oil Industry Association
(OLF)
Study Aims and Methodology
• Aim: to collect lessons learned from experiences of
operators of Norwegian FPSOs
• Information collected from 4 installations:
– Jotun A (ExxonMobil)
– Varg (Norsk Hydro)
– Asgard and Norne (Statoil)
Survey Tool
• Seven Main Areas:
– Hull and Marine
– Turret
– Layout
– Project Management
– Operations and Support
– Codes/Classification
– Manning and Safety
Hull and Marine
(172 issues/problems reported)
•
Green Water (Critical)
– 3 out of 4 FPSOs affected by greenwater loads
•
Hull – Strength (Critical)
– 3 out of 4 FPSOs suffered crack between tanks
•
Accommodation (Critical)
– Insufficient beds leading to repair/maintenance/upgrade delays
•
Ballast & Cargo Pipework (Major)
– Construction Standards for cargo and ballast pipework proven indequate, leading to weld failures, leaks and corrosion
•
Corrosion & Coatings (Major)
– Need for good inspection programme
•
Cranes (Major)
Hull and Marine
•
Helicopters (Major)
– Siting and size of helidecks (need to involve helicopter operators in future designs)
•
Hull Capacity (Major)
– Limited shuttle tanker capacity driving need for increased FPSO storage capacity
•
Inert Gas System (Major)
– Use of hydrocarbon blanketing to replace inert gas
•
Moorings (Major)
– Improved understanding of permanently stopped mooring designs (as opposed to use of individual anchor winches)
•
Motions Assumptions (Major)
– Better prediction of roll limits and its impact on topside fatigue design
•
Power Generation
– Choice of appropriate main power generation (to maximise efficiency)
Turret
(30 issues/problems reported)
•
Turret Location (Critical)
– Benefits of free swivelling turrent
•
Turret Design (Critical)
– Problems with 2 of 3 turret bearings
– Need to make all components easily serviceable and replaceable
•
Risers (Major)
– Range of problems experienced
– Good riser design and operation essential
•
Swivels (Major)
– Concerns over long term reliability
•
Drag Chains (Major)
– Range of problems leading to high maintenance and operational problems – Swivels may be the better option in many cases
Layout
(19 issues/problems reported)
• Layout (Critical)
– Layout of equipment a critical issue:
• Main generators too close to accommodation • Poor mechanical handling solutions
• Exhaust and flare radiation problems • Module overcrowding
• Poorly located vents
• Access and escape route problems • Poor workshop and stores location
– Need to involve all stakeholder in planning layout
Project Management
(29 issues/problems reported)
•
Capex Overruns and Schedule Delays (Critical)
– On only 1 of 4 were Capex overruns avoided (even then the build quality was poorer than expected and opportunities for low cost improvements missed)
– Benefits of working with contractor to maintain quality and provide assistance to improve efficiency
•
Construction Management (Major)
– Failure of design contractors and shipyard to interpret functional requirements
– Failure to manage builders and suppliers
– More upfront work needed on selection of equipment and specification of quality
•
Project Input from other Groups
Operations and Support
(74 issues/problems reported
)
•
Compression (Critical)
– 2 of 4 FPSOs had serious compression problems (gas seal failures, repeated bundle change-outs and cracked pistons)
– Need to consider benefits of larger scrubbers to provide a safety factor against unknowns
•
Compression (Major)
– Vibration from reciprocating compressors can be a problem – Care needed in procurement of compressor
– Need to review noise and vibration levels
•
Uptime Performance (Critical)
– Lack of fully objective data to access uptime performance
•
Shuttle tanker/offloading (Major)
– Need to learn from good operational practices
Manning and Safety
(7 issues/problems reported)
• Safety – General (Critical)
– No evidence FPSOs are less safe than other installations
– Evidence suggests need for active attention to safety
• Crew (Major)
Industry Challenges
•
Hull & Marine (Major)
– Accommodation – need to increase accommodation levels for short periods
•
Caisson Systems (Major)
– Evaluation needed of practicality of using inboard mounted caissons to deliver seawater direct
•
Mechanical Handling
– Develop best practices for range of handling systems
•
Hull Shape
– Learn for past experiences wrt bow shape
•
Painting
– Need to develop painting technology and methods compatible with project demands
•
Thrusters
– Develop methods for removal and repair of thrusters
Industry Challenges
•
Turret swivels/tie-backs
– Low cost method needed to upgrade swivel capacity and to pull in new risers with minimum downtime
•
Design Input from Operations
– Support operators providing input to design
•
Operations and Support
– In Situ Repairs and Modifications Critical
– Need to revise all aspects of marine standards to account for minimum maintenance and in-field repairs
•
Process
– Need for work and an industry specification for moving separation equipment
•
Role of Vendors/OEM (Major)
– Need to secure post supply technical support and minimum performance levels from suppliers
• Codes and Classification, Approvals and Safety Verification (Major) – Need to tighten FPSO class specifications