• No results found

SAP PO Confirmations

N/A
N/A
Protected

Academic year: 2021

Share "SAP PO Confirmations"

Copied!
18
0
0

Loading.... (view fulltext now)

Full text

(1)

Confirmations

MM-PUR Training

(2)

Business Process Example:

A purchase order (PO) is sent to vendor.

Vendor initially sends an OA referencing the PO. He may then follow this up e.g. with a shipping

notification referencing the PO. There is no direct link between an order

acknowledgment X and a shipping notification Y (the information provided by the latter is firmer, more precise, more up-to-date).

The GR can be posted with reference to the purchase order (PO) or with reference to the shipping notification. When a confirmation category is entered, the MRP element BS-EIN is replaced by BS-AVI in the stock/requirements list (transaction: MD04). When the GR is entered, the MRP element BS-AVI disappears.

(3)

Expediting confirmations:

If confirmations are to be expedited, the Acknowledgment required flag

must be set on the purchasing document item detail screen.

As of Release 4.5A, the following enhancements are available in connection

with reminders and expediters relating to purchasing documents:

Up to Release 4.5A, the system used the current date to calculate whether the

reminder period had been exceeded. As of Release 4.5A, you can enter a

reference date with which the calculation is to be carried out.

Up to Release 4.5A, acknowledgment/confirmation dates were not taken into

account. As of Release 4.5A, the system uses the acknowledgment or

confirmation date in addition to the reference date to calculate the reminder

periods. A prerequisite is that the confirmation category is flagged as “subject to

reminder/expediting” in Customizing for Purchasing.

(4)

Prerequisites to work with confirmations Material with material master

Confirmation control key on item detail screen Optional: Acknowledgement required flag

Confirmation maintenance options

Via Idoc: Order acknowledgement (no document is generated)

Shipping notification (a document is generated analog to VL31) Rough GR (a document is generated analog to VL41)

Note:

Only one OA can be updated per item via Idoc. So if one OA over a partial order quantity is received and then a second OA relating to the remaining quantity, the first partial quantity is also expected in the second OA, because old OAs are completely overwritten.

Via SAP transaction: VL31 (Create Shipping Notification) VL31N as of Release 4.6

VL41 (Create Rough GR) functionality comes from Retail In the PO: Via Item -> Confirmations -> Overview (no documents are Generated)

(5)

Customizing (transaction OMGZ)

(6)

External confirmation categories

You can define any kind of external confirmation

categories.

(7)

Internal confirmation categories

Internal conf. categories give you the option of using Idocs. Only the

aforementioned 3 Idocs are supported by SAP. The customer cannot define any further internal conf. categories.

The internal definition is especially important with regard to the use of Idocs because the structure of the later depends on this definition.

(8)

Confirmation control keys

You can define different confirmation control keys.

(9)

1.Confirmation sequence

You define the sequence in which the confirmation categories are expected. Note:

You can work with a maximum of 8 confirmation categories, the numbers 1 to 8 are reserved for it. The schedule line in the PO is internally assigned the number 0 and the GR the number 9.

The “GR-reference” indicator should always be selected for the last confirmation category expected in the sequence (i.e. prior to the GR). This is required

(10)

Confirmations - Sanjeev Shrivastava

Note: You can find the values in the right column in the requirements list (MD04).

(11)
(12)

Confirmations - Sanjeev Shrivastava

Why was the SL offset, and not the OA?

Offsetting logic:

1. SN has the sequence number 2. It can offset (reduce or cancel

out) all SLs and confirmations that have a lower number (SL = 0 and

OA = 1).

2. Date check: Quantities with an earlier date are offset (reduced or

cancelled out) first. Thus in this case the SL is offset first, then the

confirmation (here: order acknowledgment). Since in this case the

SL quantity is greater than the SN quantity, the latter can only partly

offset (i.e. only reduce, not fully cancel out) the former, leaving the

full OA quantity still MRP-relevant.

(13)

Confirmations - Sanjeev Shrivastava

Example 3: Same example as 2 but with different delivery dates

Prerequisite: Customizing transaction OMGZ, confirmation control key 0003 set as follows:

Why was the OA offset, and not the SL?

Offsetting logic: 1. SN has the

sequence number 2. It can offset (reduce or cancel out) all SLs and confirmations that have a lower number (SL = 0 and OA = 1). 2. Date check: Quantities with an earlier date are offset (reduced or cancelled out) first. Thus in this case the OA is offset first, then the SL.

(14)
(15)

Confirmations - Sanjeev Shrivastava

SN for 65 pc, confirming delivery on 03.17.01 => View: MRP-reduced quantity:

In a similar way to example 2, first the remaining 35 of the SL are offset (earlier date and lower sequence no.), then the 25 of the first OA.

Only then do the remaining 5 of the SN offset (reduce) the quantity of the second OA (with the delivery date 03.18.01).

Tip:

The total of the MRP-relevant quantities must agree with the SL quantity in each step as long as no GR has yet taken place.

(16)
(17)

Confirmations - Sanjeev Shrivastava

Symptom: Confirmations AND schedule lines are shown in MD04, i.e. reducing as not taken place correctly. => Check that the sequence number of the confirmation is <> 0 in Customizing.

(Prior to Rel. < 4.0 there were no checks in Customizing, so that the value 0 was accepted as the sequence number by the system.

As of Rel. 4.0, the entry of 0 is no longer accepted).

Symptom: Second confirmation overwrites the first -> check ekes-etens is not ‘0000’.

Over-/underdelivery tolerances relate to the GR quantity and PO quantity, NOT to the confirmation quantity. Non-MRP-relevant confirmations are for information only and do/are not reduced.

Correction reports

Note 215072: Correction of quantities reduced (MRP) for GR assignment Note 202875: Correction report: Redistribution using batch input

Release dependant functionalities

As of 4.0: Change affecting Customiying tables>

Previously there was one GR/assgt. Indicator for each confirmation category

With Rel. 4.0, you can define an indicator per BSTAE and confirmation category for a more fine-tuned control. As of 4.5: GR can be posted using VL transaction

(18)

Version management - Sanjeev Shrivastava

References

Related documents

In the simplest scheme based on the boolean model for retrieval, we retrieve the documents that have occurrences of both good and teacher.. Such

The corona radiata consists of one or more layers of follicular cells that surround the zona pellucida, the polar body, and the secondary oocyte.. The corona radiata is dispersed

organisasjonslæring, arbeidsplasslæring, uformell og formell læring, læring gjennom praksis, sosial praksis og så videre vil derfor være nyttige når man skal foreta en studie

more than four additional runs were required, they were needed for the 2 7-3 design, which is intuitive as this design has one more factor than the 2 6-2 design

Proprietary Schools are referred to as those classified nonpublic, which sell or offer for sale mostly post- secondary instruction which leads to an occupation..

• The development of a model named the image based feature space (IBFS) model for linking image regions or segments with text labels, as well as for automatic image

Several other cases have dealt with the non-compensability aspect of bypassing exclusive remedy, in-line with the Missouri Alliance decision. Peoplease Corp., No. 2009), Employer

4.1 The Select Committee is asked to consider the proposed development of the Customer Service Function, the recommended service delivery option and the investment required8. It