1 | P a g e
The
Technical Services
Department achieved an overall score of
2.49 (83%)
at mid- year, which is an increase from the score of
2.29 (76%)
at the end of
the first quarter. A total of 1 500 square meters of potholes have been repaired by mid-year, exceeding the mid-year target of 1 000m
2and included all
those potholes reported by the community. A total of 1 200m of gravelled road was upgraded. All
subdivisions in proclaimed townships were processed within six month of receipt by mid-year. All (20/20)
electricity connections
1were supplied within one month of application. Foundation and building
inspections were conducted within two days following request. By mid-year, 108% (R 1 088 118.12 / R1
000 000) of the allocated maintenance mid-year budget for water within the township and central business
district was spent. All (4/4) pump stations were serviced on a monthly basis as targeted. All water
interruptions were attended, all water pipe leaks and breaks were fixed and all sewer blockages were
resolved within 48 hours. In addition all (21/21) new water connections were installed within seven days of
receipt of application and water quality tests (360 year to date) were conducted on a daily basis. All (32/32)
building plans were processed within two weeks and all building and foundation inspections were
completed within three days of request. All applications for township establishment were approved by Council by mid-year and all applications for
consolidations were processed.
Challenges were faced in that only 3% of mid-year budget for maintenance on street lighting (R 24 907.47/R750 000) was spent and 61.28% of operating
budget (R 12 898 507 / R21 012 660). Only 90% of Public lighting is in good functional order due to budget constraints.
The department overall achieved targets in three (3/6) of its IDP objects.
Plan for the
future
,
Promote the welfare of the community
and
Development and Implementation
of policies
achieved targets while
Resource management of infrastructure and services
and
Improve financial viability
were under target.
Attract, develop and retain human capital
were zero weighted by
mid-year. Detail pertaining to this section of the SDBIP is provided below:
2 | P a g e
Hierarchy ID KPI O M
Annual
Target Baseline Annual Target
12/13 e from
11/12 Target Actual Achievements Corrective
Action Rating Target Actual Achievements Challenges Corrective Action Score Rating
Basic Service Delivery\Promote the welfare of the community\Waste Management
M_127 evaluation reports Number of landfill
submitted y.t.d. # 4.00 4.00 1.00 1.00
C
2.00 2.002 landfill evaluation reports submitted y.t.d. Landfill site rehabilitation maintenance report available as POE 3.00
C
2.00 2.00 Basic Service Delivery\Resourc e management of infrastructure and services\Commun ity Facilities M_129 Percentage Rand value spent on upgrading, maintenance and rehabilitation of community facilities (Rand value spent / total rand value projected y.t.d. forupgrading, maintenance and rehabilitation of community facilities as percentage) % 100.00 120.00 100.00 120.00 Spent 15 000 more than projected budget
¶
100.00 75.00 We spend according to the cases reported from publicfacilities, zero weighted because planned expenditure
can never be equal to cases reported from public facilities R75 000 rand value spent on upgrading, maintenance and rehabilitation of community faci We spend according to the cases reported from public facilities, zero weighted because planned expenditure can never be equal to cases reported from public facilities We spend according to the cases reported from public facilities, zero weighted because planned expenditure can never be equal to cases reported from public facilities 0w 0w 25.00 45.00 Basic Service Delivery\Resourc e management of infrastructure and services\Electricit y
M_233 Percentage New connections
provided as pre-paid % 100.00 0.00 100.00 100.00 Only one application made and connection completed
C
100.00 100.00 500 connections. Project reportavailable as POE 3.00
C
0.00 -100.0 0 M_234 Percentage Metre positions changed within 7 days afterapplication % 100.00 0.00 100.00 100.00 Five applications were made and all completed
C
100.00 100.00 Customer care report 3.00C
0.00 100.0-0 M_235 Percentage Electricity related enquiries reported and attended to within 24 hours % 100.00 0.00 100.00 100.00 Only five were requested and completed
C
100.00 100.00 Customer care report 3.00C
0.00 100.03 | P a g e
12/13 Basic Service Delivery\Resourc e management of infrastructure and services\Electricit y M_236 Percentage Temporary connections installed within 7 days after application% 100.00 0.00 100.00 recorded for Nothing
the quarter 0w 100.00 0.00 There were no requests received 0w 0w 100.00 0.00 M_237 Percentage Maintenance budget of electrical network / R-value electrical maintenance projected y.t.d. budget spent) (including minor infrastructure maintenance) % 100.00 0.00 100.00 37.00 Not done much maintenance not doing electrification projects and much neglected maintenance When projects are completed will switch to maintenan ce
D
100.00 100.00 R1 200 000 is Total number of budget reserved for electrical network projected y.t.d. R600 000 is Total number of budget for electrical network spent y.t.d., 3.00
C
0.00 100.0 -0 M_238 Percentage Electrical maintenance schedule compliance (number of actual maintenance activities / number of planned maintenance activities)% 100.00 0.00 100.00 100.00 accordingly Followed
C
100.00 100.00 available as POE Monthly reports 3.00C
0.00 100.0 -0 M_239 Percentage Public lighting in good functional order (number of functional public lights / total numberof public lights)
% 100.00 0.00 100.00 95.00 Some light are not working The communit y needs to report them accordingl y
I
100.00 90.00 allocated was The budget insufficient The budget allocated was insufficient To use maintenance budget 2.83I
10.00 -90.00 M_47 Percentage New electricity connections provided in licensed distribution area within 1 month of application % 90.00 100.00 90.00 100.00 Need to standardise KPI on electricity connections To be adjusted during Budget Adjustmen tC
90.00 100.00 All 20 New electricity connections were provided in licensed distribution area within 1 month of application 3.18C
-10.00 0.004 | P a g e
12/13 Basic Service Delivery\Resourc e management of infrastructure and services\Roads and storm waterM_145
Rand value Spent on maintenance and upgrade of street lighting y.t.d. R 1 500 000.0 0 150000 0.00 000.00 375 000.00 25 Target needs to be changed to R25000 per quarter which has been fully spent in the 1st quarter
D
000.00 750 907.47 24 R 24907.47 Spent on maintenance and upgrade of street lighting y.t.d. Ordersare available as POE
1.03
D
092.53 1 475 1 475 092.53
M_152 Gravelled roads Kilometre of upgraded
k
m 4.00 4.00
O
200.00 11200 Kilometre of Gravelled roads
were upgraded N/A
O
-1 196.00
-1 196.0
0
M_153 Metre2 of Potholes repaired y.t.d. # 000.02 0 29000.0 0 500.00 550.00 Material and equipment use increased
C
000.00 1 500.00 1 1500 Metre2 of Potholes repaired y.t.d. There was noPOE by end of December Will monitor that the patching team submit the correct measurements for POE in the
report 4.56
¶
500.00 500.027 0 M_154 Percentage Potholes reported by the community fixed within 2-days (Number of potholes reported by the community fixed within 2 days of reporting / total Number of potholes reported by the community as Percentage). % 100.00 100.00 100.00 100.00C
100.00 100.00 Potholes reported by the community fixed within 2-daysCustomer care report available as
POE
3.00
C
0.00 0.00M_155 Metres Stormwater pipes installed # 396.00 50.00 99.00 0.00 Pipes were not purchased A tender to be advertised next quarter
D
198.00 applicable for this This KPI is not
financial year. 0w 0w 396.00 50.00 Basic Service Delivery\Resourc e management of infrastructure and M_139 Percentage Sewer disposal works monitored every week % 100.00 100.00 100.00 100.00
C
100.00 100.00 The 2 existing sewer disposal works are monitoredevery week
5 | P a g e
12/13
services\Sanitatio
n M_140 Percentage Sewer lines ridded per
annum %
100.0
0 100.00 25.00 25.00
C
50.00 50.00 Sewer lines ridded About half of the 3.00C
50.00 50.00M_141 Percentage New sewer connections installed within 7 working days of request % 100.00 100.00 100.00 100.00
C
100.00 100.00 All 9 sewer connections installed within 7 working days of request. Customer care report availableas POE
3.00
C
0.00 0.00M_142 lines replaced within Percentage Sewer 5 working days % 100.0 0 100.00 100.00 100.00 KPI to be adjusted during Budget Adjustment
C
100.00 100.00 only one Sewer line was replaced within5 working days 3.00
C
0.00 0.00 M_143 Percentage Sewer blockages attended to within 48 hours (Number of sewer blockages attended to within 48 Hours / total number of sewer blockages reported as Percentage)% 100.00 100.00 100.00 100.00
C
100.00 100.00 report available as Customer CarePOE 3.00
C
0.00 0.00 Basic Service Delivery\Resourc e management of infrastructure and services\WaterM_130 samples taken for Number of water
analysis y.t.d. # 12.00 12.00 3.00 3.00
C
6.00 6.006 water samples taken for analysis y.t.d. Analysis report
available as POE 3.00
C
6.00 6.00 M_131 Percentage Water-borne cases investigated (Number of water-borne cases investigated / total Number of water - borne cases reported as percentage) % 100.00 0.00 100.00 100.00C
100.00 No cases reported 0w 0w 100.00 0.006 | P a g e
12/13 Basic Service Delivery\Resourc e management of infrastructure and services\WaterM_132 Number of water quality daily test conducted y.t.d. #
360.0
0 360.00 90.00 90.00
C
180.00 180.00180 water quality daily test conducted y.t.d. Monthly report available as POE 3.00
C
180.00 180.00 M_133 Percentage of Water interruptions attended within 48 hours of reporting% 100.00 100.00 100.00 100.00
C
100.00 100.00 report available as Customer CarePOE 3.00
C
0.00 0.00 M_134 Percentage New water connections installed within 7 days of application % 100.00 100.00 100.00 100.00C
100.00 100.00 21 water connections made within 7 working of application year to date Customer Care report available as POE 3.00C
0.00 0.00 M_135 Percentage Water pipe leaks and breaks fixed within48 hours of reporting
% 100.00 100.00 100.00 100.00
C
100.00 100.00 report available as Customer CarePOE 3.00
C
0.00 0.00M_136
Percentage Hydrants serviced per annum year to date (Number of hydrants serviced year to date / total number of hydrants as percentage) % 100.00 90.00 25.00 25.00 To be transferred to Social Services
C
50.00 100.00 available as POE Monthly report 5.00¶
-7 | P a g e
12/13
M_137
Percentage Maintenance budget
for water spent within the township
and CBD - reticulation (Rand
value budget allocated for water maintenance / rand value water maintenance projected y.t.d. budget spent) (include minor infrastructure maintenance) % 100.00 100.00 100.00 51.00 Underperformed Needs to ensure full implement ation thereto
D
100.00 108.80 R 1 088 118.12 was spent from total budget planned tobe spent year to date of R1 000 000
The total annual budget is R2 000 000 3.15
C
-8.80 -8.80 M_138 Percentage Pump stations serviced per month (Numberof pump stations serviced per month /
total number of pump stations scheduled for maintenance per month as percentage).
% 100.00 100.00 100.00 100.00
C
100.00 100.00 All 4 Pump stations serviced daily 3.00C
0.00 0.00Good Governance and Public Participation\Dev elopment and Implementation of policies\Administr ation M_164 Percentage Council resolutions implemented per quarter (Number of council resolutions implemented per quarter / total number of council resolutions as percentage). % 100.00 80.00 100.00 100.00
C
100.00 100.00 All 6 Council resolutions implemented. The council resolutions register available as POE 3.00C
0.00 20.00-8 | P a g e
12/13 M_165 Percentage departmental meeting resolutions implemented per quarter (departmental meeting resolutions implemented per quarter/ total Number of departmental meeting resolutions% 100.00 100.00 100.00 100.00
C
100.00 0.00 There were no departmentalmeeting resolutions 0w 0w 100.00 100.0 0 Good Governance and Public Participation\Dev elopment and Implementation of policies\Auditing M_161 Percentage AG audit qualifications raised related to department resolved % 100.00 100.00
O
N/AO
100.00 100.00 M_162 Percentage Identified risks monitored and reported (Number risks monitored andreported on / total number risks identified as percentage). % 100.00 100.00 100.00 53.00 constrains Budget Regular follow-up on risk register
D
100.00 0.00 Risks identified There were no 0w 0w 100.00 100.00
Municipal Financial Viability\Improve financial viability\Expenditu re Management M_160 Percentage Operating budget variance per department y.t.d. in terms of projected quarterly expenditure % 10.00 38.00 10.00 40.00 Updated information not available at the time of the completion of the report The delay has been escalated to the leadership and managem ent for attention
D
10.00 61.38The actual amount spent was R 12 898 507 of planned R21 012 660 for the quarter. CFO report
available as POE 1.00
D
-51.38 23.38 -Spatial Rationale\Plan for the future\Building Control M_121 Number of building plans processed within 2 weeks of receipt /Number of building plans received as Percentage% 90.00 10.00 80.00 80.00 concluded All
C
85.00 85.00 32 applications made andprocessed 3.00
C
5.00-75.00
9 | P a g e
12/13 M_122 Percentage Building inspection conducted within two days after a request (Number ofbuilding inspection conducted within
two days after request / total number of building inspections applications submitted as Percentage)
% 100.00 100.00 100.00 100.00 Completed in 3 days
C
100.00 100.00 All completed in 3 days 3.00C
0.00 0.00M_123
Percentage Foundation
inspection conducted within two days after a
request
% 100.00 100.00 100.00 100.00 completed All
C
100.00 100.00 All completed in 3 days 3.00C
0.00 0.00Spatial Rationale\Plan for the future\Organisatio nal Performance Management M_124 Number of Quarterly departmental performance reports completed within 10 working days after the end of quarter
# 100.00 80.00 100.00 0.00 Report is delayed due to late completion and submission of performance scores Must be improved during the mid-year report
D
100.00 100.00 All 6 Quarterly departmental performance reports completed within 10 working days after the end of quarter3.00
C
0.00 20.00-M_125
Number of Monthly departmental reports submitted
per annum y.t.d.
# 12.00 12.00 3.00 3.00 One report is completed
each month
C
6.00 6.00 6 Monthly departmental reports submitted year to date 3.00C
6.00 6.00 M_46 Departmental Number ofmeetings held y.t.d. # 12.00 12.00 3.00 3.00
Completed and recorded
accordingly
C
6.00 6.006 meetings held
10 | P a g e
12/13 Spatial Rationale\Plan for the future\Spatial and Town Planning Spatial Rationale\Plan for the future\Spatial and Town Planning M_112 Percentage Projects implemented for the FY 2011/2012 (Number of Projectsimplemented / total number of IDP projects budgeted for Financial Year -
2011/2012 as percentage) % 100.00 0.00 100.00 0.00 There was nothing to allocate from sector departments Waiting for responses from sector departmen ts
D
100.00 Projects are based on Provincialallocation 0w 0w 100.00 0.00 M_114 Percentage Land Use application processed within 6 months (Number of land use applications processed within 6 months /total number of land use
applications received as Percentage) % 100.00 75.00 100.00 90.00 Waiting supporting documents from the applicant Capture accordingl y once received
I
100.00 No cases reported 0w 0w 100.00 75.00 M_115 Percentage Illegal use addressed (Number of illegal use addressed / total number of illegal land use identified as Percentage) % 100.00 100.00 40.00 40.00 Escalated to Legal Services for finalisationC
60.00 No cases reported 0w 0w 100.00 100.00 M_116 Percentage applications for township establishment processed within 6 months% 100.00 50.00 100.00 100.00 All were done
accordingly
C
100.00 No cases reported 0w 0w 100.00 50.00M_117
Percentage applications for rezoning processed
within 6 months
11 | P a g e
12/13 M_118 Percentage Consent Use applications processed within 6 months of application % 100.00 50.00 100.00 100.00 All permits were concluded and submitted
C
100.00 100.00 permits were issued All temporary 3.00C
0.00 50.00-M_119 Percentage Applications for subdivisions in proclaimed townships processed within 6 months of application % 100.00 100.00 100.00 90.00 One outstanding letter to be sent out Follow up signing of the letter with the Municipal Manager
I
100.00 No cases reported 0w 0w 100.00 100.00 M_120 Percentage of applications for consolidations processed within 6 months of application% 100.00 33.00 100.00 100.00 Completed
C
100.00 No cases reported 0w 0w 100.00 33.00Transformation and Organisational Development\Attr
act, develop and retain human capital\Human Resource Management M_126 Percentage OHS recommendations implemented related to department (Number of recommendations implemented / total number of hazards identified as percentage) % 100.00 100.00 100.00 100.00 Completed
C
100.00 0.00There were no OHS recommendations
related to department
12 | P a g e
Capital Project Implementation
Hierarchy ID Project Owner Annual Target
Sep 12 Dec 12
% Targeted
Progress Progress % Actual Achievements Corrective Action Rating % Targeted Progress % Actual Progress Achievements Challenges Corrective Action Score Rating Expenditure YTD
Basic Service Delivery\Resource management of infrastructure and services\Electricity P_16 Phagameng EXT 9 Streetlight Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the Project
D
100.00 10.00 Design Stage 1.10D
0.00P_17 EXT 4 street Mabatlane lights Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the Project
D
100.00 10.00 Design Stage 1.10D
0.00 P_18 Phagameng EXT 10 street lights Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
100.00 10.00 Design Stage 1.10D
0.00 P_19 Phagameng EXT 7 street lights(Mande la) Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
100.00 10.00 Design Stage 1.10D
0.00P_20 street lights Modimolle Mod_MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the Project
D
100.00 10.00 Design Stage 1.10D
0.00 P_21 Electrificatio n of Phagameng EXT 10 Mod_ MTS 100.00 5.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
36.00 10.00 Design Stage 1.28D
0.00 P_22 Energy Efficiency and Demand Side Manager Mod_ MTS 100.00 5.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
36.00 10.00 Appointment Stage 1.28D
0.00 Basic Service Delivery\Resource management of infrastructure and services\Municipal furniture and equipmentP_11 Computers Mod_MTS 100.00 100.00 0.00 Delayed
Acquire the required computers
during budget
adjustment
D
100.00 100.00 Completed 3.00
C
7 892.98P_12 Furniture Mod_MTS 100.00 100.00 0.00 Delayed
Acquire the required furnisher
during budget
adjustment
D
13 | P a g e
Basic Service Delivery\Resource management of infrastructure and services\Roads and storm water P_06 street Phase 4 (Phelindaba, Thulare) Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage a service provider to undertake the ProjectD
50.00 75.00 Project on Progress. 4.50¶
000.00 1 500 P_07 Modimolle paving of street (Allen, Meigner) Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
50.00 15.00 Project on Progress 1.30D
15 000.00 P_08 Paving of freedom park ring road Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
50.00 15.00 Project on Progress 1.30D
2 040.00 P_09 Mabatlane EXT 4 paving ring road Mod_ MTS 100.00 25.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
50.00 25.00 Project on Progress 1.50D
000.00 1 300 P_10 Road intersection of Joe Slovo and Limpopo street Mod_ MTS 100.00 25.00 25.00 Invoices submitted and paidC
50.00 100.00 Complete d 5.00¶
¶
406.43 2 969 Basic Service Delivery\Resource management of infrastructure and services\Water P_13 Mabaleng Waste Water Treatment Works (Package Plant) Mod_ MTS 100.00 5.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
36.00 99.00 Completed 5.00¶
¶
219.52 2 765 P_14 Mabatlane Waste Water Treatment Works (Package Plant) Mod_ MTS 100.00 5.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
36.00 99.00 Completed 5.00¶
¶
778.54 3 855 P_15 Modimolle Waste Water Treatment Works Phase 2 Mod_ MTS 100.00 5.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
36.00 10.00 AppointmeContractor nt 1.28D
3 957 209.18 P_23 Upgrade of Internal Reticulation Mod_ MTS 100.00 5.00 0.00 The Project is a evaluation stage Secure services of a service provider to undertake the ProjectD
36.00 0.00 0w 0w 0.0014 | P a g e
P_24 EXT 11 waterreticulation Mod_
MTS 100.00 25.00 0.00 a evaluation stage a service provider to undertake the
Project
D
50.00 100.00 Completed 5.00