CS
DESCRIPTION DATE
NO.
DRAWING NUMBER
COVER SHEET
DRAWING TITLE REVISIONS
CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
SPRING HILL ELEMENTARY SCHOOL AUTOMATIC TEMPERATURE CONTROL
SYSTEM REPLACEMENT AT
MMB-013-22 10/12/2021
SM
M-1 CS M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12
SPRING HILL ELEMENTARY
SCHOOL
8201 Lewinsville Rd McLean, VA 22102
COVER SHEET
PROJECT SCOPE, GUIDELINES & EQUIPMENT DATA HVAC EQUIPMENT SCHEDULES
1ST AND 2ND FLOOR - ZONE FLOOR PLAN & HVAC LAYOUT CONTROL DIAGRAMS - CENTRAL PLANT SYSTEMS
CONTROL DIAGRAMS - RTU- 1, 2 CONTROL DIAGRAMS
CONTROL DIAGRAMS - RTU- 3, 4, 11, 14 CONTROL DIAGRAMS CONTROL DIAGRAMS - RTU- 7, 8, 12 CONTROL DIAGRAMS
CONTROL DIAGRAMS - RTU- 9, 10, 15, 16 CONTROL DIAGRAMS
CONTROL DIAGRAMS - RTU- 5, 13; RAHU- 1 - 9 CONTROL DIAGRAMS CONTROL DIAGRAMS - UVs, FCUs & VAVs
CONTROL DIAGRAMS - MISC. EQUIPMENT
FUNCTION BLOCK LOGIC & MECHANICAL CONTROL SYMBOLS
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-1
CONTROL SYSTEM SCOPE, UNIT DATA
& GUIDELINES
RTU SCHEDULE
STANDARD ABBREVIATIONS AHU - Air Handling Unit
BAS - Building Automation System CFM - Cubic Feet (of Air) Per Minute CH - Cabinet Heater
CHW - Chilled Water
CU - Control or Cooling Unit (VAV) CVT - Constant Volume Terminal (VAV) DP - Differential Pressure (Static) DHC - Duct Heating Coil
FCPS - Fairfax County Public Schools FCU - Fan Coil Unit
FTR - Finned Tube Radiator GPM - Gallons Per Minute HW - Hot Water
LVT - Line Voltage Thermostat MAU - Makeup Air Unit
MBH - Thousand BTU Per Hour NIC - Not Included in Contract RAHU - Rooftop Air Handling Unit RTU - Rooftop Unit
UH - Unit Heater UV - Unit Ventilator VAV - Variable Air Volume VFD - Variable Frequency Drive
SPRING HILL ELEMENTARY
SCHOOL
8201 Lewinsville Road, McLean, VA, 22102
EXHAUST FAN SCHEDULE
MMB-013-22 10/12/2021
RAHU SCHEDULE
PUMP SCHEDULE
SCOPE OF WORK
5 - REPLACE ALL HVAC EQUIPMENT (INCLUDING EXHAUST FANS ) PNEUMATIC DAMPER ACTUATORS WITH NEW ELECTRONIC ACTUATORS. CLEAN & LUBRICATE ALL UNIT DAMPER LINKAGES INCLUDING
BAROMETRIC DAMPERS AND VERIFY PROPER DAMPER OPERATION.
7 - PROVIDE AND INSTALL A NEW STAND ALONE DDC PROGRAMABLE CONTROLLER FOR EACH OF THE FOLLOWING HVAC SYSTEMS AND EQUIPMENT: CENTRAL HEATING SYSTEM (BOILERS & HW PUMPS), CHILLED WATER SYSTEMS (CHILLERS & CHW PUMPS), EACH AHU, RTU, MAU, UV AND FCU. BAS
CONTROLLERS FOR MAJOR EQUIPMENT (BOILERS, CHILLERS, PUMPS, AHUS, RTUS & MAUS) MUST HAVE CONTROL POINT (OUTPUT) OVERRIDE CAPABILITIES. THE BAS SHALL CONTROL ALL EXHAUST FANS, FTRS, CUHS AND UHS SHOWN ON THESE FLOOR PLANS THAT ARE NOT CONTROLLED BY ELECTRONIC
THERMOSTATS OR WALL SWITCH. PROVIDE AND INSTALL NEW LINE VOLTAGE THERMOSTATS WITH CONCEALED SETPOINT ADJUST WHERE SHOWN ON FLOOR PLANS.
6 - REMOVE ALL EXISTING BAS CONTROLLERS AND RETURN TO FCPS. REMOVE ALL EXISTING CONTROL DEVICES SUCH AS RELAYS, SENSORS, POWER SUPPLIES, TERMINALS, TRANSDUCERS, ETC. AND REPLACE WITH NEW WHERE APPLICABLE. RE-USE OR RETURN TO FCPS
UNINTERRUPTIBLE POWER SUPPLIES (UPS).
9 - PROVIDE AND INSTALL NEW RETURN AND SUPPLY AIR TEMPERATURE DUCT SENSORS IN ALL AHUS, RTUS & MAUS. PROVIDE & INSTALL NEW AVERAGING TYPE SENSORS TO MONITOR MIXED AIR FOR ALL AHUS & RTUS. PROVIDE & INSTALL RETURN AIR HUMIDITY DUCT SENSORS WHERE SHOWN ON THESE DRAWINGS. PROVIDE NEW SENSORS TO MONITOR DISCHARGE AIR FOR ALL UVS & FCUS AND MOUNT IN CENTER OF UNIT.
12 - PROVIDE AND INSTALL NEW OCCUPANCY (MOTION) SENSORS IN SPACES SHOWN ON THESE FLOOR PLANS AND WIRE TO LOCAL BAS CONTROLLERS AS SHOWN ON THESE DRAWINGS. PROVIDE & INSTALL CARBON DIOXIDE (CO2) SENSORS IN SPACES SHOWN ON FLOOR PLAN(S). PROVIDE CAGE TYPE
PROTECTIVE COVERS FOR CO2 SENSORS IN GYMS & CAFETERIA. PROGRAM OCCUPANCY SEQUENCE FOR THESE DEVICES AS SPECIFIED HEREIN.
13 - HVAC UNIT NAMES IN PROGRAMS AND ROOM NUMBERS ON GRAPHIC SHALL MATCH UNIT NAMES &
ROOM NUMBERS AS SHOWN ON THESE DRAWINGS. ALL SPACE SENSORS SHALL BE LABELED WITH THE HVAC ID NAME OF THE UNIT SERVING THAT AREA. CONTRACTOR SHALL FIELD VERIFY ROOM NUMBERS
AND NAMES.
10 - INSTALL NEW 2 POLE FREEZESTATS IN ALL UNITS WITH OUTSIDE AIR INTAKE AND HW OR CHW COILS.
ONE POLE FOR THE HARDWIRED SAFETY INTERLOCK SEQUENCE, THE OTHER FOR THE BAS CONTROLLER ALARM INPUT.
8 - PROVIDE AND INSTALL MOTOR CURRENT SENSORS AND STATUS RELAYS FOR ALL EF, HW & CHW PUMP MOTORS AND AHU, RTU & MAU AND FC FAN MOTORS FOR THE PURPOSE OF MONITORING AND TRENDING THE RUN STATUS OF THIS EQUIPMENT AS WELL AS ACCUMULATING RUN TIME. THE BAS WILL ALSO
MONITOR & TREND THE ALARM AND RUN STATUS POINTS OF THE BOILERS AND CHILLERS.
17 - ALL NEW VALVES AND PIPING INSULATION DISTURBED DURING THE COURSE OF THIS WORK SHALL BE RE-INSULATED WITH HEAVY DENSITY RIGID MOLDED FIBERGLASS PIPE INSULATION WITH FACTORY APPLIED
ALL SERVICE JACKET (ASJ) WITH A 'K' FACTOR NOT TO EXCEED 0.25 @ 75F MEAN TEMPERATURE. THE THICKNESS SHALL MATCH WITH THE EXISTING INSULATION. THE NEW INSULATION SHALL BE PAINTED TO MATCH THE EXISTING INSULATION. ALL VALVES, STRAINERS, ELBOWS, AND FITTINGS SHALL BE INSULATED.
18 - CONTRACTOR SHALL BE RESPONSIBLE FOR DRAINING, REFILLING THE HOT WATER AND CHILLED WATER SYSTEMS, AND BLEEDING AIR OUT OF THE SYSTEMS AFTER REFILL AS NECESSARY TO PERFORM THIS
WORK.
15 - EXISTING CONDUIT TO SENSORS AT AIR HANDLERS AND CENTRAL PLANT MAY BE RE-USED IF IN GOOD CONDITION AND IF SIZED PER NATIONAL ELECTRIC CODE. CONTRACTOR SHALL REPAIR ALL CONDUIT USED FOR CONTROLS INCLUDING CONNECTORS AND COVER PLATES AS NEEDED. ALL NEW CONDUIT FOR POWER WIRING SHALL BE INTERMEDIATE METAL CONDUIT IF LARGER THAN 1" OR ELECTRIC METALIC TUBING IF 1"
OR SMALLER. NEW CONDUIT SHALL BE SIZED PER NATIONAL ELECTRIC CODE. FOR POWER WIRING IN THE CENTRAL PLANT, LIQUID-TIGHT GALVANIZED SINGLE STRIP FLEXIBLE METAL CONDUIT MAY BE USED FOR POWER WIRING IN LENGTHS UP TO 24" AND A SEPARATE GREEN GROUND WIRE SHALL BE INSTALLED THROUGH THE FLEXIBLE CONDUIT BACK TO THE SOURCE. FOR NEW CONDUIT TO END DEVICES SUCH AS SENSOR AND ACTUATORS, METAL CLAD (MC) FLEXIBLE CONDUIT IN LENGHTS UP TO 24" MAY BE USED. ALL CONTROL WIRING SHALL BE NEW. WIRING SHALL BE CONTINUOUS FROM CONTROLLER TO INPUT SENSORS AND OUTPUT DEVICES WITHOUT SPLICING OR WIRE NUTS. WIRING TO CONTROL END DEVICES ON MOVING OR VIBRATING EQUIPMENT SHALL BE RUN IN FLEXIBLE METALIC CONDUIT IN LENGTHS UP TO 24".
11 - REPLACE EXISTING SPACE SENSORS WITH NEW SETPOINT ADJUST TYPE SENSORS. SURFACE MOUNT ON WALL WITHIN A VENTILATED COVER (EXCEPT IN HALLWAYS, BATHROOMS & SHOWERS - USE FLAT WALL PLATE TYPE WITHOUT ADJUSTER) AND INSULATE BEHIND SENSOR. NEW WIRING SHALL BE RUN FROM SENSOR TO CONTROLLER AND BE CONCEALED IN WALLS AND CEILING. PROVIDE CAGE TYPE PROTECTIVE COVERS FOR SENSORS IN GYMS & CAFETERIA, AND KITCHEN. REMOVE ALL EXISTING NIGHT SETBACK SENSORS ASSOCIATED WITH EXISTING BAS.
3 - REPLACE OUTSIDE AIR TEMPERATURE AND HUMIDITY SENSORS WITH NEW. PROVIDE AND INSTALL NEW BAS WATER TEMPERATURE SENSORS FOR CENTRAL PLANT HOT WATER AND CHILLED WATER SYSTEMS AS SHOWN ON THESE DRAWINGS. WELD NEW SENSOR WELL THREAD-O-LETS ON PIPES.
EXISTING SENSOR WELLS MAY BE REUSED IF COMPATIBLE AND CLEANED WITH NEW SENSORS. PROVIDE NEW THERMAL GREASE IN EACH WELL.
4 - REPLACE ALL HVAC EQUIPMENT (AHUS, RTUS, MAUS, UVS, FCUS, FTRS) HW & CHW COIL VALVES AND ACTUATORS WITH NEW VALVES AND ELECTRONIC ACTUATORS.
14 - PROVIDE NEW CONTROL CABINETS WITH LATCHING DOOR PANEL (WITHOUT KEY LOCK) FOR NEW BAS CONTROLLERS AND REMOVE ALL UNUSED CONTROL CABINETS. EXPOSED MOUNTING HOLES IN WALL
FROM REMOVED CABINETS SHALL BE REFILLED AND NEWLY EXPOSED AREAS SHALL BE PAINTED TO MATCH EXISTING WALL COLOR.
GENERAL: THE CONTRACTOR SHALL COMPLETELY REPLACE EXISTING HVAC AUTOMATIC TEMPERATURE CONTROL (ATC) SYSTEM WITH A NEW HVAC AUTOMATIC TEMPERATURE CONTROL SYTEM WITH DDC CONTROLS. THE NEW BUILDING AUTOMATION SYSTEM (BAS) SHALL INCLUDE OPERATING SEQUENCES THAT ARE SPECIFICALLY DESIGNED FOR THIS SITE TO PROVIDE MAXIMUM ENERGY EFFICIENCY AS WELL AS OPTIMUM OCCUPANT
COMFORT IN THE MANAGEMENT OF THE BUILDING'S HVAC SYSTEMS. THE BAS WILL ALSO INCLUDE A HIGH QUALITY, USER FRIENDLY GRAPHICAL INTERFACE. THE CONTRACTOR SHALL PROVIDE THE FOLLOWING:
1 - REMOVE ALL PNEUMATIC CONTROL DEVICES, INCLUDING ACTUATORS. REMOVE ALL EXPOSED PNEUMATIC TUBING IN THE MECHANICAL ROOMS AND ELSEWHERE. FOR PHASING PURPOSES, ALL
REMAINING UNEXPOSED PNEUMATIC LINES SHALL BE CAPPED WHILE THE AIR COMPRESSOR REMAINS IN SERVICE. AT THE END OF THE PROJECT, THE AIR COMPRESSOR SHALL BE REMOVED AND DISPOSED OF BY THE CONTRACTOR. CONTRACTOR SHALL REMOVE EXISTING DISCONNECT, CONDUIT AND POWER WIRES FROM BREAKER PANEL TO COMPRESSOR.
2 - REPLACE EXISTING THREE WAY MAIN HOT WATER MIXING VALVE WITH NEW. REPLACE PNEUMATIC ACTUATOR WITH NEW SPRING RETURN ELECTRONIC ACTUATOR. PROVIDE AND INSTALL NEW VARIABLE FREQUENCY DRIVES FOR SPECIFIED PUMPS AND DIFFERENTIAL PRESSURE TRANSMITTER(S) AT THE LOCATION SPECIFIED ON DRAWING M-2.
16 - ALL THE EXPOSED CONTROL WIRING AND POWER WIRING IN OCCUPIED SPACES INCLUDING BUT NOT LIMITED TO CLASSROOMS AND OFFICES SHALL BE RUN IN 700 SERIES WIREMOLD METAL RACEWAYS. THE COLOR OF THE RACEWAY SHALL MATCH THE COLOR OF THE WALL.
19 - CONTRACTOR SHALL HIRE A CERTIFIED TESTING, ADJUSTING, AND BALANCING (TAB) AGENCY TO PERFORM AIR AND WATER BALANCING OF THE SYSTEMS PER SECTION 01660 OF SPECIFICATIONS.
CONTRACTOR SHALL BE RESPONSIBLE FOR DISASSEMBLING AND ASSEMBLING UNITS AS NEEDED TO PERFORM BALANCING. CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIRING PIPE AND AIR DUCT INSULATION DISTURBED DURING THE COURSE OF BALANCING.
20 - CONTRACTOR SHALL INCLUDE AND BEAR THE COST OF ALL THE APPLICABLE SERVER UPGRADES NECESSARY FOR THE ADDITION OF THE SYSTEM INSTALLED PER THIS CONTRACT TO THE SERVER AND FURTHER THE CONTRACTOR SHALL MAKE CERTAIN THAT THE ADDITION OF THE NEW SYSTEM AND ANY
ASSOCIATED UPGRADES PROVIDE NO NOTICEABLE DISRUPTION TO SERVICE OR OTHER NEGATIVE IMPACTS ON REMAINING FCPS FACILITIES HOSTED ON THE SERVER
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-2
HVAC EQUIPMENT SCHEDULES
FAN COIL UNIT SCHEDULE
SPRING HILL ELEMENTARY
SCHOOL
8201 Lewinsville Road, McLean, VA, 22102
MMB-013-22 10/12/2021
VAV TERMINAL SCHEDULE
UNIT VENTILATOR SCHEDULE
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
10/12/2021
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
MMB-013-22
M-3
SPRING HILL ELEMENTARY
SCHOOL
ZONED FLOOR PLAN AND HVAC LAYOUT
8201 Lewinsville Road, McLean, VA, 22102
RTU-8 RTU-7
M
RV-4
M
RV-3
RTU-9
T
T
M
RV-1
M
RV-2
RTU-16 RTU-15
Tovd
Tovd
T
EF-48 EF-49
EF-51 EF-50
RTU-5
CUH-1 CUH-2
CUH-3 CUH-4 CUH-5
UH-1
UH-2 UH-3
UH-4 FTR-1
FTR-2
FTR-3 FTR-4
M M
EF-10 Kitchen hood
EF-42
EF-41 EF-40
EF-44 EF-38
EF-31 EF-39
T T
T T T T T
T T
TT T
T T
TT
RTU-10
T
RTU-11
EF-34 RTU-8
RTU-7 EF-37
FTR-6 FTR-5
FTR-7 FTR-8 FTR-9 FTR-10 FTR-11 FTR-12 FTR-13
T
RTU-11
RTU-5 RTU-10
T T T T
T T
DHC-1
RTU-12
RTU-13
T
T T
T
RTU-14
FC-7 FC-8 FC-1 FC-2
FC-3FC-4
FC-5 FC-6 UV- 115
T T
T
T
T
T T
RAHU-8 RAHU-7
RAHU-9
UV- 113 UV- 111 UV- 109 UV- 107 UV- 105 UV- 103
UV- 108 UV- 106 UV- 104
UV- 102 UV- 1
UV- 100
UV- 101 FC-9
T
T T T
T T T T T
T
CUH-6
T
CUH-7
T
UH-5
EF-23 EF-22 EF-21
EF-45 EF-24
EF-19 EF-18
TT
EF-46 EF-47
EF-13
EF-14 EF-12
EF-25
FC-10
T T
T T T
Ducts up to RAHU-3
Ducts up to RAHU-2
UV- 117 UV- 119
UV- 112 FC-11
FC-12 FC-13 FC-14
UV- 114 UV- 116
CUH-8
T
T T
T T
T T T
T T
RTU-3 RTU-4
T
T
RAHU-6
FC-15 FC-16
T
FC-17T
TFC-18
UV- 2 UV- 3
CUH-9
T CUH-10
CUH-11
CUH-12
T
T
CUH-13
T
CUH-14
T
T T
EF-43
EF-16
EF-33 EF-29
EF-30 EF-17
ERU-1
RAHU-5
RAHU-4 RAHU-3 RAHU-2
T T
T
UV- 206 UV- 205
Ducts down to first floor
UV- 208 UV- 210
RAHU-1
UV- 200 UV- 202 UV- 204 UV- 212
UV- 201 UV- 203 UV- 207 UV- 209 UV- 211
FC-19 FC-20 FC-21
CUH-15
CUH-16 CUH-17
CUH-18
EF-11 EF-1 EF-9
EF-26
EF-3
EF-2
EF-27
EF-28
EF-4
EF-7 EF-6
EF-5
EF-36 EF-35
T T
T T
T T
T T
T T
T T
T T
T
T T
RTU-2 RTU-1
VAV-5
VAV-1 VAV-4
VAV-6
VAV-2 VAV-3
VAV-7
VAV-13
VAV-12 VAV-8
VAV-9
VAV-10 VAV-11
SP
SP
Chiller-1
(On ground)
EF-52 EF-53
EF-57 EF-54
EF-55 EF-56
T
T T T T
T T
T T T
T
T
T T
CUH-19 CUH-20
Mechanical Room Layout
NOT TO SCALE
CHWP -P2 CHWP -P1 UH-7
T2 1
3
4
5 6
6
7
7 8
9
11 10
Outside Air Sensor location
5
SYMBOLS AND ABBREVIATIONS
RTU - ROOF TOP UNIT; AHU-AIR HANDLING UNIT; RAHU-ROOFTOP AIR HANDLING UNIT;
ERU - ENERGY RECOVERY UNIT
VARIABLE AIR VOLUME FAN POWERD TERMINAL UNIT WITH DUCT HEATING COIL UV - UNIT VENTILATOR
FC - FAN COIL UNIT EF - EXHAUST FAN
CH/UH - CABINET HEATER/UNIT HEATER FTR- FINNED TUBE RADIATION
BAS - BUILDING AUTOMATION SYSTEM SPACE TEMPERATURE SENSOR (BAS) LINE VOLTAGE THERMOSTAT
CO2 - CARBON DIOXIDE SENSOR SPACE HUMIDITY SENSOR (BAS) ZONE - HVAC CONTROL ZONE NUMBER
SPACE SENSOR (BAS) WITH LOCAL OVERRIDE DP - DIFFERENTIAL PRESSURE TRANSMITTER MOTORIZED DAMPER
DHC- DUCT HEATING COIL OCCUPANCY SENSOR
DUCT STATIC PRESSURE SENSOR
RV-RELIEF VENT WITH MOTORIZED DAMPER T
T
1
C
Tovd
M
O
SP
H
ovd
M
12
O
EF-58 T
T
T
EF-28
EF-7
T
T EF-1
EF-15
T M
EF-20
EF-32
T
C
C
O
O
O
EF-8 RTU-12
DHC-1
Boiler Boiler
Boiler-1
Boiler-2
HWP-P3
HWP-P4 UH-5
UH-6
Boiler Room Layout
NOT TO SCALE
T
T
ZONES - AREA SERVED 1 - ADMIN OFFICES
2 - CAFETERIA/KITCHEN 3- GYMNASIUM
4 - STAGE 5 - LIBRARY 6 - CLASSROOMS 7 - CLASSROOMS
8 - CLASSROOMS, VAV SECTION 9 - CLASSROOMS
10 - CLASSROOMS, SECOND FLOOR 11 - SACC ROOMS
12 - INSTRUMENT ROOM
MAIN HOT WATER SYSTEM SERVES ZONES 1, 2, 6, 7, 8, 10 ACTIVATE CHILLER-1 FOR ZONES 6, 7, 10
EQUIPMENT CONTROLLED BY BAS - RTU - 11; EF - 34, 41
- RTU - 5, 7, 8; EF - 20, 37, 39, 40; CUH - 1, 2, 3, 4, 5 - RTU - 3, 4; EF - 17, 29, 30, 33
- RTU - 9 - RTU - 12, 13
- RAHU - 2, 3, 6; EF - 2, 3, 6, 16, 26, 27, 35, 36, 37, 43; CUH - 4, 5, 8, 11, 14
- RAHU - 7, 8, 9; RTU - 14; EF - 18, 12, 14, 19, 21, 22, 23, 24, 25, 45, 46, 47; CUH - 6 - RTU - 1, 2; EF - 52, 53, 54, 55, 56, 57; CUH - 19, 20
- ERU - 1; EF - 50, 51;
- RAHU - 1, 4, 5; EF - 4, 5, 9, 11; CUH - 17, 18 - RTU - 15, 16; EF - 48, 49
- RTU - 10 Project Notes:
Install line voltage motor rated on/off switch in parallel with new LVT to control EF- 13 on wall in kiln room, install
necessary power conductors and conduit; remove existing control relay and complete power circuit
For all equipment controlled by LVT and/or or wall switch only, remove existing BAS control relay and complete power circuit. Install new EMT conduit and power conductors from the power source to LVT and the unit as necessary to complete the installation.
Replace existing 3-way HW mixing valve with new. Replace pneumatic actuator with new spring return electronic actuator.
Install VFD for chilled water pumps P-1 and P-2 and hot water pumps P-3 and P-4.
Install isolation ball valves for the Hot Water Pump P-3 and P-4 VFD DP transmitter tubes on top of 4" main HW supply HW return lines going to the building in boiler room. Install DP transmitter in boiler room at the indicated location.
For all EFs controlled by BAS: keep existing wall switch in place if applicable.
Interlock motorized outdoor air intake damper with exhaust fan
Remove existing CO2 sensors for RTU - 7 and 8. Provide and install one new CO2 sensor to control both RTUs.
New BAS shall enable and disable ERU - 1 on Zone 9 schedule via a physical output.
Electric meter location Gas meter location Water meter location
Hot Water System and RTU - 5, 7, 8, 9, 10 BAS control panels' existing location.
Chilled Water System BAS control panels' existing location.
RAHU - 7, 8, 9 and RTU - 14 BAS control panels' existing location RTU - 11 BAS control panels' existing location.
RTU - 12, 13 BAS control panels' existing location.
RAHU - 6 and RTU - 3, 4 BAS control panels' existing location RTU - 15, 16 BAS control panels' existing location
RAHU - 1, 2, 3 BAS control panels' existing location RAHU -3, 4 BAS control panels' existing location
Install new BAS control panels for corresponding equipment at existing locations wherever possible. If the installation is impossible due to space constrictions, install at alternative locations approved by FCPS project manager.
Contractor shall make information regarding MAC addresses pertinent to controllers installed within each control panel available within the panel.
Connect each RAHU, RTU and Hot Water System, and Chilled Water System Ethernet network controller to a designated FCPS WAN Ethernet port on the drop provided and installed by FCPS adjacent to control panels at the locations indicated herein.
1
2 3 4 5 6 7 8 9
10 11 12 13 14 15 17 16 18
S
1
4 3
5 7 7
7
8
4
H H
H H
H H
H H
H
H H H
H
H
H H H H H
H
H H
H H
H
H H H H
H H
H H
H H H
H H H
H
H H H
H H
O O
O O O
O O O O
O
O
O
O
O O O
O O O
O O O
O
O
O
O
O O
O O O
O O
O
O O O
O O
O O
4"
C
10 11
12
13 14
15
16 17
18
19
19
20 21 20
21
22
23
24
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
10/12/2021
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
MMB-013-22
M-4
SPRING HILL ELEMENTARY
SCHOOL
HOT WATER PLANT, CHILLER-1
8201 Lewinsville Road,
McLean, VA, 22102
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-5
SPRING HILL ELEMENTARY
SCHOOL
RTU-1, 2
CONTROL DIAGRAMS
MMB-013-22 10/12/2021
8201 Lewinsville Road,
McLean, VA, 22102
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-6
SPRING HILL ELEMENTARY
SCHOOL
ROOFTOP UNITS 3, 4, 11, 14 CONTROL
DIAGRAMS
8201 Lewinsville Road, McLean, VA, 22102
MMB-013-22
10/12/2021
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-7
SPRING HILL ELEMENTARY
SCHOOL
ROOFTOP UNITS 7, 8, 12 CONTROL
DIAGRAMS
8201 Lewinsville Road, McLean, VA, 22102
MMB-013-22
10/12/2021
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-8
SPRING HILL ELEMENTARY
SCHOOL
ROOFTOP UNITS 9, 10, 15, 16 CONTROL
DIAGRAMS
8201 Lewinsville Road, McLean, VA, 22102
MMB-013-22
10/12/2021
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-9
SPRING HILL ELEMENTARY
SCHOOL
ROOFTOP UNITS 5, 13; RAHUs 1 - 9
CONTROL DIAGRAMS
8201 Lewinsville Road, McLean, VA, 22102
MMB-013-22
10/12/2021
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE
SM
REVISIONS CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-10
SPRING HILL ELEMENTARY
SCHOOL
UV, FCU, VAV
CONTROL DIAGRAMS
MMB-013-22 10/12/2021
8201 Lewinsville Road,
McLean, VA, 22102
DESCRIPTION DATE
NO.
DRAWING NUMBER DRAWING TITLE REVISIONS
CHECKED DATE PROJECT # DRAWN
PROJECT TITLE
M-11
SM
MISC EQUIPMENT CONTROL DIAGRAMS
SPRING HILL ELEMENTARY
SCHOOL
MMB-013-22
ZONES - AREA SERVED1 - ADMIN OFFICES
2 - CAFETERIA/KITCHEN 3 - GYMNASIUM
4 - STAGE 5 - LIBRARY
6 - CLASSROOMS 7 - CLASSROOMS
8 - CLASSROOMS, VAV SECTION 9 - CLASSROOMS
10 - CLASSROOMS, SECOND FLOOR 11-SACC
12-INSTRUMENT ROOM